This document is an Attachment I - Scope of Work for Project ARN 24-0022 to redistribute uninterruptible power supply (UPS) power at the National Geospatial-Intelligence Agency's Arnold Site. The scope of work is to install new UPS power distribution switchboards, feeders, and branch circuit cables and busduct systems to power existing loads. The old UPS systems and battery cabinets will be demolished and removed from service. New distribution switchboards will be sourced from recently installed UPS systems 1-1A, 2A, 3A and 1-1B, 2B, 3B. Two new Power Distribution Units will also be installed in the Data Center and fed from the new switchboards. All work will be performed per the project specifications, drawings, and accompanying contract documents.
The related federal contract opportunity is a Request for Proposal (RFP) for Uninterruptible Power Supply (UPS) Redistribution, Solicitation Number HM157524R0016, issued by the Department of Defense National Geospatial Intelligence Agency.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UNCLASSIFIED
Attachment I
UNCLASSIFIED
National Geospatial-Intelligence Agency 3838 Vogel Road
Arnold, MO 63010
Project to Redistribute Uninterruptible Power Supply (UPS) power to UPS loads in order to remove existing UPS units located in Building 100.
Arnold Site Project ARN 24-0022
The scope of work is to install new UPS power distribution switchboards, feeders, and branch circuit cables and busduct systems to power existing loads. The old UPS systems and battery cabinets will be demolished and removed from service. New distribution switchboards will be sourced from recently installed UPS systems 1-1A, 2A, 3A and 1-1B, 2B, 3B.
Two new Power Distribution Units will also be installed in the Data Center and fed from the new switchboards.
All per the project specifications, drawings and accompanying contract documents.