Mandatory GFP
| Required Government-Furnished Property | |||
| System | Hardware | Offeror Requested-by Date | NASA Available Date |
| EVA* | Flight EVA Suit | L-3 months | |
| EVA* | Flight EVA Support Equipment, such as umbilicals and crew preference items | L-3 months | |
| EVA* | EVA Simulator/Emulator | NLT L-24 months | |
| Crew Systems | Crew Clothing | L-3 months | |
| Crew Systems | Crew Hygiene Supplies | L-3 months | |
| Crew Systems | Crew Hygiene Consumables | L-3 months | |
| Crew Systems | Crew Personal Effects | L-3 months | |
| Crew Systems | Operational Supplies | L-3 months | |
| Utilization | Sample Return Equipment | L-2 months | |
| Utilization | Utiliation Equipment | L-2 months | |
| Utilization | Cold Stowage Freezer | L-2 months | |
| Utilization | Cryo Freezer (only required if mass threshold exceeded) | L-2 months | |
| Crew Health & Performance | Radiation Detection (Monitor) | L-3 months | |
| Crew Health & Performance | Personal Medical Accessory Kit (HMAK) | L-1 month | |
| Crew Health & Performance | Medical Kit (pharmaceuticals only) | NET L-1 month | |
| Emulators/Simulators | RF Emulator | IL CDR-2 months | |
| Emulators/Simulators | HDL Cargo Simulator/Emulator for Off-Loaded Cargo | HDL DCR-3 months | |
| Emulators/Simulators | HDL Cargo Simulator/Emulator for Integrated Cargo | HDL DCR-3 months | |
| Emulators/Simulators | Gateway Avionics Emulator (Development) | IL CDR-2 months | |
| Emulators/Simulators | Gateway Avionics Emulator (Verification) | IL DCR-3 months | |
| * denotes property (not GFP) that will be provided to the contractor |
&"Times New Roman,Bold"&12&F
Enumerated Optional GFP
| Enumerated Optional Government-Furnished Property | |||||
| System | Hardware | No Earlier Than (NET) | No Later Than (NLT) | Requested by Date* | Cost as Set by NASA+ ($M) |
| Crew Health & Performance | Food System | L - 6 weeks | N /A | $2.750 | |
| Crew Health & Performance | Food Warmer | Proj. ATP + 32 months | N/A | $2.567 | |
| Crew Health & Performance | HLS Medical Kit Subsystem (Durable Medical Hardware and Supplies only) | L - 6 weeks | N/A | $2.500 | |
| Crew Systems | Trash Bags | Proj. ATP + 14 months | N/A | $0.138 | |
| Crew Systems | Waste Management System (WMS) | Proj. ATP + 32 months | N/A | $8.877 | |
| Crew Systems | WMS Consumables | Proj. ATP + 5 months | N/A | $0.750 | |
| Crew Systems | Stowage Containers for Crew Systems | Proj. ATP + 14 months | N/A | $0.250 | |
| ECLSS | Personal Protection Equipment (PPE) - Portable Fire Extinguisher | L - 3 months | N/A | $5.100 | |
| ECLSS | Personal Protection Equipment (PPE) - Emergency Mask and Cartridge - Contingency Breathing Apparatus | L - 3 months | N/A | $5.100 | |
| ECLSS | Potable Water Dispenser | L - 6 months | N/A | $8.281 | |
| Other | IVA Suit | SLD ATP + 38 months | N/A | *** | $0.780** |
| Other | Labels | SLD ATP + 3 months | L - 4 months | $0.050 | |
| * Note: The requested by date for the hardware referenced here must match the requested by date on the OGFPA form. | |||||
| ** Price is per suit | |||||
| *** GTA request needs to be prioritized at the start of the SLD contract | |||||
| Proj. ATP refers to the date where agreement is reached between the contractor and NASA and funding is available for the project to start | |||||
| + Values in this column are estimates only. The values established in the approved and proposed OGFPA form is the definitive value. |
&"Times New Roman,Bold"&12&F
Non-Enum. Requested GFP
| Non-Enumerated Optional Government-Furnished Property Requested by the Offeror | |||
| System | GFP/GFI | OGFPA Requested by Date | Cost as Set by NASA |