Attachment I - 20Aug20_Industry Day Presentation.pdf
PDF 11 MB Posted
- Attached to
- OK-COMANCHE DAM MODIFICATIONS Federal contract opportunity
- Solicitation number
- 140F0921R0002
About this file
This document provides details on a federal solicitation for the Comanche Dam Modifications project. The solicitation number is 140F0921R0002 issued by the Department of the Interior Fish and Wildlife Service Region 9 Headquarters for modifications to Comanche Dam using roller compacted concrete. Interested vendors can find additional information on project scope and requirements in Attachment I - 20Aug20_Industry Day Presentation.pdf. The opportunity type is listed as a solicitation, suggesting proposals or bids will be accepted in response. No other salient details are provided on pricing terms, response dates, or historical incumbent.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140F0921R0002_Amd_0001.pdf | ||
| Attachment H - Comanche RCC Mix Study - Rev102120.pdf | ||
| Attachment J - Design Summary Report - Comanche Dam Modifications.pdf | ||
| Attachment D - SF25 Performance Bond.pdf | ||
| Attachment B - Comanche Drawings PDF.pdf | ||
| Attachment K - Addendum to Specifications.pdf | ||
| Attachment G - Past Performance Questionaire.pdf | ||
| Sol_140F0921R0002.pdf | ||
| Attachment E - SF-25A Payment Bond.pdf | ||
| Attachment C - Davis Bacon Wage Determination No. OK20200023 .pdf | ||
| Attachment A - Comanche Specs.pdf | ||
| Attachment F - DI-137 - DOI Release of Claims.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Modifications to Comanche Dam Market Research/Industry Day Presentation
W. W. Wheeler & Associates, Inc.
Schnabel Engineering
Engineering Solutions, LLC August 20, 2020
Presentation Outline Introductions General Project Information Location & Site Access Scope of Work Overview Drawing Review Bid Tab Review Key Specifications
Immersion Vibrated RCC Schedule Informal Questions & Discussion What’s Next
Important Note:
All information, questions and response will be considered informal and market research. A formal USFWS Solicitation is scheduled to be available in September.
Introductions U.S. Fish and Wildlife Services (FWS):
● Ray Fletcher – Contracting Officer
● Dave Hibbs – Contracting Officer Representative
● Brad Iarossi, P.E. – Chief, Dam, Bridge & Seismic Safety Branch
● David Farmer – Wichita Mountains Wildlife Refuge Manager
Engineers and Government Inspector
● Steve Jamieson, P.E. – Project Manager (Engineer of Record)
● Jesse Wullenwaber, P.E. – Project Engineer (Schnabel)
● John Treacy, P.E. – Project Engineer (Wheeler)
● Christine Mugele, P.E. – Hydraulic & Hydrology Engineer (Wheeler)
● Dan Hertel / Dave Hardy – Construction Cost Expert (Engineer Solutions)
● Government Inspector – Representative from Wheeler or Schnabel
Introductions (con’t) Contractors in Attendance:
● NW Construction
● Gears Inc.
● SEMA Construction
● ESCO Construction
● Kiewit Infrastructure So
● Thalle Construction
● Garney Construction
● Barnard Construction Company
● Ames Construction Aggregate Suppliers Used for Schnabel Mix Design: Martin Marietta
General Project Information Project Objective:
● Modify Comanche Dam to address to reduce the risk and hazard associated with the dam
Formal Bidding Schedule:
Solicitation – beta.SAM.gov –September 2020 On-site Pre-bid Meeting – October 2020
Process to be determined due to COVID restrictions
Bid Due Date – November 2020
General Project Information (con’t) Project Construction Schedule:
● November 15, 2020 to April 1, 2020
Comanche Dam Existing Features
1. Concrete gravity dam
2. Constructed in 1934
3. Height: 39 feet
4. Crest Length: 375 feet
5. Crest length: 375 ft
6. Normal Storage: 45 acre-feet
Emergency Spillways
Dam Crest
Combined Service Spillway and Low-level Outlet
Upstream Face
Downstream Face
Grama Dam Existing Features
● Homogeneous Embankment dam
● Constructed in 1936
● Height: 44 ft
● Crest length: 1,044 ft
● Normal Storage: 686 acre-feet
Emergency Spillway
Dam Crest / Access Road
Approx. Low-level Outlet
Emergency Spillway Control SectionRock Quarry
Location & Site Access
Location & Site Access (con’t)
Rock Quarry at Grama Dam
Potential Rock to Use
Comanche Access Road
Comanche Dam
PHOTO 1
PHOTO 2
Comanche Access Road
PHOTO 3
PHOTO 4
Comanche Dam
Comanche Access Road + Staging Area
6PHOTO 5
PHOTO 6
Comanche Dam
Staging Area
Staging Area
Comanche Access Road + Staging Area
PHOTO 7
PHOTO 8
Comanche Dam
PHOTO 9
Staging Area
Staging Area
Staging Area
Main N-S Access Road + Gate
PHOTO 11
Refuge Headquarters
PHOTO 10 Comanche Dam
PHOTO 12
Scope of Work Overview
● Improve and maintain access roads
● Site demolition existing handrails, upstream face ladder, vibrating wire piezometers, outlet works retaining wall, and top 2.9 feet of the center auxiliary spillway crest.
● Protect existing features water level sensor service spillway inlet structure and outlet works slide gate and operator; and left auxiliary spillway section.
● Perform dewatering and water control
● Excavate to bedrock
● Complete cleaning and preparation of the D/S dam face and foundation.
● Slip line and extend the low-level outlet works
● Construct a new downstream RCC buttress from the foundation to the crest of Comanche Dam.
● Reconstruct the center auxiliary spillway crest.
● Install new galvanized handrails and access ladders on the non-overflow crest of Comanche Dam.
Drawing Review
Drawing Review: Site Access, Staging, Stockpiling
Drawing Review: Existing Plan
Drawing Review: Plan of Modifications
Drawing Review: General Sections
Drawing Review: General Sections (con’t)
Immersion Vibrated RCC
• The objective of IV RCC is to have one operation with no separate facing mixes or operations
• Schnabel is finishing a lab mix design this week
• A retarder will be included to minimize cold joints
• Some of the keys to successful IV RCC will be
• Ensuring that the gradation is correct as specified
• Getting the paste content dialed in during the test section
Immersion Vibrated RCC
Click for 3D PDF Version
Drawing Review: Clearing and Grubbing
Drawing Review: Demolition Plan
Protect – Gate Operator / Monitor Equip
Demolish – Handrails Protect –
Benchmark
Demolish – Piezometer, cables and readout box
Demolish – Abandoned LLO and Retaining Wall
Demolish – Access Ladder
Demolish – 2.9 feet of auxiliary spillway
Protect – Left Auxiliary Spillway and Retaining wall
Drawing Review: HDPE Slip-line / Extend
Drawing Review: Excavation Plan
Drawing Review: Dowel Plan
Drawing Review: Joint Drainage Plan
Drawing Review: Details
Bid Tab Review
Key Specifications Section 01 11 00 Summary of Work:
● Fire Insurance coverage for duration of the Project to include all public and private property damage and loss of a minimum of ten million dollars ($10,000,000)
Section 01 14 00 Work Restrictions:
● No Camping or Recreating in Work Site Area
Section 01 31 00 Project Management and Coordination:
● Project Management Submittal with Bid
Proposed Schedule Resumes for Project Manager, Site Superintendent and Safety Officer Resumes for RCC Superintendent and Batch Plant Operator Resumes for Grouting Supervisor
Key Specifications (con’t) Section 01 33 00 Submittals:
Section Name Reference Section
Submittals Required
Due Date or Delivery Time
Project Management and Coordination
01 31 00 Project Management Submittal Submitted with Contractor’s Bid
Construction Progress Documentation
01 32 00 Project Construction Schedule Submitted with Contractor’s Bid
Construction Progress Documentation
01 32 00 Update 3-Week Look-Ahead Schedule
Prior to each weekly Project Progress Meeting
Submittal Procedures 01 33 00 Guarantees, Warranties, Certifications
Before Final Payment
Submittal Procedures 01 33 00 Delivery Tickets Within 24 hours of delivery Safety Procedures 01 35 00 Site Health and Safety Plan Prior to Site Mobilization Regulatory Requirements 01 41 00 Project Permits Prior to Site Mobilization Quality Control 01 45 00 Testing Results Within 1 day of completion Construction Facilities 01 52 00 Pre-Construction Video Within 7 days of Site
Mobilization
Section Name Reference Section
Submittals Required
Due Date or Delivery Time
Construction Facilities 01 52 00 Construction Site Layout Plan Prior to Site Mobilization
Temporary Controls 01 57 00 Temporary Reservoir Control Plan Prior to Site Mobilization Temporary Controls 01 57 00 Dewatering Plan 7 days prior to excavation Reclamation 01 74 00 Reseeding Submittal 30 days prior to start of reseeding Closeout Procedures and Submittals
01 77 00 Project Red-Line Record Drawings Prior to final payment
Surveys 02 21 00 Surveyor Qualifications 10 calendar days prior to survey work
Surveys 02 21 00 Quantity Survey 10 calendar days prior to survey work
Surveys 02 21 00 Survey Field Notes or Electronic Files
The day following field work
Section Name Reference Section
Submittals Required
Due Date or Delivery Time
Surveys 02 21 00 Existing Survey Prior to start of HDPE liner and RCC Work
Surveys 02 21 00 Record Survey Prior to final payment Demolition 02 41 00 Demolition Plan 14 days prior to removing or saw-cutting concrete
Concrete Accessories 03 15 00 Drain Pipe Data 14 days prior to first concrete or RCC placement
Concrete Reinforcing 03 20 00 Concrete Reinforcement Dowels and Drilled Anchors Shop Drawings and Mill Test Reports
14 days prior to fabrication
Cast-in-Place Concrete 03 30 00 Concrete Mix Design 21 days prior to first concrete placement
Cast-in-Place Concrete 03 30 00 Mass Concrete and Dental Concrete Mix Design
21 days prior to first concrete placement
Section Name Reference Section
Submittals Required
Due Date or Delivery Time
Roller Compacted Concrete
03 37 23 RCC Submittal 21 days prior to first RCC placement
Structural Metal Framing 05 10 00 Miscellaneous Metalwork Submittal 21 days prior to fabrication
Erosion and Sedimentation Controls
31 25 00 Stormwater Pollution Prevention Plan
Prior to Site Mobilization
HDPE Outlet Conduit Extension
33 05 33.53 Outlet Conduit Liner Submittal 21 days prior to delivery
Section 01 41 00 Regulatory Requirements:
● The Government is obtaining the following permits for this Project:
A Nationwide 404 Permit from the U.S. Army Corps of Engineers.
A National Environmental Policy Act (NEPA) Categorical Exclusion U.S. Fish and Wildlife Endangered Species Section 7 Clearance State Historical Preservation Office (SHPO) Clearance
● The Contractor is responsible for all federal, local and state permits other than the above. At a minimum will have to provide:
A General Construction Permit (OKR10) for Stormwater Discharge from the
Oklahoma Department of Environmental Quality.
Any Temporary Construction Permits as required by Comanche County.
● No construction permits are required from the Wichita Mountains Wildlife Refuge.
Section 01 45 00 Quality Control:
● Government Testing :
Perform additional laboratory tests on cast-in-place concrete, RCC, and earthwork materials.
Cast in place: Temperature, Slump, Air content, Admixtures, Time of Sample, location, cylinders, truck number, batch ticket RCC Test Section: Perform two field density tests per RCC lift by the nuclear method in accordance with ASTM D2922; set of five 6-inch-diameter RCC cylinders for each RCC lift; Vebe test of the RCC mix prior to each shift;
Concrete Reinforced: Perform inspection of foundation, formwork, and reinforcement placement
● Contractor Testing:
Aggregate Testing: Two (2) tests on proposed source sampled at the stockpile;
Every 500 cubic yards produced.
RCC Test Section: Provide batch tickets for each batch of RCC, or proportions for each 15-minute interval for continuous mix type plants.
Batch Plant: at the beginning of each construction season and at least once per week
Section 01 55 00 Vehicular Access and Parking:
● No clearing, grubbing, or grading in the staging and stockpile areas
● The existing gate entrance to the access road from Highway 49 shall be closed and locked at all times. The contractor shall provide a separate lock to implement a double lock system for access.
● The existing access road travel surface shall be a single lane no wider than fourteen feet.
Section 01 57 00 Temporary Controls:
● Full control of day-to-day operations of outlet works at Grama Lake and Comanche Lake.
Section 01 57 00 Temporary Controls:
Comanche Dam Combined Service spillway and low level
Control Gate for low level outlet
Grama Dam service spillway
Grama Dam low level outlet works control gate tower
Uncontrolled Service Spillway (w/ Trash Rack)
Section 03 20 00 Concrete Reinforcing:
● Perform Tension Tests on at least 10% of the installed dowels in the presence of the Government Inspector, in accordance with ASTM E 488.
● Provide up-to-date calibration records to the Government Inspector prior to each proof test.
● Dowels shall be loaded to 80% of the tensile capacity of the bar.
● Dowels will be considered to have failed if outward movement of anchorage in excess of the calculated elastic elongation of the bar at the test load level occurs and the displacement continues to occur at sustained loading below the tension specified.
Section 03 37 23 Roller-Compacted Concrete:
● RCC Mix Design is currently being tested in the lab, but will be similar this:
● Vebe time between 8-12 seconds
● The RCC mix will be Immersion Vibratory RCC (IVRCC). Contractor shall be aware of the properties of a low Vebe time mix that is retarded from initial set for 18 hours. Formwork and compaction equipment should be selected based on this type of RCC mix.
● Capacity: The mixing, placing, compaction, and cleanup systems shall have a capacity of at least 75 cubic yards per hour average production rate.
● Location: The plant and aggregate stockpiles shall be in areas jointly established by the Contractor, Contracting Officer’s Representative, and Government Inspector in the field.
● A continuous mix plant shall be set up on-site or near the site and be capable of producing a uniform continuous
● Internal immersion-type vibrators shall be used to consolidate the RCC against surfaces and to mix the grout with the uncompacted RCC where grout enriched is called out.
● 90 compressive strength of RCC < 3,000 psi
● Engineer will perform nuclear density tests, Vebe time tests, and will prepare RCC test cylinders for comparison with the RCC Mix Design Report.
● RCC temperatures between 40 degrees and 70 degrees.
● Structural concrete: 4,500 psi at 28 days
● Mass concrete: 2, 000 psi at 28 days
Schedule
Informal Questions and Discussions
What’s Next ?
● Look for the Solicitation Next Month
| Modifications to Comanche Dam � Market Research/Industry Day Presentation |
| Presentation Outline |
| Introductions |
| Introductions (con’t) |
| General Project Information |
| General Project Information (con’t) |
| Comanche Dam Existing Features |
| Grama Dam Existing Features |
| Location & Site Access |
| Location & Site Access (con’t) |
| Location & Site Access (con’t) |
| Location & Site Access (con’t) |
| Location & Site Access (con’t) |
| Location & Site Access (con’t) |
| Location & Site Access (con’t) |
| Location & Site Access (con’t) |
| Scope of Work Overview |
| Drawing Review |
| Drawing Review: Site Access, Staging, Stockpiling |
| Drawing Review: Existing Plan |
| Drawing Review: Plan of Modifications |
| Drawing Review: General Sections |
| Drawing Review: General Sections (con’t) |
| Immersion Vibrated RCC |
| Immersion Vibrated RCC |
| Drawing Review: General Sections (con’t) |
| Drawing Review: General Sections (con’t) |
| Drawing Review: Clearing and Grubbing |
| Drawing Review: Demolition Plan |
| Drawing Review: HDPE Slip-line / Extend |
| Drawing Review: HDPE Slip-line / Extend |
| Drawing Review: HDPE Slip-line / Extend |
| Drawing Review: Excavation Plan |
| Drawing Review: Dowel Plan |
| Drawing Review: Joint Drainage Plan |
| Drawing Review: Details |
| Drawing Review: Details |
| Drawing Review: Details |
| Bid Tab Review |
| Key Specifications |
| Key Specifications (con’t) |
| Key Specifications (con’t) |
| Key Specifications (con’t) |
| Key Specifications (con’t) |
| Key Specifications (con’t) |
| Key Specifications (con’t) |
| Key Specifications (con’t) |
| Key Specifications (con’t) |
| Key Specifications (con’t) |
| Key Specifications (con’t) |
| Key Specifications (con’t) |
| Key Specifications (con’t) |
| Schedule |
| Informal Questions and Discussions |
| What’s Next ? |