This document contains an attachment providing a cost breakdown template for a design-build project solicitation to replace cooling towers at a Department of Veterans Affairs medical center. The solicitation will provide for all design and construction services to install two new cooling towers, associated piping, equipment including pumps, valves, flow meters, and HVAC controls. The work location is at the Orlando VA Healthcare System Lake Baldwin campus. The estimated completion period is 360 calendar days from notice to proceed. The project value is between $1 million to $5 million. It is a 100% SDVOSB set-aside with a NAICS code of 236220 and size standard of $39.5 million. The solicitation using a trade-off source selection process will be issued on or around July 21, 2021. Interested firms must be registered in SAM and VetBiz by the time of proposal submission. The selected contractor is expected to comply with environmental laws and policies and incorporate pollution prevention and waste minimization.
The cost breakdown template includes divisions for general requirements through transportation and site work, with columns for labor costs, material costs, and totals by division and in aggregate without values. Overhead, profit, and bond percentages are included but not applied in the template.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Base Offer Cost Breakdown
Project Number:
Date:
Project Title
Project Location
Offeror Name
Offeror Street
Offeror City State Zip
Item Description Labor Cost Material Cost Total Cost
Division 1 General Requirements $ - $ - $ -
Division 2 Existing Conditions - - -
Division 3 Concrete - - -
Division 4 Masonry - - -
Division 5 Metals - - -
Division 6 Wood and Plastic - - -
Division 7 Thermal & Moisture Protect - - -
Division 8 Doors and Windows - - -
Division 9 Finishes - - -
Division 10 Specialties - - -
Division 11 Equipment - - -
Division 12 Furnishings - - -
Division 13 Special Construction - - -
Division 14 Conveying Equipment - - -
Division 21 Fire Suppression - - -
Division 22 Plumbing - - -
Division 23 HVAC - - -
Division 26 Electrical - - -
Division 27 Communications - - -
Division 28 Electronic Safety & Security - - -
Division 31 Earthwork - - -
Division 32 Exterior Improvements - - -
Division 33 Utilities - - -
Division 34 Transportation Subtotal - - -
ATTACHMENT H
Division Subtotals : $ - $ - $ -
Overhead % 0.00% -
Profit % 0.00% -
Bond % 0.00% -
Overhead/Profit Subtotals : $ -
Total Base Offer Cost $ - $ - $ -