This document is a Contract Data Requirements List (CDRL) for the LOGEN II Support Services contract, detailing 12 data items (A001-A012) to be delivered by the contractor. The data items include:
A001: Briefing Materials Summary Report, A002: Meeting Minutes, A003: Scientific and Technical Reports, A004: Technical Directives, A005: Developmental Design Drawings/Models, A006: Software Product Specification, A007: Logistics Product Data, A008: Technical Report Studies, A009: Electromagnetic Environmental Effects Integration Report, A010: Failure Summary & Analysis Report, A011: Technical Directive Compliance Support, and A012: Technical Manuals and Maintenance Workload Standards. Each data item has specific submission requirements, including quarterly or as-required frequency, electronic delivery via email in MS Office format, and distribution to various government personnel. The documents are to be delivered to Fleet Readiness Center locations in the East, Southeast, and Southwest regions, with strict instructions to avoid sending classified materials to the Contracting Officer's Representative (COR).
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Statement of Work.Rv1.pdf | ||
| P6_Cost_Summary Spreadsheet.Rv1.xlsx | XLSX spreadsheet | |
| N6852025R0001_Final RFP_LOGEN II_AMEND 0002.pdf | ||
| Attachment Exhibit A CDRLs.Rv1.pdf | ||
| Final RFP N6852025R0001_QandA Part 1Answers_6.6.25.pdf | ||
| N6852025R0001_Final RFP_LOGEN II_AMEND 0001.pdf | ||
| Attachment P1-Final RFP N6852025R0001_QandA.xlsx | XLSX spreadsheet | |
| N6852025R0001_Final RFP_LOGEN II.pdf | ||
| GFPAttachment.xlsx | XLSX spreadsheet | |
| B-1 Composite Rates_final RFP.xlsx | XLSX spreadsheet | |
| Att L-1 Vol 1 KA Tables.xlsx | XLSX spreadsheet | |
| Att L-2 Vol 3 PPQ.docx | DOCX document | |
| Att L-3 Vol 3 PP-2 Con Data.xlsx | XLSX spreadsheet | |
| Attachment Exhibit B- DD1423 LOGEN II Draft CDRLs B001-B006.pdf | ||
| DD 254.pdf | ||
| LOGEN II SOW final.pdf | ||
| Attachment P7_ Annual Fully Burdened Labor .xlsx | XLSX spreadsheet | |
| Attachment P6_Cost_Summary Spreadsheet.xlsx | XLSX spreadsheet |
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item)
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
0014 A TDP TM OTHER MGMT
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
Logistics and Engineering II (LOGEN II) Support Services
N68520-TBD TBD
1. DATA ITEM
NO.
2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE
GROUP
A001 Briefing Materials Summary Report
4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18.
ESTIMATED
TOTAL
PRICE
DI-MGMT-81605 SOW 3.1.3; 3.3.6.2; 3.4.14.23; FST SITE SUPPORT LOCATIONS
FRC-E, SE, AND SW
INSERT IN
SECTION B
7. DD 250
REQ
9.DIST
STATEMENT
REQUIRED
10. FREQUENCY 12. DATE OF FIRST
SUBMISSION
14. DISTRIBUTION
NO ASREQ SEE BLK 16 b. COPIES
8. APP CODE SEE BLOCK 16 11. AS OF DATE 13. DATE OF
SUBSEQUENT
SUBMISSION
a.
ADDRESSEE
Draft
Final
N/A N/A SEE BLK 16
Reg
Repro
16. REMARKS:
BLOCK 4 – Contractor format is acceptable, using Microsoft office tools as required (for example, MS Power Point presentations).
BLOCK 9: A distribution statement is required and shall be obtained from the government by the contractor in individual task orders for delivery of the data item as required.
BLOCK 12 & 13: Submit draft within 5 to 10 business days, as required by the government, in individual task orders. Final submission within 5 days of governments draft review and receipt of comments.
BLOCK 14 – See Clause FTXT.247-9505 TECHNICAL DATA AND INFORMATION (NAVAIR) (FEB 1995) in Section F FOR ELECTRONIC DELIVERY ADDRESSES.
Deliver Electronically Via Email In MS Office or Compatible Format
* The Office of the COR is NOT to receive any CLASSIFIED material*
COR
ACOR
(AS APPLICABLE)
TPOC
TOCOR
(AS APPLICABLE)
15. TOTAL
G. PREPARED BY H. DATE
I. APPROVED BY
J. DATE
DD Form 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USE
DD Form 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USE
(1 Data Item)
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE
ITEM NO.
B. EXHIBIT C. CATEGORY:
0014 A TDP TM OTHER ADMIN
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
LOGEN II Support Services N68520-TBD TBD
1. DATA
ITEM NO.
2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE
GROUP
A002 Meeting Minutes Conference/Meeting Minutes
4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18.
ESTIMATE
D TOTAL
PRICE
DI-ADMN-81250C SOW 3.1.2.4; 3.1.3; 3.4.14.23 FRC SITE SUPPORT LOCATIONS FRC-E, SE, AND
SW
INSERT IN
SECTION B
7. DD
250 REQ
9.DIST
STATEMEN
T
REQUIRED
10.
FREQUENCY
12. DATE OF FIRST
SUBMISSION
14. DISTRIBUTION
NO ASREQ SEE BLOCK 16 b. COPIES
8. APP
CODE
D 11. AS OF
DATE
13. DATE OF
SUBSEQUENT
SUBMISSION
a.
ADDRESSEE
Draft
Final
BLOCK 4: DID requirement item 2 contractor format, compatible with government applications, is acceptable with government approval.
BLOCK 9 – Distribution authorized to Department of Defense and U.S. DoD contractors only to protect technical or operational data or information from automatic dissemination under the international exchange program or by other means. This protection covers publications required solely for official use or strictly for administrative or operational purposes. This statement may apply to manuals, pamphlets, technical orders, technical reports, and other publications containing valuable technical or operational data. 19 Dec 2022. Other requests for this document shall be referred to, Commanding Officer, Fleet Readiness Centers, 47038 McLeod Rd., Bldg. 447, Patuxent River, MD 20670.
BLOCKS 10, 12 & 13: ASREQ when meetings held requiring meeting minutes, then submit on the 10th calendar day of each month. If the 10th falls on a weekend or holiday, the date of submission is the next regular business day.
BLOCK 14 – See Clause FTXT.247-9505 TECHNICAL DATA AND INFORMATION (NAVAIR) (FEB 1995) in Section F FOR
ELECTRONIC DELIVERY ADDRESSES.
Deliver Electronically Via Email In MS Office or Compatible Format
* The Office of the COR is NOT to receive any CLASSIFIED material*
COR
ACOR
(AS APPLICABLE)
TPOC
TOCOR
(AS APPLICABLE)
G. PREPARED BY
H. DATE
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
0014 A TDP TM OTHER MISC
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
LOGEN II Support Services N68520-TBD TBD
1. DATA ITEM
NO.
2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP
A003 Scientific and Technical Reports Scientific and Technical Reports
4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
TOTAL PRICE
DI-MISC-80711A SOW 3.1.3; 3.3.3; 3.3.4.5; 3.3.9;
3.3.9.2; 3.3.9.3; 3.3.9.4; 3.3.11
FRC SITE SUPPORT LOCATIONS FRC-
E, SE, AND SW
INSERT IN
SECTION B
7. DD 250
REQ
9.DIST
STATEMENT
REQUIRED
10. FREQUENCY 12. DATE OF FIRST
SUBMISSION
14. DISTRIBUTION
NO ASREQ SEE BLK 16 b. COPIES
8. APP
CODE
SEE BLOCK 16 11. AS OF DATE 13. DATE OF
SUBSEQUENT
SUBMISSION
a. ADDRESSEE Draft
Final
BLOCK 4: Tailored content requirements: Engineering Change Proposals (ECPs) provide engineering analysis and / Or Technical Studies that propose solutions for task order requirements.
BLOCK 9: A distribution statement is required and shall be obtained from the government by the contractor in individual task orders for delivery of the data as required.
BLOCKS 12 & 13: In individual task orders, submit draft within 30 days from governments request date, and final submission as soon as allocable and NLT 30 days of governments draft review and receipt of comments.
BLOCK 14 – See Clause FTXT.247-9505 TECHNICAL DATA AND INFORMATION (NAVAIR) (FEB 1995) in Section F FOR ELECTRONIC
DELIVERY ADDRESSES.
* The Office of the COR is NOT to receive any CLASSIFIED material*
(AS APPLICABLE)
TPOC
TOCOR
(AS APPLICABLE)
DD Form 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
0014 A TDP TM OTHER X
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
LOGEN II Support Services N68520-TBD TBD
1. DATA ITEM
NO.
2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE
GROUP
A004
Technical Directives (TD)
Technical Directives (TD) in support of bulletins, Rapid Action Minor Engineering Changes (RAMECs) and Engineering Change Proposals (ECPs)
5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18.
ESTIMATED
TOTAL
PRICE
DI-SESS-81269D SOW 3.1.3; 3.3.9.5 FRC SITE LOCATIONS FRC-E, SE, AND SW INSERT IN
SECTION B
7. DD 250
REQ
9.DIST
STATEMENT
REQUIRED
10. FREQUENCY 12. DATE OF FIRST
SUBMISSION
14. DISTRIBUTION
NO ASREQ SEE BLK 16 b. COPIES
8. APP CODE SEE BLOCK 16 11. AS OF DATE 13. DATE OF
SUBSEQUENT
SUBMISSION
a. ADDRESSEE Dra ft
Final
BLOCK 4: Tailored content requirements
DID REQUIREMENTS ITEM 2 (FORMAT) – Contractor format is acceptable, pending government approval.
DID REQUIREMENTS ITEM 3 (CONTENT) – Delivery shall consist of various technical documents, as required, including: reports, plans, studies and analyses, training material, assessments, briefings, strategies, budgeting and cost estimates, POA&MS, etc.
BLOCK 9: A distribution statement is required and shall be obtained from the government by the contractor in individual task orders for delivery of the data as required.
BLOCKS 12 & 13: In individual task orders, submit draft within 30 days from governments request date, and final submission as soon as allocable and NLT 30 days of governments draft review and receipt of comments.
BLOCK 14 – See Clause FTXT.247-9505 TECHNICAL DATA AND
* The Office of the COR is NOT to receive any CLASSIFIED material. **
COR
ACOR
(AS APPLICABLE)
TPOC
TOCOR
(AS APPLICABLE)
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE-ITEM NO. B. EXHIBIT C. CATEGORY:
0014 A TDP TM OTHER X
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
LOGEN II Support Services N68520-TBD TBD
1. DATA ITEM
NO.
2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE
GROUP
A005 Developmental Design Drawings/Models and Associated Lists
Developmental Drawings /Models and Associated Lists
5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18.
ESTIMATED
TOTAL
PRICE
DI-SESS-81002F SOW 3.1.3; 3.3.1; 3.3.5; 3.3.6.1;
3.3.22.2; 3.4.14.38
FRC SITE LOCATIONS FRC-E, SE, AND
SW
INSERT IN
SECTION B
7. DD 250
REQ
9.DIST
STATEMENT
REQUIRED
10. FREQUENCY 12. DATE OF FIRST
SUBMISSION
14. DISTRIBUTION
NO ASREQ SEE BLK 16 b. COPIES
8. APP
CODE
SEE BLOCK 16 11. AS OF DATE 13. DATE OF
SUBSEQUENT
SUBMISSION
a. ADDRESSEE Draft
Final
BLOCK 4: Tailored content requirements
Did requirements item 3 (format) – the contractor format or the governments format as specified on the TDP option selection worksheet incorporated into the task order.
Did requirements item 4 (content) – Delivery shall consist of developmental design drawings / models and associated lists that define an engineering design approach in detail.
government by the contractor in individual task orders for delivery of the data.
BLOCKS 12 & 13: In individual task orders, submit draft within 30 days from governments request date, and final submission as soon as allocable and NLT 30 days of governments draft review and receipt of comments.
BLOCK 14 – See Clause FTXT.247-9505 TECHNICAL DATA AND
(AS APPLICABLE)
TPOC
TOCOR
(AS APPLICABLE)
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
0014 A TDP TM OTHER X
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
LOGEN II Support Services N68520-TBD TBD
1. DATA ITEM
NO.
2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE
GROUP
A006 Software Product Specification (SPS) Scientific and Technical Report (Software Product Specification (SPS)
5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18.
ESTIMATED
TOTAL
PRICE
DI-IPSC-81441A SOW 3.1.3; 3.1.16 FRC SITE LOCATIONS FRC-E, SE, AND
SW
INSERT IN
SECTION B
7. DD 250
REQ
9.DIST
STATEMENT
REQUIRED
10. FREQUENCY 12. DATE OF FIRST
SUBMISSION
14. DISTRIBUTION
NO AS REQ SEE BLK 16 b. COPIES
8. APP
CODE
SEE BLOCK 16 11. AS OF DATE 13. DATE OF
SUBSEQUENT
SUBMISSION
a. ADDRESSEE Draft
Final
BLOCK 4: Tailored content requirements IAW security SOW sections 3.2-3.2.7.2;
and requirement SOW sections 3.1.16; 3.3 through 3.4.20.6
Did requirements item 3. (format) – Contractor format is acceptable, pending government approval.
Did requirements item 4. (content) – Delivery shall be IAW with CDRL paragraph 4 and/or special instructions as required in individual task orders.
BLOCK 9: A distribution statement is required and shall be obtained from the government by the contractor in individual task orders for delivery of the data.
Other requests for this document shall be referred to Commanding Officer, Fleet Readiness Centers, 47038 McLeod rd., Bldg. 447, Patuxent River, MD 20670.
BLOCKS 12 & 13: In individual task orders, submit draft within 30 days from governments request date, and final submission as soon as allocable and NLT 30 days of governments draft review and receipt of comments.
BLOCK 14 – See Clause FTXT.247-9505 TECHNICAL DATA AND INFORMATION (NAVAIR) (FEB 1995) in Section F FOR ELECTRONIC
DELIVERY ADDRESSES.
Deliver Electronically Via Email In MS Office or Compatible Format
* The Office of the COR is NOT to receive any CLASSIFIED material. **
COR
ACOR (AS
APPLICABLE)
TPOC
TOCOR (AS
APPLICABLE)
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
0014 A TDP TM OTHER X
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
LOGEN II Support Services N68520-TBD TBD
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP
A007 LOGISTICS PRODUCT DATA LOGISTICS PRODUCT DATA
4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
TOTAL PRICE
SAE-GEIA-STD-0007 SOW SECTION: 3.4.1.8; 3.4.4.2 FRC SITE LOCATIONS FRC-E, SE, AND
SW
INSERT IN
SECTION B
7. DD 250
REQ
9.DIST
STATEMENT
REQUIRED
10. FREQUENCY 12. DATE OF FIRST
SUBMISSION
14. DISTRIBUTION
NO ASREQ SEE BLK 16 b. COPIES
8. APP CODE SEE BLOCK 16 11. AS OF DATE 13. DATE OF
SUBSEQUENT
SUBMISSION
a. ADDRESSEE Draft
Final
16. REMARKS: Reserved
Other requests for this document shall be referred to Commanding Officer, Fleet Readiness Centers, 47038 McLeod rd., Bldg. 447, Patuxent River, MD 20670.
BLOCKS 12 & 13: In individual task orders, submit on a Quarterly basis on a 90-day cycle from the government’s request date.
BLOCK 14 – See Clause FTXT.247-9505 TECHNICAL DATA AND
COR
ACOR
(AS APPLICABLE)
TPOC
TOCOR
(AS APPLICABLE)
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
0014 A TDP TM OTHER MISC
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
LOGEN II Support Services N68520-TBD TBD
1. DATA ITEM
NO.
2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE
GROUP
A008 Technical Report Studies-Study/Services Technical Report Studies
4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18.
ESTIMATED
TOTAL
PRICE
DI-MISC-80508B SOW 3.3.9; 3.3.14; 3.3.15; 3.3.16;
3.3.18.1;
FRC SITE LOCATIONS FRC-E, SE, AND
SW
INSERT IN
SECTION B
7. DD 250
REQ
9.DIST
STATEMENT
REQUIRED
10. FREQUENCY 12. DATE OF FIRST
SUBMISSION
14. DISTRIBUTION
NO AS REQ SEE BLK 16 b. COPIES
8. APP
CODE
SEE BLOCK 16 11. AS OF DATE 13. DATE OF
SUBSEQUENT
SUBMISSION
a. ADDRESSEE Draft
Final
BLOCK 4: Tailored content requirements
DID requirements paragraph 2 (format) – contractor format is acceptable, pending government approval.
DID requirements paragraph 3 (content) – delivery shall consist of various technical documents, as required, including: courseware materials, reports, plans, studies and analyses, instructor training materials, assessments, strategies, etc. As required by the task order.
BLOCK 9: A Distribution statement is required and shall be obtained from the government by the contractor in individual task orders for delivery of the data.
Other requests for this document shall be referred to Commanding Officer, Fleet Readiness Centers, 47038 McLeod rd., Bldg. 447, Patuxent River, MD 20670.
BLOCKS 12 & 13: In individual task orders, submit draft within 30 days from governments request date, and final submission as soon as allocable and NLT 30 days of governments draft review and receipt of comments.
BLOCK 14 – See Clause FTXT.247-9505 TECHNICAL DATA AND INFORMATION (NAVAIR) (FEB 1995) in Section F FOR ELECTRONIC
DELIVERY ADDRESSES.
Deliver Electronically Via Email In MS Office or Compatible Format
* The Office of the COR is NOT to receive any CLASSIFIED material. *
COR
ACOR
(AS APPLICABLE)
TPOC
TOCOR
(AS APPLICABLE)
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
0014 A TDP TM OTHER X
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
LOGEN II Support Services N68520-TBD TBD
1. DATA ITEM
NO.
2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE
GROUP
A009 Electromagnetic Environmental Effects (E3) Integration and Analysis Report (E31AR)
Electromagnetic Interference/Electrostatic Discharge/ Controls
5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18.
ESTIMATED
TOTAL
PRICE
DI-EMCS-81540B SOW 3.1.3; 3.3.14; 3.3.15; 3.3.16;
3.3.17; 3.4.14.14
FRC site locations FRC-E, SE, and SW INSERT IN
SECTION B
7. DD 250
REQ
9.DIST
STATEMENT
REQUIRED
10. FREQUENCY 12. DATE OF FIRST
SUBMISSION
14. DISTRIBUTION
NO ASREQ see blk 16 b. COPIES
8. APP CODE See Block 16 11. AS OF DATE 13. DATE OF
SUBSEQUENT
SUBMISSION
a. ADDRESSEE Draft
Final
N/A N/A see blk 16
BLOCK 4: tailored content requirements
DID requirements item 2 (format) – Contractor format is acceptable, pending government approval.
DID requirements item 3 (content) –IAW CDRL paragraphs 3.1 through 3.3 and/or additional specific requirements outlined in individual task orders.
BLOCK 9: a distribution statement is required and shall be obtained from the government by the contractor in individual task orders for delivery of the data.
Other requests for this document shall be referred to Commanding Officer, Fleet Readiness Centers, 47038 McLeod rd., Bldg. 447, Patuxent River, MD 20670.
BLOCKS 12 & 13: In individual task orders, submit draft within 30 days from governments request date, and final submission as soon as allocable and NLT 30 days of governments draft review and receipt of comments.
(AS APPLICABLE)
TPOC
TOCOR
(AS APPLICABLE)
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
0014 A TDP TM OTHER X
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
LOGEN II Support Services N68520-TBD TBD
1. DATA ITEM
NO.
A010
Failure Summary & Analysis Report
Failure Summary & Analysis Report
5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
TOTAL PRICE
DI-SESS-80255B SOW 3.1.3 FRCSITE LOCATIONS FRC-E, SE, AND
SW
INSERT IN
SECTION B
7. DD 250
REQ
9.DIST
STATEMENT
REQUIRED
10. FREQUENCY 12. DATE OF FIRST
SUBMISSION
14. DISTRIBUTION
NO AS REQ SEE BLK 16 b. COPIES
8. APP
CODE
SEE BLOCK 16 11. AS OF DATE 13. DATE OF
SUBSEQUENT
SUBMISSION
a. ADDRESSEE Draft
Final
BLOCK 4: Tailored content requirements
IAW sow section 3.5.13.1 the contractor shall present a summary of the R&M data collected under fracas at the scheduled program reviews as required and specified in the individual task orders.
DID requirements item 2 (format) – Contractor format is acceptable, pending government approval.
DID requirements item 3 (content) – Summarize the results of the contractor’s failure reporting, analysis, and corrective action system (fracas) implementation required by the statement of work, and shall include a cumulative tabulation of failure data.
BLOCK 9: A distribution statement is required and shall be obtained from the government by the contractor in individual task orders for delivery of the data.
Other requests for this document shall be referred to Commanding Officer, Fleet Readiness Centers, 47038 McLeod rd., Bldg. 447, Patuxent River, MD 20670.
BLOCKS 12 & 13: In individual task orders, submit draft within 30 days from governments request date, and final submission as soon as allocable and NLT 30 days of governments draft review and receipt of comments.
COR
ACOR
(AS APPLICABLE)
TPOC
TOCOR
(AS APPLICABLE)
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302.
Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
0014 A TDP TM OTHER X
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
LOGEN II Support Services N68520-TBD TBD
1. DATA ITEM
NO.
A011
TECHNICAL DIRECTIVE COMPLIANCE SUPPORT
SOURCE DATA DEVELOPMENT
5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
TOTAL PRICE
DI-MGMT-80224D SOW 3.1.3; 3.3; 3.4 FRCSITE LOCATIONS FRC-E, SE,
AND SW
INSERT IN
SECTION
B
7. DD 250
REQ
9.DIST
STATEMENT
REQUIRED
10. FREQUENCY 12. DATE OF FIRST
SUBMISSION
14. DISTRIBUTION
NO
ASREQ
SEE BLK 16 b. COPIES
8. APP
CODE
SEE BLK 16 11. AS OF DATE 13. DATE OF SUBSEQUENT
SUBMISSION
a. ADDRESSEE Dra ft
Final
Other requests for this document shall be referred to Commanding Officer, Fleet Readiness Centers, 47038 McLeod rd., Bldg. 447, Patuxent River, MD 20670.
BLOCKS 12 & 13: In individual task orders, submit on a Quarterly basis on a 90-day cycle from the government’s request date.
BLOCK 14 – See Clause FTXT.247-9505 TECHNICAL DATA AND INFORMATION (NAVAIR) (FEB 1995) in Section F FOR ELECTRONIC DELIVERY ADDRESSES.
Cover Letter Only To COR / TOCOR, Deliver Electronically Via Email In MS Office or Compatible Format.
* The Office of the COR is NOT to receive any CLASSIFIED material. **
COR
ACOR
(AS APPLICABLE)
TPOC
TOCOR
(AS APPLICABLE)
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
0014 A TDP TM OTHER X
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
LOGEN II Support Services N68520-TBD TBD
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP
A012 MANUALS, TECHNICAL – INSPECTION AND
MAINTENANCE REQUIREMETNS; INSPECTION WORK
CARDS; AND CHECKLISTS; PREPARATION OF
SCHEDULED MAINTENANCE
WORKLOAD STANDARDS (WLS)
4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
TOTAL PRICE
MIL-DTL-5096J SOW SECTION: 3.4.10.6 FRC SITE LOCATIONS FRC-E, SE, AND
SW
INSERT IN
SECTION B
7. DD 250
REQ
9.DIST
STATEMENT
REQUIRED
10. FREQUENCY 12. DATE OF FIRST
SUBMISSION
14. DISTRIBUTION
NO ASREQ SEE BLK 16 b. COPIES
8. APP CODE SEE BLOCK 16 11. AS OF DATE 13. DATE OF
SUBSEQUENT
SUBMISSION
a. ADDRESSEE Draft
Final
16. REMARKS: Reserved
Other requests for this document shall be referred to Commanding Officer, Fleet Readiness Centers, 47038 McLeod rd., Bldg. 447, Patuxent River, MD 20670.
BLOCKS 12 & 13: In individual task orders, submit on a Quarterly basis on a 90-day cycle from the government’s request date.
COR
ACOR
(AS APPLICABLE)
TPOC
TOCOR
(AS APPLICABLE)
STRUCTIONS FOR COMPLETING DD
FORM 1423
(See DoD 5010.12-M for detailed instructions.)
FOR GOVERNMENT PERSONNEL
Item A. Self-explanatory.
Item B. Self-explanatory.
Item C. Mark (X) appropriate category: TDP - Technical Data Package; TM - Technical Manual; Other - other category of data, such as "Provisioning," "Configuration Management," etc.
Item D. Enter name of system/item being acquired that data will support.
Item E. Self-explanatory (to be filled in after contract award). Item
F. Self-explanatory (to be filled in after contract award). Item G.
Signature of preparer of CDRL.
Item H. Date CDRL was prepared.
Item I. Signature of CDRL approval authority.
Item J. Date CDRL was approved.
Item 1. See DoD FAR Supplement Subpart 4.71 for proper numbering.
Item 2. Enter title as it appears on data acquisition document cited in Item 4.
Item 3. Enter subtitle of data item for further definition of data item (optional entry).
Item 4. Enter Data Item Description (DID) number, military specification number, or military standard number listed in DoD 5010.12-L (AMSDL), or one-time DID number, that defines data content and format requirements.
Item 5. Enter reference to tasking in contract that generates requirement for the data item (e.g., Statement of Work paragraph number).
Item 6. Enter technical office responsible for ensuring adequacy of the data item.
Item 7. Specify requirement for inspection/acceptance of the data item by the Government.
Item 8. Specify requirement for approval of a draft before preparation of the final data item.
Item 9. For technical data, specify requirement for contractor to mark the appropriate distribution statement on the data (ref. DoDD 5230.24).
Item 10. Specify number of times data items are to be delivered.
Item 11. Specify as-of date of data item, when applicable.
Item 12. Specify when first submittal is required.
Item 13. Specify when subsequent submittals are required, when applicable.
Item 14. Enter addressees and number of draft/final copies to be delivered to each addressee. Explain reproducible copies in Item 16.
Item 15. Enter total number of draft/final copies to be delivered.
Item 16. Use for additional/clarifying information for Items 1 through 15. Examples are: Tailoring of documents cited in Item 4; Clarification of submittal dates in Items 12 and 13; Explanation of reproducible copies in Item 14.; Desired medium for delivery of the data item.
FOR THE CONTRACTOR
Item 17. Specify appropriate price group from one of the following groups of effort in developing estimated prices for each data item listed on the DD Form 1423.
a. Group I. Definition - Data which is not otherwise essential to the contractor's performance of the primary contracted effort (production, development, testing, and administration) but which is required by DD Form 1423.
Estimated Price - Costs to be included under Group I are those applicable to preparing and assembling the data item in conformance with Government requirements, and the administration and other expenses related to reproducing and delivering such data items to the Government.
b. Group II. Definition - Data which is essential to the performance of the primary contracted effort but the contractor is required to perform additional work to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, or quality of the data item.
Estimated Price - Costs to be included under Group II are those incurred over and above the cost of the essential data item without conforming to Government requirements, and the administrative and other expenses related to reproducing and delivering such data item to the Government.
c. Group III. Definition - Data which the contractor must develop for his internal use in performance of the primary contracted effort and does not require any substantial change to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, and quality of the data item.
Estimated Price - Costs to be included under Group III are the administrative and other expenses related to reproducing and delivering such data item to the Government.
d. Group IV. Definition - Data which is developed by the contractor as part of his normal operating procedures and his effort in supplying these data to the Government is minimal.
Estimated Price - Group IV items should normally be shown on the DD Form 1423 at no cost.
Item 18. For each data item, enter an amount equal to that portion of the total price which is estimated to be attributable to the production or development for the Government of that item of data.
These estimated data prices shall be developed only from those costs which will be incurred as a direct result of the requirement to supply the data, over and above those costs which would otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not include any amount for rights in data.
The Government's right to use the data shall be governed by the pertinent provisions of the contract.