Attachment D - SP-POL-CMP-INSPECT-FY25-BAR Tank 5932 - Monthly Contractors Progress Report.xlsx

XLSX spreadsheet 212 KB Posted

Attached to
API 653 Fuel Tank Inspection, Barksdale AFB, LA
Solicitation number
W9128F25Q0008
Issued by

About this file

This document is a Monthly Contractors Progress Report for an API 653 Tank Inspection project at Barksdale AFB, LA. The key details are:

The U.S. Army Corps of Engineers (USACE) has a requirement to conduct an API Internal inspection on Facility #5932 at Barksdale AFB, LA in accordance with all applicable laws, standards, and regulations. This is for Solicitation #W9128F25Q0008. The report provides updates on the status and schedule of the inspection activities, including percentage of work completed, inspection dates, and report delivery. The report also includes a lessons learned section to capture key takeaways that can be applied to future similar projects. No pricing terms, set asides, or incumbent details are provided in this specific document.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Executive Summary Program Reporting Period: to

Program Manager: Adam Ashton

1. Executive Summary
Overall Task Order(s) Status:

Key Accomplishments:

Concerns:

Month look ahead:

&"Arial Black,Regular"&18 Tank Inspection Management Report &G

Status Schedule

2. Status/Schedule
ServiceSite CodeInstallationFacilityType of Inspection% Comp.Task Order Award DateWork Plan / HASP SubmittedSite Coordination/Kick-Off Meeting DateInspection Due DateInspection ScheduledOOS DateInspection completeReturn to ServiceReport DueDRAFT Report DistributedFINAL Report DistributedRecom'd Next Inspection DatePOP ExpirationUSACE PMContractor PM

Lessons Learned

3. Lessons Learned:
Use this section to highlight key lessons and how they can be applied to this or other similar projects/programs in future. Note that this section should not repeat the specific action points summarized in the Executive Summary (Section 1). Instead, it should highlight lessons to inform organizational learning for this and similar projects/programs in the future.
1
2
3

image1.png

File details come from the government source that posted it. Updated .