This is an Independent Government Cost Estimate (IGCE) price-cost schedule for a firm fixed price contract to replace the Electric Motor Control Center at a FEMA Region 6 facility. The solicitation number is 70FBR626R00000021, issued by the Federal Emergency Management Agency. The project scope includes replacing the facility's aging Electrical Main Panel to ensure operational continuity, safety, and regulatory compliance while addressing critical reliability issues and modernizing infrastructure.

The cost estimate template itemizes labor and materials components including journeymen electricians, foreman/site supervisor oversight, materials and parts, environmental compliance and disposal, safety oversight and regulatory compliance, and project management and documentation. However, the specific line item costs and total firm fixed price are not populated in the provided spreadsheet—all estimated unit costs display as $0.00, indicating this is a blank template prepared by the FEMA Region 6 MSD/ASB program office with contact Raymond Hixon Jr. The contract structure is firm fixed price, though this particular document serves as the government's baseline cost estimate rather than the contractor's pricing proposal.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Table 1

RFP- 70FBR626R00000019- Electric Motor Control Center Replacement
Independent Government Cost Estimate
Component: FEMA Region 6 - MSD/ASBPrepared by:
Program/Project Title: Electric Panel/Motor ControlPhone Number/Email:
Item DescriptionPart Number/ ID NumberQuantityUnit of Issue*Estimated Unit Cost*Estimated Fixed Price Per Line Item
Materials & Parts1ea
Labor, Journeymen Electricians1ea
Labor, Foreman/Site Supervisor1ea
Environmental Compliance & Disposal1ea
Safety Oversight & Regulatory Compliance1ea
Project Management & Documentation1ea
1ea
$0.00
$0.00
$0.00
$0.00
$0.00
Estimated Total Firm Fixed Price