ATTACHMENT D MATERIAL PRICE ADJUSTMENT SHEET AND EXAMPLE (2).pdf

PDF 2 MB Posted

Attached to
1941-27-R-IFBD-00012
Solicitation number
3160008308
Issued by
Mississippi

About this file

This is a Material Price Adjustment Worksheet form from the Mississippi Department of Transportation (MDOT) used to document fuel and material price adjustments for state transportation contracts. The form is designated CSD-881 and is completed by site managers to correct fuel adjustment entries when data entry errors occur during contract performance. The worksheet captures project-specific information including project number, county, material type, contract base price, estimated period, and price differential calculations. The example provided references project HISP-0022-00(023) in Jasper County for the period July 1, 2017 through July 28, 2017, involving AC-30 asphalt material with a contract base price of $3.1258 per unit and an adjusted period price of $3.3253 per unit, reflecting a price differential of $0.1995.

The example worksheet details two line items for Hot Mix asphalt: 10,000 tons of 12.5mm material at $0.055 per ton totaling $550, and 15,000 tons of 19mm material at $0.048 per ton totaling $720, with combined total material costs of $1,270. The price adjustment mechanism allows for automatic calculation of material cost adjustments based on fluctuating market prices for fuel and materials during contract performance. This form serves as a manual correction tool only when automated systems have generated entry errors, ensuring accurate payment to contractors under MDOT agreements that include price escalation or de-escalation clauses tied to material cost indices.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AT,T TD

MATERIAL PRICE ADJUSTMENT

SHEETAND EXAMPLE

CSD-881 MISSISSIPPI DEPARTMENT OF TRANSPORTATION

Rev' 6-17

Jackson, Mississippi

WORKSHEET FOR MATERIAL PRICE ADJUSTMENT

PROJECT NUMBER

COUNW

MATERIAL

CONTRACT BASE PRICE

ESTIMATED PERIOD

BASE PRICE FOR CURRENT PERIOD

PRICE DIFFERENTIALS

ADJUSTMENTS = TOTAL MATERIAL X PRICE DIFFERENTIALS

ADJUSTMENT FOR FUEL AND OTHER MATERIALS

TOTAL ADJUSTMENT

NOTE: SITE MANAGER PERFORMS ALL REQUIRED FUEL AND MATERIAL

ADJUSTMENTS. THIS FORM IS ONLY USED TO CORRECT THE FUEL

ADJUSTMENT MANUALLY IF DATA ENTRY ERRORS WERE MADE.

TO

ITEM NO ITEM DESCRIPTION QUANTITY UNIT

MATERIAL PER

UNIT

TOTAL MATERIAL

PER ITEM

TOTAL MATERIAL 0

CSD-881 MISSISSIPPI DEPARTMENT OF TRANSPORTATION

Rev' 5-17

Jackson, Mississippi

WORKSHEET FOR MATERIAL PRICE ADJUSTMENT

PROJECT NUMBER HrSP-0022-00(023) 301301-100

COUNTY Jasper

MATERIAL AC-30

CONTRACT BASE PRICE 3.1258

ESTTMATED PERTOD 7lLl20L7 TO 7/2s/20L7

BASE PRICE FOR CURRENT PERIOD

PRICE DIFFERENTIALS

ADJUSTMENTS = TOTAL MATERIAL X PRICE DIFFERENTIALS

ADJUSTMENT FOR FUEL AND OTHER MATERIALS

TOTAL ADJUSTMENT

NOTE: SITE MANAGER PERFORMS ALL REQUIRED FUEL AND MATERIAL

ADJUSTMENTS. THIS FORM IS ONLY USED TO CORRECT THE FUEL

ADJUSTMENT MANUALLY IF DATA ENTRY ERRORS WERE MADE.

3.3253

0.1995 s 2s3.37

5 2s3.37

ITEM NO ITEM DESCRIPTION QUANTITY UNIT

MATERIAL PER

UNIT

TOTAL MATERIAL

PER ITEM

403-B Hot Mix 12.5mm MT 10,000.00 Ton 0.055 5s0

401-C Hot Mix 19mm MT 15,000.00 Ton 0.048 720

TOTAL MATERIAL L270