This document is a Material Price Adjustment Worksheet issued by the Mississippi Department of Transportation (MDOT) for a specific highway construction project. The document details a project with the number HrSP-0022-00(023) located in Jasper County, involving hot mix asphalt materials for road construction. The project involves two specific hot mix asphalt items: 10,000 tons of 12.5mm MT and 15,000 tons of 19mm MT, with a contract base price for AC-30 material at $3.1258, and an estimated period from 7/1/2017 to 7/25/2017.

The worksheet calculates material price adjustments, with a current period base price of $3.3253, resulting in a price differential of $0.1995. The total material adjustment for the project is $1,270, with a specific fuel and material adjustment of $253.37. The document is designed to allow site managers to perform fuel and material adjustments, with the form serving as a manual correction tool for potential data entry errors in the automated adjustment process.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AT,T TD

MATERIAL PRICE ADJUSTMENT

SHEETAND EXAMPLE

CSD-881 MISSISSIPPI DEPARTMENT OF TRANSPORTATION

Rev' 6-17

Jackson, Mississippi

WORKSHEET FOR MATERIAL PRICE ADJUSTMENT

PROJECT NUMBER

COUNW

MATERIAL

CONTRACT BASE PRICE

ESTIMATED PERIOD

BASE PRICE FOR CURRENT PERIOD

PRICE DIFFERENTIALS

ADJUSTMENTS = TOTAL MATERIAL X PRICE DIFFERENTIALS

ADJUSTMENT FOR FUEL AND OTHER MATERIALS

TOTAL ADJUSTMENT

NOTE: SITE MANAGER PERFORMS ALL REQUIRED FUEL AND MATERIAL

ADJUSTMENTS. THIS FORM IS ONLY USED TO CORRECT THE FUEL

ADJUSTMENT MANUALLY IF DATA ENTRY ERRORS WERE MADE.

TO

ITEM NO ITEM DESCRIPTION QUANTITY UNIT

MATERIAL PER

UNIT

TOTAL MATERIAL

PER ITEM

TOTAL MATERIAL 0

CSD-881 MISSISSIPPI DEPARTMENT OF TRANSPORTATION

Rev' 5-17

Jackson, Mississippi

WORKSHEET FOR MATERIAL PRICE ADJUSTMENT

PROJECT NUMBER HrSP-0022-00(023) 301301-100

COUNTY Jasper

MATERIAL AC-30

CONTRACT BASE PRICE 3.1258

ESTTMATED PERTOD 7lLl20L7 TO 7/2s/20L7

BASE PRICE FOR CURRENT PERIOD

PRICE DIFFERENTIALS

ADJUSTMENTS = TOTAL MATERIAL X PRICE DIFFERENTIALS

ADJUSTMENT FOR FUEL AND OTHER MATERIALS

TOTAL ADJUSTMENT

NOTE: SITE MANAGER PERFORMS ALL REQUIRED FUEL AND MATERIAL

ADJUSTMENTS. THIS FORM IS ONLY USED TO CORRECT THE FUEL

ADJUSTMENT MANUALLY IF DATA ENTRY ERRORS WERE MADE.

3.3253

0.1995 s 2s3.37

5 2s3.37

ITEM NO ITEM DESCRIPTION QUANTITY UNIT

MATERIAL PER

UNIT

TOTAL MATERIAL

PER ITEM

403-B Hot Mix 12.5mm MT 10,000.00 Ton 0.055 5s0

401-C Hot Mix 19mm MT 15,000.00 Ton 0.048 720

TOTAL MATERIAL L270