ATTACHMENT D - Full Schedule - 06.26.2020.pdf

PDF 840 KB Posted

Attached to
Q702--Worcester, MA Activations Contract Amendment 002 Federal contract opportunity
Solicitation number
36C77621Q0332
Issued by
Department of Veterans Affairs Technology Acquisition Center Austin

About this file

This is a combined synopsis/solicitation from the Department of Veterans Affairs for initial outfitting, transition, and activation services at the Worcester Outpatient Clinic in Massachusetts. The VA seeks these services through a firm-fixed price contract with options to be awarded to a Service-Disabled Veteran-Owned Small Business. Quotes are due by the date specified in the solicitation. The requirement is set aside 100% for SDVOSBs. The anticipated period of performance is July 2021 through January 2022. The solicitation incorporates FAR provisions and clauses. Offerors must be registered in SAM and verified as an SDVOSB by VA. Questions regarding the solicitation must be submitted by May 24, 2021. The VA will post answers by May 28, 2021 to assist SDVOSBs in preparing quotes due in accordance with the solicitation.

View the file

Other files for this federal contract opportunity

Other files attached to Q702--Worcester, MA Activations Contract Amendment 002, newest first.
File Type Posted
36C77621Q0332 0002_1.docx DOCX document
36C77621Q0332 0002.docx DOCX document
ATTACHMENT J - Pricing Worksheet Worcester_.xlsx XLSX spreadsheet
S05 - Vendor Questions Worcester.pdf PDF
Worcester Design 403 Belmont St.pdf PDF
36C77621Q0332 0001.docx DOCX document
ATTACHMENT A - Worcester CBOC IOTA PWS 05142021_.pdf PDF
36C77621Q0332 0001_1.docx DOCX document
ATTACHMENT I - Meeting Minutes template.pdf PDF
ATTACHMENT H - Wage Rate Determination.pdf PDF
ATTACHMENT F - VSC Security Request Forms.pdf PDF
ATTACHMENT C1 - Worcester CBOC IOTA FFE 7.16 (1).pdf PDF
36C77621Q0332.docx DOCX document
ATTACHMENT E - Contract Staff Roster.pdf PDF
ATTACHMENT G - QASP.docx DOCX document
ATTACHMENT C2 - Worcester Equipment Planning for IOTA.xlsx XLSX spreadsheet
ATTACHMENT A - Worcester CBOC IOTA PWS 05142021.pdf PDF
36C77621Q0332_1.docx DOCX document
ATTACHMENT J - Pricing Worksheet Worcester.xlsx XLSX spreadsheet
ATTACHMENT B - TRAVEL AUTHORIZATION REQUEST.pdf PDF
Show all 20

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Activity ID Activity Name Orig Dur

Start Finish Total Float

[220031-008.01-MO] WCCC VA CBOC[220031-008.01-MO] WCCC VA CBOC[220031-008.01-MO] WCCC VA CBOC[220031-008.01-MO] WCCC VA CBOC[220031-008.01-MO] WCCC VA CBOC[220031-008.01-MO] WCCC VA CBOC

KEY MILESTONESKEY MILESTONESKEY MILESTONESKEY MILESTONESKEY MILESTONESKEY MILESTONES A1070 Project Duration (24 Months) 1 30-Aug-19 A 31-Aug-21 0

A4800 VA TI Approval - Release of Work 0 04-Sep-20 258

A4870 Garage Tel/Data Room Available to UMass 0 06-Nov-20 212

S35 Garage C of O 0 29-Jan-21* 0

A4810 Permanent Power Available from Utility Company 0 26-Feb-21 133

A4880 CBOC Tel/Data Rooms Available to UMass 0 03-May-21 37

A6390 Umass Complete at CBOC Tel/Data Rooms 0 17-May-21 37

S11 CBOC C of O (8/31/21) 0 31-Aug-21* 0

PROJECT SUMMARYPROJECT SUMMARYPROJECT SUMMARYPROJECT SUMMARYPROJECT SUMMARYPROJECT SUMMARY S4 West Entrance Reconfiguration 46 07-Apr-20 A 24-Jul-20 277

S5 MOB Core & Shell Construction 300 06-May-20 A 19-Jul-21 31

S6 Garage Constuction 145 01-Jul-20 29-Jan-21 0

S7 VA Tenant Improvements 173 08-Oct-20 17-Jun-21 0

S25 Sitework/Site Finishes/Landscaping 90 15-Mar-21 16-Jul-21 32

S8 Start Up Systems 21 20-May-21 18-Jun-21 0

S9 TAB / CX / System Verification 31 04-Jun-21 19-Jul-21 0

S10 Final Inspections / Punchlist 10 21-Jul-21 03-Aug-21 20

DESIGN PHASEDESIGN PHASEDESIGN PHASEDESIGN PHASEDESIGN PHASEDESIGN PHASE

UMMS/WCCC (C/S) DESIGN PHASEUMMS/WCCC (C/S) DESIGN PHASEUMMS/WCCC (C/S) DESIGN PHASEUMMS/WCCC (C/S) DESIGN PHASEUMMS/WCCC (C/S) DESIGN PHASEUMMS/WCCC (C/S) DESIGN PHASE

Site ElectricalSite ElectricalSite ElectricalSite ElectricalSite ElectricalSite Electrical

D1320 Electrical Power Design (Utility) 75 17-Jan-20 A 02-Jul-20 200

VA (TI) DESIGN PHASEVA (TI) DESIGN PHASEVA (TI) DESIGN PHASEVA (TI) DESIGN PHASEVA (TI) DESIGN PHASEVA (TI) DESIGN PHASE

A6940 Review 15 15-Jun-20 A 02-Jul-20 1

A1510 VA NTP (Lease_Sec 4.01.H) 45 03-Jul-20 03-Sep-20 1

A6950 Umass Release of TI Work 0 10-Aug-20* 0

UMMS Tenant Improvement Design (Floors 3 & 4)UMMS Tenant Improvement Design (Floors 3 & 4)UMMS Tenant Improvement Design (Floors 3 & 4)UMMS Tenant Improvement Design (Floors 3 & 4)UMMS Tenant Improvement Design (Floors 3 & 4)UMMS Tenant Improvement Design (Floors 3 & 4)

A1210 Schematic Design 10 16-Jun-20 A 10-Jul-20 203

A6960 Umass Medical Tenant Negotiations 20 13-Jul-20 07-Aug-20 211

A1220 Design Development 25 10-Aug-20 14-Sep-20 202

A1230 Construction Documents 20 15-Sep-20 13-Oct-20 202

PERMITTINGPERMITTINGPERMITTINGPERMITTINGPERMITTINGPERMITTING

MOB Core & ShellMOB Core & ShellMOB Core & ShellMOB Core & ShellMOB Core & ShellMOB Core & Shell

P1050 Permit Approval 20 26-Jun-20 24-Jul-20 277

VA Tenant ImprovementsVA Tenant ImprovementsVA Tenant ImprovementsVA Tenant ImprovementsVA Tenant ImprovementsVA Tenant Improvements

P1060 Drawing Issuance (VA) 0 03-Sep-20 228

P1070 Permit Approval (VA) 20 04-Sep-20 02-Oct-20 228

Floors 3 & 4Floors 3 & 4Floors 3 & 4Floors 3 & 4Floors 3 & 4Floors 3 & 4

A3750 Drawing Issuance (Floors 3 & 4) 0 13-Oct-20 202

A3740 Permit Approval (Floors 3 & 4) 20 14-Oct-20 10-Nov-20 202

PROCUREMENTPROCUREMENTPROCUREMENTPROCUREMENTPROCUREMENTPROCUREMENT

16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34

Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

2020 2021

Project Duration (24 Months)

VA TI Approval - Release of Work

Garage Tel/Data Room Available to UMass

Garage C of O

Permanent Power Available from Utility Company

CBOC Tel/Data Rooms Available to UMass

Umass Complete at CBOC Tel/Data Rooms

CBOC C of O (8/31/21)

West Entrance Reconfiguration

MOB Core & Shell Construction

Garage Constuction

VA Tenant Improvements

Sitework/Site Finishes/Landscaping

Start Up Systems

TAB / CX / System Verification

Final Inspections / Punchlist

Electrical Power Design (Utility)

Review

VA NTP (Lease_Sec 4.01.H)

Umass Release of TI Work

Schematic Design

Umass Medical Tenant Negotiations

Design Development

Construction Documents

Permit Approval

Drawing Issuance (VA)

Permit Approval (VA)

Drawing Issuance (Floors 3 & 4)

Permit Approval (Floors 3 & 4)

PROJECT ID: 220031.001

DATA DATE: 26-Jun-20

PRINT DATE: 26-Jun-20

Remaining Level of Effort

Actual Level of Effort

Completed Work

Remainin...

Critical Re...

Milestone

UMass VA

Worcester, MA

UMass Full Schedule

Start Finish Total Float

VA ProcurementVA ProcurementVA ProcurementVA ProcurementVA ProcurementVA Procurement

A4930 TI MEP Coordination 15 17-Jul-20 06-Aug-20 278

A1900 TI Subcontractor Awards 18 11-Aug-20 03-Sep-20 14

A1600 Shop Drawing Review/Material Procurement (TI) 45 04-Sep-20 05-Nov-20 14

MasonryMasonryMasonryMasonryMasonryMasonry

A2500 Review & Approve Masonry 5 15-Jun-20 A 26-Jun-20 12

A2510 Fabricate & Deliver Masonry 2 29-Jun-20 30-Jun-20 12

Metal Pan StairsMetal Pan StairsMetal Pan StairsMetal Pan StairsMetal Pan StairsMetal Pan Stairs

A2450 Review & Approve Metal Pan Stairs 15 24-Jun-20 A 14-Jul-20 265

A2460 Fabricate & Deliver Metal Pan Stairs 30 15-Jul-20 25-Aug-20 265

RoofingRoofingRoofingRoofingRoofingRoofing

A2520 Bid & Award Roofing 10 04-Jun-20 A 02-Jul-20 228

A2530 Prepare & Submit Roofing 30 03-Jul-20 13-Aug-20 228

A2540 Review & Approve Roofing 15 14-Aug-20 03-Sep-20 228

A2550 Fabricate & Deliver Roofing 30 04-Sep-20 15-Oct-20 228

Lighting FixturesLighting FixturesLighting FixturesLighting FixturesLighting FixturesLighting Fixtures

A3560 Bid & Award Lighting Fixtures 15 01-Jun-20 A 02-Jul-20 228

A3570 Prepare & Submit Lighting Fixtures 10 03-Jul-20 16-Jul-20 228

A3580 Review & Approve Lighting Fixtures 15 17-Jul-20 06-Aug-20 228

A3590 Fabricate & Deliver Lighting Fixtures 50 07-Aug-20 15-Oct-20 228

PanelboardsPanelboardsPanelboardsPanelboardsPanelboardsPanelboards

A3610 Prepare & Submit Panelboards 10 15-Jun-20 A 26-Jun-20 267

A3620 Review & Approve Panelboards 15 29-Jun-20 17-Jul-20 267

A3630 Fabricate & Deliver Panelboards 25 20-Jul-20 21-Aug-20 267

TransformersTransformersTransformersTransformersTransformersTransformers

A3650 Prepare & Submit Transformer 10 15-Jun-20 A 26-Jun-20 272

A3660 Review & Approve Transformer 15 29-Jun-20 17-Jul-20 272

A3670 Fabricate & Deliver Transformer 20 20-Jul-20 14-Aug-20 272

Fire AlarmFire AlarmFire AlarmFire AlarmFire AlarmFire Alarm

A3690 Prepare & Submit Fire Alarm 25 15-Jun-20 A 17-Jul-20 262

A3700 Review & Approve Fire Alarm 15 20-Jul-20 07-Aug-20 262

A3710 Fabricate & Deliver Fire Alarm 15 10-Aug-20 28-Aug-20 262

MOB Core & ShellMOB Core & ShellMOB Core & ShellMOB Core & ShellMOB Core & ShellMOB Core & Shell

FacadeFacadeFacadeFacadeFacadeFacade

Granite BaseGranite BaseGranite BaseGranite BaseGranite BaseGranite Base

A2770 Prepare & Submit Granite Base 20 05-Jun-20 A 16-Jul-20 90

A2780 Review & Approve Granite Base 10 17-Jul-20 30-Jul-20 90

A2790 Fabricate & Deliver Granite Base 40 31-Jul-20 24-Sep-20 90

CurtainwallCurtainwallCurtainwallCurtainwallCurtainwallCurtainwall

A2570 Prepare & Submit Curtainwall 20 21-Apr-20 A 02-Jul-20 40

A2580 Review & Approve Curtainwall 10 03-Jul-20 16-Jul-20 40

A2590 Fabricate & Deliver Curtainwall 80 17-Jul-20 05-Nov-20 40

Punched WindowsPunched WindowsPunched WindowsPunched WindowsPunched WindowsPunched Windows

A2610 Prepare & Submit Punched Windows 20 21-Apr-20 A 02-Jul-20 15

16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34

Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

2020 2021

TI MEP Coordination

TI Subcontractor Awards

Shop Drawing Review/Material Procurement (TI)

Review & Approve Masonry

Fabricate & Deliver Masonry

Review & Approve Metal Pan Stairs

Fabricate & Deliver Metal Pan Stairs

Bid & Award Roofing

Prepare & Submit Roofing

Review & Approve Roofing

Fabricate & Deliver Roofing

Bid & Award Lighting Fixtures

Prepare & Submit Lighting Fixtures

Review & Approve Lighting Fixtures

Fabricate & Deliver Lighting Fixtures

Prepare & Submit Panelboards

Review & Approve Panelboards

Fabricate & Deliver Panelboards

Prepare & Submit Transformer

Review & Approve Transformer

Fabricate & Deliver Transformer

Prepare & Submit Fire Alarm

Review & Approve Fire Alarm

Fabricate & Deliver Fire Alarm

Prepare & Submit Granite Base

Review & Approve Granite Base

Fabricate & Deliver Granite Base

Prepare & Submit Curtainwall

Review & Approve Curtainwall

Fabricate & Deliver Curtainwall

Prepare & Submit Punched Windows

PROJECT ID: 220031.001

DATA DATE: 26-Jun-20

PRINT DATE: 26-Jun-20

Remaining Level of Effort

Actual Level of Effort

Completed Work

Remainin...

Critical Re...

Milestone

UMass VA

Start Finish Total Float

A2620 Review & Approve Punched Windows 25 03-Jul-20 06-Aug-20 15

A2630 Fabricate & Deliver Punched Windows 80 07-Aug-20 26-Nov-20 15

Metal PanelsMetal PanelsMetal PanelsMetal PanelsMetal PanelsMetal Panels

A2650 Prepare & Submit Metal Panels 44 13-May-20 A 13-Jul-20 33

A2660 Review & Approve Metal Panels 11 14-Jul-20 28-Jul-20 33

A2670 Fabricate & Deliver Metal Panels 79 29-Jul-20 16-Nov-20 33

GlassGlassGlassGlassGlassGlass

A2880 Fabricate/Construct Mock-Up 30 12-Jun-20 A 23-Jul-20 216

A2890 Review & Approve Mock-Up 2 24-Jul-20 27-Jul-20 216

A2710 Fabricate & Deliver Glass 70 28-Jul-20 02-Nov-20 216

Stone/TerracottaStone/TerracottaStone/TerracottaStone/TerracottaStone/TerracottaStone/Terracotta

A2730 Prepare & Submit Stone/Terracotta 20 13-May-20 A 16-Jul-20 12

A2740 Review & Approve Stone/Terracotta 15 17-Jul-20 06-Aug-20 12

A2750 Fabricate & Deliver Stone/Terracotta 110 07-Aug-20 07-Jan-21 12

ElevatorsElevatorsElevatorsElevatorsElevatorsElevators

Passenger Elevators 1-3Passenger Elevators 1-3Passenger Elevators 1-3Passenger Elevators 1-3Passenger Elevators 1-3Passenger Elevators 1-3

PR1370 Elevator Equipment Procurement / Delivery Elevators 1-3 120 26-May-20 A 13-Nov-20 52

Service Elevator 4Service Elevator 4Service Elevator 4Service Elevator 4Service Elevator 4Service Elevator 4

PR1390 Elevator Equipment Procurement / Delivery Elevator 4 120 26-May-20 A 13-Nov-20 52

MEPMEPMEPMEPMEPMEP

PR1110 Shop Drawing Review and Approval (MEP) 40 05-Jun-20 A 31-Jul-20 182

PR1230 MEP Equipment Procurement / Delivery 90 03-Aug-20 10-Dec-20 182

Rooftop UnitsRooftop UnitsRooftop UnitsRooftop UnitsRooftop UnitsRooftop Units

PR1440 Shop Drawing Review and Approval (Rooftop Units) 20 05-Jun-20 A 17-Jul-20 42

PR1450 Rooftop Unit Procurement / Delivery 100 20-Jul-20 10-Dec-20 42

ChillerChillerChillerChillerChillerChiller

PR1460 Shop Drawing Review and Approval (Chiller) 20 05-Jun-20 A 17-Jul-20 64

PR1470 Chiller Procurement / Delivery 80 20-Jul-20 10-Nov-20 64

Boiler/PumpsBoiler/PumpsBoiler/PumpsBoiler/PumpsBoiler/PumpsBoiler/Pumps

PR1480 Shop Drawing Review and Approval (Boiler/Pumps) 20 12-Jun-20 A 24-Jul-20 227

PR1490 Boiler/Pumps Procurement / Delivery 50 27-Jul-20 05-Oct-20 227

ElectricalElectricalElectricalElectricalElectricalElectrical

Lighting FixturesLighting FixturesLighting FixturesLighting FixturesLighting FixturesLighting Fixtures

A3210 Prepare & Submit Lighting Fixtures 10 22-Jun-20 A 03-Jul-20 237

A3220 Review & Approve Lighting Fixtures 15 06-Jul-20 24-Jul-20 237

A3230 Fabricate & Deliver Lighting Fixtures 50 27-Jul-20 02-Oct-20 237

Site LightingSite LightingSite LightingSite LightingSite LightingSite Lighting

A3250 Prepare & Submit Site Lighting 10 22-Jun-20 A 03-Jul-20 147

A3260 Review & Approve Site Lighting 15 06-Jul-20 24-Jul-20 147

A3270 Fabricate & Deliver Site Lighting 50 27-Jul-20 02-Oct-20 147

SwitchgearSwitchgearSwitchgearSwitchgearSwitchgearSwitchgear

A3290 Prepare & Submit Switchgear 20 22-Jun-20 A 17-Jul-20 87

A3300 Review & Approve Switchgear 15 20-Jul-20 07-Aug-20 87

A3310 Fabricate & Deliver Switchgear 60 10-Aug-20 30-Oct-20 87

PanelboardsPanelboardsPanelboardsPanelboardsPanelboardsPanelboards

16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34

Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

2020 2021

Review & Approve Punched Windows

Fabricate & Deliver Punched Windows

Prepare & Submit Metal Panels

Review & Approve Metal Panels

Fabricate & Deliver Metal Panels

Fabricate/Construct Mock-Up

Review & Approve Mock-Up

Fabricate & Deliver Glass

Prepare & Submit Stone/Terracotta

Review & Approve Stone/Terracotta

Fabricate & Deliver Stone/Terracotta

Elevator Equipment Procurement / Delivery Elevators 1-3

Elevator Equipment Procurement / Delivery Elevator 4

Shop Drawing Review and Approval (MEP)

MEP Equipment Procurement / Delivery

Shop Drawing Review and Approval (Rooftop Units)

Rooftop Unit Procurement / Delivery

Shop Drawing Review and Approval (Chiller)

Chiller Procurement / Delivery

Shop Drawing Review and Approval (Boiler/Pumps)

Boiler/Pumps Procurement / Delivery

Prepare & Submit Lighting Fixtures

Review & Approve Lighting Fixtures

Fabricate & Deliver Lighting Fixtures

Prepare & Submit Site Lighting

Review & Approve Site Lighting

Fabricate & Deliver Site Lighting

Prepare & Submit Switchgear

Review & Approve Switchgear

Fabricate & Deliver Switchgear

PROJECT ID: 220031.001

DATA DATE: 26-Jun-20

PRINT DATE: 26-Jun-20

Remaining Level of Effort

Actual Level of Effort

Completed Work

Remainin...

Critical Re...

Milestone

UMass VA

Start Finish Total Float

A3330 Prepare & Submit Panelboards 10 15-Jun-20 A 26-Jun-20 137

A3340 Review & Approve Panelboards 15 29-Jun-20 17-Jul-20 137

A3350 Fabricate & Deliver Panelboards 25 20-Jul-20 21-Aug-20 137

TransformersTransformersTransformersTransformersTransformersTransformers

A3370 Prepare & Submit Transformer 10 15-Jun-20 A 26-Jun-20 142

A3380 Review & Approve Transformer 15 29-Jun-20 17-Jul-20 142

A3390 Fabricate & Deliver Transformer 20 20-Jul-20 14-Aug-20 142

Fire AlarmFire AlarmFire AlarmFire AlarmFire AlarmFire Alarm

A3410 Prepare & Submit Fire Alarm 25 15-Jun-20 A 17-Jul-20 262

A3420 Review & Approve Fire Alarm 15 20-Jul-20 07-Aug-20 262

A3430 Fabricate & Deliver Fire Alarm 15 10-Aug-20 28-Aug-20 262

GeneratorGeneratorGeneratorGeneratorGeneratorGenerator

A3450 Prepare & Submit Generator 20 15-Jun-20 A 10-Jul-20 91

A3460 Review & Approve Generator 15 13-Jul-20 31-Jul-20 91

A3470 Fabricate & Deliver Generator 70 03-Aug-20 06-Nov-20 91

Lightning ProtectionLightning ProtectionLightning ProtectionLightning ProtectionLightning ProtectionLightning Protection

A3530 Prepare & Submit Lightning Protection 15 15-Jun-20 A 03-Jul-20 142

A3540 Review & Approve Lightning Protection 15 06-Jul-20 24-Jul-20 142

A3550 Fabricate & Deliver Lightning Protection 15 27-Jul-20 14-Aug-20 142

StructureStructureStructureStructureStructureStructure

PR1200 Structural Steel Shop Drawings Submit / Approval 10 29-May-20 A 02-Jul-20 0

PR1260 Steel Fabrication 45 06-Jul-20 04-Sep-20 0

GarageGarageGarageGarageGarageGarage

FoundationFoundationFoundationFoundationFoundationFoundation

PR1320 Review and Approve Foundation Shop Drawings 15 15-May-20 A 26-Jun-20 286

PR1340 Fab & Deliver Rebar 10 29-Jun-20 13-Jul-20 286

PrecastPrecastPrecastPrecastPrecastPrecast

PR1330 Review and Approve Precast Shop Drawings 10 12-Jun-20 A 29-Jun-20 251

PR1350 Fab & Deliver Precast 44 30-Jun-20 31-Aug-20 251

Steel CanopySteel CanopySteel CanopySteel CanopySteel CanopySteel Canopy

A1980 Prepare & Submit Steel Canopy 10 29-Jun-20* 10-Jul-20 252

A1990 Review & Approve Steel Canopy 10 13-Jul-20 24-Jul-20 252

A2000 Fabricate & Deliver Steel Canopy 25 27-Jul-20 28-Aug-20 252

Passenger Elevator 5Passenger Elevator 5Passenger Elevator 5Passenger Elevator 5Passenger Elevator 5Passenger Elevator 5

PR1430 Elevator Equipment Procurement / Delivery Elevator 5 100 26-May-20 A 15-Oct-20 4

PanelboardsPanelboardsPanelboardsPanelboardsPanelboardsPanelboards

A3060 Review & Approve Panelboards 15 19-Jun-20 A 09-Jul-20 36

A3070 Fabricate & Deliver Panelboards 25 10-Jul-20 13-Aug-20 36

TransformersTransformersTransformersTransformersTransformersTransformers

A3100 Review & Approve Transformers 15 19-Jun-20 A 09-Jul-20 41

A3110 Fabricate & Deliver Transformers 20 10-Jul-20 06-Aug-20 41

Lighting FixturesLighting FixturesLighting FixturesLighting FixturesLighting FixturesLighting Fixtures

A3140 Review & Approve Lighting Fixtures 15 19-Jun-20 A 09-Jul-20 11

A3150 Fabricate & Deliver Lighting Fixtures 50 10-Jul-20 17-Sep-20 11

16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34

Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

2020 2021

Prepare & Submit Panelboards

Review & Approve Panelboards

Fabricate & Deliver Panelboards

Prepare & Submit Transformer

Review & Approve Transformer

Fabricate & Deliver Transformer

Prepare & Submit Fire Alarm

Review & Approve Fire Alarm

Fabricate & Deliver Fire Alarm

Prepare & Submit Generator

Review & Approve Generator

Fabricate & Deliver Generator

Prepare & Submit Lightning Protection

Review & Approve Lightning Protection

Fabricate & Deliver Lightning Protection

Structural Steel Shop Drawings Submit / Approval

Steel Fabrication

Review and Approve Foundation Shop Drawings

Fab & Deliver Rebar

Review and Approve Precast Shop Drawings

Fab & Deliver Precast

Prepare & Submit Steel Canopy

Review & Approve Steel Canopy

Fabricate & Deliver Steel Canopy

Elevator Equipment Procurement / Delivery Elevator 5

Review & Approve Panelboards

Fabricate & Deliver Panelboards

Review & Approve Transformers

Fabricate & Deliver Transformers

Review & Approve Lighting Fixtures

Fabricate & Deliver Lighting Fixtures

PROJECT ID: 220031.001

DATA DATE: 26-Jun-20

PRINT DATE: 26-Jun-20

Remaining Level of Effort

Actual Level of Effort

Completed Work

Remainin...

Critical Re...

Milestone

UMass VA

Start Finish Total Float

Fire AlarmFire AlarmFire AlarmFire AlarmFire AlarmFire Alarm

A3180 Review & Approve Fire Alarm 15 19-Jun-20 A 09-Jul-20 46

A3190 Fabricate & Deliver Fire Alarm 15 10-Jul-20 30-Jul-20 46

MEP CoordinationMEP CoordinationMEP CoordinationMEP CoordinationMEP CoordinationMEP Coordination

Sleeving DrawingsSleeving DrawingsSleeving DrawingsSleeving DrawingsSleeving DrawingsSleeving Drawings

GarageGarageGarageGarageGarageGarage

MPB100 Garage - Submit Sleeving Dwg 12 26-May-20 A 29-Jun-20 13

MPB150 Coordination Sheer Wall Penetrations 12 26-May-20 A 29-Jun-20 13

MPB110 Garage - Approve Sleeving Dwg 3 30-Jun-20 02-Jul-20 13

MPB120 Garage - Revise Sleeving Dwg 4 06-Jul-20 09-Jul-20 13

MPB130 Sign Off Garage Floor Sleeving Drawings 0 09-Jul-20 13

MOBMOBMOBMOBMOBMOB

UnderslabUnderslabUnderslabUnderslabUnderslabUnderslab

MP17270 Underslab - Submit Coordination Dwg 12 26-Jun-20 14-Jul-20 278

MP17280 Underslab - Approve Coordination Dwg 3 15-Jul-20 17-Jul-20 278

MP17290 Underslab - Revise Coordination Dwg 4 20-Jul-20 23-Jul-20 278

MP17300 Sign Off Underslab Coordination Drawings 0 23-Jul-20 278

1st Floor1st Floor1st Floor1st Floor1st Floor1st Floor

MP1100 01 - Submit Sleeving Dwg 12 30-Jun-20 16-Jul-20 49

MP1110 01 - Approve Sleeving Dwg 3 17-Jul-20 21-Jul-20 57

MP1120 01 - Revise Sleeving Dwg 4 22-Jul-20 27-Jul-20 57

MP1130 Sign Off 01 Floor Sleeving Drawings 0 27-Jul-20 57

2nd Floor2nd Floor2nd Floor2nd Floor2nd Floor2nd Floor

MP2100 02 - Submit Sleeving Dwg 12 17-Jul-20 03-Aug-20 49

MP2110 02 - Approve Sleeving Dwg 3 04-Aug-20 06-Aug-20 55

MP2120 02 - Revise Sleeving Dwg 4 07-Aug-20 12-Aug-20 55

MP2130 Sign Off 02 Floor Sleeving Drawings 0 12-Aug-20 55

3rd Floor3rd Floor3rd Floor3rd Floor3rd Floor3rd Floor

MP3100 03 - Submit Sleeving Dwg 12 04-Aug-20 19-Aug-20 49

MP3110 03 - Approve Sleeving Dwg 3 20-Aug-20 24-Aug-20 53

MP3120 03 - Revise Sleeving Dwg 4 25-Aug-20 28-Aug-20 53

MP3130 Sign Off 03 Floor Sleeving Drawings 0 28-Aug-20 53

4th Floor4th Floor4th Floor4th Floor4th Floor4th Floor

MP4100 04 - Submit Sleeving Dwg 12 20-Aug-20 04-Sep-20 49

MP4110 04 - Approve Sleeving Dwg 3 08-Sep-20 10-Sep-20 51

MP4120 04 - Revise Sleeving Dwg 4 11-Sep-20 16-Sep-20 51

MP4130 Sign Off 04 Floor Sleeving Drawings 0 16-Sep-20 51

RoofRoofRoofRoofRoofRoof

MP5100 05 - Submit Sleeving Dwg 12 08-Sep-20 23-Sep-20 49

MP5110 05 - Approve Sleeving Dwg 3 24-Sep-20 28-Sep-20 49

MP5120 05 - Revise Sleeving Dwg 4 29-Sep-20 02-Oct-20 49

MP5130 Sign Off 05 Floor Sleeving Drawings 0 02-Oct-20 49

MEP Coordination DrawingsMEP Coordination DrawingsMEP Coordination DrawingsMEP Coordination DrawingsMEP Coordination DrawingsMEP Coordination Drawings

GarageGarageGarageGarageGarageGarage

16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34

Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

2020 2021

Review & Approve Fire Alarm

Fabricate & Deliver Fire Alarm

Garage - Submit Sleeving Dwg

Coordination Sheer Wall Penetrations

Garage - Approve Sleeving Dwg

Garage - Revise Sleeving Dwg

Sign Off Garage Floor Sleeving Drawings

Underslab - Submit Coordination Dwg

Underslab - Approve Coordination Dwg

Underslab - Revise Coordination Dwg

Sign Off Underslab Coordination Drawings

01 - Submit Sleeving Dwg

01 - Approve Sleeving Dwg

01 - Revise Sleeving Dwg

Sign Off 01 Floor Sleeving Drawings

02 - Submit Sleeving Dwg

02 - Approve Sleeving Dwg

02 - Revise Sleeving Dwg

Sign Off 02 Floor Sleeving Drawings

03 - Submit Sleeving Dwg

03 - Approve Sleeving Dwg

03 - Revise Sleeving Dwg

Sign Off 03 Floor Sleeving Drawings

04 - Submit Sleeving Dwg

04 - Approve Sleeving Dwg

04 - Revise Sleeving Dwg

Sign Off 04 Floor Sleeving Drawings

05 - Submit Sleeving Dwg

05 - Approve Sleeving Dwg

05 - Revise Sleeving Dwg

Sign Off 05 Floor Sleeving Drawings

PROJECT ID: 220031.001

DATA DATE: 26-Jun-20

PRINT DATE: 26-Jun-20

Remaining Level of Effort

Actual Level of Effort

Completed Work

Remainin...

Critical Re...

Milestone

UMass VA

Start Finish Total Float

MP2210 Garage - Plumbing Coordination 5 10-Jul-20 16-Jul-20 149

MP2220 Garage - HVAC Coordination 5 17-Jul-20 23-Jul-20 149

MP2230 Garage - Electrical Coordination 5 24-Jul-20 30-Jul-20 149

MP2240 Garage - Final Revisions 5 31-Jul-20 06-Aug-20 149

MP2250 Garage - Submit / Approve Coordination Dwg 10 07-Aug-20 20-Aug-20 149

MP2260 Sign Off Garage Floor Coordination Drawing 0 20-Aug-20 149

MOBMOBMOBMOBMOBMOB

1st Floor1st Floor1st Floor1st Floor1st Floor1st Floor

MP5000 1st Floor - Fire Protection Coordination 10 28-Jul-20 10-Aug-20 57

MP5200 1st Floor - Ductwork Coordination 10 11-Aug-20 24-Aug-20 97

MP5210 1st Floor - Plumbing Coordination 10 25-Aug-20 08-Sep-20 97

MP5220 1st Floor - HVAC Coordination 10 09-Sep-20 22-Sep-20 97

MP5230 1st Floor - Electrical Coordination 15 23-Sep-20 14-Oct-20 97

MP5240 1st Floor - Final Revisions 5 15-Oct-20 21-Oct-20 97

MP5250 1st Floor - Submit / Approve Coordination Dwg 10 22-Oct-20 04-Nov-20 97

MP5260 Sign Off 1st Floor Coordination Drawing 0 04-Nov-20 97

2nd Floor2nd Floor2nd Floor2nd Floor2nd Floor2nd Floor

MP8000 2nd Floor - Fire Protection Coordination 10 13-Aug-20 26-Aug-20 55

MP8200 2nd Floor - Ductwork Coordination 10 27-Aug-20 10-Sep-20 85

MP8210 2nd Floor - Plumbing Coordination 10 11-Sep-20 24-Sep-20 85

MP8220 2nd Floor - HVAC Coordination 10 25-Sep-20 08-Oct-20 85

MP8230 2nd Floor - Electrical Coordination 15 09-Oct-20 30-Oct-20 85

MP8240 2nd Floor - Final Revisions 5 02-Nov-20 06-Nov-20 85

MP8250 2nd Floor - Submit / Approve Coordination Dwg 10 09-Nov-20 23-Nov-20 85

MP8260 Sign Off 2nd Floor Coordination Drawing 0 23-Nov-20 85

3rd Floor3rd Floor3rd Floor3rd Floor3rd Floor3rd Floor

MP11000 3rd Floor - Fire Protection Coordination 10 31-Aug-20 14-Sep-20 53

MP11200 3rd Floor - Ductwork Coordination 10 15-Sep-20 28-Sep-20 73

MP11210 3rd Floor - Plumbing Coordination 10 29-Sep-20 13-Oct-20 73

MP11220 3rd Floor - HVAC Coordination 10 14-Oct-20 27-Oct-20 73

MP11230 3rd Floor - Electrical Coordination 15 28-Oct-20 18-Nov-20 73

MP11240 3rd Floor - Final Revisions 5 19-Nov-20 25-Nov-20 73

MP11250 3rd Floor - Submit / Approve Coordination Dwg 10 27-Nov-20 10-Dec-20 73

MP11260 Sign Off 3rd Floor Coordination Drawing 0 10-Dec-20 73

4th Floor4th Floor4th Floor4th Floor4th Floor4th Floor

MP14000 4th Floor - Fire Protection Coordination 10 17-Sep-20 30-Sep-20 51

MP14200 4th Floor - Ductwork Coordination 10 01-Oct-20 15-Oct-20 61

MP14210 4th Floor - Plumbing Coordination 10 16-Oct-20 29-Oct-20 61

MP14220 4th Floor - HVAC Coordination 10 30-Oct-20 13-Nov-20 61

MP14230 4th Floor - Electrical Coordination 15 16-Nov-20 07-Dec-20 61

MP14240 4th Floor - Final Revisions 5 08-Dec-20 14-Dec-20 61

MP14250 4th Floor - Submit / Approve Coordination Dwg 10 15-Dec-20 29-Dec-20 61

MP14260 Sign Off 4th Floor Coordination Drawing 0 29-Dec-20 61

RoofRoofRoofRoofRoofRoof

MP17000 Roof - Fire Protection Coordination 10 05-Oct-20 19-Oct-20 49

16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34

Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

2020 2021

Garage - Plumbing Coordination

Garage - HVAC Coordination

Garage - Electrical Coordination

Garage - Final Revisions

Garage - Submit / Approve Coordination Dwg

Sign Off Garage Floor Coordination Drawing

1st Floor - Fire Protection Coordination

1st Floor - Ductwork Coordination

1st Floor - Plumbing Coordination

1st Floor - HVAC Coordination

1st Floor - Electrical Coordination

1st Floor - Final Revisions

1st Floor - Submit / Approve Coordination Dwg

Sign Off 1st Floor Coordination Drawing

2nd Floor - Fire Protection Coordination

2nd Floor - Ductwork Coordination

2nd Floor - Plumbing Coordination

2nd Floor - HVAC Coordination

2nd Floor - Electrical Coordination

2nd Floor - Final Revisions

2nd Floor - Submit / Approve Coordination Dwg

Sign Off 2nd Floor Coordination Drawing

3rd Floor - Fire Protection Coordination

3rd Floor - Ductwork Coordination

3rd Floor - Plumbing Coordination

3rd Floor - HVAC Coordination

3rd Floor - Electrical Coordination

3rd Floor - Final Revisions

3rd Floor - Submit / Approve Coordination Dwg

Sign Off 3rd Floor Coordination Drawing

4th Floor - Fire Protection Coordination

4th Floor - Ductwork Coordination

4th Floor - Plumbing Coordination

4th Floor - HVAC Coordination

4th Floor - Electrical Coordination

4th Floor - Final Revisions

4th Floor - Submit / Approve Coordination Dwg

Sign Off 4th Floor Coordination Drawing

Roof - Fire Protection Coordination

PROJECT ID: 220031.001

DATA DATE: 26-Jun-20

PRINT DATE: 26-Jun-20

Remaining Level of Effort

Actual Level of Effort

Completed Work

Remainin...

Critical Re...

Milestone

UMass VA

Start Finish Total Float

MP17200 Roof - Ductwork Coordination 10 20-Oct-20 02-Nov-20 49

MP17210 Roof - Plumbing Coordination 10 03-Nov-20 17-Nov-20 49

MP17220 Roof - HVAC Coordination 10 18-Nov-20 02-Dec-20 49

MP17230 Roof - Electrical Coordination 15 03-Dec-20 23-Dec-20 49

MP17240 Roof - Final Revisions 5 24-Dec-20 31-Dec-20 49

MP17250 Roof - Submit / Approve Coordination Dwg 10 04-Jan-21 15-Jan-21 49

MP17260 Sign Off Roof Coordination Drawing 0 15-Jan-21 49

CONSTRUCTIONCONSTRUCTIONCONSTRUCTIONCONSTRUCTIONCONSTRUCTIONCONSTRUCTION

MOBMOBMOBMOBMOBMOB

MOB Core & ShellMOB Core & ShellMOB Core & ShellMOB Core & ShellMOB Core & ShellMOB Core & Shell

Site/UtilitiesSite/UtilitiesSite/UtilitiesSite/UtilitiesSite/UtilitiesSite/Utilities

A4860 Network Conduit to MOB 15 22-Jul-20 11-Aug-20 23

A6010 Install Remaining Drainage 15 12-Aug-20 01-Sep-20 23

A6020 Remove Construction Fence 10 15-Mar-21* 26-Mar-21 32

A6030 Grade & Prep Sidewalks 10 29-Mar-21 09-Apr-21 32

A6040 Install Sidewalks 10 12-Apr-21 23-Apr-21 32

A6050 Install Handrails 10 26-Apr-21 07-May-21 32

A6060 Install Loam 10 10-May-21 21-May-21 32

A6070 Install Parking Equipment 10 24-May-21 04-Jun-21 32

A6080 Paving 10 07-Jun-21 18-Jun-21 32

A6090 Install Landscaping Plants and Shrubs 10 21-Jun-21 02-Jul-21 32

A6100 Seed Lawns 10 05-Jul-21 16-Jul-21 32

GeneratorGeneratorGeneratorGeneratorGeneratorGenerator

A6110 Run Duct Bank to CBOC 10 10-Jul-20 23-Jul-20 42

A6120 Run Duct Bank to Garage Addition 15 24-Jul-20 13-Aug-20 42

A4830 Equipment Pads 5 14-Aug-20 20-Aug-20 42

A4840 Set Utility Switch/Transformer 2 02-Nov-20 03-Nov-20 94

A4850 Set Generator/Docking Station 2 09-Nov-20 10-Nov-20 91

A6130 Frade & Prep Generator Pad 5 11-Nov-20 17-Nov-20 91

A6140 Install Grounding 5 18-Nov-20 24-Nov-20 91

A6150 Form Rebar and Place Slab 10 25-Nov-20 08-Dec-20 91

A6160 Install Generator 5 09-Dec-20 15-Dec-20 91

A6170 Connect Genrator 15 16-Dec-20 05-Jan-21 91

A6180 Testing 5 06-Jan-21 12-Jan-21 91

RT 9 Water Tie InRT 9 Water Tie InRT 9 Water Tie InRT 9 Water Tie InRT 9 Water Tie InRT 9 Water Tie In

A6200 Deliver Sleeve 15 26-Jun-20 16-Jul-20 68

A6210 Install Sleeve 10 17-Jul-20 30-Jul-20 68

A2400 Install Road Connection 4 31-Jul-20 05-Aug-20 68

StructureStructureStructureStructureStructureStructure

A6220 Underslab Utilities Columns 5 - 8 (C/S) 10 29-Jun-20 10-Jul-20 5

A6230 Underslab Utilities Columns 5 - 1 (C/S) 10 13-Jul-20 24-Jul-20 8

A3760 Backfill SOG 5 27-Jul-20 31-Jul-20 0

A3770 Vapor Barrier/Insulation at SOG 5 29-Jul-20 04-Aug-20 0

A3780 Pour SOG 3 05-Aug-20 07-Aug-20 0

16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34

Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

2020 2021

Roof - Ductwork Coordination

Roof - Plumbing Coordination

Roof - HVAC Coordination

Roof - Electrical Coordination

Roof - Final Revisions

Roof - Submit / Approve Coordination Dwg

Sign Off Roof Coordination Drawing

Network Conduit to MOB

Install Remaining Drainage

Remove Construction Fence

Grade & Prep Sidewalks

Install Sidewalks

Install Handrails

Install Loam

Install Parking Equipment

Paving

Install Landscaping Plants and Shrubs

Seed Lawns

Run Duct Bank to CBOC

Run Duct Bank to Garage Addition

Equipment Pads

Set Utility Switch/Transformer

Set Generator/Docking Station

Frade & Prep Generator Pad

Install Grounding

Form Rebar and Place Slab

Install Generator

Connect Genrator

Testing

Deliver Sleeve

Install Sleeve

Install Road Connection

Underslab Utilities Columns 5 - 8 (C/S)

Underslab Utilities Columns 5 - 1 (C/S)

Backfill SOG

Vapor Barrier/Insulation at SOG

Pour SOG

PROJECT ID: 220031.001

DATA DATE: 26-Jun-20

PRINT DATE: 26-Jun-20

Remaining Level of Effort

Actual Level of Effort

Completed Work

Remainin...

Critical Re...

Milestone

UMass VA

Start Finish Total Float

C1070 Structural Steel / Detailing / Composite Deck 48 10-Aug-20 16-Oct-20 0

A3790 Pour SOD Level 2 3 05-Oct-20 07-Oct-20 0

A3800 Pour SOD Level 3 3 08-Oct-20 12-Oct-20 2

A3810 Pour SOD Level 4 3 13-Oct-20 15-Oct-20 2

A3820 Spray Fireproofing 10 16-Oct-20 29-Oct-20 2

FoundationsFoundationsFoundationsFoundationsFoundationsFoundations

ExcavationExcavationExcavationExcavationExcavationExcavation

A1640 Excavate Interiror Footings 3 20-May-20 A 26-Jun-20 5

A1730 Backfill Foundations West 10 12-Jun-20 A 02-Jul-20 36

A6240 Backfill Foundations South 10 03-Jul-20 16-Jul-20 36

A6250 Backfill Foundations East 10 17-Jul-20 30-Jul-20 36

A6260 Backfill Foundations North 10 31-Jul-20 13-Aug-20 36

Footings & WallsFootings & WallsFootings & WallsFootings & WallsFootings & WallsFootings & Walls

A1700 FRP Interiror Footings & Walls 8 05-Jun-20 A 26-Jun-20 5

A6970 FRP Loading Dock Foundations 10 26-Jun-20 09-Jul-20 42

WaterproofingWaterproofingWaterproofingWaterproofingWaterproofingWaterproofing

A6280 Waterproof Foundations East 10 15-Jun-20 A 26-Jun-20 50

ShaftsShaftsShaftsShaftsShaftsShafts

ElevatorElevatorElevatorElevatorElevatorElevator

A1820 Install Elevators 1, 2, & 3 Shafts 8 01-Jul-20 10-Jul-20 12

A1830 Install Elevator 4 Shaft 8 13-Jul-20 22-Jul-20 12

StairwayStairwayStairwayStairwayStairwayStairway

A1840 Install Stair 1 Shaft 8 01-Jul-20 10-Jul-20 12

A1850 Install Stair 2 Shaft 8 13-Jul-20 22-Jul-20 12

Structural SteelStructural SteelStructural SteelStructural SteelStructural SteelStructural Steel

Floors 2 & 3Floors 2 & 3Floors 2 & 3Floors 2 & 3Floors 2 & 3Floors 2 & 3

A1740 Set Columns & Beams (Line 5 - 13 Rows A - E) 8 10-Aug-20 19-Aug-20 0

A1750 Set Columns & Beams (Line 1 - 4 Rows A - E) 8 20-Aug-20 31-Aug-20 16

A6300 Deck Floor 2 9 20-Aug-20 01-Sep-20 0

A6310 Detail Floor 2 10 02-Sep-20 15-Sep-20 5

A6320 Deck Floor 3 9 16-Sep-20 28-Sep-20 5

A6330 Detail Floor 3 10 29-Sep-20 12-Oct-20 5

Floor 4 & RoofFloor 4 & RoofFloor 4 & RoofFloor 4 & RoofFloor 4 & RoofFloor 4 & Roof

A1770 Set Columns & Beams (Line 5 - 13 Rows A - E) 8 27-Aug-20 07-Sep-20 0

A1780 Set Columns & Beams (Line 1 - 4 Rows A - E) 8 08-Sep-20 17-Sep-20 11

A6340 Deck Floor 4 9 08-Sep-20 18-Sep-20 0

A6350 Detail Floor 4 10 21-Sep-20 02-Oct-20 0

A1810 Deck & Detail Roof 10 05-Oct-20 16-Oct-20 0

FacadeFacadeFacadeFacadeFacadeFacade

A5210 West Elevation 80 16-Oct-20 04-Feb-21 12

A5220 North Elevation 48 27-Oct-20 31-Dec-20 37

A5230 East Elevation 64 04-Nov-20 01-Feb-21 15

A5240 South Elevation 59 16-Nov-20 04-Feb-21 12

C1240 Water Tight 0 04-Jan-21 2

West ElevationWest ElevationWest ElevationWest ElevationWest ElevationWest Elevation

16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34

Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

2020 2021

Structural Steel / Detailing / Composite Deck

Pour SOD Level 2

Pour SOD Level 3

Pour SOD Level 4

Spray Fireproofing

Excavate Interiror Footings

Backfill Foundations West

Backfill Foundations South

Backfill Foundations East

Backfill Foundations North

FRP Interiror Footings & Walls

FRP Loading Dock Foundations

Waterproof Foundations East

Install Elevators 1, 2, & 3 Shafts

Install Elevator 4 Shaft

Install Stair 1 Shaft

Install Stair 2 Shaft

Set Columns & Beams (Line 5 - 13 Rows A - E)

Set Columns & Beams (Line 1 - 4 Rows A - E)

Deck Floor 2

Detail Floor 2

Deck Floor 3

Detail Floor 3

Set Columns & Beams (Line 5 - 13 Rows A - E)

Set Columns & Beams (Line 1 - 4 Rows A - E)

Deck Floor 4

Detail Floor 4

Deck & Detail Roof

West Elevation

North Elevation

East Elevation

South Elevation

Water Tight

PROJECT ID: 220031.001

DATA DATE: 26-Jun-20

PRINT DATE: 26-Jun-20

Remaining Level of Effort

Actual Level of Effort

Completed Work

Remainin...

Critical Re...

Milestone

UMass VA

Start Finish Total Float

A3840 Exterior Framing West Elevation 7 16-Oct-20 26-Oct-20 2

A3850 Sheathing West Elevation 8 22-Oct-20 02-Nov-20 2

A3870 AVB West Elevation 10 29-Oct-20 11-Nov-20 2

A3860 Clip Angles/Supports West Elevation 3 03-Nov-20 05-Nov-20 8

A3880 Install Punched Windows West Elevation 20 27-Nov-20 24-Dec-20 17

A3890 Install Curtainwall West Elevation 5 18-Dec-20 24-Dec-20 17

A3920 Install ACM Panels West Elevation 10 25-Dec-20 07-Jan-21 17

A3900 Install Granite Base West Elevation 10 08-Jan-21 21-Jan-21 17

A3910 Install Terra Cotta West Elevation 20 08-Jan-21 04-Feb-21 12

A3930 Caulking West Elevation 5 22-Jan-21 28-Jan-21 17

North ElevationNorth ElevationNorth ElevationNorth ElevationNorth ElevationNorth Elevation

A3940 Exterior Framing North Elevation 6 27-Oct-20 03-Nov-20 3

A3950 Sheathing North Elevation 6 03-Nov-20 10-Nov-20 3

A3960 Clip Angles/Supports North Elevation 5 06-Nov-20 12-Nov-20 8

A3970 AVB North Elevation 5 12-Nov-20 18-Nov-20 2

A3990 Install Curtainwall North Elevation 20 17-Nov-20 14-Dec-20 37

A4020 Install ACM Panels North Elevation 10 01-Dec-20 14-Dec-20 37

A4000 Install Granite Base North Elevation 8 15-Dec-20 24-Dec-20 37

A4030 Caulking North Elevation 10 18-Dec-20 31-Dec-20 37

East ElevationEast ElevationEast ElevationEast ElevationEast ElevationEast Elevation

A4040 Exterior Framing East Elevation 8 04-Nov-20 13-Nov-20 3

A4050 Sheathing East Elevation 8 11-Nov-20 20-Nov-20 3

A4060 Clip Angles/Supports East Elevation 5 13-Nov-20 19-Nov-20 8

A4070 AVB East Elevation 12 19-Nov-20 04-Dec-20 2

A4090 Install Curtainwall East Elevation 25 26-Nov-20 30-Dec-20 26

A4080 Install Punched Windows East Elevation 20 27-Nov-20 24-Dec-20 15

A4120 Install ACM Panels East Elevation 25 11-Dec-20 14-Jan-21 15

A4100 Install Granite Base East Elevation 10 08-Jan-21 21-Jan-21 15

A4130 Caulking East Elevation 12 15-Jan-21 01-Feb-21 15

South ElevationSouth ElevationSouth ElevationSouth ElevationSouth ElevationSouth Elevation

A4140 Exterior Framing South Elevation 6 16-Nov-20 23-Nov-20 8

A4160 Clip Angles/Supports South Elevation 5 20-Nov-20 26-Nov-20 8

A4150 Sheathing South Elevation 6 23-Nov-20 30-Nov-20 6

A4170 AVB South Elevation 10 07-Dec-20 18-Dec-20 2

A4180 Install Punched Windows South Elevation 10 21-Dec-20 01-Jan-21 29

A4190 Install Curtainwall South Elevation 10 21-Dec-20 01-Jan-21 29

A4220 Install ACM Panels South Elevation 10 21-Dec-20 01-Jan-21 24

A4200 Install Granite Base South Elevation 8 04-Jan-21 13-Jan-21 24

A4210 Install Terra Cotta South Elevation 20 08-Jan-21 04-Feb-21 12

A4230 Caulking South Elevation 7 11-Jan-21 19-Jan-21 24

BridgeBridgeBridgeBridgeBridgeBridge

A4240 Exterior Framing Bridge 5 21-Dec-20 25-Dec-20 2

A4250 Sheathing Bridge 5 24-Dec-20 30-Dec-20 2

A4260 Clip Angles/Supports Bridge 3 28-Dec-20 30-Dec-20 21

A4270 AVB Bridge 5 29-Dec-20 04-Jan-21 2

16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34

Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

2020 2021

Exterior Framing West Elevation

Sheathing West Elevation

AVB West Elevation

Clip Angles/Supports West Elevation

Install Punched Windows West Elevation

Install Curtainwall West Elevation

Install ACM Panels West Elevation

Install Granite Base West Elevation

Install Terra Cotta West Elevation

Caulking West Elevation

Exterior Framing North Elevation

Sheathing North Elevation

Clip Angles/Supports North Elevation

AVB North Elevation

Install Curtainwall North Elevation

Install ACM Panels North Elevation

Install Granite Base North Elevation

Caulking North Elevation

Exterior Framing East Elevation

Sheathing East Elevation

Clip Angles/Supports East Elevation

AVB East Elevation

Install Curtainwall East Elevation

Install Punched Windows East Elevation

Install ACM Panels East Elevation

Install Granite Base East Elevation

Caulking East Elevation

Exterior Framing South Elevation

Clip Angles/Supports South Elevation

Sheathing South Elevation

AVB South Elevation

Install Punched Windows South Elevation

Install Curtainwall South Elevation

Install ACM Panels South Elevation

Install Granite Base South Elevation

Install Terra Cotta South Elevation

Caulking South Elevation

Exterior Framing Bridge

Sheathing Bridge

Clip Angles/Supports Bridge

AVB Bridge

PROJECT ID: 220031.001

DATA DATE: 26-Jun-20

PRINT DATE: 26-Jun-20

Remaining Level of Effort

Actual Level of Effort

Completed Work

Remainin...

Critical Re...

Milestone

UMass VA

Start Finish Total Float

A4290 Install Curtainwall Bridge 5 05-Jan-21 11-Jan-21 18

A4320 Install ACM Panels Bridge 8 12-Jan-21 21-Jan-21 18

A4330 Caulking Bridge 7 19-Jan-21 27-Jan-21 18

RoofRoofRoofRoofRoofRoof

A5100 Rooftop MEP Openings 8 19-Oct-20 28-Oct-20 44

A5110 Rooftop Mechanical Supports/Curbs 8 23-Oct-20 03-Nov-20 44

A6360 Insulation 8 04-Nov-20 13-Nov-20 44

A6370 Roof Memvrane 8 16-Nov-20 25-Nov-20 44

A6380 Detail 4 26-Nov-20 01-Dec-20 44

C1190 Bulk Water Tight (Roof Drains Tied In) 0 01-Dec-20 41

C1170 Roof Top MEP Equip. Fitup / Trim Out / Start Ups 88 11-Dec-20 19-Apr-21 44

Rigging Rooftop EquipmentRigging Rooftop EquipmentRigging Rooftop EquipmentRigging Rooftop EquipmentRigging Rooftop EquipmentRigging Rooftop Equipment

A5120 RTUs 3 11-Dec-20 15-Dec-20 45

A5130 Chiller 2 16-Dec-20 17-Dec-20 45

A5140 Exhaust Fans 2 18-Dec-20 21-Dec-20 45

Rooftop MEPRooftop MEPRooftop MEPRooftop MEPRooftop MEPRooftop MEP

A6420 HVAC Piping - Mains (CHW/HW) 15 22-Dec-20 11-Jan-21 45

A6430 HVAC Piping - Branch (CHW/HW) 15 12-Jan-21 01-Feb-21 45

A5160 HVAC Risers to RTUs 15 26-Jan-21 15-Feb-21 45

A6440 Rough Electrical - Piping 15 09-Feb-21 01-Mar-21 45

A6450 Rough Electrical - Pull Wires 10 02-Mar-21 15-Mar-21 45

A5180 BAS Controls 20 09-Mar-21 05-Apr-21 45

A5190 Power to Equipment 5 06-Apr-21 12-Apr-21 45

A5200 Fire Alarm Tie-in 5 13-Apr-21 19-Apr-21 45

ElevatorsElevatorsElevatorsElevatorsElevatorsElevators

Passenger Elevators 1-3Passenger Elevators 1-3Passenger Elevators 1-3Passenger Elevators 1-3Passenger Elevators 1-3Passenger Elevators 1-3

A6480 Rails - Passenger Elevators 1-3 13 02-Dec-20 18-Dec-20 44

A6490 Platforms - Passenger Elevators 1-3 13 21-Dec-20 06-Jan-21 44

A6500 Cable - Passenger Elevators 1-3 13 07-Jan-21 25-Jan-21 44

A6510 Raceways - Passenger Elevators 1-3 13 26-Jan-21 11-Feb-21 44

A6520 Sills and Doors - Passenger Elevators 1-3 13 12-Feb-21 02-Mar-21 44

A6530 Controls - Passenger Elevators 1-3 13 03-Mar-21 19-Mar-21 44

A6540 Cab Finishes - Passenger Elevators 1-3 13 22-Mar-21 07-Apr-21 44

A6550 Buttons and Indicators - Passenger Elevators 1-3 14 08-Apr-21 27-Apr-21 44

Service Elevator 4Service Elevator 4Service Elevator 4Service Elevator 4Service Elevator 4Service Elevator 4

A6560 Rails - Service Elevator 4 13 02-Dec-20 18-Dec-20 44

A6570 Platforms - Service Elevator 4 13 21-Dec-20 06-Jan-21 44

A6580 Cable - Service Elevator 4 13 07-Jan-21 25-Jan-21 44

A6590 Raceways - Service Elevator 4 13 26-Jan-21 11-Feb-21 44

A6600 Sills and Doors - Service Elevator 4 13 12-Feb-21 02-Mar-21 44

A6610 Controls - Service Elevator 4 13 03-Mar-21 19-Mar-21 44

A6620 Cab Finishes - Service Elevator 4 13 22-Mar-21 07-Apr-21 44

A6630 Buttons and Indicators - Service Elevator 4 14 08-Apr-21 27-Apr-21 44

InteriorsInteriorsInteriorsInteriorsInteriorsInteriors

RisersRisersRisersRisersRisersRisers

16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34

Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

2020 2021

Install Curtainwall Bridge

Install ACM Panels Bridge

Caulking Bridge

Rooftop MEP Openings

Rooftop Mechanical Supports/Curbs

Insulation

Roof Memvrane

Detail

Bulk Water Tight (Roof Drains Tied In)

Roof Top MEP Equip. Fitup / Trim Out / Start Ups

RTUs

Chiller

Exhaust Fans

HVAC Piping - Mains (CHW/HW)

HVAC Piping - Branch (CHW/HW)

HVAC Risers to RTUs

Rough Electrical - Piping

Rough Electrical - Pull Wires

BAS Controls

Power to Equipment

Fire Alarm Tie-in

Rails - Passenger Elevators 1-3

Platforms - Passenger Elevators 1-3

Cable - Passenger Elevators 1-3

Raceways - Passenger Elevators 1-3

Sills and Doors - Passenger Elevators 1-3

Controls - Passenger Elevators 1-3

Cab Finishes - Passenger Elevators 1-3

Buttons and Indicators - Passenger Elevators 1-3

Rails - Service Elevator 4

Platforms - Service Elevator 4

Cable - Service Elevator 4

Raceways - Service Elevator 4

Sills and Doors - Service Elevator 4

Controls - Service Elevator 4

Cab Finishes - Service Elevator 4

Buttons and Indicators - Service Elevator 4

PROJECT ID: 220031.001

DATA DATE: 26-Jun-20

PRINT DATE: 26-Jun-20

Remaining Level of Effort

Actual Level of Effort

Completed Work

Remainin...

Critical Re...

Milestone

UMass VA

Start Finish Total Float

87 Layout C/S Framing 8 08-Oct-20 19-Oct-20 0

88 C/S Frame Shafts/Electric Rooms - North 10 20-Oct-20 02-Nov-20 0

96 Plumbing - Storm Leader 10 27-Oct-20 09-Nov-20 0

101 Fire Protection - Standpipe 10 27-Oct-20 09-Nov-20 15

89 HVAC Piping - CHW 15 27-Oct-20 16-Nov-20 36

92 Electrical Feeders - Normal 15 27-Oct-20 16-Nov-20 31

97 Plumbing - Gas 10 03-Nov-20 16-Nov-20 0

A6460 C/S Frame Shafts/Electric Rooms - South 10 03-Nov-20 16-Nov-20 36

90 HVAC Piping - HW 15 03-Nov-20 23-Nov-20 36

98 Plumbing - CW 10 10-Nov-20 23-Nov-20 0

A6470 Fire Protection - Standpipe 10 10-Nov-20 23-Nov-20 15

91 HVAC - Ductwork 15 10-Nov-20 30-Nov-20 46

93 Electrical Feeders - Emergency 15 10-Nov-20 30-Nov-20 31

95 Tel/Data 10 17-Nov-20 30-Nov-20 36

99 Plumbing - Waste/Vent 10 17-Nov-20 30-Nov-20 15

100 Plumbing - Pump DIscharge 10 24-Nov-20 07-Dec-20 15

102 Fire Protection - Dry System 10 24-Nov-20 07-Dec-20 15

94 Electrical Feeders - Life Safety 15 24-Nov-20 14-Dec-20 31

Level 1Level 1Level 1Level 1Level 1Level 1

RoughRoughRoughRoughRoughRough

Overhead MEPOverhead MEPOverhead MEPOverhead MEPOverhead MEPOverhead MEP

106 Level 1 HVAC Piping - CHW 25 10-Nov-20 14-Dec-20 41

107 Level 1 HVAC Piping - HW 25 17-Nov-20 21-Dec-20 36

110 Level 1 Electrical Power/Lighting Conduit 40 17-Nov-20 11-Jan-21 46

111 Level 1 Fire Protection Mains 15 24-Nov-20 14-Dec-20 41

108 Level 1 HVAC Equipment/Ductwork 30 24-Nov-20 04-Jan-21 46

109 Level 1 Plumbing - CWS/HWS/R 30 24-Nov-20 04-Jan-21 0

MEPMEPMEPMEPMEPMEP

114 Level 1 Electrical Panels/Transformers 15 01-Dec-20 21-Dec-20 36

112 Level 1 HVAC Control Pathways/Panels 25 08-Dec-20 11-Jan-21 46

113 Level 1 Tel/Data 25 08-Dec-20 11-Jan-21 46

116 Level 1 Network Switch - DEMARC RM 10 15-Dec-20 28-Dec-20 31

115 Level 1 Fire Alarm 25 15-Dec-20 18-Jan-21 41

117 Level 1 In-Wall Rough 25 29-Dec-20 01-Feb-21 0

Mechanical Room Level 1Mechanical Room Level 1Mechanical Room Level 1Mechanical Room Level 1Mechanical Room Level 1Mechanical Room Level 1

A4790 Fire Service - Check Valve 10 27-Oct-20 09-Nov-20 51

A4740 Equipment Pads 10 17-Nov-20 30-Nov-20 46

A4760 Install HW/CHW Pump Skids 10 01-Dec-20 14-Dec-20 66

A4780 HVAC Piping/Controllers 40 15-Dec-20 08-Feb-21 66

FinishesFinishesFinishesFinishesFinishesFinishes

124 Level 1 C/S GWB 15 02-Feb-21 22-Feb-21 0

125 Level 1 C/S Tape/Paint 20 16-Feb-21 15-Mar-21 0

126 Level 1 C/S Ceilings 15 02-Mar-21 22-Mar-21 41

128 Level 1 C/S Bathrooms 30 09-Mar-21 19-Apr-21 0

127 Level 1 C/S MEP Finish 15 16-Mar-21 05-Apr-21 41

16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34

Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

2020 2021

Layout C/S Framing

C/S Frame Shafts/Electric Rooms - North

Plumbing - Storm Leader

Fire Protection - Standpipe

HVAC Piping - CHW

Electrical Feeders - Normal

Plumbing - Gas

C/S Frame Shafts/Electric Rooms - South

HVAC Piping - HW

Plumbing - CW

Fire Protection - Standpipe

HVAC - Ductwork

Electrical Feeders - Emergency

Tel/Data

Plumbing - Waste/Vent

Plumbing - Pump DIscharge

Fire Protection - Dry System

Electrical Feeders - Life Safety

Level 1 HVAC Piping - CHW

Level 1 HVAC Piping - HW

Level 1 Electrical Power/Lighting Conduit

Level 1 Fire Protection Mains

Level 1 HVAC Equipment/Ductwork

Level 1 Plumbing - CWS/HWS/R

Level 1 Electrical Panels/Transformers

Level 1 HVAC Control Pathways/Panels

Level 1 Tel/Data

Level 1 Network Switch - DEMARC RM

Level 1 Fire Alarm

Level 1 In-Wall Rough

Fire Service - Check Valve

Equipment Pads

Install HW/CHW Pump Skids

HVAC Piping/Controllers

Level 1 C/S GWB

Level 1 C/S Tape/Paint

Level 1 C/S Ceilings

Level 1 C/S Bathrooms

Level 1 C/S MEP Finish

PROJECT ID: 220031.001

DATA DATE: 26-Jun-20

PRINT DATE: 26-Jun-20

Remaining Level of Effort

Actual Level of Effort

Completed Work

Remainin...

Critical Re...

Milestone

UMass VA

Start Finish Total Float

129 Level 1 C/S Lobby Flooring/Wall Tile 30 20-Apr-21 31-May-21 31

130 Level 1 C/S Lobby/Entry Vestibule 20 01-Jun-21 28-Jun-21 31

Level 2Level 2Level 2Level 2Level 2Level 2

RoughRoughRoughRoughRoughRough

Overhead MEPOverhead MEPOverhead MEPOverhead MEPOverhead MEPOverhead MEP

A5310 Level 2 HVAC Piping - CHW 25 17-Nov-20 21-Dec-20 41

A5320 Level 2 HVAC Piping - HW 25 24-Nov-20 28-Dec-20 36

A5330 Level 2 Electrical Power/Lighting Conduit 40 24-Nov-20 18-Jan-21 46

A5350 Level 2 Fire Protection Mains 15 01-Dec-20 21-Dec-20 41

A5340 Level 2 HVAC Equipment/Ductwork 30 01-Dec-20 11-Jan-21 51

A5360 Level 2 Plumbing - CWS/HWS/R 30 01-Dec-20 11-Jan-21 51

MEPMEPMEPMEPMEPMEP

A5370 Level 2 Electrical Panels/Transformers 15 08-Dec-20 28-Dec-20 36

A5380 Level 2 HVAC Control Pathways/Panels 25 15-Dec-20 18-Jan-21 46

A5390 Level 2 Tel/Data 25 15-Dec-20 18-Jan-21 46

A5410 Level 2 Network Switch - DEMARC RM 10 22-Dec-20 04-Jan-21 31

A5400 Level 2 Fire Alarm 25 22-Dec-20 25-Jan-21 41

A5420 Level 2 In-Wall Rough 25 05-Jan-21 08-Feb-21 31

Main Electrical RoomMain Electrical RoomMain Electrical RoomMain Electrical RoomMain Electrical RoomMain Electrical Room

A5500 Equipment Pads 10 24-Nov-20 07-Dec-20 46

A5510 Set Switchgear/ATS 10 08-Dec-20 21-Dec-20 46

A5520 Electrical Panels/Transformers 10 15-Dec-20 28-Dec-20 46

C1160 Electrical Room. Fitup / Trim Out / Start Ups 50 29-Dec-20 11-Mar-21 43

A5530 Fire Alarm Equipment 25 11-Feb-21 17-Mar-21 44

C1270 Permanent Power Available 0 11-Mar-21 49

FinishesFinishesFinishesFinishesFinishesFinishes

A5430 Level 2 C/S GWB 15 09-Feb-21 01-Mar-21 0

A5440 Level 2 C/S Tape/Paint 20 23-Feb-21 22-Mar-21 0

A5450 Level 2 C/S Ceilings 15 09-Mar-21 29-Mar-21 41

A5460 Level 2 C/S Bathrooms 30 16-Mar-21 26-Apr-21 0

A5470 Level 2 C/S MEP Finish 15 23-Mar-21 12-Apr-21 41

A5480 Level 2 C/S Lobby Flooring/Wall Tile 30 27-Apr-21 07-Jun-21 31

A5490 Level 2 C/S Lobby/Entry Vestibule 20 08-Jun-21 05-Jul-21 31

Level 3Level 3Level 3Level 3Level 3Level 3

RoughRoughRoughRoughRoughRough

Overhead MEPOverhead MEPOverhead MEPOverhead MEPOverhead MEPOverhead MEP

A5540 Level 3 HVAC Piping - CHW 25 24-Nov-20 28-Dec-20 41

A5550 Level 3 HVAC Piping - HW 25 01-Dec-20 04-Jan-21 36

A5560 Level 3 Electrical Power/Lighting Conduit 40 01-Dec-20 25-Jan-21 46

A5580 Level 3 Fire Protection Mains 15 08-Dec-20 28-Dec-20 41

A5570 Level 3 HVAC Equipment/Ductwork 30 08-Dec-20 18-Jan-21 51

A5590 Level 3 Plumbing - CWS/HWS/R 30 08-Dec-20 18-Jan-21 51

MEPMEPMEPMEPMEPMEP

A5660 Level 3 Electrical Panels/Transformers 15 15-Dec-20 04-Jan-21 36

A5670 Level 3 HVAC Control Pathways/Panels 25 22-Dec-20 25-Jan-21 46

16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34

Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

2020 2021

Level 1 C/S Lobby Flooring/Wall Tile

Level 1 C/S Lobby/Entry Vestibule

Level 2 HVAC Piping - CHW

Level 2 HVAC Piping - HW

Level 2 Electrical Power/Lighting Conduit

Level 2 Fire Protection Mains

Level 2 HVAC Equipment/Ductwork

Level 2 Plumbing - CWS/HWS/R

Level 2 Electrical Panels/Transformers

Level 2 HVAC Control Pathways/Panels

Level 2 Tel/Data

Level 2 Network Switch - DEMARC RM

Level 2 Fire Alarm

Level 2 In-Wall Rough

Equipment Pads

Set Switchgear/ATS

Electrical Panels/Transformers

Electrical Room. Fitup / Trim Out / Start Ups

Fire Alarm Equipment

Permanent Power Available

Level 2 C/S GWB

Level 2 C/S Tape/Paint

Level 2 C/S Ceilings

Level 2 C/S Bathrooms

Level 2 C/S MEP Finish

Level 2 C/S Lobby Flooring/Wall Tile

Level 2 C/S Lobby/Entry Vestibule

Level 3 HVAC Piping - CHW

Level 3 HVAC Piping - HW

Level 3 Electrical Power/Lighting Conduit

Level 3 Fire Protection Mains

Level 3 HVAC Equipment/Ductwork

Level 3 Plumbing - CWS/HWS/R

Level 3 Electrical Panels/Transformers

Level 3 HVAC Control Pathways/Panels

PROJECT ID: 220031.001

DATA DATE: 26-Jun-20

PRINT DATE: 26-Jun-20

Remaining Level of Effort

Actual Level of Effort

Completed Work

Remainin...

Critical Re...

Milestone

UMass VA

Start Finish Total Float

A5680 Level 3 Tel/Data 25 22-Dec-20 25-Jan-21 46

A5700 Level 3 Network Switch - DEMARC RM 10 29-Dec-20 11-Jan-21 31

A5690 Level 3 Fire Alarm 25 29-Dec-20 01-Feb-21 41

A5710 Level 3 In-Wall Rough 25 12-Jan-21 15-Feb-21 31

FinishesFinishesFinishesFinishesFinishesFinishes

A5780 Level 3 C/S GWB 15 16-Feb-21 08-Mar-21 31

A5790 Level 3 C/S Tape/Paint 20 02-Mar-21 29-Mar-21 31

A5800 Level 3 C/S Ceilings 15 16-Mar-21 05-Apr-21 41

A5820 Level 3 C/S Bathrooms 30 23-Mar-21 03-May-21 31

A5810 Level 3 C/S MEP Finish 15 30-Mar-21 19-Apr-21 41

A5830 Level 3 C/S Lobby Flooring/Wall Tile 30 04-May-21 14-Jun-21 31

A5840 Level 3 C/S Lobby/Entry Vestibule 20 15-Jun-21 12-Jul-21 31

BridgeBridgeBridgeBridgeBridgeBridge

A5920 Bridge MEP Rough 30 29-Dec-20 08-Feb-21 76

A5930 Bridge Ceilings 20 13-Apr-21 10-May-21 41

A5940 Bridge Flooring 20 11-May-21 07-Jun-21 41

A5950 Bridge Finishes 20 08-Jun-21 05-Jul-21 41

Level 4Level 4Level 4Level 4Level 4Level 4

RoughRoughRoughRoughRoughRough

Overhead MEPOverhead MEPOverhead MEPOverhead MEPOverhead MEPOverhead MEP

A5600 Level 4 HVAC Piping - CHW 25 01-Dec-20 04-Jan-21 41

A5610 Level 4 HVAC Piping - HW 25 08-Dec-20 11-Jan-21 36

A5620 Level 4…

This is the start of the file's text. The full file is on GovTribe.