Attachment D - Financial Management Reporting.pdf
PDF 112 KB Posted
- Attached to
- Cybersecurity and Privacy Enterprise Solutions and Services (CyPrESS) Federal contract opportunity
- Solicitation number
- 80TECH21R0007
About this file
This document provides requirements for financial management reporting on the NASA contract for Cybersecurity and Privacy Enterprise Solutions and Services. The contractor must submit NASA Form 533 reports at the total contract level for the core baseline portion and at the individual task order level for each issued task order. The reports must break down hours and costs by labor categories, overhead expenses, other direct costs including subcontracts and materials, and total cost-plus-award-fee. Variances exceeding 10% between estimated and actual total direct labor hours and costs require a narrative explanation addressing the reason for variance and corrective actions. Reports are due monthly using Form 533M within 10 days of the accounting period close and quarterly using Form 533Q within 15 days prior to the quarter.
View the file
Other files for this federal contract opportunity
Show all 50
Cybersecurity and Privacy Enterprise Solutions and Services (CyPrESS) has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT D
FINANCIAL MANAGEMENT REPORTING
REQUIREMENTS
RFP 80TECH21R0007
CONTRACT # TBD
JUNE 2014
Contract TBD Attachment D
FINANCIAL MANAGEMENT REPORTING REQUIREMENTS
Financial Management Reports shall be submitted by the Contractor on the NASA 533 series reports, in accordance with the instructions on the reverse of the forms, NASA Procedural Requirements NPR 9501.2E entitled "NASA Contractor Financial Management Reporting,” dated May 27, 2011, and additional instructions issued by the Contracting Officer.
a. Level of Detail
For the Core baseline portion of the contract, the Contractor’s 533 Reports shall contain a summary of total Core baseline contract costs at the total contract level.
An individual 533 Report shall be provided for each Task Order at the total Task Order level, in addition to a cumulative 533 Report summarizing all Task Orders issued.
The reports shall contain a breakdown of hours and costs by the elements of cost categories listed in Section d below.
b. Variance Narrative Reporting
In accordance with Section 3.6 of NPR 9501.2, the Contractor shall include a narrative explanation for variances exceeding plus or minus 10 percent (+/- 10%) between the Total Direct Labor Hours (prime and subcontractors) and/or Total Estimated Cost amount shown in the prior month and the Actual Total Direct Labor Hours and/or Actual Total Cost amount shown in the current month for each individual Task Order and at the Core baseline total contract level. (For example, the Total Estimated Cost amount shown for June in column 8a in the May NF 533M and the Actual June Total Cost amount shown in column 7a in the June NF 533M.)
Each variance narrative shall explain the: (1) reason for the variance, (2) impact(s) on the Core baseline and/or each individual task order, and (3) specific corrective action(s) being taken or to be taken.
c. Distribution
The Contractor shall distribute 533 reports to each addressee indicated in the contract clause entitled, "Financial Management Reporting." The Contractor shall submit an initial report in the NF 533Q format within 30 working days after contract award.
After the initial report, the NF 533M reports shall be distributed not later than the tenth (10th) working day following the close of the contractors' monthly accounting period.
The 533Q reports shall be distributed not later than the fifteenth (15th) day of the month preceding the quarter being reported. The NF 533M need not be submitted in months in which an NF 533Q is submitted.
(06/2014) 3
d. Reporting Requirements
Each individual report shall, at a minimum, provide cost data by the following elements of cost categories:
1. Prime Direct Labor Hours:
(List all applicable labor categories)
Total Prime Direct Labor Hours
2. Subcontractor Direct Labor Hours:
Subcontractor A Direct Labor Hours
Subcontractor B Direct Labor Hours (List all applicable labor categories)
Subcontractor C Direct Labor Hours
Total Subcontractors Direct Labor Hours
3. Total Prime and Subcontractors Direct Labor Hours
4. Prime Direct Labor Costs:
Total Prime Direct Labor Costs
5. Subcontractor Direct Labor Costs:
Total Subcontractor Direct Labor Costs
6. Total Prime and Subcontractors Direct Labor Costs
7. Prime Overhead Expense
8. Other Direct Costs (ODCs):
a. Subcontracts (list separately, Subcontractor A, B, C, etc.)
b. Material
c. Travel
(06/2014) 4
d. Other (specify)
Total ODCs
9. Subtotal (Direct Labor, Overhead & ODCs)
10. G&A Expense
11. Total Estimated Cost
12. Provisionally Billed Award Fee
13. Award Fee Earned
14. Total Cost-Plus-Award-Fee (CPAF)