Attachment C - Wage_Determination_NJ20260042_05.18.2026.docx
DOCX document 47 KB Posted
- Attached to
- J039--561A4-25-500 Elevator Upgrade & Modernization Repairs at VA NJ HCS Lyons Buildings 6 & 53
- Solicitation number
- 36C24226R0097
About this file
This is a Wage Determination document establishing prevailing wage rates for construction work in Somerset County, New Jersey, effective May 18, 2026, applicable to federal construction contracts subject to the Davis-Bacon Act.
The wage determination covers numerous construction trade classifications including asbestos workers, bricklayers, carpenters, electricians, elevator mechanics, ironworkers, laborers, painters, plumbers, pipefitters, roofers, sprinkler fitters, sheet metal workers, and truck drivers. Rates vary significantly by classification and geographic subdivision within Somerset County, with hourly wage rates ranging from approximately $28 to $70 per hour plus fringe benefits. Notable rates include Elevator Mechanic (all other work) at $57.01 per hour with $27.61 fringe; Electrician at $65.43 per hour with $42.86 fringe; Plumber at $62.09 per hour with $45.05 fringe; and Sprinkler Fitter at $67.97 per hour with $39.35 fringe. Many classifications include special provisions for hazardous work, elevated work, overtime, and paid holidays. The document specifies that contractors must comply with Executive Order 13706 regarding paid sick leave (1 hour per 30 hours worked, up to 56 hours annually) for contracts awarded on or after January 1, 2017. Welders receive rates for their primary craft, and unlisted classifications may be added post-award through labor standards contract clauses. This wage determination directly applies to the Elevator Upgrade & Modernization Repairs project at VA New Jersey Healthcare System Lyons Campus, requiring contractors to pay prevailing wages to all workers performing the elevator upgrade work on the three passenger elevators and one service elevator in Buildings 6 and 53.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24226R0097_8.docx | DOCX document | |
| 36C24226R0097_7.docx | DOCX document | |
| 36C24226R0097_6.docx | DOCX document | |
| 36C24226R0097_5.docx | DOCX document | |
| 36C24226R0097_4.docx | DOCX document | |
| 36C24226R0097_3.docx | DOCX document | |
| 36C24226R0097_2.docx | DOCX document | |
| Attachment B - SOW_Lyons VAMC Elevators Repair Bldgs 6 and 53.docx | DOCX document | |
| Attachment E - VAAR 852.219-75 Limitation of Subcontracting - Certificate of Compliance.docx | DOCX document | |
| Attachment D - FAR 52.225-2 Buy America Certificate - 36C24226R0097.docx | DOCX document | |
| Attachment A- Price Schedule - 36C24226R0097.docx | DOCX document | |
| 36C24226R0097.docx | DOCX document |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
General Decision Number: NJ20260042 05/18/2026
State: New Jersey
Construction Types: Building
Counties: New Jersey Counties of Somerset
Modification Number Publication Date 0 01/02/2026 1 05/18/2026
ASBE0032-007 09/19/2024
Rates Fringes
ASBESTOS WORKER/HEAT & FROST INSULATOR: INCLUDES
THE APPLICATION OF ALL INSULATING MATERIALS,
PROTECTIVE COVERINGS, COATINGS AND FINISHINGS TO
ALL TYPES OF MECHANICAL SYSTEMS; ALSO, THE
APPLICATION OF FIRESTOPPING MATERIAL TO OPENINGS
AND PENETRATIONS IN WALLS, FLOORS, CEILINGS AND
CURTAIN WALLS; ALSO, ALL LEAD ABATEMENT (SOMERSET
COUNTY (BOROUGHS OF BERNARDSVILLE AND BOUND BROOK;
TOWNSHIP OF BRIDGEWATER; BOROUGH OF FAR HILLS;
TOWNSHIP OF GREEN BROOK; BOROUGHS OF NORTH
PLAINFIELD, PEAPACK-GLADSTONE, RARITAN, SOMERVILLE,
SOUTH BOUND BROOK AND WATCHUNG; TOWNSHIP OF WARREN).$ 51.74 46.20
ASBE0089-007 07/01/2024
Rates Fringes
ASBESTOS WORKER/HEAT & FROST INSULATOR: INCLUDES
THE APPLICATION OF ALL INSULATING MATERIALS,
PROTECTIVE COVERINGS, COATINGS AND FINISHINGS TO
ALL TYPES OF MECHANICAL SYSTEMS; ALSO, THE
APPLICATION OF FIRESTOPPING MATERIAL TO OPENINGS
AND PENETRATIONS IN WALLS, FLOORS, CEILINGS AND
CURTAIN WALLS; ALSO, ALL LEAD ABATEMENT (SOMERSET
COUNTY (TOWNSHIPS OF BRANCHBURG, FRANKLIN,
HILLSBOROUGH AND MONTGOMERY))
PAID HOLIDAYS:
THE LAST DAY PRIOR TO THE CHRISTMAS AND NEW YEAR'S
DAY OBSERVED HOLIDAY: 4 HRS. PAY....................$ 55.80 40.80
BRNJ0002-013 05/01/2021
Rates Fringes
BRICKLAYER
WORK ON HIGH
STACKS: 22% PER HOUR ADDITIONAL.
.............$ 45.20 33.26
BRNJ0004-001 05/01/2025
Rates Fringes
CEMENT MASON........................................$ 49.60 37.96
BRNJ0007-001 06/02/2025
Rates Fringes
TILE SETTER.........................................$ 64.90 37.28
TILE FINISHER
WORK GROUTING ALL
EPOXY: $10.00 ADDITIONAL PER DAY....................$ 50.05 33.90
CARP0006-009 05/01/2025
Rates Fringes
CARPENTER: SCAFFOLD BUILDER
THE FIRST SIXTY FEET AT THE REGULAR
RATE, 10% PER HOUR ADDITIONAL FOR EACH ADDITIONAL
FIFTY FEET THEREAFTER.
.........................$ 57.42 34.17
CARP0006-011 05/01/2025
Rates Fringes
CARPENTER: INCLUDING ACOUSTICAL CEILING
INSTALLATION, DRYWALL HANGING, FORMWORK, BATT AND
BLOWN INSULATION....................................$ 57.42 34.17
CARP0715-007 05/01/2025
Rates Fringes
MILLWRIGHT
WORK OF ERECTION AND
DISMANTLING OF ELEVATORS AND TOWERS, SUCH AS
CONCRETE CONVEYORS AND TEMPORARY MATERIAL
ELEVATORS, SCAFFOLDING OR OTHER STRUCTURES TO BE
USED AS SCAFFOLDING INSIDE OR OUTSIDE OF BUILDINGS:
THE FIRST SIXTY FEET AT THE REGULAR RATE, 10% PER
HOUR ADDITIONAL FOR EACH ADDITIONAL FIFTY FEET
THEREAFTER..........................................$ 58.84 35.06
ELEC0102-022 06/02/2025
ELECTRICIAN: INCLUDING LOW VOLTAGE WIRING
(SOMERSET
COUNTY (DOES NOT INCLUDE THE TOWNSHIP OF FRANKLIN
EAST OF A LINE FOLLOWING CEDAR GROVE LANE FROM THE
RARITAN RIVER, IN A SOUTHWESTERLY DIRECTION, TO THE
MILLSTONE BRANCH OF THE PENNSYLVANIA RAILROAD;
THEN, WEST ALONG THE RAILROAD TO THE DELAWARE AND
RARITAN CANAL; THEN, SOUTH ALONG THE CANAL TO THE
MIDDLESEX COUNTY LINE; DOES NOT INCLUDE THE
TOWNSHIP OF MONTGOMERY WEST AND SOUTH OF A LINE
FOLLOWING U.S. HWY. 206 (FORMERLY STATE HWY. 31)
NORTH FROM THE MERCER COUNTY LINE TO HARLINGEN RD.;
THEN, WEST ALONG HARLINGEN RD. AND THE
DUTCHTOWN-ZION ROAD TO THE HILLSBOROUGH TOWNSHIP
LINE)
WORK FORTY FT. OR MORE ABOVE THE GROUND OR
PROTECTIVE RIGGING (DOES NOT APPLY TO POLE WORK, OR
TO USE OF A MANLIFT OR HIGH REACH-TYPE LIFT): 10%
PER HOUR
WORK WITH, OR THE REMOVAL OF, ASBESTOS MATERIALS:
112% TIMES THE JOURNEYMAN RATE......................$ 65.43 42.86
ELECTRICIAN: CABLE SPLICER (INCLUDING LOW VOLTAGE
WIRING)
(SOMERSET COUNTY (DOES NOT
INCLUDE THE TOWNSHIP OF FRANKLIN EAST OF A LINE
FOLLOWING CEDAR GROVE LANE FROM THE RARITAN RIVER,
IN A SOUTHWESTERLY DIRECTION, TO THE MILLSTONE
BRANCH OF THE PENNSYLVANIA RAILROAD; THEN, WEST
ALONG THE RAILROAD TO THE DELAWARE AND RARITAN
CANAL; THEN, SOUTH ALONG THE CANAL TO THE MIDDLESEX
COUNTY LINE; DOES NOT INCLUDE THE TOWNSHIP OF
MONTGOMERY WEST AND SOUTH OF A LINE FOLLOWING U.S.
HWY. 206 (FORMERLY STATE HWY. 31) NORTH FROM THE
MERCER COUNTY LINE TO HARLINGEN RD.; THEN, WEST
ALONG HARLINGEN RD. AND THE DUTCHTOWN-ZION ROAD TO
THE HILLSBOROUGH TOWNSHIP LINE)
WORK FORTY FT. OR MORE
ABOVE THE GROUND OR PROTECTIVE RIGGING (DOES NOT
APPLY TO POLE WORK, OR TO USE OF A MANLIFT OR HIGH
REACH-TYPE LIFT): 10% PER HOUR
WORK WITH, OR THE REMOVAL OF, ASBESTOS MATERIALS:
112% TIMES THE JOURNEYMAN RATE......................$ 69.72 44.27
ELEC0269-019 07/07/2025
ELECTRICIAN: INCLUDING LOW VOLTAGE WIRING
(SOMERSET
COUNTY (TOWNSHIP OF MONTGOMERY (WEST AND SOUTH OF A
LINE FOLLOWING U.S. HWY. 206 (FORMERLY STATE HWY.
31) NORTH FROM THE MERCER COUNTY LINE TO HARLINGEN
RD.; THEN, WEST ALONG HARLINGEN RD. AND THE
DUTCHTOWN-ZION ROAD TO THE HILLSBOROUGH TOWNSHIP
LINE)))
..........................................$ 61.84 40.32
ELEC0456-007 05/30/2022
Rates Fringes
ELECTRICIAN: INCLUDING LOW VOLTAGE WIRING
(SOMERSET COUNTY
(TOWNSHIP OF FRANKLIN (EAST OF A LINE FOLLOWING
CEDAR GROVE LANE FROM THE RARITAN RIVER, IN A
SOUTHWESTERLY DIRECTION, TO THE MILLSTONE BRANCH OF
THE PENNSYLVANIA RAILROAD; THEN, WEST ALONG THE
RAILROAD TO THE DELAWARE AND RARITAN CANAL; THEN,
SOUTH ALONG THE CANAL TO THE MIDDLESEX COUNTY
LINE))
WORK ON LINE VOLTAGE OF 440
VOLTS AND OVER: 10% PER HOUR ADDITIONAL. WORK FROM
TRUSSES, SCAFFOLDS AND LADDERS 40 FT. OR MORE FROM
THE GROUND OR FLOOR; OR UNDER AIR PRESSURE; OR OVER
CONVEYORS OR MOVING EQUIPMENT OR MACHINERY: 10% PER
HOUR ADDITIONAL.....................................$ 55.85 39.79
ELECTRICIAN: CABLE SPLICER (INCLUDING LOW VOLTAGE
WIRING)
(SOMERSET COUNTY (TOWNSHIP OF FRANKLIN (EAST OF
A LINE FOLLOWING CEDAR GROVE LANE FROM THE RARITAN
RIVER, IN A SOUTHWESTERLY DIRECTION, TO THE
MILLSTONE BRANCH OF THE PENNSYLVANIA RAILROAD;
THEN, WEST ALONG THE RAILROAD TO THE DELAWARE AND
RARITAN CANAL; THEN, SOUTH ALONG THE CANAL TO THE
MIDDLESEX COUNTY LINE))
WORK ON LINE VOLTAGE
OF 440 VOLTS AND OVER: 10% PER HOUR ADDITIONAL.
WORK FROM TRUSSES, SCAFFOLDS AND LADDERS 40 FT. OR
MORE FROM THE GROUND OR FLOOR; OR UNDER AIR
PRESSURE; OR OVER CONVEYORS OR MOVING EQUIPMENT OR
MACHINERY: 10% PER HOUR ADDITIONAL..................$ 65.35 46.56
ELEV0001-003 03/17/2013
Rates Fringes
ELEVATOR MECHANIC: ALL OTHER WORK
PAID
NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY,
MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, COLUMBUS
DAY, VETERAN'S DAY, THANKSGIVING DAY, THE FRIDAY
AFTER THANKSGIVING DAY, AND CHRISTMAS
PAID
A WORKER WHO HAS WORKED LESS THAN 5 YEARS: 4% OF
HIS OR HER HOURLY RATE FOR ALL HOURS
A WORKER WHO HAS WORKED 5 TO 10 YEARS: 6% OF HIS OR
HER HOURLY RATE FOR ALL HOURS
A WORKER WHO HAS WORKED 15 OR MORE YEARS: 8% OF HIS
OR HER HOURLY RATE FOR ALL HOURS WORKED.
...................................................$ 57.01 27.61
ELEVATOR MECHANIC: WORK ON THE ADDITION,
REPLACEMENT, REFURBISHING OR RELOCATION OF CONTROL,
DRIVE, GENERATING EQUIPMENT, HOISTWAY OR PIT
EQUIPMENT, INCLUDING WORK INVOLVING A STRUCTURAL
RISE IN THE ELEVATOR SHAFTS IN AN EXISTING BUILDING
AND OTHER ELEVATOR WORK IN THE MACHINE ROOM,
HOISTWAY OR PIT; ALSO, CHANGES IN DESIGN AND
APPEARANCE OF BASIC ESCALATOR EQUIPMENT
PAID
NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY,
MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, COLUMBUS
DAY, VETERAN'S DAY, THANKSGIVING DAY, THE FRIDAY
AFTER THANKSGIVING DAY, AND CHRISTMAS
PAID
A WORKER WHO HAS WORKED LESS THAN 5 YEARS: 4% OF
HIS OR HER HOURLY RATE FOR ALL HOURS
A WORKER WHO HAS WORKED 5 TO 10 YEARS: 6% OF HIS OR
HER HOURLY RATE FOR ALL HOURS
A WORKER WHO HAS WORKED 15 OR MORE YEARS: 8% OF HIS
OR HER HOURLY RATE FOR ALL HOURS WORKED.
...................................................$ 45.14 27.46
ENGI0825-020 07/01/2025
Rates Fringes
POWER EQUIPMENT OPERATOR: GROUP 5 OILER
HAZARDOUS WASTE REMOVAL WORK: WORK
ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE
SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH
HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE
EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE
PROTECTION: 20% PER HOUR ADDITIONAL.
PAID HOLIDAYS: NEW YEAR'S DAY,
WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY,
INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION
DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS
DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE
PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR,
THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY
AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS
THE WORK DAY BEFORE AND THE WORK DAY AFTER THE
HOLIDAY.............................................$ 52.88 37.50
POWER EQUIPMENT OPERATOR: GROUP 4 BOBCAT/SKID
LOADER; COMPRESSOR (SINGLE); FARM TRACTOR; FRONT
END LOADER (UNDER 1 CU. YD.); HYDROSEEDER; ROLLER,
GRADE; PUMP, HYDRAULIC
HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR
FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE
THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS
MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS
REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION:
20% PER HOUR ADDITIONAL.
PAID HOLIDAYS: NEW YEAR'S DAY,
WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY,
INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION
DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS
DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE
PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR,
THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY
AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS
THE WORK DAY BEFORE AND THE WORK DAY AFTER THE
HOLIDAY.............................................$ 56.59 37.50
POWER EQUIPMENT OPERATOR: GROUP 3 ASPHALT SPREADER;
BULLDOZER;COMPRESSOR(2 OR 3) (IN BATTERY) (WITHIN
100 FT.); FORKLIFT; FRONT END LOADER (1 CU. YD.
AND OVER BUT LESS THAN 2 CU. YD.); LULL; MECHANIC;
PAVER, ASPHALT; ROLLER, BLACKTOP; TRACTOR
HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR
FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE
THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS
MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS
REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION:
20% PER HOUR ADDITIONAL.
PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S
BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY,
LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S
DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED
1) THAT THE WORKER WORKS THREE OF THE PRECEDING
FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY
BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE
HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY
BEFORE AND THE WORK DAY AFTER THE HOLIDAY...........$ 58.22 37.50
POWER EQUIPMENT OPERATOR: GROUP 2 BACKHOE LOADER
COMBO; CONCRETE PUMPER; GRADER/BLADE (FINISH);
HOIST; HYDRAULIC CRANE, 10 TONS AND UNDER; FRONT
END LOADER (2 CU. YD. BUT LESS THAN 5 CU. YD.);
SCRAPER; SIDE BOOM
HAZARDOUS WASTE
REMOVAL WORK: WORK ON A STATE OR FEDERALLY
DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER
IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND
WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR
RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR
ADDITIONAL.
PAID HOLIDAYS: NEW YEAR'S DAY,
WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY,
INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION
DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS
DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE
PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR,
THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY
AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS
THE WORK DAY BEFORE AND THE WORK DAY AFTER THE
HOLIDAY.............................................$ 60.13 37.50
POWER EQUIPMENT OPERATOR: GROUP 1 BACKHOE,
INCLUDING BACKHOE TRACK; BOOM; CONCRETE PAVING
MACHINE; CRANE (ALL TYPES, INCLUDING OVERHEAD AND
STRADDLE TRAVELING TYPE); DRILL (DOWN-THE-HOLE
DRILL, ROTARY DRILL, SELF-PROPELLED HYDRAULIC
DRILL, SELF-POWERED DRILL); ELEVATING GRADER;
EXCAVATOR; FRONT END LOADER (5 CU. YD. AND OVER);
PILEDRIVER (LENGTH OF BOOM, INCLUDING LENGTH OF
LEADS, SHALL DETERMINE PREMIUM RATE APPLICABLE);
TRENCHER
HAZARDOUS
WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY
DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER
IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND
WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR
RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR
ADDITIONAL.
PAID
HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY
OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR
DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY,
THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1)
THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE
WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY
BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE
HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY
BEFORE AND THE WORK DAY AFTER THE HOLIDAY...........$ 61.72 37.50
IRON0011-010 07/01/2025
Rates Fringes
IRONWORKER: STRUCTURAL, ORNAMENTAL, RIGGER
(SOMERSET COUNTY (NORTHERN HALF OF COUNTY)).........$ 52.24 50.32
IRONWORKER: REINFORCING (SOMERSET COUNTY (NORTHERN
HALF OF COUNTY))....................................$ 49.94 50.32
IRON0399-018 07/01/2024
Rates Fringes
IRONWORKER: STRUCTURAL, ORNAMENTAL, RIGGER
(SOMERSET COUNTY (SOUTHERN HALF OF COUNTY)).........$ 54.24 38.40
IRONWORKER: REINFORCING (SOMERSET COUNTY (SOUTHERN
HALF OF COUNTY))....................................$ 53.24 38.40
LABO0008-001 05/01/2011
LABORER: ASBESTOS REMOVAL
THE REMOVAL, ABATEMENT, ENCLOSURE AND
DECONTAMINATION OF PERSONAL PROTECTIVE EQUIPMENT,
CHEMICAL PROTECTIVE CLOTHING AND MACHINERY RELATING
TO ASBESTOS AND/OR TOXIC AND HAZARDOUS WASTE OR
MATERIALS WHICH SHALL INCLUDE BUT NOT NECESSARILY
BE LIMITED TO: THE ERECTION, MOVING, SERVICING AND
DISMANTLING OF ALL ENCLOSURES, SCAFFOLDING AND
BARRICADES; THE OPERATION OF ALL TOOLS AND
EQUIPMENT NORMALLY USED IN THE REMOVAL OR ABATEMENT
OF ASBESTOS AND TOXIC OR HAZARDOUS WASTE OR
MATERIALS; THE LABELING, BAGGING, CARTONING,
CRATING, OR OTHER PACKAGING OF MATERIALS FOR
DISPOSAL; THE CLEAN-UP OF THE WORKSITE; AND ALL
OTHER WORK INCIDENTAL TO THE REMOVAL, ABATEMENT,
ENCAPSULATION, ENCLOSURE, AND DECONTAMINATION OF
ASBESTOS AND TOXIC OR HAZARDOUS WASTE OR MATERIALS;
AND, IN ADDITION, ALL WORK TASKS INVOLVED IN THE
MAINTENANCE AND OPERATION OF ENERGY RESOURCE
RECOVERY PLANTS (CO-GENERATION PLANTS)..............$ 28.37 21.62
LABO0077-002 05/01/2022
Rates Fringes
LABORER: MASON TENDER: BRICK/CEMENT/CONCRETE........$ 36.50 30.22
LABO0077-005 05/01/2022
Rates Fringes
LABORER: ASPHALT SHOVELER, ASPHALT SPREADER, COMMON
OR GENERAL LABORER, LANDSCAPE LABORER, POWER TOOL
OPERATOR AND SCREEDMAN..............................$ 35.75 30.22
PAIN0711-018 05/01/2025
Rates Fringes
DRYWALL FINISHER/TAPER..............................$ 44.87 30.15
PAIN0711-020 05/01/2025
Rates Fringes
PAINTER: BRUSH AND ROLLER...........................$ 45.55 29.86
PAINTER: PAPERHANGER................................$ 45.55 29.86
PAINTER: SPRAY......................................$ 45.55 29.86
PAIN0711-021 05/01/2025
Rates Fringes
GLAZIER
WORK WELDING OR USING A CUTTING TORCH:
$1.00 PER HOUR
WORK ON A SWING STAGE SCAFFOLD; ON A PIPE SCAFFOLD
PROVIDING THE WORKING HEIGHT OF THE PLATFORM IS 30
FT. OR ABOVE; AND ON MOTORIZED LIFTS PROVIDED THAT
THE HEIGHT OF THE LIFT PLATFORM IS ABOVE THE SECOND
FLOOR OR ABOVE THIRTY FEET: $1.00 PER HOUR
ADDITIONAL..........................................$ 52.68 31.29
PLAS0008-008 05/01/2021
Rates Fringes
PLASTERER...........................................$ 38.37 31.64
PLUM0009-020 07/01/2025
Rates Fringes
PLUMBER: EXCLUDING HVAC PIPE INSTALLATION (SOMERSET
COUNTY (TOWNSHIP OF MONTGOMERY; BOROUGH OF ROCKY
HILL))..............................................$ 59.57 46.45
PIPEFITTER: INCLUDING HVAC PIPE INSTALLATION
(SOMERSET COUNTY (TOWNSHIP OF MONTGOMERY; BOROUGH
OF ROCKY HILL)).....................................$ 59.57 46.45
PLUMBER/PIPEFITTER: SERVICE AND REPAIR (SOMERSET
COUNTY (TOWNSHIP OF MONTGOMERY; BOROUGH OF ROCKY
HILL))..............................................$ 46.23 29.23
PLUM0024-011 05/01/2025
Rates Fringes
PLUMBER: EXCLUDING HVAC PIPE INSTALLATION (SOMERSET
COUNTY (DOES NOT INCLUDE THE TOWNSHIP OF
MONTGOMERY; BOROUGH OF ROCKY HILL)).................$ 62.09 45.05
PLUM0475-012 05/01/2025
Rates Fringes
PIPEFITTER: INCLUDING HVAC PIPE INSTALLATION
(SOMERSET COUNTY (DOES NOT INCLUDE THE TOWNSHIP OF
MONTGOMERY; BOROUGH OF ROCKY HILL)).................$ 56.34 50.80
ROOF0004-004 06/01/2024
ROOFER: ALL TYPES
(SOMERSET COUNTY
(NORTH OF A LINE DRAWN FROM THE MERCER/SOMERSET
COUNTY LINE ALONG ROUTE #206 NORTH TO ROUTE #514;
THEN, WEST ALONG ROUTE #514 TO THE
HUNTERDON/SOMERSET COUNTY LINE))....................$ 44.52 32.25
ROOF0030-029 05/01/2025
Rates Fringes
ROOFER: SLATE AND TILE
(SOMERSET COUNTY (SOUTH OF A LINE DRAWN FROM THE
MERCER/SOMERSET COUNTY LINE NORTH ALONG ROUTE #206
TO ROUTE #514; THEN, WEST ALONG ROUTE #514 TO THE
HUNTERDON/SOMERSET COUNTY LINE)
MOPPER, AND
OPERATOR OF FELT-LAYING MACHINE: $0.50 PER HOUR
ADDITIONAL. WORK APPLYING ROOFING MATERIAL, ON ANY
NEW CONSTRUCTION JOB, ON THOSE DAYS ON WHICH A
FELT-LAYING MACHINE OR SLAG-DISPENSING MACHINE IS
USED: $0.50 PER HOUR ADDITIONAL.
PAID HOLIDAY: THE LAST
WORKING DAY BEFORE CHRISTMAS, TO BE PAID AT THE
RATE OF FOUR HOURS PAY..............................$ 38.95 21.85
ROOFER: SHINGLES
(SOMERSET COUNTY (SOUTH
OF A LINE DRAWN FROM THE MERCER/SOMERSET COUNTY
LINE NORTH ALONG ROUTE #206 TO ROUTE #514; THEN,
WEST ALONG ROUTE #514 TO THE HUNTERDON/SOMERSET
COUNTY LINE)
MOPPER, AND OPERATOR OF
FELT-LAYING MACHINE: $0.50 PER HOUR ADDITIONAL.
WORK APPLYING ROOFING MATERIAL, ON ANY NEW
CONSTRUCTION JOB, ON THOSE DAYS ON WHICH A
FELT-LAYING MACHINE OR SLAG-DISPENSING MACHINE IS
USED: $0.50 PER HOUR ADDITIONAL.
PAID
HOLIDAY: THE LAST WORKING DAY BEFORE CHRISTMAS,
TO BE PAID AT THE RATE OF FOUR HOURS PAY............$ 35.95 21.85
ROOFER: ALL OTHER WORK
(SOMERSET COUNTY (SOUTH OF A LINE DRAWN FROM THE
MERCER/SOMERSET COUNTY LINE NORTH ALONG ROUTE #206
TO ROUTE #514; THEN, WEST ALONG ROUTE #514 TO THE
HUNTERDON/SOMERSET COUNTY LINE)
MOPPER, AND OPERATOR OF FELT-LAYING MACHINE:
$0.50 PER HOUR ADDITIONAL. WORK APPLYING ROOFING
MATERIAL, ON ANY NEW CONSTRUCTION JOB, ON THOSE
DAYS ON WHICH A FELT-LAYING MACHINE OR
SLAG-DISPENSING MACHINE IS USED: $0.50 PER HOUR
ADDITIONAL.
PAID HOLIDAY: THE LAST WORKING
DAY BEFORE CHRISTMAS, TO BE PAID AT THE RATE OF
FOUR HOURS PAY......................................$ 46.03 34.27
SFNJ0669-008 07/01/2025
Rates Fringes
SPRINKLER FITTER: FIRE SPRINKLERS (SOMERSET COUNTY
(TOWNSHIPS OF BRANCHBURG AND MONTGOMERY; BOROUGH OF
ROCKY HILL))........................................$ 49.97 41.35
SFNJ0696-004 01/01/2025
Rates Fringes
SPRINKLER FITTER: FIRE SPRINKLERS (SOMERSET COUNTY
(REMAINDER OF COUNTY))..............................$ 67.97 39.35
SHEE0025-005 06/01/2024
Rates Fringes
SHEET METAL WORKER: INCLUDING HVAC DUCT
INSTALLATION........................................$ 51.30 51.55
TEAM0469-005 05/01/2025
TRUCK DRIVER: OFF THE ROAD TRUCK
HAZARDOUS WASTE REMOVAL
WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS
WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT
WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL
PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY,
SKIN AND EYE PROTECTION: $3.00 PER HOUR
WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS
WASTE SITE, IN A ZONE REQUIRING LEVEL A PERSONAL
PROTECTION FOR ANY WORKERS OTHER THAN THE TRUCK
DRIVER: $3.00 PER HOUR
WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS
WASTE SITE WHERE THE WORKER IS NOT WORKING IN A
ZONE REQUIRING LEVEL A, B OR C PERSONAL PROTECTION:
$1.00 PER HOUR
PAID
NEW YEAR'S DAY, PRESIDENT'S DAY, DECORATION DAY,
INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION
DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS
VACATION PAY
WORKERS WORKING OR RECEIVING PAY FOR 80 DAYS WITHIN
A YEAR RECEIVE ONE WEEK PAID VACATION (48 HOURS);
125 DAYS RECEIVE TWO WEEKS PAID VACATION (96
HOURS); 145 DAYS RECEIVE 15 DAYS PAID VACATION (120
HOURS); 15 YEARS SENIORITY AND 145 DAYS RECEIVE 4
WEEKS PAID VACATION (160 HOURS).
...............$ 48.78 42.66
TRUCK DRIVER: DUMP TRUCK
HAZARDOUS WASTE REMOVAL
WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS
WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT
WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL
PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY,
SKIN AND EYE PROTECTION: $3.00 PER HOUR
WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS
WASTE SITE, IN A ZONE REQUIRING LEVEL A PERSONAL
PROTECTION FOR ANY WORKERS OTHER THAN THE TRUCK
DRIVER: $3.00 PER HOUR
WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS
WASTE SITE WHERE THE WORKER IS NOT WORKING IN A
ZONE REQUIRING LEVEL A, B OR C PERSONAL PROTECTION:
$1.00 PER HOUR
PAID
NEW YEAR'S DAY, PRESIDENT'S DAY, DECORATION DAY,
INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION
DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS
VACATION PAY
WORKERS WORKING OR RECEIVING PAY FOR 80 DAYS WITHIN
A YEAR RECEIVE ONE WEEK PAID VACATION (48 HOURS);
125 DAYS RECEIVE TWO WEEKS PAID VACATION (96
HOURS); 145 DAYS RECEIVE 15 DAYS PAID VACATION (120
HOURS); 15 YEARS SENIORITY AND 145 DAYS RECEIVE 4
WEEKS PAID VACATION (160 HOURS).
..............................................$ 48.63 42.66
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at https://www.dol.gov/agencies/whd/government-contracts.
Note: Executive Order 13658 generally applies to contracts subject to the Davis-Bacon Act that were awarded on or between January 1, 2015 and January 29, 2022, and that have not been renewed or extended on or after January 30, 2022. Executive Order 13658 does not apply to contracts subject only to the Davis-Bacon Related Acts regardless of when they were awarded. If a contract is subject to Executive Order 13658, the contractor must pay all covered workers at least $13.65 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract from May 11, 2026, through December 31, 2026. The applicable Executive Order minimum wage rate will be adjusted annually.
Additional information on contractor requirements and worker protections under Executive Order 13658 is available at www.dol.gov/whd/govcontracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (iii)).
The body of each wage determination lists the classifications and wage rates that have been found to be prevailing for the type(s) of construction and geographic area covered by the wage determination. The classifications are listed in alphabetical order under rate identifiers indicating whether the particular rate is a union rate (current union negotiated rate), a survey rate, a weighted union average rate, a state adopted rate, or a supplemental classification rate.
Union Rate Identifiers
A four-letter identifier beginning with characters other than �SU�, �UAVG�, �SA�, or �SC� denotes that a union rate was prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2024. PLUM is an identifier of the union whose collectively bargained rate prevailed in the survey for this classification, which in this example would be Plumbers.
0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. The date, 07/01/2024 in the example, is the effective date of the most current negotiated rate.
Union prevailing wage rates are updated to reflect all changes over time that are reported to WHD in the rates in the collective bargaining agreement (CBA) governing the classification.
Union Average Rate Identifiers
The UAVG identifier indicates that no single rate prevailed for those classifications, but that 100% of the data reported for the classifications reflected union rates. EXAMPLE:
UAVG-OH-0010 01/01/2024. UAVG indicates that the rate is a weighted union average rate. OH indicates the State of Ohio.
The next number, 0010 in the example, is an internal number used in producing the wage determination. The date, 01/01/2024 in the example, indicates the date the wage determination was updated to reflect the most current union average rate.
A UAVG rate will be updated once a year, usually in January, to reflect a weighted average of the current rates in the collective bargaining agreements on which the rate is based.
Survey Rate Identifiers
The �SU� identifier indicates that either a single non-union rate prevailed (as defined in 29 CFR 1.2) for this classification in the survey or that the rate was derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As a weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SUFL2022-007 6/27/2024. SU indicates the rate is a single non-union prevailing rate or a weighted average of survey data for that classification. FL indicates the State of Florida. 2022 is the year of the survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. The date, 6/27/2024 in the example, indicates the survey completion date for the classifications and rates under that identifier.
�SU� wage rates typically remain in effect until a new survey is conducted. However, the Wage and Hour Division (WHD) has the discretion to update such rates under 29 CFR 1.6(c)(1).
State Adopted Rate Identifiers
The �SA� identifier indicates that the classifications and prevailing wage rates set by a state (or local) government were adopted under 29 C.F.R 1.3(g)-(h). Example: SAME2023-007 01/03/2024. SA reflects that the rates are state adopted. ME refers to the State of Maine. 2023 is the year during which the state completed the survey on which the listed classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination.
The date, 01/03/2024 in the example, reflects the date on which the classifications and rates under the �SA� identifier took effect under state law in the state from which the rates were adopted.
WAGE DETERMINATION APPEALS PROCESS
1) Has there been an initial decision in the matter? This can be:
a) a survey underlying a wage determination
b) an existing published wage determination
c) an initial WHD letter setting forth a position on a wage determination matter
d) an initial conformance (additional classification and rate) determination On survey related matters, initial contact, including requests for summaries of surveys, should be directed to the WHD Branch of Wage Surveys. Requests can be submitted via email to davisbaconinfo@dol.gov or by mail to:
Branch of Wage Surveys Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210 Regarding any other wage determination matter such as conformance decisions, requests for initial decisions should be directed to the WHD Branch of Construction Wage Determinations.
Requests can be submitted via email to BCWD-Office@dol.gov or by mail to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2) If an initial decision has been issued, then any interested party (those affected by the action) that disagrees with the decision can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7).
Requests for review and reconsideration can be submitted via email to dba.reconsideration@dol.gov or by mail to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210 The request should be accompanied by a full statement of the interested party's position and any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210.
END OF GENERAL DECISION
File details come from the government source that posted it. Updated .