ATTACHMENT C - Supplemental Price Breakdown.xlsx
XLSX spreadsheet 11 KB Posted
- Attached to
- Z1DA--Replace Research HVAC Systems | 662-21-105 Federal contract opportunity
- Solicitation number
- 36C26121R0082
About this file
This document contains an attachment with pricing details and a federal contract opportunity notice. The attachment provides a pricing schedule for replacing research HVAC systems at a VA facility, including line items for project management, mobilization, demolition, crane operations, chiller connections, damper replacement, controls integration, electrical work, overhead, profit, insurance, taxes, and bonds.
The federal contract opportunity is a pre-solicitation notice for a request for proposal to replace a chiller system and repair two air handling units at a VA facility in San Francisco. The project cost is estimated between $100,000 and $250,000. The applicable NAICS code is 238220 and it is a total SDVOSB set-aside. Questions regarding the forthcoming RFP must be directed to the specified point of contact in writing by July 25, 2021, and solicitation documents will be available on or around that date.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Wage Decision CA20210018_7-23-2021.pdf | ||
| 662-21-105 Specifications-Combined.pdf | ||
| ATTACHMENT A - Criteria 1-Experience.xlsx | XLSX spreadsheet | |
| 2018 Contractor Preconstruction Safety Handbook.pdf | ||
| SOW Attachment 3 - B41 AHU-1 and AHU-2 MFG Dwgs.pdf | ||
| 36C26121R0082.docx | DOCX document | |
| SF CAMPUS MAP 11.07.19 - B41 Entrance.pdf | ||
| ATTACHMENT B - Criteria 2-Contractor Certification Safety and Environmental.docx | DOCX document | |
| SOW Attachment 2 - B41 Mechanical Drawings.pdf | ||
| SOW Attachment 1 - Task Locations and Existing Equipment Photos.pdf | ||
| SOW 662-21-105 Replace Research HVAC Systems v03-21.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| ATTACHMENT C - PRICING SCHEDULE | |||
| Replace Research HVAC Systems | |||
| DESCRIPTION | MATERIAL | LABOR | TOTAL |
| General Requirements | |||
| Project Manager/QC | $ | $ | $ |
| Superintendent/Safety | $ | $ | $ |
| Mobilization | $ | $ | $ |
| General Requirements Total | $ | $ | $ |
| Existing Conditions | |||
| Demolition | $ | $ | $ |
| Crane Operations (Chillers) | $ | $ | $ |
| Existing Conditions Total | $ | $ | $ |
| Plumbing | |||
| Chiller Connections - CHW Header | $ | $ | $ |
| Plumbing Total | $ | $ | $ |
| HVAC | |||
| Chiller Replacements, Startup, Testing | $ | $ | $ |
| AHU Damper Replacement | $ | $ | $ |
| Chiller Controls Integration | $ | $ | $ |
| HVAC Totals | $ | $ | $ |
| Electrical Work | |||
| Chiller Electrical Connections | $ | $ | $ |
| Electrical Work Total | $ | $ | $ |
| Sub Total | $ | $ | $ |
| Overhead | $ | $ | $ |
| Sub total | $ | $ | $ |
| Profit | $ | $ | $ |
| Sub total | |||
| Insurance and Taxes | |||
| Sub total | $ | $ | $ |
| Bonds | $ | $ | $ |
| TOTAL | $ | $ | $ |
File details come from the government source that posted it. Updated .