This pre-solicitation announcement describes an upcoming Request for Proposal for replacement HVAC systems construction services. The project will replace a chiller system and repair two air handling units at the VA San Francisco Health Care System campus building 41. The scope of work includes demolition, repair, replacement, installation and commissioning of materials and labor. The applicable NAICS code is 238220 for plumbing, heating and air conditioning contractors, with a small business size standard of $16.5M. This RFP will be a total set-aside for Service-Disabled Veteran Owned Small Businesses. Solicitation documents will be available on July 25, 2021, with an estimated project cost between $100,000 and $250,000. Questions must be sent in writing by the specified date to the identified point of contact.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Wage Decision CA20210018_7-23-2021.pdf | ||
| ATTACHMENT A - Criteria 1-Experience.xlsx | XLSX spreadsheet | |
| 2018 Contractor Preconstruction Safety Handbook.pdf | ||
| SOW Attachment 3 - B41 AHU-1 and AHU-2 MFG Dwgs.pdf | ||
| 36C26121R0082.docx | DOCX document | |
| ATTACHMENT C - Supplemental Price Breakdown.xlsx | XLSX spreadsheet | |
| SF CAMPUS MAP 11.07.19 - B41 Entrance.pdf | ||
| ATTACHMENT B - Criteria 2-Contractor Certification Safety and Environmental.docx | DOCX document | |
| SOW Attachment 2 - B41 Mechanical Drawings.pdf | ||
| SOW Attachment 1 - Task Locations and Existing Equipment Photos.pdf | ||
| SOW 662-21-105 Replace Research HVAC Systems v03-21.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
San Francisco VA Medical Center 12-21-20
662-21-105 Replace Research HVAC Systems
662-21-105 00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
SECTION NO. DIVISION AND SECTION TITLES DATE
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 12-20
01 33 23 Shop Drawings, Product Data, and Samples 12-20
01 35 26 Safety Requirements 12-20
01 42 19 Reference Standards 12-20
01 57 19 Temporary Environmental Controls 12-20
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition 12-20
DIVISION 03 – CONCRETE
03 30 00 Cast-in-place Concrete 12-20
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 60 00 Flashing and Sheet Metal 12-20
07 84 00 Firestopping 12-20
07 92 00 Joint Sealants 12-20
DIVISION 13 – SPECIAL CONSTRUCTION
13 05 41 Seismic Restraint Requirements 12-20
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 05 11 Common Work Results for HVAC 12-20
23 05 12 General Motor Requirements for HVAC and Steam
Generation Equipment
12-20
23 05 41 Noise and Vibration Control for HVAC Piping and
Equipment
12-20
23 21 13 Hydronic Piping 12-20
23 21 23 Hydronic Pumps 12-20
23 23 00 Refrigerant Piping 12-20
23 31 00 HVAC Ducts and Casings 12-20
23 34 00 HVAC Fans 12-20
23 37 00 Air Outlets and Inlets 12-20
23 40 00 HVAC Air Cleaning Devices 12-20
23 64 00 Packaged Water Chillers 12-20
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 12-20
San Francisco VA Medical Center 12-21-20
662-21-105 00 01 10-2
SECTION NO. DIVISION AND SECTION TITLES DATE
26 05 19 Low-Voltage Electrical Power Conductors and Cables 12-20
26 05 26 Grounding and Bonding for Electrical Systems 12-20
26 05 33 Raceway and Boxes for Electrical Systems 12-20
26 29 11 Motor Controllers 12-20
San Francisco VA Medical Center 12-05-20 i
SECTION 01 00 00
GENERAL REQUIREMENTS
TABLE OF CONTENTS
1.1 SAFETY REQUIREMENTS
1.2 GENERAL INTENTION
1.3 STATEMENT OF BID ITEM(S)
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
1.5 CONSTRUCTION SECURITY REQUIREMENTS
1.6 FIRE SAFETY
1.7 OPERATIONS AND STORAGE AREAS
1.8 ALTERATIONS
1.9 INFECTION PREVENTION MEASURES
1.10 DISPOSAL AND RETENTION
1.11 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,
UTILITIES, AND IMPROVEMENTS
1.12 RESTORATION
1.13 PHYSICAL DATA
1.14 USE OF ROADWAYS
1.15 PRECONSTRUCTION RISK ASSESSMENT
1.16 TEMPORARY USE OF EXISTING ELEVATORS
1.17 TEMPORARY TOILETS
1.18 AVAILABILITY AND USE OF UTILITY SERVICES
1.19 TESTS
1.20 INSTRUCTIONS
1.21 RELOCATED EQUIPMENT and ITEMS
1.22 CONSTRUCTION SIGN
1.23 SAFETY SIGN
1.24 CONSTRUCTION AND DEMOLITION DEBRIS MANAGEMENT
1.25 HISTORIC PRESERVATION
1.26 PARKING
1.27 I.D. BADGES
San Francisco VA Medical Center 12-05-20 ii
1.28 CONSTRUCTION SCHEDULE
1.29 DAILY LOGS
1.30 TB TESTING REQUIREMENTS
1.31 SEASONAL INFLUENZA VACCINE REQUIREMENTS
1.32 ASBESTOS
San Francisco VA Medical Center 02-05-20
SECTION 01 00 00
GENERAL REQUIREMENTS
1.1 SAFETY REQUIREMENTS
Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. The San Francisco Veterans Affairs (VA) Medical Center has a requirement to replace a chiller system and repair two air handling units serving Building 41, located at 4150 Clement St, San Francisco CA
94121.
B. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work as required by the Statement of
Work and specifications.
C. This work shall include but not limited to signage for detour of traffic, infection control containment, barricades, and related prep work or finish work. The contractor shall make every effort to return any surrounding areas impacted by project back to existing conditions.
Any new penetrations through fire walls shall be caulked to maintain fire rating requirements. Any new utilities must not be tied or supported to other existing dissimilar utilities and supported by building structure.
D. Before beginning any demolition work, the contractor shall survey the site and examine the drawings and specifications to determine the extent of the work. The contractor shall take necessary precautions to avoid damages to existing items to remain in place, to be reused, or to remain the property of the Medical Center; any damaged items shall be repaired or replaced as approved by the COR.
E. Visits to the site by Bidders may be made only by appointment with the
Medical Center.
F. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
1.3 STATEMENT OF BID ITEM(S)
A. BLDG 41 CHILLER REPLACMENT: Work includes all labor, material, equipment and supervision to perform the required work on this project, as specified in the Statement of Work.
A. BLDG 41 AHU DAMPER REPAIRS: Work includes all labor, material, equipment and supervision to perform the required work on this project, as specified in the Statement of Work.
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. The contractor shall maintain on the job site one (1) printed set of specifications, one (1) printed copy of all RFI’s and any documents that modify the original specifications and drawings.
B. Discrepancies between the specifications and the statement of work shall be reported by the contractor to the Contracting Officer and the
Contracting Officer’s Representative for resolution.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The general contractor is responsible for assuring that all subcontractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. For working outside the “standard daily contract work hours” as defined in the Operations and Storage Areas section of this document, the general contractor shall give 3 days notice to the
Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the Contracting Officer.
4. VA reserves the right to close down or shut down the project site and order general contractor’s employees off the premises in the event of a national emergency. The general contractor may return to the site only with the written approval of the Contracting Officer.
5. Contractor shall adhere to all security standards regarding VA data.
C&A requirements do not apply, and a Security Accreditation Package is not required.
E. Document Control:
1. Before starting any work, the general contractor/subcontractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of
“sensitive information”.
2. The general contractor is responsible for safekeeping of all drawings, project manuals, and other project information. This information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.
Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.
4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting
Officer.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document
Management Software (EDMS).
a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the
EDMS system.
b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
F. Parking
1. Paid parking is required on all days of the week and for all shifts.
A daily parking permit shall be obtained at one of the three paid parking machines located around the SFVAMC campus at the cost of $1 per 24-hour period. The $1 parking permit fee applies for trucks, vans, automobiles, motorcycles, motorized scooters or any other motorized vehicle using a single parking space. Employees parking in car/van pool or handicapped spaces must also pay the parking fee.
2. Parking passes must be purchased daily and will expire in 24 hours.
There will be no refunds.
3. Parking is available on a first come/first serve basis. Payment of the parking permit fee does not guarantee that a parking space will be available.
4. Each vehicle parked in an employee parking lot must display a valid parking pass. Payment of the parking permit fee and display of the receipt on the front dashboard of the vehicle will validate parking for the 24-hour period. Vehicles parked in an employee lot without the tag visibly displayed or payment of the daily rate and display of the receipt will be subject to any of the following penalties:
issuance of a U.S. Court Violation Notice, administrative action, or tow away. Parking in a designated patient, volunteer, GSA vehicle, or visitor lot parking space will also be subject to the above penalties.
5. Vehicles shall park in designated parking spaces only. Vehicles parked in locations other than designated parking spaces will be subject to issuance of a U.S. Court Violation Notice, administrative action, or vehicle tow away.
6. Motorcyclists must park in spaces designated for their use.
1.6 FIRE SAFETY
A. Applicable Publications: Publications listed below form part of this
Article to extent referenced. Publications are referenced in text by basic designations only.
1. American Society for Testing and Materials (ASTM):
E84-18...............Surface Burning Characteristics of Building
Materials
2. National Fire Protection Association (NFPA):
10-2018..............Standard for Portable Fire Extinguishers
30-2018..............Flammable and Combustible Liquids Code
51B-2014.............Standard for Fire Prevention During Welding, Cutting and Other Hot Work
70-2017..............National Electrical Code
241-2013.............Standard for Safeguarding Construction, Alteration, and Demolition Operations
3. Occupational Safety and Health Administration (OSHA):
29 CFR 1926..........Safety and Health Regulations for Construction
B. Fire Safety Plan: Establish and maintain a fire protection program in accordance with 29 CFR 1926. Prior to start of work, prepare a plan detailing project-specific fire safety measures, including periodic status reports, and submit to COR for review for compliance with contract requirements in accordance with Section 01 33 23, SHOP
DRAWINGS, PRODUCT DATA, AND SAMPLES prior to any worker for the contractor or subcontractors beginning work, they shall undergo a safety briefing provided by the general contractor’s competent person per OSHA requirements. This briefing shall include information on the construction limits, VAMC safety guidelines, means of egress, break areas, work hours, locations of restrooms, use of VAMC equipment, etc.
Documentation shall be provided to the COR that individuals have undergone contractor’s safety briefing.
C. Site and Building Access: Maintain free and unobstructed access to facility emergency services and for fire, police and other emergency response forces in accordance with NFPA 241.
D. Separate temporary facilities, such as trailers, storage sheds, and dumpsters, from existing buildings and new construction by distances in accordance with NFPA 241. For small facilities with less than 6 m (20 feet) exposing overall length, separate by 3 m (10 feet).
E. Means of Egress: Do not block exiting for occupied buildings, including paths from exits to roads. Minimize disruptions and coordinate with
COR.
F. Egress Routes for Construction Workers: Maintain free and unobstructed egress. Inspect daily. Report findings and corrective actions weekly to
COR.
G. Fire Extinguishers: Provide and maintain extinguishers in construction areas and temporary storage areas in accordance with 29 CFR 1926, NFPA
241 and NFPA 10.
H. Flammable and Combustible Liquids: Store, dispense and use liquids in accordance with 29 CFR 1926, NFPA 241 and NFPA 30.
I. Existing Fire Protection: Do not impair automatic sprinklers, smoke and heat detection, and fire alarm systems, except for portions immediately under construction, and temporarily for connections. Provide fire watch for impairments more than 4 hours in a 24-hour period. All existing or temporary fire protection systems (fire alarms, sprinklers) located in construction areas shall be tested as coordinated with the Medical
Center. Parameters for the testing and results of any tests performed shall be recorded by the Medical Center and copies provided to the COR
Engineer.
J. Smoke Detectors: Prevent accidental operation. Remove temporary covers at end of work operations each day. Coordinate with COR.
K. Hot Work: Perform and safeguard hot work operations in accordance with
NFPA 241 and NFPA 51B. Coordinate with COR. Obtain permits from facility Safety through COR at least 48 hours in advance. Designate contractor's responsible project-site fire prevention program manager to permit hot work.
L. Fire Hazard Prevention and Safety Inspections: Inspect entire construction areas weekly. Coordinate with, and report findings and corrective actions weekly to COR.
M. Smoking: Smoking is prohibited in and adjacent to construction areas inside existing buildings and additions under construction. In separate and detached buildings under construction, smoking is prohibited except in designated smoking rest areas.
N. Dispose of waste and debris in accordance with NFPA 241. Remove from buildings daily.
O. Perform other construction, alteration and demolition operations in accordance with 29 CFR 1926.
P. If required, submit documentation to the COR that personnel have been trained in the fire safety aspects of working in areas with impaired structural or compartmentalization features.
Q. Above Ceiling Permit: Contractors are restricted from working above ceiling without the required Above Ceiling Permit. This required when working above any ceilings in the Medical Center outside of contained construction areas.
R. Temporary Electrical: Contractors are not allowed to use power supplied
VA unless approved by COR. If approved, use and installations shall be in accordance with 29 CFR 1926, NFPA 241 and NFPA 70. At no time will
VA approve temporary power connection from a critical electrical circuit.
1.7 OPERATIONS AND STORAGE AREAS
A. The contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The contractor shall hold and save the
Government, its officers and agents, free and harmless from liability of any nature occasioned by the contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the contractor only with the approval of the
Contracting Officer and shall be built with labor and materials furnished by the contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the contractor and shall be removed by the contractor at its expense upon completion of the work.
C. The contractor shall, under regulations prescribed by the Contracting
Officer, use only established roadways, or use temporary roadways constructed by the contractor when and as authorized by the Contracting
Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the contractor shall protect them from damage. The contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D. Working space and space available for storing materials shall be as determined by the COR.
E. Workers are subject to rules of Medical Center applicable to their conduct.
E. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.
F. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and contractor's personnel, except as permitted by COR where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of
Veterans Affairs in quantities sufficient for not more than four work days. Provide unobstructed access to Medical Center areas required to remain in operation.
3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of contractor's materials and equipment will be permitted subject to fire and safety requirements.
G. Construction Safety Rounds: VA will perform construction safety rounds weekly. Contractor superintendent or contractor’s Competent Person will be present during these safety inspections. COR will identify the date and time of these weekly inspections.
H. Phasing: To ensure such executions, contractor shall furnish the COR with a schedule of approximate phasing dates on which the contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such phasing dates to ensure accomplishment of this work in successive phases mutually agreeable to Medical Center Director, COR and contractor.
I. Buildings will be occupied during performance of work.
1. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to Department of
Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting, etc. to facilitate patient and staff access.
Coordinate alteration work in areas occupied by Department of
Veterans Affairs so that Medical Center operations will continue during the construction period.
J. Utilities Services: Maintain existing utility services for Medical
Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services.
Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized.
When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval.
2. Contractor shall submit a request to interrupt any such services to
COR, in writing, 21 days in advance of proposed interruption.
Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 28 calendar days prior to the desired time and shall be performed as directed by the COR.
5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the contractor.
K. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
L. To minimize interference of construction activities with flow of
Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles. Wherever excavation for new utility lines cross existing roads, at least one lane must be open to traffic at all times with approval.
2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.
M. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article 1.14, USE OF ROADWAYS.
N. Contract Work Hours and Federal Holidays: Standard daily contract work hours at the San Francisco VA Medical Center (SFVAMC) are from 7:30 AM to 5:00 PM, Monday through Friday, except for Federal Holidays. The contractor shall submit to the Contracting Officer (CO) for approval, in writing, a notice of its desire to work during any period/hours other than the standard. Notice shall include a detailed description of the type of work to be performed and its location. These “non-standard” hours are referred to as “WHEN Hours” (Weekend-Holiday-Evening-Night).
The notice requesting work during WHEN hours shall be submitted not less than three (3) working days prior to each period of work scheduled at times other than normal duty hours to include Federal holidays.
“WHEN Hours” shall be included in the contractor’s budget and on their schedule with description of type of duties, duration, and manpower information. Contractors are reminded that patients are generally asleep after 10:00 PM. Therefore, approval is subject to the availability of the COR, the type of work to be performed, the specific hours requested, and the anticipated noise level that will be generated by contractor activity. Under no circumstance will the contractor proceed without express written approval of the Contracting Officer.
When weekend work is approved by the COR, work shall be limited to no earlier than 7:30 AM start to 5:00 PM completion of construction period weekends. Any time out side of that window will be considered evening or night work and will require its own approval.
1. Work Phasing/Scheduling: Contractor shall work closely with the COR in developing a work schedule for contract performance. Simultaneous or transitional work on/between multiple facilities may be required.
Advance coordination by the contractor is critical and required.
Note, concurrent work performance is anticipated on all line items for this project.
2. The work to be performed on this project will include occupied areas; however, arrangements may be made so that the area may be blocked off during performance of work if feasible. The contractor shall notify the COR of intent to start work, with two (2) weeks’ notice, in any specific assigned area. The contractor shall coordinate the work of all activities whereby both the Government and the contractor can continue operations with the least possible interference and inconvenience.
3. The contractor is required to have a minimum of crews for work covered by this contract, and provide additional crew(s) as the work justifies. Each crew can operate simultaneously and independently of the other crew(s).
4. The following is a list of Federal Holidays observed by all Federal
Installations:
New Year's Day, January 1
Birthday of Martin Luther King, Jr, 3rd Monday in January
Washington's Birthday, 3rd Monday in February
Memorial Day, Last Monday in May
Independence Day, July 4
Labor Day, 1st Monday in September
Columbus Day, 2nd Monday in September
Veterans Day, November 11
Thanksgiving Day, 4th Thursday in November
Christmas Day, December 25
Any of the above holidays falling on a Saturday will be observed on the preceding Friday; holidays falling on a Sunday will be observed on the following Monday. Also included is any date specifically declared by the President of the United States of America as a
National Holiday.
5. No deliveries of construction equipment, materials, HVAC equipment, dumpsters (or pick up of dumpsters), cranes, concrete trucks, etc.
before 7:30 AM on weekdays and 8 AM on weekends. Exception will be for oversize loads that require delivery before a certain time due to permitting conditions, and shall require a minimum of 3 days notice to the COR prior to arrival at SFVAMC. No contractor vehicles, delivery vehicle, cranes, concrete trucks, hauling trucks, etc. will be staged within 500 yards of the SFVAMC prior to driving onto SFVAMC grounds.
1.8 ALTERATIONS
A Survey: Before any work is started, the contractor shall make a thorough survey with the COR of areas of buildings in which alterations occur and areas which are anticipated routes of access.
B. Any items required to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this paragraph B, the contract will be modified accordingly, under provisions of clause entitled
"DIFFERING SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR 52.243-4 and VAAR 852.236-88).
C. Re-Survey: Thirty days before expected partial or final inspection date, the contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of contractor to restore damage caused by contractor's workers in executing work of this contract.
D. Protection: Provide the following protective measures:
1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
E. Final Cleanup: Upon completion of project, or as work progresses, remove all construction debris from above ceiling, vertical shafts and utility chases that have been part of the construction.
F. Disposal and Retention: Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows per Article 1.9, DISPOSAL AND
RETENTION.
1.9 INFECTION PREVENTION MEASURES
A. Implement the requirements of VAMC’s Infection Control Risk Assessment
(ICRA) team. ICRA Group may monitor dust near the construction work and require the contractor to take corrective action immediately if the safe levels are exceeded.
B. Establish and maintain a dust control program as part of the contractor’s infection preventive measures in accordance with the guidelines provided by ICRA Group. Prior to start of work, prepare a plan detailing project-specific dust protection measures, including periodic status reports, and submit to COR for review for compliance with contract requirements. No work shall start without approved ICRA permit and full coordination with COR.
1. All personnel involved in the construction or renovation activity shall be educated and trained in infection prevention measures established by the Medical Center.
C. Medical Center Infection Control personnel shall monitor for airborne disease (e.g. aspergillosis) as appropriate during construction. A baseline of conditions may be established by the Medical Center prior to the start of work and periodically during the construction stage to determine impact of construction activities on indoor air quality. In addition:
1. The COR and VAMC Infection Control personnel shall review pressure differential monitoring documentation to verify that pressure differentials in the construction zone and in the patient-care rooms are appropriate for their settings. The requirement for negative air pressure in the construction zone shall depend on the location and type of activity. Upon notification, the contractor shall implement corrective measures to restore proper pressure differentials as needed.
2. In case of any problem, the Medical Center, along with assistance from the contractor, shall conduct an environmental assessment to find and eliminate the source.
D. In general, the following preventive measures shall be adopted during construction to keep down dust and prevent mold.
1. Do not perform dust producing tasks within occupied areas without the approval of the COR. For construction in any areas that will remain jointly occupied by the Medical Center and contractor’s workers, the contractor shall:
a. Provide plastic, fire-resistant sheets to isolate larger areas when generating dust indoors.
b. HEPA filtration is required where the exhaust dust may reenter the breathing zone. Contractor shall verify that construction exhaust to exterior is not reintroduced to the Medical Center through intake vents, or building openings. Install HEPA (High
Efficiency Particulate Accumulator) filter vacuum system rated at
95% capture of 0.3 microns including pollen, mold spores and dust particles. Insure continuous negative air pressures occurring within the work area. HEPA filters should have ASHRAE 85 or other pre-filter to extend the useful life of the HEPA. Provide both primary and secondary filtrations units. Exhaust hoses shall be heavy duty, flexible steel reinforced and exhausted so that dust is not reintroduced to the Medical Center.
c. Adhesive Walk-off/Carpet Walk-off Mats, minimum 600mm x 900mm
(24” x 36”), shall be used at all interior transitions from the construction area to occupied Medical Center area. These mats shall be changed as often as required to maintain clean work areas directly outside construction area always.
d. Vacuum and wet mop all transition areas from construction to the occupied Medical Center at the end of each workday. Vacuum shall utilize HEPA filtration. Maintain surrounding area frequently.
Remove debris as they are created. Transport these outside the construction area in containers with tightly fitting lids.
e. The contractor shall not haul debris through patient-care areas without prior approval of the COR and the Medical Center. When approved, debris shall be hauled in enclosed dust proof containers or wrapped in plastic and sealed with duct tape. No sharp objects should be allowed to cut through the plastic. Wipe down the exterior of the containers with a damp rag to remove dust. All equipment, tools, material, etc. transported through occupied areas shall be made free from dust and moisture by vacuuming and wipe down.
f. Using a HEPA vacuum, clean inside the barrier and vacuum ceiling tile prior to replacement. Any ceiling access panels opened for investigation beyond sealed areas shall be sealed immediately when unattended.
g. There shall be no standing water during construction. This includes water in equipment drip pans and open containers within the construction areas. All accidental spills must be cleaned up and dried within 12 hours. Remove and dispose of porous materials that remain damp for more than 72 hours.
h. At completion, remove construction barriers and ceiling protection carefully, outside of normal work hours. Vacuum and clean all surfaces free of dust after the removal.
E. Final Cleanup:
1. Upon completion of project, or as work progresses, remove all construction debris from above ceiling, vertical shafts and utility chases that have been part of the construction.
2. Perform HEPA vacuum cleaning of all surfaces in the construction area. This includes walls, ceilings, cabinets, furniture (built-in or free standing), partitions, flooring, etc.
3. All new air ducts shall be cleaned prior to final inspection.
1.10 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the Government are identified by attached tags or noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.
2. Items not reserved shall become property of the contractor and be removed by contractor from Medical Center.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with contractor's operation.
1.11 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS
A. The contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workers, the contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.
B. The contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the contractor. The contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the contractor fails or refuses to repair the damage promptly, the
Contracting Officer may have the necessary work performed and charge the cost to the contractor.
1.12 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the
COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged.
Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At contractor's own expense, contractor shall immediately restore to service and repair any damage caused by contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"
(FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE CONDITIONS" (FAR
52.236-2).
1.13 PHYSICAL DATA
A. Data and information furnished or referred to in this specification is for the contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the contractor.
B. Government does not guarantee that other materials will not be encountered nor that proportions, conditions or character of several materials will not vary from those indicated by explorations. Bidders are expected to examine site of work and logs of borings; and, after investigation, decide for themselves character of materials and make their bids accordingly. Upon proper application to Department of
Veterans Affairs, bidders will be permitted to make subsurface explorations of their own at site.
1.14 USE OF ROADWAYS
A. For hauling, use only established public roads and roads on Medical
Center property and, when authorized by the COR, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed and restoration performed by the contractor at contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.
1.15 PRECONSTRUCTION RISK ASSESSMENT
A. For every construction project, the contractor and the COR are required to perform a Pre-Construction Risk Assessment (PCRA). The contractor must submit the PCRA within 15 days from issuance of the Notice to
Proceed.
1.16 TEMPORARY USE OF EXISTING ELEVATORS
A. Contractor will be allowed the use of existing elevators. The contractor shall provide maximum protection of elevator components.
1.17 TEMPORARY TOILETS
A. Contractor shall provide temporary sanitary toilet and handwashing accommodations for use of Contractor's workers. Keep such places clean and free from flies, and all connections and appliances connected therewith are to be removed prior to completion of contract, and premises left perfectly clean.
1.18 AVAILABILITY AND USE OF UTILITY SERVICES
A. The Government shall make all reasonably required amounts of utilities available to the contractor from existing outlets and supplies, as specified in the contract. The contractor shall carefully conserve any utilities furnished without charge.
B. Electricity (for Construction and Testing): Furnish all temporary electric services.
1. Obtain electricity by connecting to the Medical Center electrical distribution system. Electricity is available at no cost to the contractor.
1.19 TESTS
A. Conduct final tests required in various sections of specifications in presence of an authorized representative of the Contracting Officer.
contractor shall furnish all labor, materials, equipment, instruments, and forms, to conduct and record such tests.
B. All related components as defined above shall be functioning when any system component is tested. Tests shall be completed within a reasonably period of time during which operating and environmental conditions remain reasonably constant and are typical of the design conditions.
C. Individual test result of any component, where required, will only be accepted when submitted with the test results of related components and of the entire system.
1.20 INSTRUCTIONS
A. Contractor shall furnish Maintenance and Operating manuals (hard copies and/or electronic) and verbal instructions when required by the various sections of the specifications and as hereinafter specified.
B. Manuals: Maintenance and operating manuals for each separate piece of equipment shall be delivered to the COR coincidental with the delivery of the equipment to the job site. Manuals shall be complete, detailed guides for the maintenance and operation of equipment. They shall include complete information necessary for starting, adjusting, maintaining in continuous operation for long periods of time and dismantling and reassembling of the complete units and sub-assembly components. Manuals must reference the exact model, style and size of the piece of equipment and system being furnished. Manuals referencing equipment similar to but of a different model, style, and size than that furnished will not be accepted.
C. Instructions: Contractor shall provide qualified representatives to give detailed training to assigned Department of Veterans Affairs personnel in the operation and complete maintenance for each piece of equipment. All such training will be at the job site. These requirements are more specifically detailed in the various technical sections. Instructions for different items of equipment that are component parts of a complete system, shall be given in an integrated, progressive manner. All instructors for every piece of component equipment in a system shall be available until instructions for all items included in the system have been completed. This is to assure proper instruction in the operation of inter-related systems. All instruction periods shall be at such times as scheduled by the COR and shall be considered concluded only when the COR is satisfied in regard to complete and thorough coverage. The Department of Veterans Affairs reserves the right to request the removal of, and substitution for, any instructor who, in the opinion of the COR, does not demonstrate sufficient qualifications in accordance with requirements for instructors above.
1.21 RELOCATED EQUIPMENT AND ITEMS
Section Removed
1.22 CONSTRUCTION SIGN
A. Provide two (2) construction signs at each entrance to the construction area. Signs shall be of a durable material, 300 mm (12 inch) high and
760 mm (30 inch) wide. Background shall be of yellow gloss paint.
Lettering shall be in blue gloss paint, with letters 50 mm (2 inch) high in Helvetica. Letter as follows:
DANGER - KEEP OUT
CONSTRUCTION AREA
AUTHORIZED PERSONNEL ONLY
PLEASE EXCUSE THE INCONVENIENCE
WE ARE WORKING TO IMPROVE YOUR FACILITY
B. Maintain signs and remove them when directed by the COR.
1.23 SAFETY SIGN
A. Prior to commencing work, the contractor shall provide proof that an
OSHA-certified “competent person” (CP) (29 CFR 1926.20 (b) (2)) will maintain a presence at the work site whenever the general or subcontractors are present.
B. All contracted employees must be able to speak and understand English.
Contracted employees must be legally employed in the United States of
America.
C. All employees of general contractor or subcontractors shall have the
10-hour or 30-hour OSHA certified Construction Safety course and/or other relevant competency training. Copies of training records shall be submitted before start of work.
D. Provide Safety Signs per OSHA requirements and as directed by the
Contracting Officer's Representative. All safety signs shall be commercially produced.
1.24 CONSTRUCTION AND DEMOLITION DEBRIS MANAGEMENT
A. This project requires compliance with the City of San Francisco’s
Construction and Demolition Ordinance, number 27-06, for managing construction and demolition debris, where at least 65% can be reused/recycled and diverted away from the landfill. Compliance with this City Ordinance can be accomplished through using a registered transporter and registered facility for managing the construction/demolition debris. For more information, refer to the following websites:
Construction and Demolition Ordinance:
https://sfenvironment.org/sites/default/files/fliers/files/cd_ordinance
List of Registered Transporters:
https://sfenvironment.org/sites/default/files/fliers/files/sfe_zw_cd_re gistered_transporters_list_102020.pdf
List of Registered Facilities:
https://sfenvironment.org/sites/default/files/fliers/files/sfe_zw_cd_re gistered_facilities_list_102020.pdf
Construction and Demolition Forms and Resources https://sfenvironment.org/construction-demolition-resources
1.25 HISTORIC PRESERVATION
A. Where the contractor or any of the contractor's employees, prior to, or during the construction work, are advised of or discover any possible archeological, historical and/or cultural resources, the contractor shall immediately notify the COR verbally, and then with a written follow up.
1.26 PARKING
A. There will be minimal parking space on site available to the contractor for staging, container, or debris box. Coordinate through the COR prior to staging or placing container or debris box.
https://sfenvironment.org/sites/default/files/fliers/files/cd_ordinance.pdf https://sfenvironment.org/sites/default/files/fliers/files/cd_ordinance.pdf https://sfenvironment.org/sites/default/files/fliers/files/sfe_zw_cd_registered_transporters_list_102020.pdf https://sfenvironment.org/sites/default/files/fliers/files/sfe_zw_cd_registered_transporters_list_102020.pdf https://sfenvironment.org/sites/default/files/fliers/files/sfe_zw_cd_registered_facilities_list_102020.pdf https://sfenvironment.org/sites/default/files/fliers/files/sfe_zw_cd_registered_facilities_list_102020.pdf https://sfenvironment.org/construction-demolition-resources
1.27 I.D. BADGES
A. All workers are required to obtain a time-limited I.D. badge from the
VA Police Service, located on the ground floor of Building 203. This badge must be worn always when workers are on site.
1.28 CONSTRUCTION SCHEDULE
A. The contractor shall develop a Construction Schedule demonstrating fulfillment of contract requirements, shall keep the schedule up-to-date as required in this Article, and shall utilize the schedule for coordinating and monitoring work under the Contract (including activities of subcontractors, vendors, and suppliers). The schedule shall be prepared in the format of a Gantt or Bar Chart, utilizing
Microsoft Project or similar computer application, subject to approval by the COR.
B. Within 2 calendar days after receipt of Notice to Proceed, the contractor shall submit a complete Construction Schedule for review by the COR under provisions of Section 01 33 23, SHOP DRAWINGS, PRODUCT
DATA, AND SAMPLES. Within 10 calendar days of receipt of the
Construction Schedule, the Contracting Officer’s Representative will return the submittal with any comments or objections, and if appropriate, schedule a meeting with the contractor for joint review, correction, or adjustment of the schedule. Within 14 calendar days after the later of the return of the submittal or the joint review meeting, the contractor shall revise and submit the revised schedule for the Contracting Officer’s Representative approval.
C. The Construction Schedule shall show construction activities in sufficient detail to monitor work progress, to support application and certificates for payment, and to coordinate submittal review, inspection, and other activities of the COR and his consultants.
Activities shall be identified by trade and nature of task, and shall show durations for the activity from allowable early-start and late-start to early-finish and late-finish, with graphic distinctions between these…