ATTACHMENT C - Specifications _ Guidelines.pdf

PDF 725 KB Posted

Attached to
Sanitary Lines CCTV Inspection Services (City project #25-56)
Solicitation number
12-2025
Issued by
Colorado

About this file

The document is a comprehensive specification and guideline for a sanitary sewer closed-circuit television (CCTV) inspection project for the City of Littleton, Colorado, issued as Attachment C to Project No. 25-56. The project involves professional services for inspecting approximately 59,756 linear feet of sanitary sewer pipes ranging from 6 to 30 inches in diameter, with work to be performed in multiple phases including pre-cleaning inspection, potential sewer pipe cleaning, and post-cleaning inspection. The contractor will be required to use color pan and tilt or side wall scanning cameras to conduct detailed pipe assessments, document findings using NASSCO Pipeline Assessment Certification Program (PACP) standards, and provide electronic reports and databases. All inspections must conform to current NASSCO PACP standards and include comprehensive documentation of pipe conditions, service connections, and potential defects.

The project specifications outline detailed requirements for equipment, personnel qualifications, and technical standards, with specific provisions for payment, measurement, and performance. Contractors must provide PACP-certified operators, use specialized inspection equipment, and submit comprehensive electronic documentation. Payment will be based on linear footage inspected, with unit prices varying by pipe size, and invoicing will occur by sewer segment upon completion of all work and punch list items. The contract includes provisions for additional work, emergency response, and strict quality control measures. Contractors must also provide appropriate insurance, safety plans, and meet specific pre-qualification requirements, including having supervisory personnel with at least three years of specialized sewer inspection experience.

View the file

Other files

File Type Posted
ATTACHMENT A - Sample Contract.pdf PDF
ATTACHMENT B - Contract Certification Form.pdf PDF
RFP.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

2025 SANITARY SEWER INSPECTION/CCTV PROJECT

CITY PROJECT No. 25-56

CITY OF LITTLETON, COLORADO

PROJECT SPECIAL PROVISIONS

MODIFICATIONS TO COLORADO DEPARTMENT OF TRANSPORTATION

STANDARD SPECIFICATIONS

The technical specifications for this project shall be the Colorado Department of Transportation 2023 Standard Specifications for Road and Bridge Construction and Standard Special Provisions, and the Metropolitan Government Pavement Engineers Council 2021 Version of Pavement Design Standards and Construction Specifications. The following special provisions supplement or modify the Standard Specifications and Supplemental Specifications and take precedence over the Standard Specifications, Supplemental Specifications, and plans.

PROJECT SPECIAL PROVISIONS

COMMENCEMENT AND COMPLETION OF WORK 2

REVISION OF SECTION 107 PUBLIC CONVENIENCE AND SAFETY 3

REVISION OF SECTION 630 CONSTRUCTION ZONE TRAFFIC CONTROL 6

ATTACHMENT C

COMMENCEMENT AND COMPLETION OF WORK

Minimum Salient features to be shown on the Contractor's Progress Schedule for all schedules (in the tabulation of quantities) are:

1. Traffic Control Plan and permit applications (City of Englewood, CDOT, City of

Sheridan, City of Littleton)

2. Submittals

3. Traffic Control

4. Pipe cleaning and preparation

5. Inspection

6. Submit CCTV and manhole inspection data

7. Final Acceptance

REVISION OF SECTION 107

PUBLIC CONVENIENCE AND SAFETY

Section 107 of the Standard Specifications is hereby revised for this project as follows:

107.07 shall be revised to include the following:

The Contractor shall provide the following services on an ongoing basis throughout the duration of the project:

a) A contact person for the project shall be designated by the Contractor at the preconstruction conference. This individual shall be primarily responsible for maintaining communications with the Engineer and businesses; provide information on a regular basis to private individuals, local organizations interested in the project and the affected agencies. The following agencies shall be coordinated with on an ongoing basis:

City of Littleton – Engineering, Utilities, Streets, Police

City of Englewood – Communications, Police, Public Works

Fire Districts – South Metro Fire

RTD - Denver

b) A letter of introduction shall be delivered to all affected property owners, tenants and/or residents prior to mobilization. The letter shall contain the following information as a minimum:

Contractor – Name, Address, Phone Number Field Superintendent – Name, Mobile Phone Number Schedule and description of work

The Contractor shall provide written notice a minimum of seven (7) days prior to the actual start of work at all site locations. In addition to this written notice, the Contractor shall erect temporary “NO PARKING” signs along segments where on street parking would block the work or may impact the scheduled work minimum 48-hours in advance. Towing operations shall not be utilized without prior City approval.

Updates shall be provided to affected persons on a weekly basis after mobilization and 48-hours prior to any significant changes to temporary traffic control setups.

Payment for the above requirements will not be made separately but shall be included in the Work.

REVISION OF SECTIONS 603 and 604

SEWER PIPE AND MANHOLE INSPECTION

Section 603 of the Standard Specifications is hereby revised as follows:

Subsection 603.01 is deleted and replaced with the following:

This work consists of televising the inside of existing sanitary sewer mains using Closed Circuit Television (CCTV) in NASSCO PACP format, and inspections of manholes and structures in NASSCO MACP format.

CONSTRUCTION REQUIREMENTS

Subsection 603.03-603.11 are deleted and replaced with the following:

603.04 Preparation. Sanitary sewers shall be cleaned prior to inspection. This includes removal of obstructions such as solids and roots. The following specifications apply and attached:

Sewer Pipe Cleaning, Specification Guideline, November 2014, NASSCO

All lines shall be inspected after cleaning. Inspection shall be performed by experienced personnel trained in locating breaks, obstacles, and service connections by closed circuit television (CCTV) and certified in PACP and MACP inspection through NASSCO. The interior shall be carefully inspected to determine the location of any conditions. A videotape and log shall be provided to the City, see below. CCTV procedures shall follow the following guideline (is attached):

Pipe Condition Assessment Using CCTV, Performance Specification Guideline, NASSCO, October 2014.

DATA FILE REQUIREMENTS

All pipe videos and inspection files shall be provided in NASSCO v7.0 PACP format, with a separate database and video file for EACH segment (.mdb file, and .mp4 file for each segment), appropriate for direct import into the City of Littleton’s GraniteNET software. All asset references shall be in City of Littleton naming convention (SSMHXXXXX for manholes and SSGMXXXXX for mainline sewer gravity main pipe).

Data files must be named in the following format:

For video: SSMHXXXXX_SSMHXXXXX.mp4 For database files: SSGMXXXXX.mdb

1. All required (red) fields filled by NASSCO standard (currently 7.0)

2. PACP Header – Always include 25: Pipe Segment Reference

3. MACP Component – Always include 118: Structure ID for each pipe connection

4. Check media folder used in mdb – Whatever location path is used for inspections in mdb should match to corresponding media folders.

Note: Files that do not adhere to these requirements will be rejected and shall be resubmitted in correct format for final payment.

METHOD OF MEASUREMENT

Subsection 603.12 is deleted and replaced with the following:

Sewer pipe inspection will be measured by the linear foot (LF), complete in place and accepted.

Pipe inspection length will not be measured but will be the net length of pipe shown on the plans, except when field changes or ordered or when there are discovered errors on the plans.

Manhole and structure inspections will be measured by EACH.

BASIS OF PAYMENT

Subsection 603.13 is deleted and replaced with the following:

Sewer pipe and manhole/structure inspections will be paid for at the contract unit price for each pay item and will include all materials, labor, and equipment necessary to complete the work as described herein.

REVISION OF SECTION 630

CONSTRUCTION ZONE TRAFFIC CONTROL

Section 630 of the Standard Specifications is hereby revised as follows:

Subsection 630.01 shall be modified to read:

As required by, in descending order of precedence, these plans and special specifications, the current Standard Specifications, as augmented by the Colorado Department of Transportation M&S Standards, and the Manual on Uniform Traffic Control Devices for Streets and Highways.

Contractor shall verify all traffic control requirements for right of way permits from City of Littleton.

Subsection 630.10 shall be modified to read:

Temporary Traffic Control throughout the construction area shall be the responsibility of the Contractor. Before starting construction, the Contractor shall submit, in writing, the proposed Method of Handling Traffic (MHT) for the initial phase of construction. When a different MHT is required for a subsequent construction phase, it must be submitted two weeks prior to starting that phase. All proposed MHT’s shall be approved, in writing, by the Engineer or CDOT as applicable. No phase of construction shall start until an acceptable MHT has been received and approved by the City of Englewood or City of Littleton right of way permit offices. The proposed methods shall include, as a minimum, the following:

1. A detailed diagram which shows the location of all sign placements, including advance construction signs (if not previously approved) and speed limit signs; method length and time duration for lane closures; and location of flag persons.

2. A tabulation of all traffic control devices shown in the detailed diagram including, but not limited to: construction signs, vertical panel; vertical panel with light; Type 1 and Type 2 barricades; cones; drum channelizing devices; concrete barrier (temporary); advance warning flashing or sequencing arrow panel.

Approval of the proposed MHT is intended to indicate all devices to complete the Work safely.

Such approval does not relieve the contractor of liability specifically assigned to him under the Contract. The Contractor shall erect and maintain warning lights, signs, barricades, and sufficient safeguards around all excavations, embankments, and obstructions.

The Contractor shall, at the preconstruction conference, designate one of his employees, to be responsible for traffic control management. This responsibility shall include management for the contractor’s signing and all other details covered by the specifications which contribute to the convenience, safety, and orderly movement of traffic and to the comfort of the traveling public.

The designated employee will have the Certification of the Traffic Control Supervisor as a Worksite Traffic Supervisor by the American Traffic Safety Services Association (ATSSA) in lieu of completion of the CDOT minimum training requirements.

Traffic Control shall be maintained on a 24-hour per day basis. The Contractor shall make arrangements so that the Traffic Control Supervisor or his approved representative will be available on every working day, “on call” at all times and available upon the Engineer’s request at other than normal working hours. The Traffic Control Supervisor shall have an up-to-date copy of Part VI of the MUTCD, pertaining to traffic controls for street and highway constructions, available at all times.

The contractor shall apply for and receive Right-of-Way Permits (Contractor shall bear permit costs) prior to commencing operations. City of Littleton ROW permits will be issued upon approval of CDOT’s permit. Due to the mobility of the operation, the contractor will need to provide traffic control consistent with the MUTCD. For cleaning and preparation operations, the contractor will need to provide an MHT.

The Work will occur on local streets, the Contractor shall maintain a minimum of one lane open during the resurfacing operations and shall utilize flagger personnel to direct the traveling public around the work area.

Subsection 630.13 is revised to include the following:

1. Working hours shall be 7:00 a.m. to 7:00 p.m. Monday through Friday on local streets.

Work within CDOT right of way may be subject to additional restrictions.

2. The use of alternate one-way traffic on streets may be approved on a case-by-case basis, and must be approved in advance.

3. No lane closures are permitted without approval. No complete closure will be permitted.

4. All work done outside the times above must be approved by the applicable City official in writing.

5. Any work performed outside the times listed above may not be accepted and may be subject to fees.

Subsection 630.15 shall be replaced with the following:

Payment of traffic control necessary to complete the work shall be full compensation for furnishing, erecting cleaning, maintaining, resetting, repairing, replacing, moving, removing, and disposing of all construction traffic control devices. Payment shall also include all flagging associated with the work.

Subsection 630.16 shall be replaced with the following:

Traffic control shall be paid on a lump sum basis to be paid for as follows: 50 percent of the Schedule amount upon first utilization and the remaining 50 percent of the Schedule amount when 75 percent of the original schedule amount has been earned.

Payment for approved towing operations shall be reimbursed based on submitted invoices.

PAY ITEM PAY UNIT

Traffic Control Lump Sum

NASSCO, Inc.

2470 Longstone Lane, Suite M

Marriottsville, MD 21104

SEWER PIPE CLEANING

SPECIFICATION GUIDELINE

November, 2014

Thanks to the following participants for the development of this document:

Josh Ballum - NozzTeq

Diego Calderón - NASSCO Ted DeBoda - NASSCO

Al Hogan - American Concrete Pipe Association Harold Kosova - National Power Rodding

Pete Kellum - TeleVac Guy Leslie - RapidView

Gerry Muenchmeyer - Muenchmeyer Associates Heather Myers - NASSCO John Nelson - Visu-Sewer

Doug Sanders - City of Virginia Beach Joe Schotthoefer - Doetsch Environmental Services

George Selembo - InfoSense John Shaw - John Shaw Consulting

Marilyn Shepard - NASSCO Master Trainer Bill Shook - AP/M Permaform

Jimmy Stewart - Brenford Environmental Systems Mike Vislay - Envirosight

Jerry Weimer - City of Cincinnati (Chair)

Disclaimer

These specifications were prepared by NASSCO and peer reviewed by industry professionals. These specifications are not specific to any one product and should be considered a guideline only. Conditions for use may require additions, deletions or amendments to these guidelines so as to conform to project specific site conditions. NASSCO assumes no liability as to content, use and application of these guidelines.

Index

INTRODUCTION

SUGGESTED PROJECT STEPS

MANDATORY PRE-BID/PRE-CONSTRUCTION AND PROJECT MEETINGS

PART 1 - GENERAL

1.1 SCOPE OF SERVICES AND WORK PHASING

1.2 OWNER

1.3 TIME OF PERFORMANCE, SCHEDULING AND LIQUIDATED DAMAGES

1.4 COMPLIANCE AND ACCEPTANCE

1.5 REFERENCED DOCUMENTS

1.6 SUBMITTALS

PART 2 - SPECIAL PROVISIONS

2.1 OWNER RIGHTS

2.2 EMERGENCY RESPONSE

2.3 WORKING HOURS

2.4 DECREASE/INCREASE IN SERVICE AND STOP WORK DUE TO INCLEMENT

WEATHER

2.5 PRE-CONSTRUCTION MEETING

2.6 CLOSE-OUT PROCEDURES

2.7 PRE-QUALIFICATIONS

PART 3 - GENERAL PROVISIONS

3.1 MAINTENANCE OF TRAFFIC

3.2 EXISTING UTILITIES

3.3 REQUEST FOR SUPPLEMENTARY INFORMATION

3.4 USE OF PREMISES

3.5 PROTECTION OF TREES

3.6 FENCING

3.7 RESTORATION

3.8 CLEANUP

3.9 PROPERTY DAMAGE

3.11 ACCESS TO MUNICIPAL WATER SUPPLIES

PART 4 - EXECUTION

4.1 GENERAL

4.2 SEWER CLEANING AND GRINDING OF SERVICE CONNECTIONS

4.3 TELEVISION INSPECTION AND COMPUTERIZED EQUIPMENT

PART 5 - PAYMENT FOR WORK

5.1 MEASUREMENT AND PAYMENT

HEADER FIELD CHECKLIST

CLEANING PROJECT BID SHEET (SAMPLE)……………………………………………………………..26

INTRODUCTION

These specifications were written to provide a comprehensive, uniform and consistent template for the procurement of sewer line cleaning and inspection services based on the current industry services and technologies. They have been created and reviewed by industry experts including Contractors, Equipment Manufacturers and their Representatives, Municipalities, Engineers, Operators, and Field Technicians. It is hoped that facility Owners will find this useful in their procurement processes and that other parties involved in this industry find it helpful in clarifying what might otherwise be ambiguous.

This document was developed to provide clarity on the issues that have proven problematic for the procurement of pipeline cleaning services. Encompassing all industry perspectives, this document strives to offer an understanding and knowledge base from which all parties can communicate in a clear and concise manner.

This document was created to allow flexibility for the end-user, whether the Owner, engineer and or municipality. As a guideline, this document is not meant to be simply cut and pasted into a specification. Flexibility rests in the ability to customize the specification to your specific budget and service requirements. The specification requires the facility Owner to make decisions while creating the document. This level of customization is necessary because specific services or technologies may not be applicable to all geographic locations or each specific project. Decisions must be made to alter and affect the outcome of the project to best suit the budget and service requirements.

Should you find this document lacking in any way, we would welcome your comments and suggestions for improvement in future revisions.

SUGGESTED PROJECT STEPS

The following is basic, step by step guidance for the successful planning, implementation and completion of a sewer cleaning and/or CCTV project. These steps have been compiled, reviewed and presented by the NASSCO Industry Standards Committee, which is comprised of experts in the field including Contractors, Owners (public and private), Equipment Manufacturers, Operators and Engineers. The following is based upon their experiences on these projects.

1. Establish need based upon existing sewer O&M Program(s)

2. Determine Scope of Work

a. Consider budget available for project

b. May need to consult with other Owners or experts to compile reasonable cost estimates

3. Create a detailed project map from existing conveyance system maps to include as much information as possible

a. Pipe size

b. Scheduled pipe length

c. Material

d. Age of sewer

e. Depths

f. Shapes

g. Determination if debris in sewer is hazardous

h. Potential hazards in sewer (ex. H2S, explosive, corrosive)

4. Gather Data on area(s) of Cleaning/CCTV Project

a. Accessibility

b. Restrictions

c. Environmental issues

d. Water access and costs

e. Dumping availability and costs

5. Determine if Owner or Contractor will do Preliminary Inspection or if it already exists

6. Write Bid Specifications

a. Define types of cleaning

b. Define level of cleaning expected (95%)

c. Establish verification method (CCTV-PACP)

d. Establish payment method and schedule

e. Include the time frame for completion and possible liquidated damages if not completed on time

f. Establish mandatory pre-bid meeting to:

i. Ensure that everyone understands your expectations

ii. Interview the bidding Contractors

iii. Eliminate bidders claiming they were not informed of something and did not bid accordingly and who may request unsubstantiated extras during the project

iv. Ensure that there are interested bidders knowledgeable about your project and not an uninformed bidder, etc.

v. Establish method to work out differences to prevent issues later in project

g. Define required deliverables

h. Establish payments/ responsibility/ location for water usage and debris disposal to

i. Prevent change orders and issues with dumping of debris

ii. Establish when and how work may be billed

iii. Outline which party is responsible for each activity

iv. Define liability for damages

v. Help prevent defaults and lawsuits

i. Define liability for stuck equipment and damaged utility

i. Make it clear, who will retrieve stuck equipment and who will pay for retrieval of equipment and repair of sewer

ii. Established when each party is responsible

7. Publish Project Notice in local, regional papers, plan houses, etc.

8. Pre-qualify potential Bidders

a. Review Bids

b. Check References

c. Verify quality of work / timeliness and quality of deliverables

d. Verify Certifications and experience

9. Hold Mandatory Pre-Bid Meeting

10. Receive and Open Bids

11. Review apparent low bid and make award recommendation

12. Award Bid

13. Issue Notice of Award

14. Receive and review contract required documents (insurance, bond, etc.)

15. Issue Notice to Proceed

16. Hold Mandatory Pre-Construction Meeting to include Field Personnel

a. See Mandatory Pre-bid and Pre-construction Project Meetings

b. Reinforces all issues in contract and clarifies any questions from field personnel

17. Begin Project

18. Weekly Update Meetings

a. Deals with problems and issues early.

19. Receive Lien Release(s)

20. Issue Notice of Completion

21. Issue Final Payment

22. End Project Meeting

23. Close Project

MANDATORY PRE-BID/PRE-CONSTRUCTION AND PROJECT MEETINGS

Making these meetings mandatory will ensure the full understanding and project requirements by both the Contractor and Owner.

PRE-BID MEETINGS

CONTRACTORS MUST ATTEND A MANDATORY PRE-BID CONFERENCE at the (LOCATION) located at (ADDRESS) at (TIME DATE) to discuss the Bidding Documents and Specifications. CONTRACTORS WHO DO NOT ATTEND THE PRE-BID CONFERENCE WILL

BE DISQUALIFIED FROM THE BIDDING PROCESS.

The purpose of this MANDATORY PRE-BID meeting is to ensure that all companies bidding on the project fully understand the scope of work, definitions and interpretation of all items in the bid documents. Questions may be answered at the MANDATORY PRE-BID; However all questions will be required to be submitted in writing by (DATE) to Owner and (EMAIL ADDRESS) and will be addressed in addendum, Questions and answer will be distributed to all attendees at the MANDATORY PRE-BID meeting.

PROJECT MEETINGS

A. Pre-Construction Meeting - MANDATORY See attendance requirements below B. Progress Meetings - Attendance requirement to be determined by the Owner prior to the scheduled meeting.

C. Project Completion Meeting - Attendance requirement to be determined by the

Owner prior to the scheduled meeting.

MANDATORY PRE-CONSTRUCTION MEETINGS

The Owner will schedule a Pre-Construction Meeting to

A. Finalize communication and coordination protocols B. Review the Final Planning Document with special attention to

1. Schedule

2. Public Notification

3. Traffic Control

4. Flow Control

C. Discuss the ensuing field work prior to starting the project. This meeting may be held at a location designated by the Owner. The purpose of this meeting is to ensure that the successful bidder fully understands and will comply with all contract documents and Owner requirements.

Guidelines for the Pre-Construction Meeting:

A. Schedule: No later than 15 days after date of Notice to Proceed

B. Location: A central site, convenient for all parties, designated by the Owner

C. Attendance

1. Owner.

2. Owner’s Inspector

3. Engineer

4. Contractor’s Representative

5. Contractor's Superintendent

6. Major Subcontractors

7. Major Suppliers

8. Others, as appropriate

D. Suggested Agenda

1. Distribution and discussion of

a. List of major Subcontractors and Suppliers

b. Projected Construction Schedules

2. Critical work sequencing

3. Major equipment deliveries and priorities

4. Project Coordination

a. Designation of responsible personnel

b. Communication protocol

5. Procedures and processing of

a. Field decision

b. Requests for Information

c. Submittals

d. Deliverables

e. Change Orders

f. Applications for Payment

6. Procedures for maintaining Record Documents

7. Use of premises

a. Office, work and storage areas

b. Owner's requirements

8. Construction facilities, controls and construction aids

9. Temporary utilities

PART 1 - GENERAL

1.1 SCOPE OF SERVICES AND WORK PHASING

A. The purpose of this bid is to obtain competitive unit prices for all labor, material, and equipment necessary to clean and inspect via closed-circuit television (CCTV) existing sanitary and combined sewers ranging in size from 6- to 30-inch diameter. The work includes hydraulic root cutting and cleaning, grinding protruding break-in service connections, remote televising and recording of the sewer. All project locations will be within the Owner service area.

B. The work to be completed on each section of sewer will be performed in phases as defined in the following:

1. Phase 1 Pre-cleaning Inspection.

a. The preferred method for Pre-Cleaning Inspection is color CCTV conforming to NASSCO Pipeline Assessment Certification Program (PACP), and for the data to be exported electronically in a PACP certified format. Since this inspection is performed prior to cleaning, it is understood that the video may not provide an “unobstructed view of the entire pipe”.

b. The Contractor may propose other methods to the Owner prior to bid for inspection such as, zoom camera inspection, digital sidewall scanning inspections, acoustical technology, etc.

c. If the Contractor is performing the Pre-Cleaning Inspection, the method must be pre-approved by the Owner prior to inspection of the sewer interior.

2. Phase 2 Sewer Pipe Cleaning. Based on the Owner’s review, he or she will determine if additional work will be required. At the sole discretion of the Owner is to either declare the work on the particular sewer segment complete or notify the Contractor of additional work (i.e. Phase 3: Light Sewer Cleaning, Heavy Cleaning, Deposit Cut, Root Cut Medium, Root Cut Ball, or Lateral Cut)

3. Phase 3 Additional Sewer Pipe Cleaning (Optional). The Contractor shall perform the assigned additional work, which may be any one of the following items as defined in these specifications: Light Sewer Cleaning, Heavy Cleaning, Deposit Cut, Root Cut Medium, Root Cut Ball, or Lateral Cut

4. Phase 4 Post Cleaning Inspection. Final televising of the sewer segment to evaluate the condition of the sewer segment after all cleaning has been performed in Phase 3. Phase 4 will be required to be performed and will be reimbursed at the bid unit price.

a. The recorded video must show the entire circumference of the sewer. Any flow control to remove standing water and debris shall be incidental to the contract. It is not the intent of this specification to require bypass pumping to control heavy flow; however, the Contractor must, at a minimum, make reasonable effort to control the flow by using flushing equipment to temporarily retain flow or to remove standing water. The Contractor must also consider weather conditions to obtain the best video image of the sewer. This may require the Contractor to delay any video work after major rain events until the system can return to lower dry weather flow. The Contractor shall submit PACP data to include the electronic video reports, logs, etc. for the Owner’s review as required in Part 1 Section 6.

b. The segments of sewer to be cleaned and televised through this contract will be located primarily within the paved areas of the public right-of-way;

however, there may be some sewer segments that are located within public easements on private property. The successful bidder, with assistance of the Owner as required, will be responsible to coordinate and gain access to any and all sewer segments and will be responsible for any restoration in accordance with Part III Section 5. This will include written authorization between Contractor and landowner.

C. The Contractor shall furnish all labor, components, materials, tools, and appurtenances necessary for the performance and completion of the contract.

D. Award of the contract will be determined through an evaluation of bids and made in light of the best interest of the Owner.

E. The Contractor will be held fully liable for any damages incurred that are caused by his or her negligence.

F. Patents, Trade Secrets, and Copyrights: The Contractor shall pay all license fees and royalties and assume all costs incidental to the use in the performance of the work or the incorporation in the work of any invention, design, process, product or device which is the subject of patent rights, trade secrets protection rights, or copyrights held by others. The Contractor shall indemnify and hold harmless the Owner and Engineer and anyone directly or indirectly employed by either of them from and against all claims, damages, losses and expenses (including attorney’s fees and court and arbitration costs) arising out of any infringement of patent rights, trade secret protection rights, or copyrights incidental to the use in the performance of the work or resulting from the incorporation in the work of any invention, design, process, product or device not specified in the contract documents, and shall defend all such claims in connection with any alleged infringement of such rights.

1.2 OWNER

A. This contract will be administered and performed under the direction and inspection of the Owner. Questions pertaining to this contract, before and after award, should be directed to the Owner at (PHONE NUMBER) and (EMAIL ADDRESS).

1.3 TIME OF PERFORMANCE, SCHEDULING AND LIQUIDATED DAMAGES

A. Upon award of the contract, the Contractor shall CCTV at least three (3) segments or 1,000 feet of pipe and submit the data to the Owner to verify that the CCTV database is compatible with the Owner’s PACP Database, and the deliverables are acceptable to the Owner. The Owner shall verify acceptability of the deliverables within five (5) business days of receipt. After the Owner verifies compatibility of the database, the Owner shall then issue to the Contractor a written “Notice to Proceed” including a date for commencement of work. The Contractor shall begin work on the date stated in the written “Notice To Proceed” (but no later than 10 calendar days after receipt) with an adequate force and sufficient resources to demonstrate due diligence in the performance of the contract.

B. It is understood that the bidder may have other contracts with the Owner during the period of this contract. By bidding this work, the bidder is agreeing to provide an adequate number of crews in order to perform the work concurrently with due diligence and as specified in his approved schedule.

1.4 COMPLIANCE AND ACCEPTANCE

A. Compliance with this contract shall be complete when all conditions set forth in these specifications have been met. The following defines each work item, the level of effort, and quality of work that will be necessary to meet the intent of this specification:

B. Pre-cleaning Inspection:

1. The preferred method for Pre-Cleaning Inspection is color CCTV conforming to

National Association of Sewer Service Companies’ (NASSCO) Pipeline Assessment Certification Program (PACP), exported electronically in a PACP compliant format. Other methods for inspection, including CCTV, zoom camera inspection, digital sidewall scanning inspections, acoustical technologies, etc.

must be preapproved by the Owner prior to inspection of the sewer interior.

2. Should the level or type of debris differ from the original inspection, the work type can be adjusted by the Owner to the proper work type and the work shall be paid at the adjusted, proper rate. The Contractor shall be responsible for providing evidence of the change in conditions to the Owner.

C. Light Sewer Cleaning (Each Segment)

1. Removal of Deposits Settled (DS):

a. Up to 12-inches 25%

b. 13- to 24-inches 15%

c. 25- to 30-inches 10%

2. The Contractor shall clean the sewer and associated manholes, including drop connections and benches, to remove all Deposits Settled (DS), so that the sewer is ready for televising. This will require an unlimited amount of passes of a hydraulic flusher to remove all loose debris and collect it for removal in the downstream manhole. All debris must be removed from the sewer, including any debris that may have been washed up into any service connections (does not include known pre-existing conditions in service connections), drop connections or the bench wall of the manholes. This item does not include any root cutting, deposit removal, or grinding of protruding service connections.

D. Heavy Sewer Cleaning (Each Segment)

1. Removal of Obstructions (OB) and Deposits Settled (DS) that exceed percentage established for light cleaning. This also includes Deposits Attached Grease (DAGS) if able to remove with rotating nozzle or other mechanical means; not to include saws or cutters. Compliance with this section requires substantial effort towards cleaning

2. Under this bid item, the Contractor shall remove all obstructions in the sewer. All debris must be removed from the sewer, including any debris that may have been washed up into any service connections (does not include known pre-existing conditions in service connections), drop connections or the bench wall of the manholes. This includes all grease, rocks, debris, sticks, etc. that will reduce the hydraulic capacity of the sewer and limit future maintenance access of remote equipment. This work will include an unlimited number of passes by high velocity hydro-cleaning equipment. A mechanical/hydraulic Spinner Nozzle may be used where necessary at no additional cost to the District; however, the Contractor shall be responsible for any damage to the sewer or any service connections. This item does not include cutting/grinding protruding break-in connections, as that work will be paid under a separate bid item.

3. The Contractor shall maintain detailed documentation of cleaning efforts made to remove these items. Such documentation shall be made available to the Owner at any time.

4. The Contractor shall immediately notify the Owner if he believes that this level of cleaning will cause a sewer collapse due to the existing deterioration of the host pipe. The Owner’s determination whether to continue or stop work is final.

E. Root Cut (Each segment)

1. Root Cut Medium - Removal of Roots Medium (RM), and Root Balls (RB) in one or two joints.

2. Root Cut Ball – Removal of Root Balls (RB) removed in at least 3 joints.

3. The Owner shall determine if the sewer segment requires root cut cleaning. All roots must be screened, collected, and removed from the sewer for proper disposal.

4. The Contractor shall immediately notify the Owner if he believes that these activities performed under this paragraph will cause a sewer collapse due to the existing deterioration of the host pipe. Owner's determination whether to continue or stop work is final.

F. Deposit Cut (Each Segment)

1. Removal of Deposits Attached Encrustation (DAE) and Deposits Attached Grease

(DAGS) that require a cutter to remove.

2. Under this bid item, the Contractor shall remove all obstructions in the sewer. All debris must be removed from the sewer, including any debris that may have been washed up into any service connections (does not include known pre-existing conditions in service connections), drop connections or the bench wall of the manholes. This includes all deposits, grease, debris, sticks, etc. that will reduce the hydraulic capacity of the sewer and limit future maintenance access of remote equipment. This work will include an adequate number of passes using high velocity hydro-cleaning equipment required to produce a clean pipe in accordance with these specifications. A mechanical/hydraulic root, chain cutter, etc. may be used where necessary at no additional cost to the Owner; however, the Contractor shall be responsible for any damage to the sewer or any service connections. This item does not include cutting/grinding protruding break-in connections, as that work will be paid under a separate bid item

3. Compliance with this section requires substantial effort towards cleaning, chipping, cutting, grinding, etc. to remove hardened deposits, grease, etc. The Contractor shall use remote CCTV equipment to monitor the progress of the work and ensure that the sewer is not damaged.

4. The Contractor shall immediately notify the Owner if he believes that activities performed under this paragraph will cause damage due to the existing deterioration of the host pipe. The Owner's determination whether to continue or stop work is final.

5. The Contractor shall maintain detailed documentation of cleaning efforts made to remove these items.

6. If attached deposits cannot be removed by tools normally used in the industry, the Owner should be consulted immediately. The Owner and the Contractor should discuss whether to cancel the work on that segmentation or negotiate a flat rate or hourly rate for the Contractor to do the work.

G. Lateral Cuts

1. Removing protruding laterals, excludes DIP, SP, CAS etc.

2. The Owner shall determine when break-in service connections will require grinding based on his review of the initial survey television inspection. The Contractor shall cut/grind the protruding service connection by using a remote grinding/cutting device capable of removing, concrete, vitrified clay, PVC and other types of pipe material. The device shall be specifically designed to cut/grind protruding service connections. The Contractor shall use remote CCTV equipment to monitor the progress of the work and ensure that the service connection is not damaged.

3. The protruding break-in service connection shall be cut/ground flush to the main sewer pipe without scouring or damaging the main sewer or service connection.

All cuttings must be screened, collected, and removed from the sewer for proper disposal.

4. During the final survey television inspection, the Contractor shall slowly pan the entire circumference of the trimmed connection to verify the quality of the work.

5. The Contractor shall immediately notify the Owner if he believes that the pipe is not structurally sound. The Contractor and Owner shall discuss the severity and risk of cutting/grinding the lateral. The Owner shall then determine, if they want the lateral cut/ground, at the Owners risk, or if the work should not be performed on this contract.

6. If other than typical lateral materials are encountered, the Contractor shall notify the Owner and the Owner and Contractor should discuss the ability, costs and risks associated with cutting/grinding the lateral. The Owner shall decide, whether to cut/grind the lateral or to not cut/grind the lateral. If the Owner decides to cut/grind the lateral, the price should be negotiated between the Owner and Contractor, prior to cutting/grinding the lateral.

H. Debris Records

1. The Contractor shall keep records of types of debris, removed from each segment of pipe and provide these records to Owner in the format requested by Owner.

I. Final Survey Television Inspection

1. As in the initial survey television inspection pay item, CCTV inspections will be conducted entirely in digital format.

2. All CCTV work shall conform to the most current NASSCO PACP standards. The documentation of the work shall consist of NASSCO PACP CCTV Reports, Unmodified NASSCO PACP database, logs, electronic reports, etc. noting defects and observations encountered during the inspection.

1.5 REFERENCED DOCUMENTS

A. All work must also conform to the latest edition of the following specifications:

1. State Department of Transportation, Construction and Materials Specification.

2. Rules and Regulations and Standard Drawings.

3. Rules and Regulations of the Office of the County Engineer.

4. If there is a difference in these specifications, the Rules and Regulations shall govern, DOT Specification.

5. NASSCO PACP Standards.

6. Other standards as appropriate.

B. Liability and Assumptions

In order to minimize and appropriately allocate costs and risks, it is in the best interest of all contracted parties (Owner and Contractor) and prospective parties (i.e. Bidders) to understand thoroughly the risks associated with any particular project. For that reason we will define herein, what is standard practice in the procurement and completion of sewer cleaning and inspection so that everyone involved can effectively assess their obligations, risks, and duties.

C. Assumptions It is reasonable and customary to assume the following, unless otherwise detailed in writing:

i. The Owner has provided the Parties (Contractor and/or Bidders), in writing, with all of the information that the Owners possess that would allow the Parties to accurately and fully assess the entire scope of the project.

ii. The Owner possesses or has contracted the services of a person or entity who possesses the knowledge, expertise and experience to fully understand the scope of the service for which they are attempting to contract with the Parties.

iii. The Parties are knowledgeable, capable and legally authorized to contract for the services in question.

iv. The infrastructure for which the services are requested are in suitable condition to allow for the activities which are usual and customary for the services requested without undue risk to the Parties equipment or personnel, unless otherwise described by the Owner in writing.

D. Liabilities

Should it be found during initial investigation and/or during the course of performance that conditions are different than those which are typical and customary and outside of the assumptions listed above, the Contractor may negotiate a reasonable change in terms. The Owner reserves the right to re-bid such work if it results in a substantial increase in cost by more than 5% of the total project

E. Notification

1. If observed defects are believed to be such that further cleaning operations may compromise the structural integrity and/or cause the pipe to become unusable, the Contractor must provide written communication to the Owner’s designee of the observed condition(s) and reason to believe that continued cleaning operations may cause substantial damage. The Owner will then direct the Contractor as to what services, precautions, etc., the Owner will require of the Contractor. If the contract documents do not address this potential, then the Owner and Contractor will negotiate in good faith, the conditions under which the work is to continue or cease to continue.

2. This exception may only be used to prevent asset damage and shall not be used to eliminate difficult or adverse cleaning areas that were previously documented in these documents or by prior written communication with the Owner.

1.6 SUBMITTALS

A. All submittals are due as scheduled. Work will not proceed until all submittals are received and approved. The project manager reserves the right to adjust the due dates of the submittals based on Contractor performance. The Contractor shall label each submittal indicating what is represented, name of Contractor, and project number. All submittals identified as being in error shall be re-performed and corrected at the Contractor’s expense.

B. Submittals Required with Bid Documents include:

1. List of references per Part II Section 7.

2. Documentation of Certification of PACP Software

C. Pollution and Liability Insurance

1. The Contractor's commercial general liability limits must be not less than $___, total occurrence limit, and include pesticide or herbicide applicator coverage.

2. Pollution insurance. At the time of the bid opening, the Contractor shall submit written evidence that he has the ability to obtain pollution liability coverage. This coverage shall protect the Contractor, the Owner, and the Owner's officers, agents and employees from claims for damages for bodily or personal injury, sickness or disease, including death, and from claims for damages to property and/or the environment, which may arise directly out of the use of chemicals and/or pollution.

An “A” rated insurance company shall provide the Contractor’s Liability insurance.

3. Liability Insurance. 7 (seven) days prior to the pre-construction meeting, the Contractor shall submit written evidence that he has obtained pollution liability coverage; limits must be not less than $___ total occurrence limit. In addition, the Contractor's commercial general liability limits must be not less than $___, total occurrence limit, and include pesticide or herbicide applicator coverage. The Owner shall be named as an additional insured with respect to General Liability.

D. Submittals required of the Successful Bidder seven (7) days prior to the Pre-construction Meeting

1. Name of the project supervisor and resumes.

2. Documentation of NASSCO PACP certification for all CCTV operators, database and software.

3. Site Safety Plan. A complete generic site safety plan must be submitted one week prior to the pre-construction meeting. Work will not begin until an approved site safety plan is in place.

4. Sample inspection CCTV data and video or data from other approved inspection method.

E. Submittals Required for the Pre-construction Meeting

1. An initial comprehensive schedule of work, see Part IV, Paragraph D (To be approved by the Owner

2. Management Organization: Provide an organization chart depicting the essential organizational elements and senior personnel of the proposed Contractor and the functions and interrelationships of the personnel proposed to provide technical support, project management and supervision for this project. Provide succinct resumes of the personnel proposed to provide technical support and project management for this project. The personnel designated in the management summary for essential positions shall not be changed except with the permission of Owner. The Owner will only approve such a change when, in its opinion, the substitute personnel have equal or greater qualifications and experience to those intended to be replaced.

3. Proof that Contractor is an approved/bonded Contractor with the Owner.

F. Submittals Required One Week Prior to Any Cleaning & Televising Work

1. Site specific site safety plan addenda.

2. Entry releases, if applicable

G. Weekly Submittals

1. Detailed updates to the work schedule will be provided to the project manager no later than 1:00 p.m. on the Friday preceding the next week's cleaning and televising work.

2. DVDs, logs, and / or electronic worksheets submitted 7 days prior to work). All field paperwork must be submitted before the Contractor’s invoice will be processed for payment.

3. Corrections to punch list items as required by the project manager to fulfill the requirements of this specification.

H. Final Submittals Prior to Payment

1. Corrections to punch list items as required by the(Owner to fulfill the requirements of this specification.

PART 2 - SPECIAL PROVISIONS

2.1 OWNER RIGHTS

A. The Owner reserves the right to stop the work when, in the project manager's judgment, the Contractor's work or activities are threatening the health and safety of the public or endangering the environment or endangering the waters of the state.

Work shall not proceed until a satisfactory resolution has been achieved, as determined in the sole and unfettered opinion of the Owner.

B. The Contractor or Subcontractor shall not perform any work which is not specifically identified in the work schedule unless approved by the Owner. Notification of such work must be received no later than 8:00 a.m. on the day the work is to be performed.

A list of persons available to be notified will be given at the pre-construction meeting.

2.2 EMERGENCY RESPONSE

The Contractor shall provide a telephone number and pager number to the Owner. These numbers are intended for the project manager’s use in contacting the evening/weekend/holiday emergency work crew for emergencies resulting from the Contractor’s actions or lack thereof during this project. This crew shall be responsible for contacting the Owner within one-half hour after the first verbal or electronic notification. If the Contractor's crew has not responded to the site of the emergency within one hour of the first summons, verbal or electronic, the Owner will make all necessary repairs and bill the Contractor for all work performed. Costs related to the emergency response will be incidental to the contract and not measured for payment.

2.3 WORKING HOURS

A. The Contractor must complete all work such that no homeowner is without sewer service, unless otherwise directed by the Owner. Local noise ordinances or agencies having control over roadway closures may control starting or stopping operations. Prior to starting operations, the Contractor shall advise the Owner of the restrictions imposed by the local agencies.

B. No work will be allowed on weekends or holidays except at the discretion of the Owner.

2.4 DECREASE/INCREASE IN SERVICE AND STOP WORK DUE TO INCLEMENT

WEATHER

The Owner, at its option, may increase or decrease any or all service requirements provided for under this contract. The Owner further reserves the right to suspend or stop the performance of any or all of the work of this contract due to inclement weather conditions.

2.5 PRE-CONSTRUCTION MEETING

A. Following award of the contract and before starting any work the Contractor, job superintendent/project manager, and crew leader shall meet with the Owner. The Contractor will be notified of the date, time, and place of the meeting.

B. Attendance:

1. Owner

2. Owners Inspector

3. Engineer

4. Contractor’s Representative

5. Contractor's Superintendent

6. Major Subcontractors

7. Major Suppliers

8. Others, as appropriate

C. Agenda:

1. Distribution and discussion of:

a. List of Major Subcontractors and Suppliers.

b. Projected Construction Schedules.

2. Critical Work Sequencing.

3. Major Equipment Deliveries and Priorities.

4. Project Coordination.

a. Designation of Responsible Personnel.

5. Procedures and processing of:

a. Field decisions.

b. Requests for Information.

c. Submittals.

d. Deliverables

e. Change Orders.

f. Applications for Payment.

6. Procedures for maintaining Record Documents.

7. Use of Premises:

a. Office, Work and Storage Areas.

b. Owner's Requirements.

8. Construction Facilities, Controls and Construction Aids.

9. Procedures for Reporting Sanitary Sewer Overflows (SSOs).

10. Temporary Utilities.

2.6 CLOSE-OUT PROCEDURES

A. Progress Meetings: Project closeout will be completed in phases by project. The

Owner will hold progress meetings at predetermined intervals, or as determined necessary by the Owner. Items covered in the meetings include the following.

1. Punch List: This list will detail all items requiring correction, repair, or improvements in order to be accepted. The Contractor will address these items within 7 calendar days or as specified by the Owner. Failure to complete punch list items will result in a stop work notice and delay of payment until completed to the satisfaction of the Owner.

2. Reports and Submittals: Final reports, post-tapes and other submittals previously described will be finalized and submitted.

3. Review of the status of pay estimates.

4. Issue project worksheets, as necessary.

5. Work scheduling issues.

2.7 PRE-QUALIFICATIONS

A. The successful low bidder must have an onsite field supervisor with a minimum five

(5) years of experience specializing in the cleaning and televising of sewers. A foreman for each crew performing cleaning and television inspection with a minimum of five years of experience specializing in that type of work may be substituted for the onsite field supervisor requirement. The Contractor shall provide the names, titles, phone numbers and addresses of a minimum of two references that can be used to verify this experience. The references must be contract managers or persons of authority over cleaning and televising work performed by the Contractor.

1. The Contractor shall also provide 5 similar projects with cleaning and inspection equipment as proposed for this project.

2. The Contractor must have foreman or supervisors meeting all pre-qualifications for the duration of the contract.

B. PACP Requirements

1. Current NASSCO PACP certification of all CCTV operators, working on this project, will be required for all CCTV work.

2. Database shall be an unmodified NASSCO-PACP (Current Version) Certified Access…