Technical Specifications Summary: Cascade Hatchery Rearing Ponds Bird Predation Structure
This document comprises the Technical Specifications for a state of Oregon construction project to build a bird predation structure at the Cascade Hatchery. The scope of work includes reusing or replacing existing structural members (specifically vertical braces and connecting elements such as bolts, welds, and plates), procuring and installing all new structural steel members for the East Ponds with fasteners and finishing materials, and supplying new predator wire for structures over the East ponds. The project is identified as Engineering Project #24-015 and requires coordination with ongoing hatchery operations, with water flow in the headbox needing to remain operational and only allowing 1-2 hour shutdowns with advance planning. The specifications comprise 32 sections across nine divisions, covering general requirements, concrete work, structural and miscellaneous metals, welding, coatings, and surface restoration. Key divisions include Division 01 (General Requirements), Division 03 (Concrete), Division 05 (Metals), Division 09 (Finishes), and Division 32 (Exterior Improvements).
The technical specifications establish detailed requirements for all work phases including submittals, quality control, testing, material standards, and execution procedures. Notable provisions include requirements for AISC-certified fabricators and erectors, AWS-qualified welders, independent testing laboratory engagement at the contractor's expense, and strict adherence to build America Buy America Act (BABAA) certification requirements if applicable. Concrete work must achieve 4000 psi compressive strength at 28 days with permeability-reducing admixtures for water-retaining structures, and all materials must be nontoxic to fish species given the aquaculture environment. Surface preparation standards reference SSPC specifications, with abrasive blast cleaning requirements varying by exposure conditions (SP-5 for submerged surfaces, SP-6 for general industrial use). The contractor bears responsibility for site safety, temporary facilities, erosion control, and compliance with Oregon OSHA standards and the Oregon Structural Specialty Code, with final acceptance contingent upon successful leak testing of water-holding structures and restoration of all disturbed site areas.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TABLE OF CONTENTS TS-i
Cascade Hatchery
Rearing Ponds Bird Predation Structure
Engineering Project # 24-015
TECHNICAL SPECIFICATIONS
CASCADE HATCHERY
REARING PONDS BIRD PREDATION STRUCTURE
TABLE OF CONTENTS
Division .... Section Title .................................................................................................... ...…Page Number
DIVISION 01 – GENERAL REQUIREMENTS
01 09 10 Reference Standards ....................................................................................................... TS-3
01 11 00 Summary of Work .......................................................................................................... TS-7
01 22 00 Measurement and Payment ............................................................................................ TS-11
01 31 00 Project Management and Coordination .......................................................................... TS-13
01 33 00 Submittal Procedures ...................................................................................................... TS-21
01 35 13 Project Procedures .......................................................................................................... TS-25
01 37 00 Schedule of Values ......................................................................................................... TS-27
01 40 00 Quality Control ............................................................................................................... TS-29
01 50 00 Temporary Facilities and Controls ................................................................................. TS-33
01 60 00 Product Requirements .................................................................................................... TS-39
01 70 00 Project Closeout ............................................................................................................. TS-41
01 78 39 Project Record Documents ............................................................................................. TS-43
DIVISION 03 – CONCRETE
03 30 00 Cast-In-Place Concrete ................................................................................................... TS-49
DIVISION 05 – METALS
05 05 22 Metal Welding ................................................................................................................ TS-77
05 12 00 Structural Steel Framing ................................................................................................. TS-83
05 50 00 Metal Fabrications .......................................................................................................... TS-91
DIVISION 09 – FINISHES
09 96 00 High-Performance Coatings ........................................................................................... TS-101
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 12 18 Surface Restoration ........................................................................................................ TS-115
TABLE OF CONTENTS TS-ii
Rearing Ponds Bird Predation Structure
Engineering Project # 24-015
PAGE LEFT BLANK INTENTIONALLY
DIVISION 01 – GENERAL REQUIREMENTS
Rearing Ponds Bird Predation Structure
TS-1
Rearing Ponds Bird Predation Structure
Engineering Project # 24-015
TS-2
REFERENCE STANDARDS 01 09 10
Rearing Ponds Bird Predation Structure
Engineering Project # 24-015
SECTION 01 09 10 – REFERENCE STANDARDS
PART 1 – GENERAL
1.1 QUALITY ASSURANCE
A. Titles of Sections and Paragraphs: Captions accompanying Technical Specification sections and paragraphs are for convenience of reference only and are not to be used to define the lim-its of subcontracts.
B. Applicable publications: Whenever in these Technical Specifications references are made to published specifications, codes, standards, or other requirements, it shall be understood that wherever no date is specified, only the latest specifications, standards, or requirements of the respective issuing agencies which have been published as of the date that the Work is adver-tised for bids, shall apply; except to the extent that said standards or requirements may be in conflict with applicable laws, ordinances, or governing codes. No requirements set forth here-in or shown on the Drawings shall be waived because of any provision of, or omission from, said standards or requirements.
C. Without limiting the generality of other requirements of the Technical Specifications, all
Work specified herein shall conform to or exceed the requirements of applicable codes and the applicable requirements of the following documents to the extent that the provisions of such documents are not in conflict with the requirements of these Technical Specifications nor the applicable codes.
D. In case of conflict between codes, reference standards, Drawings and the other Contract Doc-uments, the most stringent requirements shall govern. Conflicts shall be brought to the atten-tion of the Owner’s Authorized Representative for written clarification and directions prior to ordering or providing any materials or labor.
E. Applicable Standard Technical Specifications: The Contractor shall construct the Work speci-fied herein in accordance with the requirements of the Contract Documents and the refer-enced portions of those referenced codes, standards, and specifications listed herein (except, that wherever references to “Standard Specifications” are made, the provisions therein for measurement and payment shall not apply).
F. References herein to “OSHA Regulations for Construction” shall mean Title 29, Part 1926, Construction Safety and Health Regulations, Code of Federal Regulations (OSHA), including all changes and amendments thereto.
G. References herein to “OSHA Standards” shall mean Title 29, Part 1910, Occupational Safety and Health Standards, Code of Federal Regulations (OSHA), including all changes and amendments thereto.
1.2 REFERENCE SPECIFICATIONS, CODES AND STANDARDS
A. THE FOLLOWING DOCUMENTS OR AGENCIES MAY BE REFERENCED IN THE
CONTRACT DOCUMENTS
AA Aluminum Association
AABC Associated Air Balance Council
AAMA Architectural Aluminum Manufacturers Association
AAR Association of American Railroads
AASHTO American Association of State Highway and Transportation Officials
AATCC American Association of Textile Chemists and Colorists
ACI American Concrete Institute
ADC Air Duct Council
TS-3
Rearing Ponds Bird Predation Structure
Engineering Project # 24-015
AEIC Associated Edison Illuminating Companies
ABMA American Bearing Manufacturers Association, Inc.
AGA American Gas Association
AGC Associated General Contractors of America
AGMA American Gear Manufacturers Association
AHAM Association of Home Appliance Manufacturers
AI The Asphalt Institute
AIA American Institute of Architects
AISC American Institute of Steel Construction
AISI American Iron and Steel Institute
AITC American Institute of Timber Construction
AMCA Air Movement and Control Association International, Inc.
ANS American Nuclear Society
ANSI American National Standards Institute, Inc.
APA APA-The Engineered Wood Association
API American Petroleum Institute
APWA American Public Works Association
AREA American Railway Engineering Association
AHRI Air-Conditioning, Heating, and Refrigeration Institute
ASA Acoustical Society of America
ASABE American Society of Agricultural and Biological Engineers
ASCE American Society of Civil Engineers
ASHRAE American Society of Heating, Refrigerating, and Air Conditioning
Engineers
ASLE American Society of Lubricating Engineers
ASME American Society of Mechanical Engineers
ASPA American Sod Producers Association
ASQC American Society of Quality Control
ASSE American Society of Sanitary Engineers
ASTM American Society for Testing and Materials
AWPA American Wood Preservers Association
AWPI American Wood Preservers Institute
AWS American Welding Society
AWWA American Water Works Association
BBC Basic Building Code, Building Officials and Code Administrators
International
BHMA Builders Hardware Manufacturer’s Association
CBM Certified Ballast Manufacturers
CDA Copper Development Association
CEMA Conveyors Equipment Manufacturers Association
CGA Compressed Gas Association
CLPCA California Lathing and Plastering Contractors Association
CLFMI Chain Link Fence Manufacturers Institute
CMA Concrete Masonry Association
COE Corp of Engineers
CRSI Concrete Reinforcing Steel Institute
CSI Construction Specifications Institute
DCDMA Diamond Core Drill Manufacturers Association
DOE Department of Ecology
TS-4
Rearing Ponds Bird Predation Structure
Engineering Project # 24-015
DOT Department of Transportation
EEI Edison Electric Institute
EIA Electronic Industries Association
EJCDC Engineer’s Joint Contract Documents Committee
EJMA Expansion Joint Manufacturer’s Association
EPA Environmental Protection Agency
ETL Electrical Test Laboratories
FGMA Flat Glass Marketing Association
FM Factory Mutual
FS Federal Specification
GA Gypsum Association
IBC International Building Code
ICBO International Conference of Building Officials
ICC Interstate Commerce Commission
IEEE Institute of Electrical and Electronics Engineers
IES Illuminating Engineering Society
IME Institute of Makers of Explosives
IMIA International Masonry Industry All-Weather Council
IP Institute of Petroleum (London)
IPC Institute of Printed Circuits
IPCEA Insulated Power Cable Engineers Association
ISA Instrument Society of America
ISO International Organization for Standardization
ITE Institute of Traffic Engineers
MBMA Metal Building Manufacturer’s Association
MFMA Maple Flooring Manufacturer’s Association
MIL Military Specification
ML/SFA Metal Lath/Steel Framing Association
MPTA Mechanical Power Transmission Association
MTI Marine Testing Institute
NAAMM National Association of Architectural Metal Manufacturers
NACE National Association of Corrosion Engineers
NBS National Bureau of Standards
NCCLS National Committee for Clinical Laboratory Standards
NEBB National Environmental Balancing Bureau
NEC National Electrical Code
NEMA National Electrical Manufacturer’s Association
NESC National Electric Safety Code
NFPA National Fire Protection Association
NLGI National Lubricating Grease Institute
NMA National Microfilm Association
NWMA National Woodwork Manufacturers Association
OAC Oregon Administrative Code
ODOT Oregon Department of Transportation
OSSC Oregon Structural Specialty Code
OSEPA Oregon State Environmental Protection Agency
OSHA Occupational Safety and Health Administration
PCA Portland Cement Association
PCI Prestressed Concrete Institute
TS-5
Rearing Ponds Bird Predation Structure
Engineering Project # 24-015
PS Product Standard
RCO Revised Code of Oregon
RIS Redwood Inspection Service
RVIA Recreational Vehicle Industry Association
RWMA Resistance Welder Manufacturers Association
SAE Society of Automotive Engineers
SAMA Scientific Apparatus Makers Association
SDI Steel Deck Institute
SDI Steel Door Institute
SIS Swedish Standards Association
SJI Steel Joist Institute
SMA Screen Manufacturers Association
SMACCNA Sheet Metal and Air Conditioning Contractors National Association
SPR Simplified Practice Recommendation
SSBC Southern Standard Building Code, Southern Building Code Congress
SSPC Steel Structures Painting Council
SSPWC Standard Specifications for Public Works Construction
TAPPI Technical Association of the Pulp and Paper Industry
TFI The Fertilizer Institute
UL Underwriters Laboratories, Inc.
WCLIB West Coast Lumber Inspection Bureau
WCRSI Western Concrete Reinforcing Steel Institute
WIC Woodwork Institute of California
WRI Wire Reinforcement Institute, Inc.
WSDOT Washington State Department of Transportation
WWPA Western Wood Products Association
1.3 STANDARD SPECIFICATIONS
A. Where indicated in these Contract Documents, Work shall be in accordance with the refer-enced sections of the most current edition of the Oregon Standard Specifications for Con-struction, hereinafter referred to as “Standard Specifications.”
B. The Technical Specifications of these Contract Documents shall supersede any provisions of the Standard Specifications in conflict herewith.
C. Reference to measurements and payment in the Standard Specifications do not apply to this
Contract.
D. References to department, secretary, state, or other similar terms in the Standard Specifica-tions shall mean Owner’s Authorized Representative.
PART 2 – PRODUCTS (NOT USED)
PART 3 – EXECUTION (NOT USED)
END OF SECTION 01 09 10
TS-6
SUMMARY OF WORK 01 10 00
Rearing Ponds Bird Predation Structure
SECTION 01 10 00 – SUMMARY OF WORK
PART 1 – GENERAL
1.1 SECTION INCLUDES
A. This Section includes a general description of the Work required for this Contract.
1.2 CONTRACT DOCUMENTS
A. This Project shall be constructed in accordance with:
1. Cascade Hatchery: Rearing Ponds Bird Predation Structure – Project Manual.
2. Cascade Hatchery: Rearing Ponds Bird Predation Structure – Construction Drawings.
3. Oregon Standard Specifications for Construction, Current Edition.
B. Standard Plans or Specifications, when referenced in this Project Manual, shall mean Oregon
Standard Specifications for Construction, most current edition; Volume 2; Technical
Specifications. A copy of this document shall be onsite during construction.
1.3 PROJECT DESCRIPTION
A. Contractor shall provide all necessary expertise, labor, equipment, materials, incidentals, and permits required to procure and install structural steel as detailed on the plans, including but not limited to:
1. Reuse or replacement of existing members as noted, specifically vertical braces and connecting elements such as bolts, welds, and plates.
2. Procuring and installing all new structural steel members for the East ponds, including fasteners, connecting elements, paint, and finishes.
3. Procuring and installing new predator wire for new structure installed over the East ponds.
B. The Work to be performed under this Contract shall consist of furnishing tools, equipment, materials, supplies, manufactured articles, and for furnishing transportation and services, including fuel, power, water, and essential communications, and for the performance of all labor, work, or other operations required for the fulfillment of the Contract in strict accordance with the Contract Documents. Refer to Work by Owner in paragraph 1.4 below.
1.4 WORK BY OWNER
A. The Owner will furnish the following items as noted on the Drawings:
1. None.
1.5 LABOR AND SAFETY STANDARDS
A. All Work shall be done in accordance with these Technical Specifications and requirements of the State of Oregon and OSHA standards.
1.6 TEMPORARY FACILITIES
A. The Contractor shall furnish all temporary facilities such as portable toilets, job office, security fencing, and temporary power as needed to perform the Work. Refer to Technical Specification
01 50 00 “Temporary Facilities and Controls.”
1.7 PROJECT CONDITIONS
A. The Contractor shall coordinate the Work with the Owner’s Authorized Representative to minimize disturbance of ongoing hatchery operations.
TS-7
B. It is expected that fish production will continue requiring use of most or all of the ponds during construction. Water flow in the headbox will need remain on, with the hatchery only able to shutdown flow for 1-2 hours with sufficient pre-planning and coordination.
C. The Contractor shall follow the requirements as listed in the attached Archaelogical and Human
Remains Inadvertent Discovery Plan (IDP) for Cultural Resources as shown in the appropriate
Exhibit. Full adherence to all Federal, State, and local laws shall apply to any ground disturbance.
1.8 WORK AND STORAGE AREA
A. The primary Work, storage, and staging areas are designated on the Drawings and shall be available to the Contractor for Work including all functions incidental to the Work and storage areas during the construction period. All operations and storage of materials by the Contractor shall be confined to the immediate Work area and other approved areas as directed by the
Hatchery Manager.
1.9 ACCESS TO THE WORK AREA
A. The Contractor shall repair any damage to access facilities and roadways for which the
Contractor is responsible and shall restore them to conditions at least equaling preconstruction conditions.
B. The Contractor shall take reasonable measures to limit entry of unauthorized persons and vehicles to the Work areas and to allow for access for employees, agents, etc., required for the performance of this Contract, and to authorized personnel of Federal, State, and local agencies, and to others having a right thereto.
1.10 RESTORATION OF EXISTING FACILITIES
A. The Contractor shall perform all Work to lines, grades, and cross sections shown on the
Drawings. Final grades shall match existing grades unless otherwise noted on the Drawings.
Where final grades are indicated on the Drawings, grades shall slope uniformly between elevations shown. All final grades shall be free of hollows which would pond water and sloped to allow for surface drainage. All earthwork shall have finish surfaces which have neat, reasonably uniform appearance.
1.11 EASEMENTS AND RIGHTS-OF-WAYS
A. Confine construction operations to the immediate vicinity of the locations indicated on
Drawings and use due care in placing construction tools, equipment, excavated materials, and pipeline materials and supplies so as to cause the least possible damage to property and interference with traffic.
1.12 PERMITS
A. The Contractor shall be responsible for obtaining and paying for all permits necessary to complete the Work.
1.13 SUBSTANTIAL COMPLETION
A. Substantial Completion dates are listed in the ITB.
PART 2 – PRODUCTS (NOT USED)
PART 3 – EXECUTION (NOT USED)
TS-8
END OF SECTION 01 10 00
TS-9
TS-10
MEASUREMENT AND PAYMENT 01 22 00
Rearing Ponds Bird Predation Structure
Engineering Project # 24-015
SECTION 01 22 00 – MEASUREMENT AND PAYMENT
PART 1 – GENERAL
1.1 MEASUREMENT AND PAYMENT AND DESCRIPTION OF BID ITEMS
A. Partial payment of bid items shall be in conformance with the General Conditions. Partial payment for Work completed, and materials installed which will become an integral part of the finished Work, shall be determined by the Owner’s Authorized Representative, and shall be made on the basis of duly certified and approved estimates of the Work, which, in the opinion of the Owner’s Authorized Representative, has been satisfactorily completed. It is understood that the determination by the Owner’s Authorized Representative as to whether or not a certificate or estimate for payment should be issued, or the amount of said payment, shall be based entirely upon the opinion of the Owner’s Authorized Representative. Said determination shall include without limitation the following factors:
1. All phases of the Work being accomplished in a proper manner and being pursued in a proper sequence of operation, particularly with regard to testing, cleanup, and surface restoration.
2. The observance by the Contractor of the requirement that all Work and operations be preceded by necessary submittals and approvals.
3. On the monthly estimates, partial payments for Work performed but not completed, may be made in accordance State of Oregon General Conditions for Public Improvement
Contracts (General Conditions).
4. Retainage may be deducted from the above amounts as specified in the Contract.
a. The Contract price shall constitute full compensation for furnishing all plant, labor, equipment and materials, mobilization, demobilization, travel, and performing all operations required to complete the Work, as specified or incidental to, and as shown on the Drawings and Technical Specifications.
1.2 BASE BID
A. GENERAL
1. Bid Item – Mobilization, Demobilization, and Bonding – Lump Sum
The lump sum bid price for mobilization and demobilization includes preparatory work and operations necessary for the movement of personnel, equipment, supplies, and incidentals to and from the Project Site; for the establishment of offices, buildings, and other facilities necessary for the Work; costs for permit fees, bonds, and insurance for the
Work; site cleanup during the Project and at the completion of the Project; and for other operations performed or costs incurred before the beginning of the Work.
B. METALS
2. Bid Item – Pond Predation Structure – Lump Sum
The lump sum bid price shall include all labor, materials, and equipment necessary for procurement and installation of all new steel structure, as well as revisions to the existing structure as detailed in the Contract Documents. Item includes, but is not limited to, all structural steel members, connecting plates, fasteners, anchor bolts, welding materials, protective coatings, touch up paint, predator wire, and grout required to implement the
Scope of Work. This includes entirely new sections of structure, revisions to existing connections, and removing & reusing existing elements.
TS-11
MEASUREMENT AND PAYMENT 01 22 00
Rearing Ponds Bird Predation Structure
Engineering Project # 24-015
PART 2 – PRODUCTS (NOT USED)
PART 3 – EXECUTION (NOT USED)
END OF SECTION 01 22 00
TS-12
PROJECT MANAGEMENT AND COORDINATION 01 31 00
Rearing Ponds Bird Predation Structure
Engineering Project # 24-015
SECTION 01 31 00 – PROJECT MANAGEMENT AND COORDINATION
PART 1 – GENERAL
1.1 SECTION INCLUDES
A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. Project Coordination.
2. Preconstruction meeting.
3. Progress meetings.
4. Preinstallation conferences.
5. Requests for Information (RFI).
6. Coordination drawings.
1.2 RELATED TECHNICAL SPECIFICATION SECTIONS
A. Section 01 40 00 – Quality Control.
B. Section 01 70 00 – Project Closeout.
1.3 DEFINITIONS
A. RFI: Request from Contractor seeking information required by or clarifications of the
Contract Documents.
1.4 PROJECT COORDINATION
A. Coordinate scheduling, submittals, and the Work of the various Sections of the Technical
Specifications to assure efficient and orderly sequence of installation of interdependent construction elements, with provisions for accommodating items installed later.
B. Verify that utility requirement characteristics of operating equipment are compatible with building utilities. Coordinate Work of various Sections having interdependent responsibilities for installing, connecting to, and placing in service, all such equipment.
C. Coordinate space requirements and installation of mechanical and electrical Work, which are indicated diagrammatically on Drawings. Follow routing shown for piping, ductwork, and conduit as closely as practicable; place runs parallel with lines of building. Utilize spaces efficiently to maximize accessibility for other installations, for maintenance, and for repairs.
1. Provide coordination drawings showing space requirements of various trades in accordance with coordination drawing Article below.
D. In finished areas, except as otherwise indicated, conceal pipes, ducts, and wiring within the construction. Coordinate locations of fixtures and outlets with finish construction and components.
E. Coordinate completion and cleanup of Work of separate Sections in preparation for
Substantial Completion and for portions of Work designated for Owner occupancy.
F. After Owner occupancy of premises, coordinate access to site for correction of defective
Work and Work not in accordance with Contract Documents, to minimize disruption of
Owner activities.
G. Conservation: Coordinate construction activities to ensure that operations are carried out with consideration given to conservation of energy, water, and materials. Coordinate use of temporary utilities to minimize waste.
1. Salvage materials and equipment involved in performance of, but not actually incorporated into, the Work. See other Sections for disposition of salvaged materials that are designated as Owner’s property.
TS-13
Rearing Ponds Bird Predation Structure
Engineering Project # 24-015
PART 2 – PRODUCTS (NOT USED)
PART 3 – EXECUTION
3.1 PRECONSTRUCTION MEETING
A. Owner’s Authorized Representative will schedule a meeting after Notice to Proceed.
B. Attendance Required:
1. Owner’s Authorized Representative.
2. Contractor.
3. Contractor’s Superintendent.
4. Major Subcontractors.
5. Major Suppliers when requested; others as appropriate.
C. Agenda:
1. Introductions.
2. Distribution of Contract Documents.
3. Submission of list of subcontractors, list of Products, schedule of values, and progress schedule.
4. Designation of personnel representing the parties to Contract and Owner.
5. Procedures and processing of field decisions, submittals, substitutions, applications for payments, BOLI requirements, proposal request, Change Orders, and Contract Closeout procedures.
6. Project overview.
7. Schedule review.
8. Critical work sequencing.
9. Related work by Owner and coordination with Contractor.
10. Owner’s requirements.
11. Construction facilities and controls.
12. Security and housekeeping procedures.
13. Procedures for testing.
14. Procedures for maintaining record documents.
15. Requirements for start-up of equipment.
16. Inspection and acceptance of equipment put into service during the construction period.
17. Status of permits.
18. Waste management plan.
19. Temporary utilities.
20. Use of premises and ongoing facility operations.
D. Owner’s Authorized Representative will prepare a memorandum and distribute copies within two (2) days after meeting to participants, with copies to participants, and those affected by decisions made.
E. Persons designated by the Contractor to attend and participate shall have all required authority to commit the Contractor to solutions as agreed upon in the meeting.
3.2 PROGRESS MEETINGS
A. Owner’s Authorized Representative will schedule and administer meetings throughout progress of the Work at maximum weekly intervals.
B. Owner’s Authorized Representative will make arrangements for meetings, prepare agenda with copies for participants, and preside at meetings.
C. Attendance Required: Job superintendent, Owner’s Authorized Representative, and major subcontractors and suppliers, as appropriate to agenda topics for each meeting.
TS-14
Rearing Ponds Bird Predation Structure
Engineering Project # 24-015
D. Agenda:
1. Corrections to previous minutes.
2. Outstanding old business items.
3. New business items.
a. Civil.
b. Architectural.
c. Structural.
d. Plumbing.
e. Mechanical.
f. Electrical.
4. Submittals.
5. Requests for Information.
6. Change Order Proposals.
7. Schedule review.
8. Record Document review.
E. Record minutes and distribute copies within two (2) days after meeting to participants, with one copy to Contractor, participants, and those affected by decisions made.
1. Minutes shall number topics in a manner that reflects when each topic was first raised.
2. Each topic shall reflect who is responsible for acting on the topic and date by which resolution is required.
3. No topic shall be dropped from the minutes until the method of resolution is recorded.
F. Persons designated by the Contractor to attend and participate shall have all required authority to commit the Contractor to solutions as agreed upon in the meeting.
3.3 PREINSTALLATION CONFERENCES
A. When required in individual Technical Specification Sections, Contractor shall convene a preinstallation conference at Work site prior to commencing Work of the Section.
B. Attendance Required: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting.
C. Notify Owner’s Authorized Representative minimum four (4) days in advance of meeting date.
D. Review Contract Documents and submittals relating to the affected Work.
E. Review conditions of installation, preparation and installation procedures, and coordination with related Work.
F. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.
G. Reporting: Distribute minutes of the meeting to each party present and to other parties requiring information.
H. Do not proceed with installation if the conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.
3.4 PROJECT CLOSEOUT CONFERENCE
A. Owner’s Authorized Representative will schedule and conduct a Project closeout conference, at a time convenient to Owner, but no later than sixty (60) days prior to the scheduled date of
Substantial Completion.
1. Conduct the conference to review requirements and responsibilities related to Project closeout.
TS-15
Rearing Ponds Bird Predation Structure
Engineering Project # 24-015
2. Attendees: Owner’s Authorized Representative, and Contractor and its superintendent;
major subcontractors; suppliers; and other concerned parties shall attend the meeting.
Participants at the meeting shall be familiar with the Project and authorized to conclude matters relating to the Work.
3. Agenda: Discuss items of significance that could affect or delay Project closeout, including the following:
a. Preparation of record documents.
b. Procedures required prior to inspection for Substantial Completion and for final inspection for acceptance.
c. Submittal of written warranties.
d. Requirements for preparing operations and maintenance data.
e. Requirements for delivery of material samples, attic stock, and spare parts.
f. Requirements for demonstration and training.
g. Preparation of Contractor’s punch list.
h. Procedures for processing Applications for Payment at Substantial Completion and for final payment.
i. Submittal procedures.
j. Owner’s partial occupancy requirements.
k. Installation of Owner’s furniture, fixtures, and equipment.
l. Responsibility for removing temporary facilities and controls.
4. Minutes: Entity conducting meeting will record and distribute meeting minutes.
3.5 REQUESTS FOR INFORMATION (RFIs)
A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, prepare and submit an RFI in the form specified.
1. RFIs shall originate with Contractor. Owner’s Authorized Representative will return RFIs submitted to Owner’s Authorized Representative by other entities controlled by
Contractor with no response.
2. Limit topics on each RFI to a single topic to expedite response. If more than a single topic is covered in an RFI, the Contractor accepts full responsibility for any and all cost or schedule delays if RFI is not answered in a timely manner.
3. Coordinate and submit RFIs in a prompt manner so as to avoid delays in Contractor’s work or work of subcontractors.
4. Coordinate Work in field and ensure Work involving RFIs being reviewed by the
Owner’s Authorized Representative does not proceed without direction from the Owner’s
Authorized Representative. Costs for corrective Work shall be the responsibility of the
Contractor.
5. If Contractor disagrees with Owner’s Authorized Representative response to Contractor’s
RFI, Contractor shall notify Owner’s Authorized Representative within seven (7) days of receipt of response. Lack of such notification shall be understood to mean that Contractor agrees with response.
B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:
1. Date.
2. RFI number, numbered sequentially.
3. RFI subject.
4. Technical Specification Section number and title and related paragraphs, as appropriate.
5. Drawing number and detail references, as appropriate.
6. Field dimensions and conditions, as appropriate.
TS-16
Rearing Ponds Bird Predation Structure
Engineering Project # 24-015
7. Contractor’s suggested resolution. If proposed solution impacts the Contract Time or the
Contract Sum, state impact in the RFI.
8. The following statement:
a. “This reply is not an authorization to proceed with work involving additional cost, time, or both. If any reply requires a change to the Contract Documents, a Change
Order must be executed in accordance with the Contract Documents prior to implementation of the reply. Proceeding with the Work in accordance with this RFI response indicates Contractor’s acknowledgement that there will be no change in the
Contract Sum or Contract Time.”
9. Contractor’s signature.
10. Attachments: Include sketches, descriptions, measurements, photos, product data, shop drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
C. Contractor shall utilize the Owner’s Authorized Representative email to submit and receive
RFIs and their responses.
D. Owner’s Authorized Representative will review each RFI, determine action required, and respond. Allow seven (7) working days for Owner’s Authorized Representative response for each RFI. RFIs received by Owner’s Authorized Representative after 1:00 p.m. will be considered as received the following working day.
1. The following RFIs will be returned without action:
a. Requests for approval of substitutions.
b. Requests for adjustments in the Contract Time or the Contract Sum.
c. Requests for interpretation of Owner’s Authorized Representative actions on submittals.
d. Incomplete RFIs or inaccurately prepared RFIs.
2. Owner’s Authorized Representative action may include a request for additional information, in which case Owner’s Authorized Representative time for response will date from time of receipt of additional information.
3. Owner’s Authorized Representative action on RFIs that may result in a change to the
Contract Time or the Contract Sum may be eligible for Contractor to submit a Change
Order Request according to the General Conditions.
a. If Contractor believes the RFI response warrants change in the Contract Time or the
Contract Sum, notify Owner’s Authorized Representative in writing within ten (10) days of receipt of the RFI response.
b. A response to an RFI is not direction or approval of a change to either Contract Time or Contract Sum.
c. Proceeding with the Work in accordance with an RFI response, without such written notification and an approved Change Order, indicates Contractor’s acknowledgement that there is no change to the Contract Time or the Contract Sum.
E. On receipt of Owner’s Authorized Representative action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify Owner’s
Authorized Representative within three (3) days if Contractor disagrees with response.
3.6 COORDINATION DRAWINGS
A. General: Prepare coordination drawings in accordance with requirements in individual
Sections, where installation is not completely shown on shop drawings, where limited space availability necessitates coordination, or if coordination is required to facilitate integration of products and materials fabricated or installed by more than one entity.
1. Content: Project specific information, drawn accurately to a scale large enough to
TS-17
Rearing Ponds Bird Predation Structure
Engineering Project # 24-015 indicate and resolve conflicts. Do not base coordination drawings on standard printed data. Include the following information, as applicable:
a. Prepare sections, elevations, and details as needed to describe relationship of various systems and components.
b. Coordinate the addition of trade specific information to the coordination drawings by multiple contractors in a sequence that best provides for coordination of the information and resolution of conflicts between installed components before submitting for review.
c. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, plumbing, and electrical systems.
d. Indicate space requirements for routine maintenance and for anticipated replacement of components during the life of the installation.
e. Show location and size of access doors required for access to concealed dampers, valves, and other controls.
f. Indicate required installation sequences.
g. Indicate dimensions shown on the Drawings. Specifically, note dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to Owner’s Authorized Representative indicating proposed resolution of such conflicts. Minor dimension changes and difficult installations will not be considered changes to the Contract.
2. Review: Owner’s Authorized Representative will review coordination drawings to confirm that the Work is being coordinated, but not for the details of the coordination, which are the Contractor’s responsibility. If the Owner’s Authorized Representative determines that the coordination drawings are not being prepared in sufficient scope or detail, or are otherwise deficient, the Owner’s Authorized Representative will so inform the Contractor, who shall make changes as directed and resubmit.
B. Coordination Drawing Organization: Organize coordination drawings as follows:
1. Floor Plans and Reflected Ceiling Plans: Show architectural and structural elements, and mechanical, plumbing, fire protection, fire alarm, and electrical Work. Show locations of visible ceiling mounted devices relative to acoustical ceiling grid. Supplement plan drawings with section drawings where required to adequately represent the Work.
2. Plenum Space: Indicate subframing for support of ceiling and wall systems, mechanical and electrical equipment, and related Work. Locate components within ceiling plenum to accommodate layout of light fixtures indicated on Drawings. Indicate areas of conflict between light fixtures and other components.
3. Mechanical Rooms: Provide coordination drawings for mechanical rooms showing plans and elevations of mechanical, plumbing, fire protection, fire alarm, and electrical equipment.
4. Structural Penetrations: Indicate penetrations and openings required for all disciplines.
5. Slab Edge and Embedded Items: Indicate slab edge locations and sizes and locations of embedded items for metal fabrications, sleeves, anchor bolts, bearing plates, angles, door floor closers, slab depressions for floor finishes, curbs and housekeeping pads, and similar items.
6. Mechanical and Plumbing Work: Show the following:
a. Sizes and bottom elevations of ductwork, piping, and conduit runs, including insulation, bracing, flanges, and support systems.
b. Dimensions of major components, such as dampers, valves, diffusers, access doors, cleanouts, and electrical distribution equipment.
c. Fire rated enclosures around ductwork.
TS-18
Rearing Ponds Bird Predation Structure
Engineering Project # 24-015
7. Electrical Work: Show the following:
a. Runs of vertical and horizontal conduit 1 1/4 inches in diameter and larger.
b. Light fixture, exit light, emergency battery pack, smoke detector, and other fire-alarm locations.
c. Panel board, switch board, switchgear, transformer, busway, generator, and motor control center locations.
d. Location of pull boxes and junction boxes, dimensioned from column center lines.
8. Fire Protection System: Show the following:
a. Locations of standpipes, mains piping, branch lines, pipe drops, and sprinkler heads.
9. Review: Owner’s Authorized Representative will review coordination drawings to confirm that the Work is being coordinated, but not for the details of the coordination, which are Contractor’s responsibility. If Owner’s Authorized Representative determines that coordination drawings are not being prepared in sufficient scope or detail, or are otherwise deficient, Owner’s Authorized Representative will so inform Contractor, who shall make changes as directed and resubmit.
10. Coordination Drawing Prints: Prepare coordination drawing prints according to requirements in Technical Specification Section 01 33 00 “Submittal Procedures.”
END OF SECTION 01 31 00
TS-19
Rearing Ponds Bird Predation Structure
Engineering Project # 24-015
TS-20
SUBMITTAL PROCEDURES 01 33 00
Rearing Ponds Bird Predation Structure
Engineering Project # 24-015
SECTION 01 33 00 – SUBMITTAL PROCEDURES
PART – GENERAL
1.1 RELATED REQUIREMENTS SPECIFIED ELSEWHERE
A. Other provisions pertaining to submittals are included in the General Conditions, the Supple-mentary General Conditions, and in the various Sections of the Technical Specifications.
1.2 SUBMITTAL REQUIREMENTS
A. General:
1. If Build America, Buy America Act (BABAA) requirements are in place for this Project, the Contractor shall submit certification that all materials and manufactured goods pro-vided under this Technical Specification meet the BABAA requirements. Please refer to ITB Attachment E-1 for specific details on the material and manufactured goods requirements.
2. All submittals shall be identified by Project title and number and shall include Contrac-tor’s name, date, and revision date. In addition, shop drawings, product data, and sam-ples shall include names of subcontractor and supplier, applicable Technical Specifica-tion Section number and Contractor’s stamp, initialed or signed, certifying to review of submittal, verification of field measurements, and compliance with Contract Documents.
3. All submittals shall be accompanied by a submittal transmittal form. Equipment numbers shall be listed for items being submitted. A separate form shall be used for each specific item, class of material, equipment, and items specified in separate, discrete sections, for which the submittal is required. Submittals for various items shall be made with a single form when the items taken together constitute a manufacturer’s package or are so func-tionally related that expediency indicates checking or review of the group or package as a whole.
4. A unique number, sequentially assigned, shall be noted on the transmittal form accompa-nying each item submitted. Original submittal numbers shall have the following format:
“XXX”; where “XXX” is the sequential number assigned by the Contractor. Resubmittal shall have the following format: “XXX-Y”; where “XXX” is the originally assigned submittal number and “Y” is a sequential letter assigned for resubmittals; i.e., A, B, or C being the 1st, 2nd, and 3rd resubmittals, respectively. Submittal 25B, for example, is the second resubmittal of Submittal 25.
5. Submittal Completeness: Submittals which do not have all the information required to be submitted are not acceptable and will be returned without review.
B. Shop Drawings: Submit two (2) copies of each shop drawing required by the Technical Spec-ifications. Show the information, dimensions, connections, and other details necessary to en-sure that the shop drawings accurately interpret the Contract Documents. Show adjoining Work in such detail as required indicating proper connections. Where adjoining connected Work requires shop drawings or product data, submit such information for review at the same time so that connections can be accurately checked.
C. Product Data: Submit two (2) copies of each item of product data required by the Technical Specifications. Modify product data by deleting information which is not applicable to the Project or by marking each copy to identify pertinent products. Supplement standard in-formation, if necessary, to provide additional information applicable to Project. It is recog-nized that in some cases manufacturer’s product data will be adequate and further shop draw-ings as stated in the Technical Specifications may not be required, unless requested by the Owner’s Authorized Representative.
TS-21
Rearing Ponds Bird Predation Structure
Engineering Project # 24-015
D. Samples:
1. Submit two (2) of each sample required by the Technical Specifications (unless specific number is specified). Samples shall show the quality, type, range of color, finish, and texture of the material intended to be furnished for the Work.
2. Samples shall become the property of the Owner unless specifically stated otherwise and will not be incorporated in the Work.
E. Review Procedure: Unless otherwise specified, within ten (10) to fourteen (14) days after re-ceipt of the submittal, the Owner’s Authorized Representative will review the submittal. The returned submittal will indicate one of the following actions:
1. If the review indicates that the material, equipment, or work method is in general con-formance with the design concept and complies with the Drawings and Technical Speci-fications, submittal copies will be marked “NO EXCEPTION TAKEN” and given review action 1. In this event, the Contractor may begin to implement the work method or in-corporate the material or equipment covered by the submittal.
2. If the review indicates that limited corrections are required, copies will be marked
“NOTE MARKINGS” and given review action 2. The Contractor may begin implement-ing the work method or incorporating the material and equipment covered by the submit-tal in accordance with the noted corrections. Where submittal information will be incor-porated in O&M data, a corrected copy shall be provided; otherwise, no further action is required.
3. If the review reveals that the submittal is insufficient or contains incorrect data, copies will be marked “COMMENTS ATTACHED.” If the comments are of a nature that can be confirmed without a resubmittal, copies will be further marked “CONFIRM” and giv-en review action 3. If the comments require a revision and resubmittal, copies will be further marked “RESUBMIT” and given review action 4. Except at their own risk, the
Contractor shall not undertake Work covered by this submittal until the attached com-ments have been either confirmed by a separate written communication or the submittal has been revised, resubmitted, and returned marked with “NO EXCEPTIONS TAKEN” or “NOTE MARKINGS.”
4. If the review indicates that the material, equipment, or work method is not in general con-formance with the design concept or in compliance with the Drawings and Technical
Specifications, copies of the submittal will be marked “REJECTED” and given review action 5. Except at their own risk, the Contractor shall not undertake Work covered by such submittals until a new submittal is made and returned marked either “NO
EXCEPTIONS TAKEN” or “NOTE MARKINGS.”
F. Effects of Review of Contractor’s Submittals: Review of Drawings, method of work, or in-formation regarding materials or equipment the Contractor proposes to provide, shall not re-lieve the Contractor of its responsibility for errors therein and shall not be regarded as an as-sumption of risks or liability by the Owner, and the Contractor shall have no claim under the
Contract on account of the failure, or partial failure, of the method of work, material, or equipment so reviewed. A mark of “NO EXCEPTIONS TAKEN” or “NOTE MARKINGS” shall mean that the Owner’s Authorized Representative has no objection to the Contractor, upon the Contractor’s own responsibility, using the plan or method of work proposed, or providing the materials or equipment proposed.
1.3 SCHEDULE
A. The Contractor shall provide the following schedules and submit them not later than seven
(7) days after notice to proceed.
1. Contractor’s construction schedule:
TS-22
Rearing Ponds Bird Predation Structure
Engineering Project # 24-015
a. The Contractor shall prepare and submit to the Owner’s Authorized Representative for review an overall construction schedule covering all Work to be performed.
b. The schedule shall indicate the sequence of the Work, the time of starting and com-pletion of each part, and the installation dates for major items.
c. The schedule shall be submitted to the Owner’s Authorized Representative for re-view. This schedule shall be revised and resubmitted as necessary until it is accepta-ble to the Owner’s Authorized Representative. Action on payment requests will be contingent upon receipt of an acceptable construction schedule.
2. The construction schedule shall include, but not be limited to the following items:
a. Shop drawing receipt from Contractor, submitted to Owner’s Authorized Representa-tive, review, and return to Contractor.
b. Material and equipment order, delivery, installation, and check out.
c. Demolition.
d. Excavation and foundation preparation.
e. Constructing concrete structures.
f. Piping installation.
g. Backfilling, grading, seeding, and paving.
h. Installation of gates, miscellaneous metals, and equipment.
i. Substantial Completion of improvements.
j. Subcontractor work.
k. Final cleanup.
l. Testing activities.
m. Allowance for inclement weather.
3. The construction schedule shall be a series of line diagrams showing a step by step se-quence of each construction activity. Construction activities proceeding simultaneously should be shown as parallel lines. Each activity shall be labeled and the estimated num-ber of days to complete the activity shall be shown on the schedule.
4. Should the Contractor fail to meet any critical dates within the schedule, the Contractor shall immediately undertake appropriate action which shall assure an acceptable return to the approved construction schedule.
5. The Contractor accepts the risk of any delays caused by the rate of progress of the Work to be performed under the Contract, and that in the event the Contractor is delayed in the prosecution and completion of its Work because of such conditions; Contractor shall have no claim for damages or Contract adjustment.
B. Contractor’s List of Subcontractors: Establish the items of Work proposed to be accom-plished by subcontractors, the name and address of each proposed subcontractor, and the date proposed to award each subcontract.
C. Schedule of Submittals: Establish for each item for which shop drawings, product data, or samples are required, the date of submission will be made, and the date approval is required for the installation to be completed in accordance with the Construction Schedule.
D. The Contractor’s list of subcontractors and schedule of submittals shall be based upon the
Contractor’s progress schedule so that the Work can progress in accordance with the ap-proved progress schedule.
E. The Contractor shall immediately advise the Owner’s Authorized Representative of any pro-posed changes in his submitted schedules. If, in the opinion of the Owner’s Authorized Rep-resentative, any submitted schedule is inadequate to ensure completion of Work within the time limit or is otherwise not in accordance with the Technical Specification, or if the Work is not being adequately or…