Attachment B (Special Provisions and Specifications).docx

DOCX document 63 KB Posted

Attached to
US 395 Culvert Repair Valley Falls - Lakeview Project
Solicitation number
S-73000-00010366
Issued by
Lake County, Oregon

About this file

This document is an Attachment B (Special Provisions and Specifications) for a state and local contract opportunity in Oregon. The project consists of providing work zone traffic control, CCTV inspection, and installation of CIPP liners at 8 culvert locations along US 395 (Freemont Highway) in the Valley Falls to Lakeview area, Phase 2. The work is to be completed in accordance with the 2024 Oregon Standard Specifications for Construction and the State of Oregon General Conditions for Public Improvement Contracts. The project manager is Scotty Freitas with the Oregon Department of Transportation. The project is located in Lake County, Oregon, and the allowed periods for lane closures are specified.

The pricing and payment terms are detailed, including measurement and payment for the CIPP liner installation and video pipe inspection work. No utility conflicts are anticipated, and the contractor will be responsible for notifying utilities prior to performing work. The project completion date must be within the specified contract time, and the contractor will be required to submit a project schedule at the preconstruction conference.

View the file

Other files

File Type Posted
00010366 Intent To Award.xlsx XLSX spreadsheet
Attachment A (Plans)~10.pdf PDF
ITB_PW_Final~7.docx DOCX document
00010366 Preliminary Results.xlsx XLSX spreadsheet
Attachment C (Bid Pricing Form)~7.xlsx XLSX spreadsheet
Sample Services Agreement~8.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US 395: Culvert Project, Valley Falls to Lakeview, Phase 2

Attachment B

SPECIAL PROVISIONS AND SPECIFICATIONS FOR

US 395: CULVERT PROJECT

VALLEY FALLS TO LAKEVIEW, PHASE 2

SCOPE

The work to be done under this Contract, on US 395 (Freemont Highway) consists of supplying the materials, equipment, labor and incidentals required to perform the following tasks as described in the Contract Plans and these Special Provisions and Specifications:

· Provide Work Zone Traffic Control at each culvert location (8)

· CCTV all culverts prior to and after liner installation

· Install CIPP Liner as per the plans (8 locations)

· Perform additional and incidental work as called for by the Contract plans and specifications and as directed.

The locations are as follows:

· Location # 1US 395Mile-Post 126.28
· Location # 2US 395Mile-Post 128.40
· Location # 3US 395Mile-Post 134.48
· Location # 4US 395Mile-Post 134.76
· Location # 5US 395Mile-Post 136.84
· Location # 6US 395Mile-Post 136.99
· Location # 7US 395Mile-Post 138.39
· Location # 8US 395Mile-Post 141.97

PROJECT INFORMATION

PROJECT MANAGER:

Scotty Freitas MBM/MCM Project Manager – Klamath Falls 2557 Altamont Drive Klamath Falls, OR. 97603 Phone: (541) 883-5538 Email: Douglas.S.FREITAS@odot.oregon.gov

APPLICABLE STANDARD SPECIFICATIONS AND SPECIAL PROVISIONS

STATE OF OREGON GENERAL CONDITIONS FOR PUBLIC IMPROVEMENT CONTRACTS: In addition to the solicitation laws and rules, this ITB and the resulting Contract are governed by the STATE OF OREGON GENERAL CONDITIONS FOR PUBLIC IMPROVEMENT CONTRACTS, January 1, 2012, Edition (“General Conditions”) which, although not physically attached, are incorporated herein by reference as an Attachment with the same force and effect as though fully set forth herein. The General Conditions can be obtained from the Department of Administrative Services, 1225 Ferry Street SE U140, Salem, OR 97301-4285, by telephone (503) 378-4642 or online at:

https://www.oregon.gov/das/Procurement/Guiddoc/GenCon4PI.pdf

2024 OREGON STANDARD SPECIFICATIONS FOR CONSTRUCTION: The 2024 Oregon Standard Specifications for Construction (Standard Specifications) include detailed technical specifications in Parts 00200 through 03000 inclusive (Technical Specifications) that apply to this ITB and the resulting Contract. Some sections of the Technical Specifications are identified and modified herein, Special Provisions and Specifications. Sections of the Technical Specifications not modified remain applicable to the Contract according to their original terms. Unless they are identified herein, Special Provisions and Specifications, sections of the Standard Specifications in Part 00100 (General Conditions) are not applicable to this Contract. Bidders can also access this information at the following Internet address:

https://www.oregon.gov/odot/Business/Specs/2024_STANDARD_SPECIFICATIONS.pdf

Silence of Specifications: The apparent silence of the specifications as to any detail, or the apparent omission of a detailed description concerning any point, shall be regarded as meaning that the highest value commercial practices are to prevail and that only materials and workmanship of first quality are to be used.

COOPERATION WITH UTILITIES: There are no anticipated conflicts with utilities associated with the Work. This project is located within the Oregon Utility Notification Center area, which is a utilities notification system for notifying owners of utilities about work being performed in the vicinity of their facilities. Contractor shall notify owners of Utilities prior to the performance of work in the vicinity of their Utilities. The utilities notification system telephone number is 811 (or use the old number which is 1-800-332-2344).

PAYMENT TO CONTRACTOR: The Contractor shall be paid upon completion of contract work. A bill must be submitted to the Project Manager for payment processing.

COMPLETION AND BILLING: All billing invoices shall include the Standard Certification:

“I, the undersigned, hereby certify that the above charge on Agreement No._____________________ is true and correct, and payment therefore has not been received.”

Signed ___________________________________

PRECONSTRUCTION CONFERENCE, SCHEDULE AND LIMITATIONS OF OPERATIONS: The Contractor shall meet with the Project Manager for a preconstruction conference at a mutually agreed upon time. Work shall commence within 10 working days of this meeting providing the Notice to Proceed has been received. At the preconstruction conference, Contractor shall submit a project schedule to plan, coordinate and control the progress of construction and traffic control installations. The project schedule must take into account the orderly, timely, and efficient prosecution of the work in sufficient detail to enable both the Contractor and the Project Manager to plan, coordinate, appraise, document, and control their respective contract responsibilities. The predicted Completion date(s) for the project schedule shall be within the specified contract time.

PROFESSIONAL OF RECORD CERTIFICATION

The following Special Provisions were prepared and/or reviewed by the Engineer whose professional seal appears below. These Specifications are not valid unless the appropriate signed seal appears below and shall not be modified without the approval of the Engineer.

OREGON DEPARTMENT OF TRANSPORTATION

SPECIAL PROVISIONS

FOR

US 395: CULVERT PROJECT

VALLEY FALLS TO LAKEVIEW, PHASE 2

PROFESSIONAL OF RECORD CERTIFICATION(s):

Seal w/signature.

I certify the Special Provision Section(s) listed below are applicable to the design for the subject project. Modified Special Provisions were prepared by me or under my supervision.

SECTIONS: 00220, 00410, 00412, 00413, 00415

Date Signed: 6/11/2024

SECTION 00210 - MOBILIZATION

Comply with Section 00210 of the Standard Specifications.

SECTION 00220 - ACCOMMODATIONS OF PUBLIC TRAFFIC

Comply with Section 00220 of the Standard Specifications modified as follows:

Add the following subsection:

00220.40(e)(1) Closed Lanes - Replace this subsection, except for the subsection number and title, with the following:

One Traffic Lane may be closed on the Freemont Highway (US 395) when allowed, shown, or directed during the following periods of time except as indicated in 00220.40(e)(2):

· Lane closures resulting in a single lane of two-way traffic controlled by flaggers are allowed anytime to maximum length of closure to one mile.

SECTION 00221 – COMMON PROVISIONS FOR WORK ZONE TRAFFIC CONTROL

Comply with Section 00221 of the Standard Specifications.

SECTION 00222 – TEMPORARY TRAFFIC CONTROL SIGNS

Comply with Section 00222 of the Standard Specifications.

SECTION 00223 - WORK ZONE TRAFFIC CONTROL LABOR AND VEHICLES

Comply with Section 00223 of the Standard Specifications.

SECTION 00280 – EROSION AND SEDIMENT CONTROL

Comply with Section 00280 of the Standard Specifications.

SECTION 00290 – ENVIRONMENTAL PROTECTION

Comply with Section 00290 of the Standard Specifications.

SECTION 00410 - REHABILITATE EXISTING PIPE

Section 00410, which is not a Standard Specification, is included in this Project by Special Provision.

Description

00410.00 Scope ‑ This Work consists of rehabilitating existing pipes according to Section 00412 or Section 00413 as indicated in Table 00410-1 as shown and selected.

00410.01 Installation Options ‑ Choose one of the approved rehabilitation methods indicated in Table 00410-1.

00410.02 Submittals ‑ Submit a pipe rehabilitation summary indicating which method is selected for each location/station as indicated in Table 00410-1. Submit required documentation according to Section 00412, or Section 00413 for the renewal methods indicated in Table 00410-1.

Materials

00410.10 General ‑ Furnish Materials according to Section 00412 or Section 00413 as indicated in Table 00410-1 and selected.

00410.13 Location ‑ Rehabilitate existing pipe(s) according to Table 00410-1:

Table 00410-1

Location/Station

Pipe Size (Dia.)

(Rise x Span) (Inches) Specification Section(s) Allowed

US 395, MP 126.28
18”
SP00412, SP00413
US 395, MP 128.40
18”
SP00412, SP00413
US 395, MP 134.48
18”
SP00412, SP00413
US 395, MP 134.76
24”
SP00412, SP00413
US 395, MP 136.84
24”
SP00412, SP00413
US 395, MP 136.99
36”
SP00412, SP00413
US 395, MP 138.39
18”
SP00412, SP00413
US 395, MP 141.97
18”
SP00412, SP00413

Construction

00410.40 General ‑ Construct pipe rehabilitation according to Section 00412 or Section 00413 as indicated in Table 00410-1 and selected.

Measurement

00410.80 Measurement ‑ The quantities of Work performed under this Section will be measured according to the following:

(a) Rehabilitate pipe ‑ The quantities of installed cured-in-place pipe (CIPP) liners will be measured on the length basis. The length will be measured, with no deduction for Structures or fittings, along the pipe flow line from center to center of manholes, inlets, Structures, special sections, or the ends of pipe, whichever is applicable.

(b) Service Line Reconnections ‑ The quantities of service line reconnections will be measured on the unit basis, regardless of size.

Payment

00410.90 Payment ‑ The accepted quantities of Work performed under this Section will be paid for at the Contract unit price, per unit of measurement, for the following items:

Pay Item Unit of Measurement

(a)Rehabilitate, ___18__ Inch pipeFoot
(b)Rehabilitate, ___24__ Inch pipeFoot
(c)Rehabilitate, ___36__ Inch pipeFoot

In item (a), the diameter of the host pipe will be inserted in the blanks.

Payment will be payment in full for furnishing and placing all Materials, and for furnishing all Equipment, labor, and Incidentals necessary to complete the Work as specified.

SECTION 00412 - CURED-IN-PLACE PIPE LINING

Comply with Section 00412 of the Standard Specifications modified as follows:

00412.02 Design Parameters - Add the following to the end of this subsection:

Maximum Height of fill from invert
US 395, M.P.126.285 ft.
US 395, M.P.128.404 ft.
US 395, M.P.134.4810 ft.
US 395, M.P.134.764 ft.
US 395, M.P.136.848 ft.
US 395, M.P.136.994 ft.
US 395, M.P.138.3915 ft.
US 395, M.P.141.978 ft.

Groundwater Elevation above invert N/A

00412.71 Post Installation Video Inspection ‑ Replace this subsection, except for the subsection number and title, with the following:

After installation of the CIPP perform a post-installation video inspection of the pipe according to Section 00415.

00412.80 Measurement ‑ Replace this subsection, except for the subsection number and title, with the following:

CIPP Liner and Service Line Reconnections will be measured according to 00410.80.

00412.90 Payment ‑ Replace this subsection, except for the subsection number and title, with the following:

CIPP Liner and Service Line Reconnections will be paid for according to 00410.90.

SECTION 00413 - GRP CURED-IN-PLACE PIPE LINING & UV CURE

Comply with Section 00413 of the Standard Specifications modified as follows:

00413.02 Design Parameters - Add the following to the end of this subsection:

Maximum Height of fill from invert
US 395, M.P.126.285 ft.
US 395, M.P.128.404 ft.
US 395, M.P.134.4810 ft.
US 395, M.P.134.764 ft.
US 395, M.P.136.848 ft.
US 395, M.P.136.994 ft.
US 395, M.P.138.3915 ft.
US 395, M.P.141.978 ft.

Groundwater Elevation above Invert N/A

00413.80 Measurement ‑ Replace this subsection, except for the subsection number and title, with the following:

CIPP Liner will be measured according to 00410.80.

00413.90 Payment ‑ Replace this subsection, except for the subsection number and title, with the following:

CIPP Liner will be paid for according to 00410.90.

SECTION 00415 - VIDEO PIPE INSPECTION

Replace Section 00415 of the Standard Specifications with the following Section 00415:

Description

00415.00 Scope ‑ This Work consists of inspecting pipes by video accompanied by a recorded narrative and written report of the findings.

Equipment

00415.20 Mainline Inspection Equipment ‑ Use the following Equipment unless otherwise approved.

(a) Video Camera ‑ Use a digital color video camera with the ability to rotate 360 degrees, tilt to a 90 degree angle to the axis of the pipe and a zoom ration of at least 40:1. A light source that provides a clear image of the full pipe circumference and all areas of concern. Provide a camera and lighting system capable of operating in 100% humidity conditions.

(b) Transporter ‑ Use an all-wheel drive or track mounted transporter capable of inspecting pipes ranging in size from 12 to 60 inches and does not obstruct the camera view. A vertical and horizontal adjustable camera to maintain the camera along the approximate center of the pipe at all times. The transporter will have an adjustable operating speed while recording not to exceed 30 feet per minute.

(c) Recording Device ‑ Provide a device capable of recording video with the pipe identification, a remote meter counter displaying length along the profile in tenths of feet and indicating the camera’s position from the starting point. Calibrate the meter counter to be accurate within 0.5 percent over the length of pipe being inspected. The device must be capable of recording a digital video with a minimum resolution of 720 x 480.

Construction

00415.40 Video Inspection:

(a) Notice and Access ‑ Notify the Engineer a minimum of 48 hours before beginning cleaning or video inspection. Allow the Engineer access at all times, to observe the video monitor and all other operations.

(b) Cleaning ‑ Clean the pipe by removing all debris, sediment, and other accumulated material that would adversely impact the liner installation and function. Remove and dispose of all debris according to 00290.20.

00415.41 Liner Pre Installation Video Inspection ‑ Perform a pre-installation video inspection 5 Calendar Days before beginning Work. Begin Inspection at one end of the pipe and proceed through the entire pipe length at a speed not greater than 30 feet per minute. Move the camera through the pipe and provide a continuous 360 degree pan of each pipe joint. Stop and record all cracks, deformities, and defects to document the pipe condition, including the location of all lateral connections to the mainline.

Provide a verbal narrative on each video inspection recording. Include the company name, operator’s name, date and time of the inspection, site location, description of the pipe type, size and length, and direction of travel. As part of the recorded audio portion of the video, include a description of all observed defects, deformities, location of lateral connections and locations where digital photographs are taken.

If, during the inspection operation, the camera will not pass through the entire segment, set up Equipment so that the inspection can be performed from the opposite access point back to the obstruction.

(a) Mainline Inspection Use video inspection equipment meeting the requirements of 0415.20. Each video inspection will display and record an on-screen header containing; location, pipe type, size, date and time of inspection, direction of travel, distance and owner.

00415.42 Liner Post Installation Video Inspection ‑ Perform post construction video inspection according to 00415.40 and 00415.41.

Finishing and Cleaning Up

00415.70 Video Inspection Recording and Written Inspection Report ‑ Furnish two copies of all preconstruction and post construction inspection video and reports within three Calendar Days after completing the inspections. If inspection video or audio recording quality is poor, the Engineer has the right to reject the recording and request new video inspection at no additional cost to the Agency.

(a) Inspection Report ‑ Provide an inspection report that includes each defect, deformity, and joint along with the distance from the inspection starting point. Provide still digital images in the report along with a reference and description of each defect, deformity and joint.

00415.71 Corrections to Deficiencies in Work ‑ Submit a repair plan to the Engineer for approval of all detrimental pipe deficiencies that are revealed in the recording and written report. Repair all deficiencies within 48 hours after receiving notification. Re-perform the video inspection, submit the new video, and update the written report at no additional cost to the Agency.

Measurement

00415.80 Measurement ‑ The quantities of Work performed under this Section will be measured according to the following:

(a) Mainline Video Inspection ‑ Mainline video inspection will be measured on the length basis. The length will be measured, with no deduction for Structures or fittings, along the pipe flow line from center to center of manholes, inlets, special sections, or the ends of pipe, whichever is applicable. Pipes with sloped ends will be measured from the top of the sloped end section.

Payment

00415.90 Payment ‑ The accepted quantities of Work performed under this Section will be paid for at the Contract unit price, per unit of measurement, for the following items:

Pay Item Unit of Measurement

· (a) Mainline Video Inspection Foot

Payment will be payment in full for furnishing all Equipment, labor, and Incidentals necessary to complete the Work as specified.

SECTION 00445 – SANITARY, STORM, CULVERT, SIPHON, AND IRRIGATION PIPE

Comply with Section 00445 of the Standard Specifications.

SECTION 00842 ‐ FACILITY IDENTIFICATION MARKERS

Comply with Section 00842 of the Standard Specifications.

ITB-COMM.DOC, REV 6/19998