00010366 Preliminary Results.xlsx
XLSX spreadsheet 23 KB Posted
- Solicitation number
- S-73000-00010366
- Issued by
- Lake County, Oregon
About this file
The document provided is a bid tabulation worksheet for the US 395 Culvert Repair Valley Falls - Lakeview Project, which is a state and local contract opportunity issued by the State of Oregon and Lake County. The project involves supplying the materials, equipment, labor, and incidentals necessary to provide traffic control at 8 culvert locations, install 8 CIPP liners per the plans, and perform any additional or incidental work as directed by the contract. The bid tabulation includes bids from six contractors, with details on bid items such as mobilization, temporary work zone traffic control, portable changeable message signs, pollution control plan, erosion control, culvert rehabilitation, mainline video inspection, and culvert drainage markers. The bid closing date is July 9, 2024, at 10:00 AM.
The bid tabulation provides the unit prices and total prices for each bid item from the six contractors, with the total bid amounts ranging from $267,030 to $370,880. The project appears to be funded by state and local sources, but the specific funding requirements and amounts are not provided in the document. There is no information regarding set-asides, incumbents, or the current contracting environment.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 00010366 Intent To Award.xlsx | XLSX spreadsheet | |
| Attachment A (Plans)~10.pdf | ||
| ITB_PW_Final~7.docx | DOCX document | |
| Attachment C (Bid Pricing Form)~7.xlsx | XLSX spreadsheet | |
| Sample Services Agreement~8.pdf | ||
| Attachment B (Special Provisions and Specifications).docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Date Issued: | 7/9/24 | ||||||
| ITB No. | S-73000-00010366 | BIDDER | |||||
| NAME: | Iron Horse LLC | Timber Mountain Construction LLC | Hayes Construction Services Inc | JR Carlon Corp | Whitaker Construction Company | ||
| Bid Closing: | 07/09/2024 @ 10:00AM | ||||||
| Description: | US 395 Culvert Repair Project | ||||||
| This bid tabulation is not an indicator of award. It is only a tabulation of the bids submitted for consideration. |
| Bid Item # | Description | Est | |
| QTY | UNIT | UNIT | |
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL |
PRICE
| 1 | Mobilization | 1 | LS | $ 20,000.00 | $ 20,000.00 | $ 32,750.00 | $ 32,750.00 | $ 75,000.00 | $ 75,000.00 | $ 40,000.00 | $ 40,000.00 | $ 100,000.00 | $ 100,000.00 | $ - 0 | $ - 0 | $ - 0 | |||
| 2 | Temporary Work Zone Traffic Control, Complete | 1 | LS | $ 25,000.00 | $ 25,000.00 | $ 19,500.00 | $ 19,500.00 | $ 18,400.00 | $ 18,400.00 | $ 16,384.00 | $ 16,384.00 | $ 30,000.00 | $ 30,000.00 | $ - 0 | $ - 0 | $ - 0 | |||
| 3 | Portable Changeable Message Signs | 2 | EACH | $ 4,500.00 | $ 9,000.00 | $ 2,000.00 | $ 4,000.00 | $ 3,500.00 | $ 7,000.00 | $ 1,100.00 | $ 2,200.00 | $ 8,750.00 | $ 17,500.00 | $ - 0 | $ - 0 | $ - 0 | |||
| 4 | Pollution Control Plan | 1 | LS | $ 2,000.00 | $ 2,000.00 | $ 1,450.00 | $ 1,450.00 | $ 1,500.00 | $ 1,500.00 | $ 750.00 | $ 750.00 | $ 2,500.00 | $ 2,500.00 | $ - 0 | $ - 0 | $ - 0 | |||
| 5 | Erosion Control | 1 | LS | $ 5,000.00 | $ 5,000.00 | $ 2,875.00 | $ 2,875.00 | $ 1,500.00 | $ 1,500.00 | $ 750.00 | $ 750.00 | $ 9,000.00 | $ 9,000.00 | $ - 0 | $ - 0 | $ - 0 | |||
| 6 | Rehabilitate 18" culvert | 356 | FOOT | $ 275.00 | $ 97,900.00 | $ 352.00 | $ 125,312.00 | $ 353.35 | $ 125,792.60 | $ 425.00 | $ 151,300.00 | $ 325.00 | $ 115,700.00 | $ - 0 | $ - 0 | $ - 0 | |||
| 7 | Rehabilitate 24" culvert | 126 | FOOT | $ 397.00 | $ 50,022.00 | $ 488.00 | $ 61,488.00 | $ 474.10 | $ 59,736.60 | $ 605.00 | $ 76,230.00 | $ 400.00 | $ 50,400.00 | $ - 0 | $ - 0 | $ - 0 | |||
| 8 | Rehabilitate 36" culvert | 61 | FOOT | $ 590.00 | $ 35,990.00 | $ 1,204.00 | $ 73,444.00 | $ 790.35 | $ 48,211.35 | $ 825.00 | $ 50,325.00 | $ 665.00 | $ 40,565.00 | $ - 0 | $ - 0 | $ - 0 | |||
| 9 | Mainline Video Inspection | 1086 | FOOT | $ 13.00 | $ 14,118.00 | $ 3.00 | $ 3,258.00 | $ 18.00 | $ 19,548.00 | $ 25.00 | $ 27,150.00 | $ 2.50 | $ 2,715.00 | $ - 0 | $ - 0 | $ - 0 | |||
| 10 | Culvert Drainage Markers, Type 1 | 10 | EACH | $ 800.00 | $ 8,000.00 | $ 400.00 | $ 4,000.00 | $ 300.00 | $ 3,000.00 | $ 50.00 | $ 500.00 | $ 250.00 | $ 2,500.00 | $ - 0 | $ - 0 | $ - 0 | |||
| TOTAL | $ 267,030.00 | $ 328,077.00 | $ 359,688.55 | $ 365,589.00 | $ 370,880.00 | $ - 0 | $ - 0 | $ - 0 |