This is a project timeline spreadsheet detailing the Contract Line Item Numbers (CLINs) and periods of performance for an Animal Research IOT&A project at Sepulveda VA. The base period begins July 28, 2025, and includes four primary tasks: Program Management Support, Interior Design/FF&E/Space Planning, Concept of Operations and Transition Planning, and Acquisition Planning Services, all running through July 27, 2026.
The project includes two option years for Program Management Support (July 2026-July 2027 and July 2027-May 2028) and five optional tasks: Acquisition Packages Development (6 months), Warehousing Management Services (7 months), Relocation Services (6 months), Activation Services/Post-Occupancy Support (8 months), and Staff Training/Orientation (6 months). The optional tasks are scheduled to begin in 2027, with the overall project completion date set for May 27, 2028. Cost reimbursable travel and other direct costs are included as separate CLINs for the base period and both option years.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Timeline
| Sepulveda Animal Research IOT&A | |||||||||||||||||||||||||||||||||||||||
| 07/25 | 08/25 | 09/25 | 10/25 | 11/25 | 12/25 | 01/26 | 02/26 | 03/26 | 04/26 | 05/26 | 06/26 | 07/26 | 08/26 | 09/26 | 10/26 | 11/26 | 12/26 | 1/27 | 2/27 | 03/27 | 04/27 | 05/27 | 06/27 | 07/27 | 08/27 | 09/27 | 10/27 | 11/27 | 12/27 | 01/28 | 02/28 | 03/28 | 04/28 | 05/28 | |||||
| Task Number | CLIN | Task Order Title | Period of Performance | Construction Award | BOD | First Day | |||||||||||||||||||||||||||||||||
| PWS 16.1 | Base | CLIN 0001 | PM Support Base Year | 07/28/2025 - 07/27/2026 | |||||||||||||||||||||||||||||||||||
| PWS 16.1 | Option Year | CLIN 1001 | PM Support Option Year 1 | 07/28/2026 - 07/27/2027 | |||||||||||||||||||||||||||||||||||
| PWS 16.1 | Option Year | CLIN 2001 | PM Support Option Year 2 | 07/28/2027 - 05/27/2028 | |||||||||||||||||||||||||||||||||||
| PWS 16.2 | Base | CLIN 0002 | Interior Design, FF&E and Space Planning | 07/28/2025 - 07/27/2026 | |||||||||||||||||||||||||||||||||||
| PWS 16.3 | Base | CLIN 0003 | Concept of Operations and Transition Planning | 07/28/2025 - 07/27/2026 | |||||||||||||||||||||||||||||||||||
| PWS 16.4 | Base | CLIN 0004 | Acquisition Planning Services | 07/28/2025 - 07/27/2026 | |||||||||||||||||||||||||||||||||||
| PWS 17.1 | Optional Task | CLIN 0007 | Acquisition Packages Development | 02/13/2027 - 08/12/2027 | |||||||||||||||||||||||||||||||||||
| PWS 17.2 | Optional Task | CLIN 0008 | Warehousing and Warehousing Management Services | 06/13/2027 - 01/12/2028 | |||||||||||||||||||||||||||||||||||
| PWS 17.3 | Optional Task | CLIN 0009 | Relocation Services | 09/28/2027 - 03/27/2028 | |||||||||||||||||||||||||||||||||||
| PWS 17.4 | Optional Task | CLIN 0010 | Activation Services and Post Occupancy Support | 09/28/2027 - 05/27/2028 | |||||||||||||||||||||||||||||||||||
| PWS 17.5 | Optional Task | CLIN 0011 | Staff Training and Orientation | 09/28/2027 - 03/27/2028 |
CLINs
| Period | CLIN NO. | TASK | Est. PoP | FY | Duration |
| Base | 0001 | PM Support | 07/28/2025 - 07/27/2026 | 25 | 12 MO |
| Base | 0002 | Interior Design, FF&E and Space Planning | 07/28/2025 - 07/27/2026 | 25 | 12 MO |
| Base | 0003 | Concept of Operations (CONOPS) and Transition Planning | 07/28/2025 - 07/27/2026 | 25 | 12 MO |
| Base | 0004 | Acqusition Planning Services | 07/28/2025 - 07/27/2026 | 25 | 12 MO |
| Base | 0005 | Cost Reiumbursable Travel | 07/28/2025 - 07/27/2026 | 25 | 12 MO |
| Base | 0006 | Other Direct Costs-Cost Reimbursable | 07/28/2025 - 07/27/2026 | 25 | 12 MO |
| Optional Task 1 | 0007 | Acquisition Packages Development | 02/13/2027 - 08/12/2027 | 27 | 6 MO |
| Optional Task 2 | 0008 | Warehousing and Warehousing Management Services | 06/13/2027 - 01/12/2028 | 27 | 7 MO |
| Optional Task 3 | 0009 | Relocation Services | 09/28/2027 - 03/27/2028 | 27 | 6 MO |
| Optional Task 4 | 0010 | Activation Services and Post Occupancy Support | 09/28/2027 - 05/27/2028 | 27 | 8 MO |
| Optional Task 5 | 0011 | Staff Training and Orientation | 09/28/2027 - 03/27/2028 | 27 | 6 MO |
| Option Year 1 | 1001 | PM Support | 07/28/2026 - 07/27/2027 | 26 | 12 MO |
| Option Year 1 | 1005 | Cost Reiumursable Travel | 07/28/2026 - 07/27/2027 | 26 | 12 MO |
| Option Year 1 | 1006 | Other Direct Costs | 07/28/2026 - 07/27/2027 | 26 | 12 MO |
| Option Year 2 | 2001 | PM Support | 07/28/2027 - 05/27/2028 | 27 | 10 MO |
| Option Year 2 | 2005 | Cost Reiumursable Travel | 07/28/2027 - 05/27/2028 | 27 | 10 MO |
| Option Year 2 | 2006 | Other Direct Costs | 07/28/2027 - 05/27/2028 | 27 | 10 MO |