Attachment B
SCHEDULE OF SUPPLIES AND SERVICES
PRICE/COST SCHEDULE
Contractor shall provide all labor, supervision, materials, and supplies necessary to provide complete Refuse/Waste Management Services for the Puerto Rico National Cemetery, 50 Avenida Cementerio Nacional, Bayamón, Puerto Rico 00961, in accordance to the Description of Need.
The Base Contract performance period is from May 1, 2021 (or Date of Award), through May 30, 2022 with four (4) one-year options through May 30, 2026, if exercised.
Note: all Option Years are subject to the availability of appropriated funds; options are not guaranteed, and the Government’s decision not to exercise an option shall not be understood, construed, or intended as a termination.
PUERTO RICO NATIONAL CEMETERY
REFUSE/WASTE MANAGEMENT SERVICES
May 1, 2021 through April 30, 2022 with (4) 1-Year Options through April 30, 2026
PRICE/COST SCHEDULE
BASE YEAR: MAY 1, 2021 – APRIL 30, 2022:
CLIN Description: Material/Product Est. Qty Unit Unit Cost Total Cost
Pick up and dispose non-hazardous solid waste with 8 cubic yards close top dumpster once per week.
52 Job $ $
0002 Pick up and dispose of recycling material with 6 cubic yards close top dumpster twice per month.
24 Job $ $
0003 Remove, transport and off-site disposal of excess fill-dirt from spoils area of PRNC (26 cubic meters dump truck).
104 Job $ $
Grand Total Estimated:
OPTION YEAR #2: MAY 1, 2023 – APRIL 30, 2024:
solid waste with 8 cubic yards close top dumpster once per week.
52 Job
2002 Pick up and dispose of recycling material with 6 cubic yards close top dumpster twice per month.
24 Job
2003 Remove, transport and off-site disposal of excess fill-dirt from spoils area of PRNC (26 cubic meters dump
104 Job
OPTION YEAR #1: MAY 1, 2022 – APRIL 30, 2023:
solid waste with 8 cubic yards close top dumpster once per week.
52 Job
1002 Pick up and dispose of recycling material with 6 cubic yards close top dumpster twice per month.
24 Job
1003 Remove, transport and off-site disposal of excess fill-dirt from spoils area of PRNC (26 cubic meters dump
OPTION YEAR #3: MAY 1, 2024 – APRIL 30, 2025:
solid waste with cubic yards close top dumpster once per week.
52 Job
3002 Pick up and dispose of recycling material with 6 cubic yards close top dumpster twice per month.
24 Job
3003 Remove, transport and off-site disposal of excess fill-dirt from spoils area of PRNC (26 cubic meters dump
OPTION YEAR #4: MAY 1, 2025 – APRIL 30, 2026:
solid waste with 8 cubic yards close top dumpster once per week.
52 Job
4002 Pick up and dispose of recycling material with 6 cubic yards close top dumpster twice per month.
24 Job
4003 Remove, transport and off-site disposal of excess fill-dirt from spoils area of PRNC (26 cubic meters dump
SUMMARY TOTALS
Summary Total:
Base Year: $
Option Year I: $
Option Year II: $
Option Year III: $
Option Year IV: $
Summary Grand Total (Base + all Option Years): $