Attachment B (INSTRUCTIONS).pdf

PDF 105 KB Posted

Attached to
Base STL IPD Parking Lot Project Federal contract opportunity
Solicitation number
70Z02926QGALV0065
Issued by
Department of Homeland Security US Coast Guard

About this file

This document is Attachment B, which provides instructions regarding the Performance of Work by the Contractor clause (FAR 52.236-1) that applies to the solicitation and resulting contract award.

The primary requirement mandates that the prime contractor must perform on-site, with its own organization, work equivalent to at least 50 percent of the total contract value. This percentage may only be reduced through a supplemental agreement if the contractor requests a reduction and the Contracting Officer determines it advantageous to the Government. Work performed by the contractor's laborers, mechanics, and foreman/superintendent on the contractor's payroll and under direct supervision counts toward this requirement, as does the cost of materials and equipment installed by such labor. Work by executive, administrative, and clerical forces is excluded from this calculation. The contractor must submit a statement simultaneously with the schedule of costs designating which portions of work will be performed by the contractor's own forces, and any changes to activity identifiers or responsibility codes require Contracting Officer approval. Non-compliance results in a 15 percent retention withhold on the value of unauthorized subcontracted work. All bidders must be actively registered in SAM.gov and must provide representations as prescribed in clause 52.236-1 to be considered for award.

View the file

Other files for this federal contract opportunity

Other files attached to Base STL IPD Parking Lot Project, newest first.
File Type Posted
70Z02926QGALV0065_0_US.pdf PDF
Parking Lot Concrete Pour SOW.docx DOCX document
Attachment A.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment B (instructions)

Bidders are advised that Far clause 52.236-1 Performance of Work by the Contractor applies to the solicitation and award.

52.236-1Performance of Work by the Contractor.

Performance of Work by the Contractor (Apr 1984)

The Contractor shall perform on the site, and with its own organization, work equivalent to at least FIFTY (50) percent of the total amount of work to be performed under the contract. This percentage may be reduced by a supplemental agreement to this contract if, during performing the work, the Contractor requests a reduction, and the Contracting Officer determines that the reduction would be to the advantage of the Government.

(End of clause)

In accordance with the Code of Federal Regulations, Title 48, 852.236-72 Performance of Work by the Contractor.

As prescribed in 836.501, insert the following clause:

Performance of Work by the Contractor (APR 2019)

(a) In accordance with FAR 52.236-1, the contract work accomplished on the site by laborers, mechanics, and foreman/superintendent on the Contractor's payroll and under their direct supervision shall be used in establishing the percent of work to be performed by the Contractor.

Cost of material and equipment installed by such labor may be included. The work by the Contractor's executive, administrative and clerical forces shall be excluded in establishing compliance with the requirements of this clause.

(b) The Contractor shall submit, simultaneously with the schedule of costs required by the Payments under Fixed-Price Construction Contracts clause of the contract, a statement designating the portions of contract work to be performed with the Contractor's own forces. The approved schedule of costs will be used in determining the value of a work activity/event, or portions thereof, of the work for the purpose of this article.

(c) Changes to established activity/event identifiers or responsibility codes for Contractor activities shall not be made without approval from the Contracting Officer.

(d) In the event the Contractor fails to comply with FAR 52.236-1, Performance of Work by the Contractor, the Contracting Officer will withhold retention in the amount of 15% of the value of any work activity/element being invoiced that was not authorized by the Contracting Officer to be performed by someone other than the prime Contractor's own workforce.

All contractors must be actively registered in SAM. gov and must provide representations prescribed in clause 52.236-1 in Section III and see attachment B to be considered.

The Contractor shall submit, simultaneously with the schedule of costs required by the Payments under Fixed-Price Construction Contracts clause of the contract, a statement designating the portions of contract work to be performed with the Contractor's own forces.