Attachment B - Coach Specification.pdf
PDF 178 KB Posted
- Attached to
- RFP#139-24, Rochester Mechanical Services
- Solicitation number
- BD-24-1206-40000-40000-105683
- Issued by
- Plymouth County, Massachusetts
About this file
This document appears to be Attachment B - Coach Specification related to the RFP#139-24, Rochester Mechanical Services contract opportunity issued by the Massachusetts Bay Transportation Authority (MBTA). The attachment outlines the scope of work for the overhaul of passenger coaches, including exterior reconditioning, interior refurbishment, HVAC system replacement, and truck/coupler repairs and replacements. The work covers a wide range of components and systems, with the MBTA providing all necessary materials. The contract opportunity appears to be for the state of Massachusetts.
The pricing terms, funding requirements, and other salient commercial details are not included in this attachment. However, it is likely that these details would be specified elsewhere in the RFP documentation or contract opportunity details.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Form D - Price Response~6.xlsx | XLSX spreadsheet | |
| Addendum 2~44.pdf | ||
| Attachment A - Locomotive Specifications.pdf | ||
| Addendum 1~70.pdf | ||
| RFP 139-24 - Rochester Mechanical Services 7.31.2024.pdf | ||
| Form D - Price Response Addendum 1.xlsx | XLSX spreadsheet | |
| Form D - Price Response Addendum 2~2.xlsx | XLSX spreadsheet | |
| FORM C.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment B
Coach Overhaul Summary Scope
• All materials to be provided by MBTA unless otherwise specified.
• Materials received from MBTA or 3rd Party are to be inspected prior to installation.
• The MBTA must be notified of any defective materials received prior to proceeding.
A. Exterior
1. Complete Reconditioning of Exterior
2. Repair all body damage as needed
3. Repair all exterior passenger doors
4. Replace door latches
5. Replace all Door Rubbers and Seals
6. Replace Diaphragms
7. Replace Air Bags
8. Replace Wheel Sensors
9. Replace Air Manifolds
10. Replace all Air Valves
11. Replace Coupler and Draft Gear
12. Coupler Pocket inspection and repair
13. Replace Passenger Car to Car Guards
14. Replace wheels and axles with new
15. Repair and Paint Roof
16. Wrap, Paint & Graphics (FRA and MBTA)
a. Option to be performed by others
17. Replace Windows and Gaskets
18. Recondition/Paint Vestibules
19. Test Trainline – Repair as necessary
20. Replace and test exterior lighting
B. Interior
1. Complete reconditioning of all Interior Wall and Ceiling Panels
2. Replace Interior Trim - Stainless Steel and Plastic
3. Repair Walls and Partitions
4. Recondition Luggage Racks
5. Recondition Seat Frames, Stanchions and End Caps
6. Install New Seating
7. Replace Ply Metal Flooring
8. Replace Sub Floor Wiring
9. Replace floor covering
10. Rebuild & Recondition Lighting
11. Replace Interior & Emergency Lighting
12. Replace all Floor Heat
13. Recondition all HVAC Ducts/Grates/Floor Heat Enclosures
14. Rebuild & Recondition Traps
15. Recondition Trainline connections
16. Recondition PA
17. Apply LLEPM and FRA required signage
18. All Doors/Tracks Reconditioned
19. Recondition existing Rest Room (Option to Modify existing Rest Room to Conductors' Closet)
20. Install ADA compliant Rest Room as required
C. HVAC
1. Replace Condensers
2. Replace Evaporators
3. Replace Compressor
4. Replace all lines with new
5. Clean, inspect and repair all ductwork
6. Charge and Test system
D. Truck – Bolster – Equalizer Beams - Coupler
1. Remove and replace trucks with overhauled units
a. Inspect overhauled trucks and components prior to installation
b. Inspect and adjust after installation
2. Replace all valves hoses and manifolds
3. Coupler pocket inspection – repair as necessary
4. Install new Coupler and Carrier Iron
5. Inspect air system – perform leveling and single car test
| Attachment B |
| Coach Overhaul Summary Scope |
| B. Interior |
File details come from the government source that posted it. Updated .