This is a Bid Schedule (Pricing Sheet) for a site-wide transformer oil testing contract with the National Institute of Standards and Technology (NIST). The contract covers a base year and four option years, with pricing to be submitted by contractors for each line item across all contract periods.

The scope of work includes transformer visual inspection and oil sample collection for 122 transformers per period, along with quality oil analyses, PCB analyses, and dissolved gas analyses (DGA) for specified quantities. Each contract period includes mobilization, nitrogen blanket services, and job hazard analyses with final written reports. Additionally, the base year includes an optional transformer oil leak repair service (quantity 1 EA). The pricing sheet establishes 122 transformers as the baseline inspection quantity and 36 transformers for PCB testing across the base year and all four option years. Each period also includes a "drawn down account" line item with to-be-determined (TBD) pricing for contingency services. Contractors must submit unit prices and extended prices for all line items in the base year and each option year, with the cost of safety plans, JHAs, and final written reports included in the quoted prices. The work will be performed at the NIST facility in Gaithersburg, Maryland, and is intended to mitigate risks associated with transformer failure, including arc flash, component failure, structural fire, and electric shock hazards.

View the file

Other files for this federal contract opportunity

Other files attached to Transformer Service, newest first.
File Type Posted
1333ND26QNB190490P004 SF30.pdf PDF
FormSF30.pdf PDF
SCA WD 2015 4269 Rev34 8222026.txt TXT text file
Government Responses to Questions 2.docx DOCX document
SOW_Rev5.docx DOCX document
Attachment B - Bid Schedule_Rev 2.xlsx XLSX spreadsheet
1333ND26QNB190490P002 .pdf PDF
Government Responses to Questions.docx DOCX document
1333ND26QNB190490-P001.pdf PDF
Instructions to Offerors-Tracked C.docx DOCX document
Instructions to Offerors CLEAN.docx DOCX document
Attachment E - B206 photos.pdf PDF
Attachment A - Transformer list_Rev 2.xlsx XLSX spreadsheet
Attachment C- Guidelines for Contractors_Rev1.pdf PDF
Attachment D- Sample Report.pdf PDF
RFQ-1333ND26QNB190490 .pdf PDF
Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bid schedule

ATTACHMENT B - BID SCHEDULE
BASE YEAR AND FOUR OPTION YEARS
SITE-WIDE TRANSFORMER OIL TESTING

Note: Cost of the Safety plan or JHA, and final written report are included for base year and 4 option years

Base Year
ITEM NO.QuantityUnitUnit PriceExtended Price
0001Transformer oil testing.
0001ATask1- Mobilization1LOT
0001BTask 1 - Transformer visual inspection and Transformer Oil Sample collection.122EA
0001CTask 1 - Nitrogen blanket as it requires1LOT
0001DTask 1 - Job hazard Analyses (JHA) and Final written Report1LOT
0001ETask 2 - Quality Oil Analyses122EA
0001FTask 2 - PCB Analyses36EA
0001GTask 2 - Disolved Gas Analyes (DGA)122EA
0002Drawn down account
Drawn down1LOTTBDTBD
0003Optional Transformer Oil Leak Repair
Repair Transformer Oil Leak per SOW - Base Year Only1EA
Option year 1
1001Transformer oil testing.
1001ATask1- Mobilization1LOT
1001BTask 1 - Transformer visual inspection and Transformer Oil Sample collection.122EA
1001CTask 1 - Nitrogen blanket as it requires1LOT
1001DTask 1 - Job hazard Analyses (JHA) and Final written Report1LOT
1001ETask 2 - Quality Oil Analyses122EA
1001FTask 2 - PCB Analyses36EA
1001GTask 2 - Disolved Gas Analyes (DGA)122EA
1002Drawn down account
Drawn down1LOTTBDTBD
Option year 2
2001Transformer oil testing.
2001ATask1- Mobilization1LOT
2001BTask 1 - Transformer visual inspection and Transformer Oil Sample collection.122EA
2001CTask 1 - Nitrogen blanket as it requires1LOT
2001DTask 1 - Job hazard Analyses (JHA) and Final written Report1LOT
2001ETask 2 - Quality Oil Analyses122EA
2001FTask 2 - PCB Analyses36EA
2001GTask 2 - Disolved Gas Analyes (DGA)122EA
2002Drawn down account
Drawn down1LOTTBDTBD
Option year 3
3001Transformer oil testing.
3001ATask1- Mobilization1LOT
3001BTask 1 - Transformer visual inspection and Transformer Oil Sample collection.122EA
3001CTask 1 - Nitrogen blanket as it requires1LOT
3001DTask 1 - Job hazard Analyses (JHA) and Final written Report1LOT
3001ETask 2 - Quality Oil Analyses122EA
3001FTask 2 - PCB Analyses36EA
3001GTask 2 - Disolved Gas Analyes (DGA)122EA
3002Drawn down account
Drawn down1LOTTBDTBD
Option year 4
4001Transformer oil testing.
4001ATask1- Mobilization1LOT
4001BTask 1 - Transformer visual inspection and Transformer Oil Sample collection.122EA
4001CTask 1 - Nitrogen blanket as it requires1LOT
4001DTask 1 - Job hazard Analyses (JHA) and Final written Report1LOT
4001ETask 2 - Quality Oil Analyses122EA
4001FTask 2 - PCB Analyses36EA
4001GTask 2 - Disolved Gas Analyes (DGA)122EA
4002Drawn down account
Drawn down1LOTTBDTBD