This is a technical specifications document from the Oregon Parks and Recreation Department (OPRD) for Contract #12038/Project #37403 regarding parking lot improvements at Face Rock State Scenic Viewpoint in 2024. The project includes demolition, site preparation, traffic control, foundation stabilization, aggregate base installation, asphalt paving (Level 3 HMAC), geotextile fabric installation, grinding and inlay work, roadway striping, curb and sidewalk construction, catch basin improvements, signage installation, restroom foundation work, electrical service installation, erosion control, and landscape restoration. The work requires maintaining public access throughout construction while coordinating with the Project Manager for safety and traffic control. Construction operations are restricted to 7AM-5PM Monday through Friday unless otherwise approved.

The technical specifications detail requirements for measurement and payment methods, with items paid on various bases including lump sum, cubic yard, ton, square yard, linear foot, and per each unit basis. The contractor must provide all permits, labor, equipment, tools, supervision, materials and incidentals required to complete the work according to plans and specifications. Quality control requirements include density testing for asphalt at a minimum frequency of three tests per project or one test per 500 tons placed. The document outlines specific material requirements for items like aggregate base, asphalt concrete, and pavement markings, along with execution requirements for items such as earthwork, paving, and traffic control.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Oregon Parks and

Recreation

Department

CONTRACT SPECIFICATIONS

For

2024 Face Rock State Scenic Viewpoint

Parking Lot Improvements

Project Number: 37403

Contract Number: 12038

November, 2024

Oregon Parks and Recreation Department

Technical Services Division

725 Summer Street NE, Suite C

Salem, Oregon 97301

THIS PAGE INTENTIONALLY LEFT BLANK

i

Table of Contents

TABLE OF CONTENTS

PAGE

SECTION 01010 – SUMMARY OF WORK

SECTION 01019 – CONTRACT CONSIDERATIONS

SECTION 01025 – MEASUREMENT AND PAYMENT

SECTION 01028 – MODIFICATION PROCEDURES

SECTION 01090 – REFERENCE STANDARDS

SECTION 01300 – SUBMITTALS PROCEDURE

SECTION 01570 – TRAFFIC CONTROL

SECTION 02200 – EARTHWORK

SECTION 02220 – COLD PLANE PAVEMENT MILLING

SECTION 02700 – ASPHALTIC CONCRETE PAVING AND RESURFACING

SECTION 02765 – PAVEMENT MARKINGS

ii

Table of Contents

Face Rock State Scenic Viewpoint

Section 01010 - 1

SUMMARY OF WORK

SECTION 01010 – SUMMARY OF WORK

PART 1 – GENERAL

1.01 DESCRIPTION OF WORK

A. Requirements of the STATE OF OREGON GENERAL CONDITIONS FOR PUBLIC

IMPROVEMENT CONTRACTS (“General Conditions”) dated January 1, 2012, as modified by the Oregon Department of Justice on November 13, 2024, apply to the

Technical Specifications and Plans for this Project.

B. Contractor shall furnish all permits, labor, equipment, tools, supervision, materials and incidentals required to complete the Work in accordance with the Plans, Specifications and terms of the Contract. Also refer to the Invitation to Bid (“ITB”) and the Contract for additional requirements and information. Work includes, but is not limited to, the following:

1. Mobilization – Bonds & Insurance

2. Survey Layout

3. Demolition & Site Preparation

4. Traffic & Pedestrian Control

5. Foundation Stabilization

6. Aggregate Base (All Sizes)

7. Asphalt - Level 3 HMAC

8. Geotextile Fabric

9. 3-Inch Grind & Inlay

10. Painted Roadway Striping

11. Standard Vertical Curb

12. Pedestrian Ramp

13. Standard Sidewalk

14. Catch Basin Frame & Grate

15. Sign, Post & Footing

16. Prefabricated Restroom Foundation

17. Electrical Service Installation

18. Erosion Control

19. Landscape & Restoration

C. Project is for the Oregon Parks and Recreation Department, herein referred to as Owner.

D. The Owner’s Authorized Representative, herein referred to as Project Manager is:

Darrell Monk

Oregon Parks & Recreation Department

725 Summer St NE, Ste. C

Salem, OR 97301

(503) 298-1879

1.02 CONSTRUCTION STAKEOUT AND LAYOUT

A. The Plans show approximate locations and dimensions of existing utilities and facilities adjacent to and in the proposed Work, as shown on the Plans, for the Contractor’s information. Final stakeout of the construction Work shall be provided by Contractor and approved by Project Manager. The Contractor will be solely responsible for locating all

Section 01010 - 2

SUMMARY OF WORK

existing utilities within the Project sites. No additional stakeout will be provided by the

Owner.

B. Contractor is responsible for properly laying out the Work and verifying lines and measurements of the Work. Contractor to verify the figures shown on the Plans before any construction takes place or products are ordered. Report errors or inaccuracies to the

Project Manager for resolution before commencing Work.

1.03 OWNER OCCUPANCY

A. The Owner will not close any areas of Face Rock State Scenic Viewpoint (the “Park”) except the area under construction and temporary closures as approved in advance by the

Project Manager for approved limited durations.

1.04 CONTRACTOR USE OF SITE AND PREMISES

A. Construction Operations: Limited to construction areas around the project sites.

B. Contractor shall at all times conduct their operations to ensure the greatest public safety and least inconvenience to the public and adjacent landowners.

C. Contractor shall receive approval from the Project Manager as to the staging and stockpiling of the equipment and materials used on the Project.

D. Storage of material onsite is at Contractor’s own risk.

E. Hauling Restrictions: Comply with all legal load restrictions in the hauling of material.

Load restrictions shall meet state load restrictions.

F. Parking: Contractor and Subcontractors shall park at approved locations, and as directed by the Project Manager.

G. Rest rooms: Contractor shall provide temporary rest room facilities for its workers and

Subcontractors as required.

1.05 CONSTRUCTION SCHEDULE

A. Refer to the Contract for construction schedule, Substantial and Final Completion dates.

B. Contractor shall not begin any on-site Work of this Project before required permits have been obtained, a proposed construction schedule is submitted, along with required submittals in accordance with Section 01300, and the Project Manager has given written approval of the submittals and construction schedule provided by the Contractor.

1.06 SPECIFICATION LANGUAGE

A. Portions of the Specifications are written in imperative and streamlined form. This imperative language is directed to the Contractor, unless specifically noted otherwise.

The words “shall be” shall be included by inference where a colon (:) is used within sentences or phrases. Example: Aggregate: ASTM C33.

Section 01010 - 3

SUMMARY OF WORK

END OF SECTION

Section 01019 - 4

CONTRACT CONSIDERATIONS

SECTION 01019 – CONTRACT CONSIDERATIONS

1.01 SPECIAL PROJECT REQUIREMENTS

A. While portions of the Park are closed for construction, areas surrounding the construction site and driveways, parking lots and walkways in the area shall be open to the public from start of construction until the completion date. The Contractor shall coordinate with the Project Manager to provide both access and public safety during construction.

Devices required to provide for public safety during construction shall be provided and installed by the Contractor at the expense of the Contractor. If required safety devices are not installed, Work shall not commence until such devices are installed. The Contract

Time will not be extended based on working Days lost due to the non-compliance of safety devices.

B. Construction operations shall be restricted to normal daily operating hours and the normal

Open/Close schedule of the Park but not outside the hours of 7AM – 5PM, Monday –

Friday unless otherwise arranged and approved in writing by the Project Manager.

C. No Work shall be performed on any legal holiday or weekends without prior written approval from the Project Manager.

D. Smoking is not allowed at the project site.

E. Contractor shall notify the Project Manager in advance when Contractor, Subcontractor or any employees are to be on Park property.

F. Contractor shall comply fully with manufacturer’s instructions and recommendations.

Should manufacturer’s instructions conflict with Contract Documents, Contractor shall request clarification from Project Manager before proceeding.

G. Contractor shall furnish all planning, investigation, material, equipment, labor and permits to complete the Work in accordance with the Plans, Specifications and terms of this Contract, except as specified otherwise herein.

H. All changes to normal traffic patterns must be clearly explained in the Traffic Control

Plan and approved by the Project Manager.

I. For paving projects, Contractor shall stay on roadway surfaces at all times, unless approved by the Project Manager. No staging of equipment or storage of materials shall be allowed off the existing roadway surface without the Project Manager approval.

1.02 EXISTING UTILITIES

A. In general, the locations of existing utilities, whether above ground or underground or under the roof, are to be determined as needed by the Contractor. Work in some cases must be done in close proximity to said utilities and live electrical service lines, pipes, drains, and structures not shown, which may require a change in operations, cost and time.

Section 01019 - 5

CONTRACT CONSIDERATIONS

B. Utilities damaged by Contractor’s activities shall be reestablished, to the satisfaction of the Project Manager. If the Contractor fails to repair the damaged utility, costs for repairing the utility shall be deducted from final payment.

C. Contractor shall comply with Oregon Administrative Rules Division 952, Relating to

Abandoned Underground Facilities. An “Abandoned Facility” means an underground facility that is no longer in service and is physically disconnected from the operating facility that is in service. In addition to notification requirements of this rule, Contractor shall notify Project Manager of any Abandoned Underground Facilities which are discovered during the course of the Project.

1.03 PROGRESS CLEANING

A. Contractor shall maintain areas free of waste materials, debris, and rubbish at all times.

Contractor shall maintain site in a clean and orderly condition. Contractor shall provide legal debris disposal (or recycle waste materials if feasible) off-site for all debris generated while working on this Project.

B. Contractor shall remove debris and rubbish from pipe chases and other closed or remote spaces on a daily basis.

C. Contractor shall remove waste materials, debris and rubbish from the site immediately upon such materials becoming unfit for use in the Work. In the event this material is not removed, Project Manager will give one notification in writing as to the removal of such waste materials, debris and rubbish. If the Contractor does not clean up the waste materials, debris and rubbish within 24 hours as directed by the Project Manager, the

Project Manager reserves the right, but does not have the duty, to have the material removed and the expense shall be deducted from payment to the Contractor. This debris shall be removed at the end of each workday.

D. Contractor shall provide legal debris disposal off-site for all debris generated while working on this Project.

1.04 TEMPORARY UTILITIES

A. Connections to existing utilities (electric, water, sewer, telephone service) may be allowed as approved by the Project Manager. Contractor shall make arrangements for connections. Contractor shall pay for cost of connection and use. Contractor shall exercise measures to conserve energy and water.

B. Provide toilet and wash-up facilities for the work force at the site. Comply with applicable laws, ordinances and regulations pertaining to public health and sanitation.

PART 2 – MATERIALS (Not Applicable)

PART 3 – EXECUTION (Not Applicable)

Section 01019 - 6

CONTRACT CONSIDERATIONS

Section 01025 - 7

MEASUREMENT & PAYMENT

SECTION 01025 – MEASUREMENT AND PAYMENT

1.01 DESCRIPTION

A. All Payments shall be as provided in the State of Oregon General Conditions for Public

Improvement Contracts. References to other documents in the Plans and in the

Specifications, such as ODOT and ODOT/APWA are not intended to include references to measurement and payment that may exist in those other documents. Specific

Measurements for Work Items are detailed in this Specification Section 01025.

B. If no Item exists for a portion of the Work, include the costs in a related Item.

C. No separate payment will be made for any item that is not specifically set forth in the

Solicitation, and all costs therefore shall be included in the prices named in the

Solicitation for the various appurtenant items of Work.

D. Quantities listed in the Contract Document do not govern final payment. Payments to the

Contractor will be made only for actual quantities of Contract items performed in accordance with terms of the Contract and for items of Work actually performed under

Change Orders.

E. Indirect costs, such as supervision and overhead, profit, and the General Conditions specified in the Contract, all shall be allocated to each item as applicable for Work defined in the item. No separate payment will be made to the Contractor for these items.

F. Payments shall include full compensation for all labor, equipment, and materials necessary to perform the specified Work.

G. Partial payments to be made under the Contract shall be based on the percent of Work complete as approved by the Project Manager according to the State of Oregon General

Conditions for Public Improvement Contracts.

H. Material requiring weighing to be weighed by scale. Allowable scales with Project

Manager approval are commercial vehicle weigh scales, plant automatic weight batching and mixing control printer system, or plant weight hopper printer system.

Pay Items to be measured by weight shall include all Contractor costs for furnishing appropriate weight tickets and transporting materials to the scales or to check weighing.

The scales shall conform to ORS 618, and NIST Handbook 44, and shall be:

• Licensed by the Oregon Department of Agriculture;

• Technically suitable for weighing the materials;

• Properly installed and maintained; and

• Accurate to the required tolerances.

The Owner may periodically have a representative at the scales to observe the weighing procedures.

Section 01025 - 8

1.02 ITEM MEASUREMENT AND PAYMENT

NOTE: See the ITB Pricing Form. Payment shall include full compensation for all labor, equipment, materials and incidentals needed to accomplish the Work as shown and described in the Contract Documents.

A. ITEMS - SITE RELATED:

1. Mobilization Bonds & Insurance:

a. Measurement and payment for this bid item shall be made on a lump sum basis. The amount to be allowed for Mobilization in the partial payment to be made under the Contract will be as follows:

b. When 5% of the total original Contract amount is earned from other items, not including advances on materials, 50% of the amount bid for

Mobilization, or 2.5% of the original Contract amount, whichever is the least, less normal retainage, will be paid.

c. When 10% of the total original Contract amount is earned from other items, not including advances on materials, 100% of the amount bid for

Mobilization, or 5% of the original Contract amount, whichever is the least, less normal retainage, will be paid.

d. Upon completion of all Work on the Project, payment of any amount bid for

Mobilization in excess of 5% of the total original Contract amount will be paid.

e. The above schedule of progress payments for Mobilization shall not limit or preclude progress payments otherwise provided by the Contract.

2. Survey Layout:

a. Measurement and payment for Survey Layout shall be made on a lump sum basis.

b. Work shall include supplying all labor, equipment, and materials required for all survey, staking, and layout necessary for construction of the project as shown in the contract documents. Construction survey and staking shall be performed directly by or under the direct responsible charge of a licensed surveyor in the State of Oregon.

3. Demolition & Site Preparation:

a. Measurement and payment for Demolition & Site Preparation shall be made on a lump sum basis.

b. Work shall include supplying all labor, equipment, materials and incidentals including but not limited to demolishing existing restroom, disposal hauling, fees, site preparation and Work as shown and described in the Contract

Documents.

Section 01025 - 9

4. Traffic & Pedestrian Control:

a. Measurement and payment for Traffic & Pedestrian Control shall be made on a lump sum basis.

required to complete the Work as shown and described in the Contract

5. Foundation Stabilization:

a. Measurement and payment for Foundation Stabilization shall be made on a cubic yard basis.

including but not limited to dig-outs, compacted subgrade, geogrid, compacted base rock, and Work as shown and described in the Contract

6. Aggregate Base (All Sizes):

a. Measurement and payment for Aggregate Base (All Sizes) shall be made on a ton in place basis.

including but not limited to subbase compaction, grading, aggregate, base compaction and Work as shown and described in the Contract Documents.

7. Asphalt – Level 3 HMAC:

a. Measurement and payment for Asphalt – Level 3 HMAC shall be made on a ton in place basis to the nearest 0.01 ton. The quantities for payment shall be calculated from weight tickets provided from the supplier.

including but not limited to asphalt, pre-leveling, compaction, and Work as shown and described in the Contract Documents.

8. Geotextile Fabric:

a. Measurement and payment for Geotextile Fabric shall be made on a square yard basis.

required to complete the Work as shown and described in the Contract

9. 3-Inch Grind & Inlay:

a. Measurement and payment for 3-Inch Grind & Inlay shall be made on a square yard basis.

Section 01025 - 10

MEASUREMENT & PAYMENT

b. Work shall include supplying all labor, equipment, materials and incidentals including but not limited to grinding and legal disposal of existing asphalt, and Work as shown and described in the Contract Documents.

10. Painted Roadway Striping:

a. Measurement and payment for Painted Roadway Striping shall be made on a lump sum basis.

including but not limited to layout of all striping and symbols, striping, symbols and Work as shown and described in the Contract Documents.

11. Standard Vertical Curb:

a. Measurement and payment for Standard Vertical Curb shall be made on a linear foot basis.

including but not limited to layout, concrete, forms, finish and Work as

12. Pedestrian Ramp:

a. Measurement and payment for Pedestrian Ramp shall be made on a square foot basis starting at the front of the curb to the back of the ramp area.

Transition panels shall be paid for under the sidewalk line item.

including but not limited to layout, concrete, forms, detectable warning, finish and Work as shown and described in the Contract Documents.

13. Standard Sidewalk:

a. Measurement and payment for Standard Sidewalk shall be made on a square foot basis starting at the back of the curb to the back of the sidewalk.

including but not limited to concrete, forms, finish and Work as shown and described in the Contract Documents.

14. Catch Basin Frame & Grate:

a. Measurement and payment for Catch Basin Frame & Grate shall be made on a per each basis.

including but not limited to replace catch basin frame, grate and Work as

15. Sign, Post & Footing:

Section 01025 - 11

MEASUREMENT & PAYMENT

a. Measurement and payment for Sign, Post & Footing shall be made on a per each basis.

including but not limited to sign, post, footing and Work as shown and described in the Contract Documents.

16. Prefabricated Restroom Foundation:

a. Measurement and payment for Prefabricated Restroom Foundation shall be made on a lump sum basis.

including but not limited to site grading, subbase compaction, aggregate base and Work as shown and described in the Contract Documents.

17. Electrical Service:

a. Measurement and payment for Electrical Service shall be made on a lump sum basis.

including but not limited to trenching, conduits, conductors, locate wire, controls, and startup of a complete operational system and Work as shown and described in the Contract Documents.

18. Erosion Control:

a. Measurement and payment for Erosion Control shall be made on a lump sum basis.

including but not limited to straw wattles, silt fence, catch basin filters, miscellaneous erosion control BMP’s, and Work as shown and described in the Contract Documents.

19. Landscape Restoration:

a. Measurement and payment for Landscape Restoration shall be made on a lump sum basis.

b. Work shall include suppling all labor, equipment, materials and incidentals including but not limited to restoration of all disturbed areas, place and grading of imported topsoil, install native seed and mulch and Work as

PART 2 – MATERIALS (not applicable)

PART 3 – EXECUTION (not applicable)

Section 01025 - 12

Section 01028 - 13

MODIFICATION PROCEDURES

SECTION 01028 – MODIFICATION PROCEDURES

1.01 SUMMARY

A. Section includes the administrative requirements for Requests for Information (“RFI”) and

Proposal Requests (“PR”).

B. Prior to execution of a Change Order (“CO”), the following documents shall be submitted as indicated.

1.02 REQUEST FOR INFORMATION

A. General:

1. RFI are requests for information originated, prepared and submitted by the

Contractor to the Project Manager only when the Contractor is unable to determine from the Contract Documents, the material, process, system or Work to be installed. Endeavor to keep the number of RFI to a minimum. For critical or emergency items, contact Project Manager at once.

2. If Project Manager clarification results in additional cost or time, do not proceed with the Work indicated by the RFI until the Project Manager provides an approved copy of the RFI or until a PR is fully-executed. A CO will be processed to include this type of change.

3. Submit RFI on form provided by Project Manager.

4. Number RFI sequentially; include date submitted.

5. Identify Project, pertinent Plan sheet, detail number, and Specification Section.

6. Specifically identify time response information as required to avoid impact on construction schedule or cost. Project Manager will endeavor to respond to proper RFI within 7-Days, if possible.

B. RFI shall include written and graphic solutions proposed by Contractor. Project Manager will determine if Contractor’s proposal is in accordance with Contract Documents and design intent of Project.

1. Contractor's failure to make a reasonable effort to propose realistic solution may result in RFI being returned with no action.

2. RFI that request information that is clearly shown in the Contract Documents will be considered frivolous/improper and will be returned with no action.

C. Maintain current and accurate RFI Log.

Section 01028 - 14

MODIFICATION PROCEDURES

1.03 PROPOSAL REQUEST

1. Provide quotations for extra Work or changes in Work when requested by the

Project Manager, on a PR form to be provided by the Project Manager.

2. Provide a detailed itemization of the costs to the degree necessary for evaluation by the Project Manager. Indicate if a change to the Contract Time is warranted.

B. Maintain current and accurate PR log.

C. Issuance of a PR is not an authorization to proceed with extra or changed Work until fully executed by Owner and Contractor. Do not proceed with the Work indicated in the PR until the Project Manager provides a fully-executed copy. A CO will be processed to include approved PR.

PART 2 – MATERIALS (not applicable)

PART 3 – EXECUTION (not applicable)

Section 01090 - 15

REFERENCE STANDARDS

SECTION 01090 – REFERENCE STANDARDS

1.01 REFERENCED STANDARDS:

All Work shall conform to the issue of following referenced standards which is current at date of receipt of bids. Whenever the following abbreviations are used in these Contract Documents, they are to be construed the same as follows:

AA Aluminum Association

AASHTO American Association of State Highway and Transportation Officials

ACI American Concrete Institute

ACM American Construction Manual

AISC American Institute of Steel Construction

ANSI American National Standards Institute

APA American Plywood Association

APWA American Public Works Association

ASHRAE American Society of Heating, Refrigerating and Air-Conditioning

Engineers

ASTM American Society for Testing and Materials

AWPA American Wood Preservers' Association

AWS American Welding Society

AWWA American Water Works Association

CRSI Concrete Reinforcing Steel Institute

FM Factory Mutual FS Federal Specifications (“FS”)

ICEA Insulated Cable Engineers Association

IEEE Institute of Electrical and Electronic Engineers

JIC Joint Industrial Council

MIL Military Standards

NEC National Electric Code (Oregon Amended) NECA National Electrical Contractors Association NEMA National Electrical Manufacturers Association

NESC National Electrical Safety Code NFPA National Fire Protection Association ODOT Oregon Standard Specifications for Highway Construction by the Oregon

Department of Transportation

ODOT/APWA Oregon Standard Specifications for Construction by the Oregon

Department of Transportation and Oregon Chapter of APWA

OSSC Oregon Structural Specialty Code

OSHA Occupational Safety and Health Administration

QPL Qualified Products Listing by the Oregon Department of Transportation, Materials and Research Section

PCI MNL Pre-stressed Concrete Institute

SAMA Scientific Apparatus Manufactures Association

SMACNA Sheet Metal and Air Conditioning Contractors' National Association

UBC Uniform Building Code State of Oregon, Structural Specialty Code

Amended UFC Uniform Fire Code with State and Local Amendments

UL Underwriters Laboratories

UPC Uniform Plumbing Code State of Oregon, Plumbing Specialty Code

WCLIB West Coast Lumber Inspection Bureau

Section 01090 - 16

REFERENCE STANDARDS

Section 01300 - 17

SUBMITTALS PROCEDURE

SECTION 01300 – SUBMITTALS PROCEDURE

A. This Section specifies procedures for the technical submittals shown in the Specifications.

B. Submittals shall contain information that will enable the Project Manager to assess whether the Contractor’s proposed materials, equipment or methods of work are in general conformance to the design intent and in compliance with the Plans and Specifications. The information may consist of drawings, specifications, descriptive data, certificates, samples, test results and/or other information, as specifically required in the Specifications.

C. Furnish to the Project Manager the following items for equipment, articles and materials incorporated in the Work:

1. Submittals for items identified in individual Specification sections.

2. Manufacturer’s special tools and special accessories normally furnished by the manufacturer and which, by their specific nature and special design, are suited for convenient and expeditious adjustment, maintenance and repair.

3. One set of installation instructions, parts lists; routine preventative maintenance and operation manuals; corrective maintenance instructions; drawings and other like data pertinent for maintenance and repair.

4. Manufacturer’s and dealer’s warranties and guarantees that are normally available to purchasers. Such warranties and guarantees shall be made effective to the State of Oregon as the purchaser.

1.02 CONTRACTOR RESPONSIBILITIES

A. Prior to submittal transmittal to the Project Manager,

1. Ensure the accuracy and completeness of the information contained in each submittal and that the material, equipment or method of work is as described in the submittal.

2. Ensure information is legible by the Owner. Faxed submittals are NOT acceptable.

3. Ensure that the information is transmitted:

a. Prior to purchasing/leasing/ordering/installing

b. Early enough to allow a 7-day review period by the Owner without impacting the construction schedule.

4. Verify the material and equipment described in each submittal conforms to the requirements of the Specifications and Plans.

5. Ensure there is no conflict with other submittals.

Section 01300 - 18

6. Notify the Project Manager in each case where such submittal may affect the work of another contractor or Owner.

B. Substitutions may be considered provided they are submitted within the time period stated in the ITB and the substitution complies with the Specifications herein. Obtain written approval from the Project Manager, prior to bidding, by submitting the Substitution Request

Form to the Project Manager (located at the end of this Section).

C. Refer to the ITB and State of Oregon General Conditions for additional information regarding submittals and substitutions.

PART 2 – PRODUCTS (not applicable)

PART 3 – EXECUTION

3.01 TRANSMITTAL PROCEDURE

1. For each required submittal, submit one (1) copy of all required information not less than fourteen (14) Days prior to purchase or installation (if previously purchased). One copy will be returned to the Contractor. Individual sheets shall not exceed 22 inches x 34 inches. Submittals may be made electronically via email with PDF attachments as approved by Project Manager.

2. Use a Submittal/Transmittal Form for material and equipment submittals. Use a separate form for items specified in separate, discrete sections for which the submittal is required. Use a single form for submittals for various items when the items taken together constitute a manufacturer’s package or are related such that expediency indicates review of the package as a whole.

3. Note the unique sequentially assigned number that will accompany each item submitted, on the transmittal form. Original submittal numbers shall have the format: “XXX”; where “XXX” is the sequential number assigned by the

Contractor. Resubmittals shall have the format: “XXX-Y”; where “XXX” is the originally assigned submittal number and “Y” is a sequential letter assigned for resubmittals, i.e., A, B or C being the 1st, 2nd and 3rd resubmittals, respectively.

B. Deviation from Contract: Submit a request for substitution for deviations from the

Specifications or Plans. Include the reason for the deviation and cost differential for the deviation. Deviations from the Contract shall be authorized by Change Order only.

C. Submittal Completeness: submittals that do not have all the information required to be submitted are not acceptable and will be returned without review.

D. Project Manager reserves the right to ask for submittals not referenced in this document.

Section 01300 - 19

3.02 REVIEW PROCEDURE

A. The Project Manager will review the submittal and return it to the Contractor. The returned material will consist of one (1) marked-up copy of the submittal. The returned submittal will indicate one of the following actions:

1. If the review indicates the material, equipment or work method is in general conformance with the Plans/Specifications, the submittal copies shall be marked

“Approved.” In this event, the Contractor may begin to incorporate the material/equipment/work method covered in the submittal.

2. If the review indicates the submittal is insufficient or that limited corrections are required, the submittal copies may be marked “Approved as Noted.” The

Contractor may begin to implement the work method or incorporate materials/comments covered in the submittal in accordance with the corrections/comments noted.

3. If the review reveals the submittal is insufficient or contains incorrect data and the comments require revision and resubmittal, the submittal copies shall be marked “Not Approved, Resubmit.” In this case, the Contractor shall not then undertake Work covered by this submittal until the submittal has been revised, resubmitted and returned to the Contractor with a marking of “Approved” or

“Approved as Noted.”

4. If the review reveals the material, equipment, or Work does not require submittal, then the submitted copies shall be marked “Review Not Required Per Contract

Documents.” In this event, the Contractor may begin to incorporate the material/equipment/Work covered by the submittal and no further action is required.

3.03 EFFECT OF REVIEW OF CONTRACTOR’S SUBMITTALS

A. Submittal review of what the Contractor proposes to provide shall not relieve the Contractor of his responsibility for errors therein, nor shall it be regarded as an assumption of risks or liability by the Owner, or by any officer or employee of the Owner. Contractor shall have no claim under the Contract on account of the failure, or partial failure, of the method of work, material or equipment so reviewed. A mark of “Approved” or “Approved as Noted” shall mean the Project Manager has no objection to the Contractor, upon the Contractor’s own responsibility, using the plan or method of work proposed, or providing the materials or equipment proposed.

Section 01300 - 20

SUBSTITUTION REQUEST FORM

TO _________________________________________________________________________________

PROJECT ___________________________________________________________________________

We hereby submit for your consideration the following product instead of the specified item for the above

Project

Section _________________ Paragraph ____________________ Specified Item ___________________

Proposed Substitution:

Attach complete technical data, including laboratory tests, if applicable. Include complete information on changes to Plans and Specifications that proposed substitution will require for proper installation. Fill in

Blanks Below:

A. Does the substitution affect dimensions shown on Plans? Yes____No____. If yes, clearly indicate changes.

B. Will the undersigned pay for changes to the building design, including architectural, engineering and detailing costs caused by the requested substitution? Yes______ No_______.

C. What effect does substitution have on other trades?

D. What effect does substitution have on construction schedule?

E. Differences between proposed substitution and specified item?

F. Manufacturer's guarantees of the proposed and specified items are:

______ Same _______ Different (explain on attachment)

The undersigned states that the function, appearance and quality are equivalent or superior to the specified item.

Submitted by:

Signature________________________________Title_________________________________________

Firm______________________________, By____________________________ Date_______________

Telephone_____________________________ E-mail:________________________________________

___ACCEPTED, ___NOT ACCEPTED, ___RECEIVED TOO LATE

Section 01570 - 21

TRAFFIC CONTROL

SECTION 01570 – TRAFFIC CONTROL

A. This Work consists of furnishing, erecting, and maintaining temporary barricades, signs, and other traffic control devices, and provision of temporary roadways, detours, and other safeguards necessary for orderly flow of traffic during performance of the Work.

B. The Contractor shall submit a Traffic Control Plan (“TCP”) to the Project Manager which addresses public and emergency access as related to the Project for approval. The

Contractor shall update the TCP as required during the progress of the Work.

PART 2 - MATERIALS

2.01 SUBMITTALS

A. The Contractor shall develop and provide to the Project Manager, at least fourteen (14)

Days in advance of the time the traffic control will be required or haul routes employed, a

TCP which will, as a minimum:

1. Conform with the current edition of the Manual on Uniform Traffic Control

Devices (“MUTCD”), as published by the U.S. Department of Transportation –

Federal Highway Administration; the Oregon Supplements to the MUTCD as published by the State of Oregon Department of Transportation; and as approved by the Project Manager through the TCP.

2. Annotate proposed location of barricades, lighting, signing, temporary striping and other traffic control devices.

3. Provide emergency exits from buildings within and immediately adjacent to the construction site.

4. Maintain emergency access; access to public service buildings shall be provided at all times. If driveway or mail access is to be restricted, notice shall be given to the Project Manager seven (7) Days prior to the date of the restriction.

5. Provide public service buildings, safe and acceptable driveway access during their operating hours.

6. Provide Road Closure Plans.

7. Provide Detour Route Plans for local access.

8. Channel traffic flow through the work zone per approved TCP.

9. Ensure the plan addresses all modes of transportation, including vehicles, bicycles, pedestrians, transit, and adjacent property access.

Section 01570 - 22

10. Ensure the plan shows pertinent roadway features that will be obstructed by construction activity, such as fire hydrants.

11. Provide a TCP for all road closure and detours. Include details of detour traffic control plans for each proposed closure.

12. Any special traffic control associated with school bus routing must be reviewed and approved by the Project Manager.

2.02 REQUIREMENTS

A. The TCP must be approved in writing by OPRD before any Work commences.

B. The Project Manager shall approve all temporary public service building signs. Portable

Changeable Message Signs (“PCMS”) are not permitted for public service buildings.

C. Emergency vehicle, pedestrian and bicycle access shall be maintained at all times.

D. Vehicular and pedestrian routing on streets where the Work is not being performed shall not be revised without approval of a supplemental TCP by the Project Manager.

E. Advance Information Signs and Warning Arrow Panels:

1. Information Signs:

a) Black lettering on orange background.

b) List beginning of Work, work zone limits, nature of the Work, and nature of traffic restrictions.

c) Post two weeks before beginning the Work on the affected work zone.

2.03 COORDINATION

A. The Contractor shall coordinate all construction to offer the least possible obstruction and inconvenience to the public. The Contractor shall have under construction no greater length or amount of Work than can be executed properly with due regards to the rights of the public.

B. The Contractor shall coordinate all revisions to the existing TCP with the Project

Manager. Traffic controls are to remain in operation unless determined to be unnecessary and confusing under the approved TCP. As Work progresses, and as conditions permit, relocated or removed traffic and street name signs shall be reset by the Contractor with new signs in their permanent locations. All damaged or lost traffic control devices shall be replaced by the Contractor at the Contractor’s expense.

2.04 NOTIFICATIONS

A. Written approval of the TCP and/or supplemental TCP shall be obtained from the Project

Manager prior to initiating Work.

Section 01570 - 23

TRAFFIC CONTROL

B. Written approval shall be obtained from the Project Manager before scheduling closure of any street. The notification shall give the time of commencement and completion of the

Work, names of streets to be closed, schedule of operation, routes or detours.

C. To accommodate emergency vehicle rerouting, notification shall be given to Project

Manager in writing, not less than 72 hours prior to construction operations that modify existing traffic flow conditions.

2.05 SPECIAL SIGNS

A. Signs with special or non-standard messages may be necessary to properly convey information to the motorist or pedestrian. The Contractor shall be responsible for installing and maintaining these signs.

PART 3 - EXECUTION

3.01 TRAFFIC MAINTENANCE

A. The Contractor shall maintain a normal flow of vehicular and pedestrian traffic to prevent accidents and to protect the Work throughout the construction stages until completion of the Work. The Contractor shall make all necessary arrangements to reroute traffic, provide and maintain barriers, cones, guards, barricades, and construction warning and regulatory signs. The Contractor shall protect other portions of the Work during construction and until completion. This includes providing and maintaining barricade lights, construction signs, guards, temporary crossovers.

B. Rerouting of traffic by the Contractor shall be limited to the shortest time necessary to provide effective construction operations. Where construction time can be reduced, the

Contractor may be allowed to completely close the roadway to through traffic. Required travel lanes shall not be blocked by the Contractor’s activities, including trucks delivering materials, unless pre-approved by the Project Manager. Material deliveries and other related trucking activities shall occur in the Contractor’s protected Work or staging areas.

Upon completion of a segment of Work in streets, the Contractor shall restore traffic operations to normal flow as soon as possible.

C. The Contractor shall provide emergency vehicle access at all times throughout the

Project. Temporary steel plates shall be used by the Contractor to accommodate traffic over excavation. The Contractor shall obtain approval from the Project Manager prior to restriction of access in any section of the roadway.

D. The Contractor shall maintain pedestrian movements through construction areas.

Facilities for pedestrians include provisions for the safe movement of mobility and sight-impaired individuals.

E. The Contractor shall provide flagging if the work zone conditions pose a hazard to the public and/or at the requirement of the Project Manager. No separate item will be paid by the Owner for flagging.

3.02 ACCESS

A. The Contractor shall maintain access to other Park facilities at all times.

Section 01570 - 24

B. If, during some urgent stages of construction, the Project Manager determines that temporary closure of an access to a property is unavoidable, the closure shall be coordinated with the property owners and approved by the Project Manager at least 48 hours in advance of closure. If required, alternative access and mail delivery shall be provided. Property access shall not be closed until the alternative access is available.

3.03 SAFETY

A. The Contractor shall provide adequate safeguards, safety devices and protective equipment and take all necessary actions to protect life, health and safety of the public and construction crew and to protect property in connection with the performance of

Work covered by the Contract.

B. The Contractor shall provide and erect all necessary standard construction signs, warning signs and detour signs to warn and protect the public at all times from injury or damage as a result of the Contractor’s operations.

C. The Contractor shall furnish standard signs, as well as other appropriate signs prescribed by the Project Manager as applicable and necessary for the Work. Signs on posts and supports shall be erected and maintained by the Contractor in a neat and presentable condition until they are no longer necessary. When a sign is no longer necessary, the

Contractor, upon approval by the Project Manager, shall take down such sign. Signs necessary for nighttime traffic control, or that remain in place during hours of darkness, shall be fully reflectorized.

D. The Contractor shall safeguard and direct traffic after the existing signs have been removed. Preservation and maintenance of traffic control and street name signs shall be the sole responsibility of the Contractor. The Contractor, at the Contractor’s expense, shall replace signs and other traffic control devices damaged or lost by the Contractor.

E. Areas under work zone traffic control shall be monitored at least two (2) times daily.

Disturbed signs and traffic control devices shall be reset immediately. Non-applicable signs shall be removed or covered.

F. Upon failure of the Contractor to provide necessary traffic control when ordered to do so by the Project Manager, the Project Manager may, without further notice to the

Contractor, provide the necessary traffic control. The cost of the traffic control shall be deducted from any payment due the Contractor.

G. The Contractor shall provide adequate traffic control for protection of the Work and the public at all times. The Contractor shall be liable for injuries and damages to persons and property suffered by reason of the Contractor’s operations or negligence.

3.04 CONSTRUCTION AND MAINTENANCE OF DETOURS

A. The Contractor shall provide for all on-site and off-site detours required or necessitated by the Work, including side street crossings and temporary bridges over excavation or freshly placed concrete.

B. Detours shall be constructed and maintained in a safe condition per the approved TCP.

Section 01570 - 25

C. Detours shall be removed by the Contractor when no longer required.

D. Work zone traffic control shall be checked by the Contractor at least two (2) times per day. The Contractor shall clean, restore or replace traffic control devices that are dirty, damaged or are not functioning per the approved TCP.

E. The Contractor shall keep all roadways clean to the satisfaction of the Project Manager to assure the safe passage of pedestrians and vehicles through the work site.

Section 01570 - 26

Section 02200 - 27

EARTHWORK

SECTION 02200 – EARTHWORK

A. This Section includes the requirements for the excavation, backfill, compaction and grading of the Project site to the lines and grades shown on the Plans and required by the

Specifications. Earthwork includes, but is not limited to, the following:

1. Excavation of all material encountered to the limits shown on the Plans, including excavation and backfill for building foundations and utility trenches.

2. Hauling and disposal or stockpiling of excess excavated material to sites secured by the Contractor and approved by the Project Manager.

3. Locating and protecting existing facilities and utilities.

4. Placement and compaction of fill.

5. Grading and reshaping of grades.

6. Furnishing and installing sub-base and base rock, soil and topsoil where shown on the Plans or required by the Specifications.

7. Compaction of sub-grade, sub-base and base rock, soil and topsoil.

8. All miscellaneous items of Work required to complete the Earthwork.

1.02 DEFINITIONS

A. Excavation: Removal of material to establish sub-grade elevations regardless of the type, nature, or condition of the materials encountered. Contractor shall assume full responsibility to estimate the kind and extent of the various materials to be encountered.

B. Rock excavation: Removal of boulders having a volume of 2 cubic yards or more, solid bedrock and ledge rock that cannot be excavated or removed by dozers with rippers, but require systematic drilling and blasting or the use of pneumatic rock splitters, hammers, and wedges. If material that is classified as rock is mechanically removed with grading equipment, the volume of material removed shall be measured and paid for as common excavation.

C. Common excavation: Removal of all material not classified as rock excavation.

D. Over-excavation: Removal of suitable material below the limits designated for

E. Site Structures: Footings, foundations, slabs, pavements or other features constructed above or below ground surfaces.

F. Unauthorized Excavation: Removal of materials beyond indicated sub-grade elevations or dimensions without direction or approval by the Project Manager.

Section 02200 - 28

G. Disposal Material: Excavated material beyond the quantities required for the Project or unusable for the Project. This includes materials that are unsuitable for fill, in excess of fill quantities required, and/or contaminated.

H. Fill (embankment): Material placed immediately on top of existing ground or

I. Sub-grade: Uppermost surface of an excavation or embankment.

J. Sub-base: Material placed immediately on top of the sub-grade only under the following conditions:

1. In all areas where unstable sub-grade is present.

2. In all areas where structural fill has been placed.

3. In all areas where fill material is required as shown on the Plans.

K. Base Material: Material placed immediately on top of the sub-grade or sub-base and immediately beneath the finish surface (i.e. pavement, concrete).

L. Leveling Course: Uppermost surface of the aggregate base, usually 2" thick, used to eliminate irregularities in the contour of the aggregate base surface prior to placing asphaltic concrete.

1.03 QUALITY ASSURANCE

A. Codes and Standards: Comply with requirements of authorities having jurisdiction.

1.04 NOTIFICATION

A. Notify Project Manager 48 hours prior to earthwork operations requiring observation or approval.

PART 2 – MATERIALS

2.01 FILL

A. Soil - Soil shall be free of unsuitable materials or other characteristics detrimental to the construction of firm, dense, and sound embankments.

B. Structural Fill - Structural fill shall be an angular, hard, durable, free draining material, visibly well graded from coarse to fine with the maximum size of 3 inches.

2.02 SUB-BASE ROCK

A. Combination of durable sand, gravel and cobbles which contain no particle with a dimension greater than 3 inches, and no unstable material, as approved by the Project

Manager.

Section 02200 - 29

2.03 AGGREGATE BASE

A. Aggregate base shall be crushed rock or as shown on the Plans; reasonably well graded from coarse to fine. Materials shall conform to the requirements of Section 00641 of

ODOT/APWA.

3.01 GENERAL

A. Dewater as required to perform the Work. Prevent surface, subsurface, or groundwater from entering excavations, ponding on sub-grades or flooding site areas or adjacent properties

B. Slope ground away from paved areas and building site. Avoid forming pockets that will collect and retain the free flow of surface water. Divert surface water to natural drainage courses.

C. No excavation shall be left open more than 5 Days unless otherwise approved by the

Project Manager.

D. All excavations left open overnight shall be fenced with wire mesh or plastic mesh fence secured to steel posts all around the excavation as approved by the Project Manager.

E. Disposal material is the property of the Contractor and therefore it is the sole responsibility of the Contractor. Disposal material shall be hauled off site and completely removed from the Owner's property. Disposal of contaminated soil shall be in accordance with federal, state, and local laws and regulations.

F. Contractor shall conduct excavation Work in such a manner as required to protect existing trees and vegetation on site.

G. Protect structures, utilities, pavements and other facilities from damage caused by settlement, lateral movement, undermining, erosion, and other hazards caused by earthwork operations.

H. Protect sub-grades against freezing temperatures. Provide insulation to protect as necessary.

I. Provide measures to prevent erosion or displacement of soils, either by water or air, to adjacent site areas and properties.

Section 02200 - 30

3.02 EXCAVATION

A. Comply with local codes, ordinances and requirements of authorities having jurisdiction, including maintaining stable excavations.

B. Excavate for pavements, storm management facilities, utilities and site structures to indicated cross sections, elevations, and grades.

C. Unauthorized excavation to be corrected at Contractor’s expense, including remedial

Work directed by the Project Manager.

3.03 SUB-GRADE AND SUB-BASE

A. Excavation shall be carried to lines and grades shown on the Plans, and as required to accommodate specified fills (embankment), sub-base rock, base rock, paving, and concrete. Any over excavation due to faulty workmanship will be brought to grade by the Contractor at their expense.

B. Grade Control - Establish and maintain the required lines and grades during construction operations. Check sub-grade for conformity to design grades and sections immediately before placing structural fill, sub-base and base rock.

C. Sub-grade shall be free of ruts, depressions, and irregularities.

D. Sub-grade Preparation –Compact excavated sub-grade prior to placing fill, sub-base rock and/or base rock as approved by the Project Manager.