This document provides instructions for completing project fact sheets to be submitted in response to a solicitation seeking general construction services. Offerors must complete all blocks for up to three past projects, limiting each project description to three pages. Required information includes the name of the company and its role; project name, location, owner details; dates started and completed; contract amount; size in gross square feet; at least two photos; and a narrative description of work performed by the offeror, work subcontracted, and work performed by others.

The related federal contract opportunity is a solicitation from the General Services Administration seeking proposals for Architectural Barriers Act Accessibility Standard compliance work at the Ron De Lugo Federal Building and U.S. Courthouse in St. Thomas, USVI. The project scope includes necessary limited improvements to bring the facility into compliance to the maximum extent possible. The NAICS code is 236220 and the size standard is $45 million in annual receipts. A pre-proposal conference and site visit will be held on March 21, 2023. Interested offerors must request access through SAM.gov to view secured documents and submit electronic proposals no later than the date and time stated in the solicitation.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment A3 – Project Fact Sheet Instructions: Complete all blocks. Limit the length to a maximum of three (3) pages per project, any information beyond the first three (3) pages will not be considered.

1. Name of Company that Performed this Work (this should be the name of your company, the Offeror)

Role (Prime G.C., C.M.C., Subcontractor, Joint-Venture Partner, etc.):

2. Name of Project

3. Location of Project

4. Project Owner Information 4a. Agency or Company Name

4b. Point of Contact (Name, Phone, and Email)

5. Date Started

6. Date Completed (Substantial Completion)

7. Contract Amount ($ USD)

8. Description of Project and Work Actually Performed by your Company

8a. Size of project (gross square feet)

8b. Project Photos (provide at least two (2))

8c. Narrative description of the Work, including the major disciplines and trades involved.

Make sure you identify the work you performed, the Work that you subcontracted, and whether any work was performed by others.