Attachment A1 - EKCC Narrative & Summary.pdf

PDF 178 KB Posted

Attached to
RFP-102-26 CM/GC DOC EKCC Facade & HVAC
Solicitation number
RFP-785-2600000119-1
Issued by
Mercer County, Kentucky

About this file

This document is a Design Narrative for Construction Manager/General Contractor Services for the Eastern Kentucky Correctional Complex (EKCC) Façade/Structure Repair and HVAC Replacement project located in West Liberty, Kentucky. The comprehensive renovation project involves extensive upgrades to multiple buildings within the correctional facility complex, including the Administration Building, four Housing Units, Warehouse, Minimum Security Unit, and Guard Tower. The scope of work includes complete facade replacement, structural repairs, HVAC system overhaul, electrical system upgrades, fire suppression modifications, and the creation of a new two-story training center within the warehouse. Key elements include removing and replacing existing exterior insulation and finish systems, installing new prefinished aluminum panels, replacing windows and doors, comprehensive mechanical system replacements, and upgrading electrical and fire alarm systems across the facility.

The project involves significant demolition and reconstruction, with work spanning multiple building areas and system types. The total campus encompasses approximately 260,000 square feet across 157 acres, with construction targeting improvements in building envelope, mechanical systems, electrical infrastructure, and overall facility functionality. The renovation will add chillers to each housing unit and the administration building, replace all ductwork with exterior insulated ductwork, upgrade control systems, add air conditioning to previously unconditioned spaces, and implement new mechanical rooms and equipment. The project will utilize multiple building codes, including the 2018 Kentucky Building Code, 2015 International Building Code, and various other technical standards. The comprehensive renovation aims to modernize the facility's infrastructure, improve environmental controls, and enhance overall operational efficiency of the correctional complex.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Construction Manager/General Contractor Services Page 1 of 11 EKCC Façade/Structure Repair and HVAC Replacement West Liberty, Kentucky

1 1

DESIGN NARRATIVE

FACILITY DESCRIPTION

The Eastern Kentucky Correctional complex was originally constructed in two phases. Phase 1 was built from construction documents dated October, 1986. The construction was completed in 1990. Phase 2 soon followed. It was built from construction prints dated October, 1988. The construction was completed in 1992.

The facility consists of the Administration Building, four Housing Units, one Minimum Security Building, Warehouse, a detached Security Tower and a collection of smaller support buildings. There is approximately 260,000 square feet of buildings in the main campus area. The facility sits on approximately 157 acres of land.

Architecture – Exterior Envelope

Existing Conditions

Roof – The roofs on the Administration and the Housing Unit buildings were replaced in 2022. The Minimum-Security Unit roof was replaced in 2015. The Warehouse roof was replaced in 2003.

Exterior Insulation and Finish System (EIFS.) - The exterior cladding of the facility is generally in poor condition. The primary wall construction is in-fill concrete masonry units with a site cast concrete frame. Insulation is achieved through 2” of polystyrene insulation in the EIFS assembly. The outer coating has been previously painted in some areas and has the original coating in others. All the EIFS is in a failing condition. The painted portion is in a better condition, but still well past its service life.

Hollow Metal (HM) Framed Windows and Doors – The existing windows and doors on the facility are in poor condition. Daylighting and views are provided primarily by fixed glazing within HM window frames.

The frames have been grouted solid and are attached to the wall with embedded steel anchors. The glazing appears to be a combination of insulated glazing units and single layer laminated safety glass depending on the nature of the activity of the space they serve. The majority of the doors are heavy gauge steel doors in HM frames that have been grouted solid and are attached to the wall with embedded steel anchors. There is a high degree of rust in the existing door and window frames.

New Work

Demolition Administration Building, Guard Tower #2, and Housing Units – The existing EIFS cladding on the Administration is being removed to the face of the existing CMU wall with the exception of the area nominally defined by column lines 1, 0.2, H.9 and N.1. The EIFS cladding on the Housing Units and Guard Tower #2 is completely being removed back to face of CMU. The existing EIFS installed over metal stud throughout is being removed back to structure. At the existing Sally Port, in Area B, the ceiling will be selectively demo’d to accommodate the installation of the new cladding. All existing exterior windows, doors, overhead doors and louvers throughout will be removed and replaced with the

Construction Manager/General Contractor Services Page 2 of 11

2 2 exception of the door and sidelites into room Sally Port AD-1266 in Dorm 9. There are two guard shacks at the Administration Building, in Area H, that will need to be moved during the cladding work and reinstalled at the end of the cladding work. There are cages in some of the Dorm Yards that will need to be disassembled and reinstalled or replaced at the end of the reclad work. Ceilings will be demo’d in coordination with the Mechanical, Electrical and Plumbing work. There will be some interior wall demo in coordination with the Mechanical, Electrical and Plumbing work. There will be roof demolition in coordination with the Mechanical, Electrical and Plumbing Work. There are free standing masonry walls at Housing Units 1, 2, 3 & 4 and Dorm 9 that will have their existing finish removed. The security gates for the Housing Unit wing exits stairs and yard exits will be removed. Razor wire will need to be removed as needed and reinstalled.

Warehouse and MSU – The Warehouse will have multiple interior CMU walls removed in the area nominally defined by column lines 8, 15a, JJ and MM. There will also be new openings made in the exterior wall for a new exit door, an existing interior window will be removed, an interior door will be removed and an exterior overhead door will be removed. Demolition of slab to install new plumbing will also be needed. See Structural for demolition of 3 columns, associated roof framing and decking.

There will also be the removal of multiple roof structures and a complete removal of the roof assembly down to the deck in the area nominally defined by column lines 8, 15a, JJ and MM. The MSU (Minimum Security Unit) will have ceilings and walls demo’d in support of the Mechanical, Electrical and Plumbing Work.

Roof Administration Building, Guard Tower #2, and Housing Units – The majority of the existing roof will be maintained. The majority of the existing parapet is anticipated to be maintained. The base flashing and termination of the roof membrane as it turns up and is integrated with the new cladding above will need to be reworked and repaired to coordinate the installation of the new cladding. This is a typical issue at all intermediate roofs as they transition to the wall to the upper roofs.

During the 2022 reroofing project the new parapet installation detail was developed with the intention to accommodate the installation of the new cladding in this project. The intent of the 2022 parapet detail was to provide space to remove the existing EIFS and install the new cladding while keeping the parapet in place. Locations where it is known there are issues in maintaining the existing parapet cap are as follows; the Administration Building buttresses, the Administration roof plazas at doors A-202 and A-205 to accommodate new guardrails, the Housing Unit wing stair tower areas, the Housing Unit mechanical stair towers and at the radiused walls of the Housing Units.

Roof repairs will be as needed to coordinate with all Structural, Mechanical, Plumbing, Electrical and equipment relocation work. On the 2nd floor of the Administration Building, at the roof plazas, located at doors A-202 and A-205, there may be additional rework to the existing roof with the new scope of work due to the relationship between the roof elevation and the floor elevation, contractor to review.

Warehouse and MSU - The majority of the existing roof at the Warehouse and Minimum Security Unit (MSU) will be retained. Coordination with Structural, Mechanical, Electrical, Plumbing and equipment relocation work will be required throughout. The roofing above deck and parapet flashing above the Warehouse, nominally between column lines 8, 15a, JJ and MM, will be completely replaced. See Structural for additional roof demolition.

Exterior Cladding and Misc. Work

Construction Manager/General Contractor Services Page 3 of 11

3 3

Administration Building, Guard Tower #2, and Housing Units – The existing buildings will be completely reclad with new prefinished, factory foamed, insulated aluminum panels, minus the area at the Administration Building nominally defined by column lines 1, .01, H.9 and N.1. There will be Architectural Louvers integrated with the metal panel system in these buildings as well. The metal panel at grade will receive a new cast in place concrete ledge and precast sill. There are several locations where new metal stud framing will need to be installed to support new sheathing and the metal panel system, coordinate with Structural. Locations where the metal framing will be needed are as follows, exterior soffits, existing exterior Sally Port (ceiling, soffit and suspended wall), as well as the buttresses.

The Housing Units will receive new canopies at the 1st floor entrances. Razor wire will need to be reinstalled upon completion of cladding work.

Warehouse and MSU – There is no recladding occurring at the Warehouse or MSU. See Mechanical for louver information.

Hollow Metal (HM) Framed Windows and Doors Administration Building, Guard Tower #2, and Housing Units – All existing exterior windows and doors throughout will be removed and replaced, with the exception of the door and side lites into room Sally Port AD-1266 in Dorm 9, with new Hollow Metal Frames and security glass. All new windows at grade or at plaza level (see Administration Building 2nd floor roof decks) receive a new concrete sill. Windows at grade also receive a new concrete ledge and precast sill stone. There are several Architectural Louvers called out to be fit within the Hollow Metal Window Frames.

Warehouse and MSU – There is only one new exterior Hollow Metal door to be provided in the Warehouse. There are multiple new interior doors. There are no new windows to be installed in the Warehouse.

Interior Fit Up Administration Building, Guard Tower #2, and Housing Units – The interior fit up work for these buildings is mainly associated with the Mechanical, Electrical and Plumbing work; installation of new ceilings and soffits. There are several new chases being installed that are scattered through the Administration Building. There is patch and repair work associated with the Mechanical, Electrical, Plumbing work and the window and door replacement. There is one new interior security door being installed between Lobby AD-1330 and Corridor AD-2301, door A-210.

Warehouse and MSU – The interior fit up for the warehouse is extensive. The portion of the Warehouse nominally bounded by column lines 8, 15a, JJ and MM will be fit up to be training space for the campus. There will be a 2nd floor installed in this existing double height space that will also be fit up to be training space. The spaces associated with the fit up include Classrooms, Open Classroom, Breakroom, Office, general support spaces, bathrooms on both floors and a “White Box Space” on the 2nd floor. There will also be a new elevator installed and two stairs. The MSU (Minimum Security Unit) will have ceilings replaced in support of the Mechanical, Electrical and Plumbing Work. There is patch and repair work associated with the Mechanical, Electrical, Plumbing work as well.

Architectural Site Work Administration Building, Guard Tower #2, and Housing Units – The Housing Units and Dorm 9 have several free-standing masonry walls. These walls will be parged and painted. New fencing and gates will be installed associated with the Housing Unit wing exist stair towers and the Housing Unit yard security gates. Several of the inmate activity yards, at both the Housing Units and Dorm 9, will have cages that will need to be reinstalled or replaced. There are two existing Guard Shacks at the Administration Building, in Area H that will need to be reinstalled.

Construction Manager/General Contractor Services Page 4 of 11

4 4

Warehouse and MSU – There is no Architectural Site Work at the Warehouse and MSU.

Site Work

Access – Access to the site is controlled, construction vehicles and personal vehicles will need to check in with security each time they enter the site. A construction access route to the construction staging area has been identified behind the existing Warehouse building. Large vehicle access to the secured area of the facility is limited by the existing sallyport with low roof clearances. To enable construction, a new exterior sallyport will be constructed early in the work to allow large construction vehicles into the secured areas. Access within the secured site will be via existing asphalt paved roadways

Pavements - Existing concrete walkways and service access pavements are original and in poor condition. Subgrade has failed in some locations.

Security Fencing - Security fencing is generally in good condition, with the exception of the existing access gates at the existing Sallyport, which will be replaced.

New Work

New Exterior Sallyport – As one of the initial phases of construction, a new exterior, fenced Sallyport will be constructed near the Warehouse building. This work will require removal and relocation of the existing salt storage, relocation of a portion of the perimeter asphalt drive, grade work and pavements.

The new Sallyport will be surrounded by security fencing, with security slide gates at each end to control access. This work will require removal of small sections of the existing double perimeter fence to install gates. This work will be done one section at a time, to ensure the perimeter is always securely fenced.

Building Perimeter Work – to facilitate installation of a new brick ledge for the new metal paneling, grade at the building façade will be removed / excavated. This will include concrete in some areas, asphalt pavement in fenced yards, and grass / turf in perimeter areas. Concrete pavement will be removed as part of the concrete replacement scope. Asphalt in fenced yards will be sawcut and removed, then put back with cast in place concrete to provide a cleaner edge. Lawn areas will be backfilled and lightly compacted, then hydroseeded or sodded.

Interior Courtyard Areas / Concrete Pavements – Concrete pavement will be demolished and replaced.

This work will occur sequentially, with demolition and replacement being complete before the work moves to the next Courtyard area. As part of this demolition, the existing concrete amphitheater stairs, retaining walls and planter walls will be removed. Grade in the current sunken lawn areas will be raised to the level of the pavements, using backfill from onsite crushed demolished concrete and imported soil.

Existing storm structures in the lawns will be raised to match new finish grades. One courtyard will have a new woven wire fence installed to facilitate canine training in that yard.

Interior Fenced Yards – To facilitate the new façade work and additional building renovation scope, work in the interior yards will include sawcutting and removal of asphalt and replacement with a 36”

Construction Manager/General Contractor Services Page 5 of 11

5 5 concrete strip. Additionally, removal of the existing fenced cage areas will be required to facilitate work and equipment and these shall be reinstalled or replaced in kind. Additionally, minimal fencing improvements at perimeter fenced yards will be required to facilitate façade work.

Other Site Improvements / Site Restoration – Additional asphalt improvements at the new Sallyport as well as at the perimeter drive will be made to accommodate entrance and improved turning radii. New mechanical equipment (chillers) to be installed outside of yard areas will require new heavy duty concrete pads and site work, including utility adjustments and site restoration. Existing gravel drives behind the Warehouse are likely required to have some additional surfacing and compaction to restore from construction activities. Lawn areas will be restored with fine grading and hydroseeding.

STRUCTURAL NARRATIVE

The structural scope of the building includes renovations of the existing structure, modifications to allow for a new HVAC system, and the addition of a second floor in one existing building.

Design Criteria:

• Building Risk Category III

• Floor Live Loads, reduced as allowed by code

• Roof Live Loads, reduced as allowed by code

• Ground Snow Load, pg = 15 pounds per square foot

Structure – Façade/Structure Repair/Replacement Housing Units/Guard Tower – The existing steel floor grating and steel mesh wall panels have deteriorated and will be replaced with new galvanized steel rectangular bar grating and galvanized mesh panels. The steel frame, stair structure, and handrail/guardrail system has degraded and will be blast cleaned and a new coating will be applied. Where any structural steel member has deteriorated to 10% section loss or more, it will be repaired. Doors at the 4 corners of the housing unit will be replaced and a structural header will be installed for the new door attachment. Concrete curbs will be added where needed for the architectural cladding.

Guard Shacks – A new concrete slab will be poured to support a prefabricated guard shack.

Salt Storage – A new retaining wall structure will be built south of the warehouse for the new salt storage area.

Exterior Cladding – The existing cladding around the perimeter of the Administration building will be replaced. Cold-formed steel framing is used to support the new cladding.

Administration Building – A new opening will be made with a steel lintel overhead and concrete stairs leading up to the opening.

Structure – HVAC Replacement Warehouse – A second floor will be added to the existing warehouse. Two sets of steel stairs and an elevator shaft will be constructed on micropile foundations. The second floor will consist of composite deck on steel beams supported by the existing steel columns. The existing coal dump will be infilled and a new slab will be poured flush with the existing floor. Some openings will be cut in the existing masonry wall for mechanical louvers; steel lintels will be installed over the new openings. Concrete curbs will be installed into the concrete slabs on each level around bathrooms. The existing slab will be cut and then

Construction Manager/General Contractor Services Page 6 of 11

6 6 patched to allow for the installation of new utility lines. The existing roof structure will be demolished at select locations where large holes were and a new roof with new steel beams will be installed.

Mechanical Units – Several mechanical units will be installed on roofs and floors of the administration building. Holes will be cut into the existing roof for duct access and reinforced with steel frames. Some joists and joist girders will be reinforced to account for the added loads; at some locations, new joists are added next to existing joists.

Dorm 9 – Mechanical access holes will be cut into the walls around the mechanical floor and later replaced when mechanical work is completed.

HVAC NARRATIVE

Existing chilled water plant in warehouse serves all buildings on site. This project will add chillers at each housing unit, administration building, and warehouse/minimum security prison. All supply ductwork has duct lining causing a lot of problems through the years. All ductwork will be replaced with exterior insulated ductwork. Boiler plant was decommissioned years ago, and boilers distributed throughout the buildings. All boilers will be replaced throughout. Control systems are not operable or totally missing. This project will replace all controls throughout all buildings.

A large quantity of spaces in administration building was only heated and ventilated. This project will add air conditioning to all shops, gyms, and spaces that were not previously conditioned. All air handlers will be replaced.

New Work – Administration Building

Area A and B Upper floor of Area A and Area B is served from air handlers in main mechanical room located on third floor of Area C. All existing ductwork, GRDs, and dampers will be removed and replaced with VAV with hot water reheat boxes. Generally, every office and space will be individually zoned with its own VAV box. Existing AHU units will be replaced with new VAV air handling units. The installation will consist of:

1. Demolition of all existing HVAC air handlers/ductwork/controls

2. New Air Handlers in new mechanical room

3. New ductwork and GRDs

4. New hot water piping to all VAV boxes from Central Heating Plant in main mechanical room

5. All new controls

Area A Lower Level Low level is served via an air handler in a lower mechanical room. This will be replace with a new VAV air Handler serving VAV boxes.

The installation will consist of:

1. Demolition of all existing HVAC air handlers/ductwork/controls

2. New Air Handler in lower mechanical room

3. New Ductwork and GRDS

4. New hot water piping to all VAV boxes from Central Heating Plant in the main mechanical room

5. All new controls

6. New Chilled water piping from main mechanical room.

Construction Manager/General Contractor Services Page 7 of 11

7 7

7. New Louver on exterior wall.

Area C Upper Level The main mechanical room on the third level will be totally renovated. All air handlers mostly multizone units will be replaced with new multizone units in similar locations. It is anticipated that these will be replaced one at a time to allow relocation of occupants in associated areas.

The installation will consist of:

1. Demolition of all existing HVAC air handlers, boilers, pumps and piping in this room

2. New Air Handlers that serve areas – A, B, C, H

3. New chilled water pumps

4. New hot water pumps zoned for each area

5. New boiler plant

6. New chillers.

7. All new controls

8. Existing rooftop outside air vents will be reused for new air handlers

Area C Second Level All areas on second level are served from multizone units on third level. All ductwork and GRDs will be replaced with new.

Area C Lower Level All areas on lower level are served from multizone units on third level. All ductwork and GRDs will be replaced with new

Areas G and F Existing Heating and Ventilation only air handlers sit of mezzanines. These and all ductwork and controls will be replaced in each shop area. Unit heaters in hallways will be replaced. The installation will consist of:

1. Demolition of existing air handlers and related ductwork and controls.

2. New air handlers equipped with chilled water coil, hot water coil, and reheat coil (for control of humidification in large space with minimum sensible load).

3. New ductwork and GRDs.

4. Reuse existing outside air vents on roof for new units.

5. New HVAC Controls with door interlocks to turn off chilled water coil when garage door is open.

6. New chilled water and hot water piping served from main mechanical room at top of Area C.

Area D Existing air handlers were generally heating and ventilation in the spaces. These are being changed to rooftop units with chilled water coils, hot water coils. The installation will consist of:

1. Demolition of existing air handlers and related ductwork and controls.

2. New air handlers equipped with chilled water coil, hot water coil, and reheat coil (for control of humidification in large space with minimum sensible load).

3. New ductwork and GRDs.

4. New HVAC Controls with door interlocks to turn off chilled water coil when garage door is open.

5. New chilled water and hot water piping served from main mechanical room at top of Area C.

Area E

Construction Manager/General Contractor Services Page 8 of 11

8 8

Existing segregated housing unit is served via a multizone air handler in second floor mechanical room with associated boiler and chilled water from central plant. This will all be removed and a new multizone rooftop unit will be installed over the mechanical room and it will be served via chilled and hot water from the main mechanical room in Area C. The installation will consist of:

1. Demolition of all existing ductwork, multizone units, boilers, pumps and controls.

2. New Rooftop unit to serve all areas of the building.

3. All new ductwork and GRDs

4. All new Controls

5. Return air fan and smoke control functions for entire system.

Area H Lower Level Area H lower level is the kitchen areas and work in that area is not in the scope of the project. Existing air handler in Area C main mechanical room and associated makeup air units will all remain as is.

However, new chilled and hot water piping will be installed through this area to reach areas J and K.

Area H Upper Level Area H upper level is served from air handlers in the main mechanical room in Area C. The installation will consist of:

1. Demolition of all existing ductwork and GRDs

2. Installation of all new ductwork and GRDs

Area J Lower Level Area J lower-level East side is served from an air handler in the main mechanical room in Area C. This will be replaced with a rooftop unit directly over East dining areas. The west side of Area J is currently served by an existing rooftop unit and replaced in same location.

The installation will consist of:

1. Demolition of ductwork, GRDs in all areas

2. New ductwork and GRDs in all areas

3. New rooftop units - RTU-1 and RTU-2

4. New Controls

5. New hot water piping to RTUs

Area K Area consists of gyms and small multipurpose rooms on gym floor level. Hot water is via boilers in mechanical rooms and chilled water serves a small air handler for the multipurpose rooms. The gyms are heated and ventilated. This project will replace all HVAC in these areas and convert gyms to air conditioning. The installation will consist of:

1. Demolition of all existing HVAC, air handlers, boilers, and pumps and piping.

2. New Air Handlers with chilled water and hot water. A reheat coil will be provided for humidity control.

3. All new ductwork and GRDs

4. Chilled water and hot water piping from main mechanical room in Area C

5. Reuse of outside air ventilators on roof.

New Work – Housing Units

Construction Manager/General Contractor Services Page 9 of 11

9 9

All four housing units are served by a mechanical room on level 5. Each wing’s four level area served via a multizone unit in the mechanical room. The return ductwork is connected to an exhaust fan that is smoke exhaust rated and each wing is grouped together for smoke exhaust system. Existing boilers will be replaced with new. Chilled water is via central plant now and will be removed via two new chillers installed this project. The installation will consist of:

1. Demolition of each air handler serving a wing and some miscellaneous rooms.

2. Two new chillers ground mounted.

3. New Chilled water piping connections to chillers and air handlers – some mains shall be reused.

4. New hot water piping connections to air handlers and all new for boilers – some mains shall be reused.

5. New boiler plant.

6. New chilled water and hot water pumps and hydronic specialties.

7. New Controls

8. Special Inspection commissioning of the smoke exhaust systems will be required.

9. Piping chase from exterior of the building at grade level to main mechanical room will have a wall removed in each story to allow new piping and electrical circuits to be installed. This will be later closed up upon completion of the project.

Existing Conditions – Warehouse and Minimum-Security Prison Building contains an abandoned coal central boiler plant and chiller plant between column lines JJ and MM. All this will eventually remove in this project to make room for a two-story training center. This building also houses large storage areas for food and suppliers for the entire prison as well as a connected Minimum Security Prison.

New Work – Warehouse and Minimum-Security Prison A new mechanical room will be built in the location of the existing chilled water plant that will house boilers, chilled water and hot water pumps that serve the entire facility. Two new chillers will be installed on the exterior wall of the new mechanical room to serve the entire facility. The installation will consist of:

1. LARGE DEMOLITION – of the existing coal fueled boiler plant including coal silos, and boilers.

The amount of work is large and a site visit to review existing conditions to obtain the true scope of demolition is strongly encouraged.

2. Replace air handlers in warehouse office area the serve the warehouse functions between column lines NN and OO.

3. Replace all ductwork and GRDs in office area between column lines NN and OO and entire minimum security prison.

4. Provide new multizone unit for minimum security prison. Provide return air fan rated for smoke control system. Entire minimum security prison shall have a smoke control system.

5. Special inspections of smoke exhaust systems will be required.

6. Remove and demo water towers, chillers, pumps and all controls for chilled water plant between column lines JJ and MM.

7. Provide new mechanical room in new training center with boilers, pumps, and chilled water pumps that serve the entire facility.

8. Provide new hot water piping from new mechanical room to minimum security prison mechanical room

9. Provide new VAV HVAC system for two story training center that includes hot water reheat VAV boxes.

Construction Manager/General Contractor Services Page 10 of 11

10 10

PLUMBING NARRATIVE

New Training Center at Warehouse All new DWV and Potable water system for the training center at the warehouse. This includes stacked restrooms, water heater, janitors’ closets on each floor and sanitary and potable water tie-ins to existing services. This is the only scope for plumbing on this project.

ELECTRICAL NARRATIVE

New Training Center at Warehouse Electrical for new training center is typical of a school type function with receptacles in classrooms and data ports liberally distributed throughout. New lighting throughout in drop gid ceilings. Large rooms on the first floor and second floor will be fit up for future program development. Electrical for all new systems and equipment in new mechanical room. The new Training center will also be provided with a new fire alarm system – voice annunciated.

There will be a lot of demolition of existing electrical where the old coal boiler plant and chilled water plant is being removed.

All new lighting in minimum security prison, training center, and warehouse office areas.

Administration Building Lighting – Anywhere ceilings are being removed and replaced as a result of the HVAC installation, the lighting will be replaced. It was noted that even though we are planning on a one for one replacement reusing existing circuits – many light circuit junction boxes are not attached to the building structure so there will be a lot of remediation work for lighting circuits.

Power – Generally throughout the entire project the electrical power work will be confined to removal of existing HVAC circuit to new circuits being adjusted as necessary if the amperages are different.

However, for the new 400-ton chillers being installed it will require that a 12470V to 480 Volt substation be installed on the roof near one of the chillers. There will be new work to the medium voltage equipment in the main mechanical room to accommodate this new circuit. This may be a long lead time and needs attention for phasing.

Fire Alarm systems will be modified by installation of new duct smoke detectors for air handlers that qualify.

FOUND ELECTRICAL CONDITIONS – An allowance may be needed for found electrical code violations encountered above ceilings when that work occurs. Many unit prices will need to be provided to apply against the items found in which the allowance will cover. This will also apply for the minimum-security prison, housing units, and office areas of the warehouse.

Housing Units Electrical work will be included for new boilers, pumps and air handlers. New circuits will be derived from the upper mechanical room to chillers installed at grade. Route of the circuits shall be through an existing pipe chase.

Construction Manager/General Contractor Services Page 11 of 11

11 11

Fire Alarm – Fire alarm work will include new duct smoke detectors and recommissioning of the smoke control systems with new HVAC equipment.

There are data cables present that will need to be replaced if not properly installed. This work if needed will be part of the electrical inspection allowance noted under Administration Building.

No new interior light fixture replacements are required for this building.

FIRE SUPPRESSION NARRATIVE

New Training Center at Warehouse Provide new riser and 100% wet coverage fire suppression system for the two story training center.

Administration Building Replace heads for new ceilings throughout. Provide new heads under ductwork 48” and larger.

Housing Units Provide new heads under new ductwork runs where ductwork is 48” and larger. Existing fire department connections are located at the piping chase in the corner of the building. These will be in conflict with the new chiller piping. The FDC’s will be relocated to the front of the stair tower for better fire department access.

Project Code Information

This project's Code Analysis is broken up by building; Administration, Housing Units and Warehouse.

The specific Code information for each building can be found on sheets G-003 and G-004 in Volume 1 for the Administration Building and Housing Units, and on sheet G-005 in Volume 2 for the Warehouse. The Codes used in the write up are as follows; 2018 Kentucky Building Code/2015 Internation Building Code, 2015 International Fire Code, 2022 Kentucky State Plumbing Law, 2015 International Mechanical Code, 2017 National Electrical Code, 2012 International Energy Code and 2009 International Code Council/ANSI A117.1. Additionally, the Warehouse Life Safety Plans for the fit up can be found on sheets A-W-001 and A-W-002 in Volume 2.

END OF NARRATIVE