Attachment_A_Statment_of_Work.docx
DOCX document 31 KB Posted
- Attached to
- EB Voltage Regulator Board Replacement Federal contract opportunity
- Solicitation number
- 140R4023Q0008
About this file
This statement of work describes a requirement for a voltage regulator board replacement project at the Elephant Butte Powerplant in New Mexico. The scope involves retrofitting three existing Basler ECS-2100 voltage regulators with current Basler DECS-2100 regulators, including removal and installation, commissioning, training, drawings and manuals. Additional replacement components and services such as startup testing and reports are also required. Bidders must be factory-trained Basler technicians able to provide certifications. The evaluation criteria emphasize technical specifications, warranty, delivery schedule and past performance on similar projects. Responses are due by October 1st and work must be completed between October 2023 and January 2024 under the supervision of the Bureau of Reclamation at the Elephant Butte Powerplant.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140R4023Q0008_Amd_0001.pdf | ||
| Questions_and_Answers_0001.docx | DOCX document | |
| Drawing_1_24-508-02864_01_00.pdf | ||
| Schedule_B_Pricing.docx | DOCX document | |
| Drawing_2_24-508-02865_02_00.pdf | ||
| Sol_140R4023Q0008.pdf | ||
| Submission_Instructions_to_Offerors.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work EB Voltage Regulator Board Replacement
BACKGROUND
Reclamation requires that the voltage regulators on all (3) generator units be refurbished. The current voltage regulators are Basler ECS-2100. The main processor chip on the Basler ECS-2100 is obsolete and cannot be repaired, replaced nor is it supported anymore and is a known point of failure. Reclamation is looking to replace the Basler ECS-2100 with the current Basler Regulator DECS-2100.
SCOPE
Retrofit the current Basler ECS-2100 voltage regulators with current Basler DECS-2100 voltage regulators. Vendor shall include all labor, parts, equipment to install, commission, and train personnel on the three generating units at Elephant Butte Field Division.
REQUIREMENT
Digital front end retrofit the current Basler ECS-2100 voltage regulators to DECS-2100 voltage regulator on generator units 1, 2, 3 with installation, commissioning, and training. This requirement must meet the following criteria:
1. Provide the current version of Basler BESTCOMS™ Pro Controller configuration tool
2. Auto tuning of control loops
3. Must use existing rectifier bridge
4. Plug and play replacement
a. Compatible with existing analog to digital I/O boards
5. All equipment must fit within existing equipment footprint see attached drawings. Drawings show unit 1 but dimensions are typical for all three units.
6. Research of the existing Generator Control System to finalize Installation Details.
7. Removal of the existing ECS2100 control equipment and Installation of the new Basler Electric DECS-2100 Front-End Retrofit.
8. Supply any additional cabinet wiring, which may be needed, with regard to the installation of the new Basler Electric Exciter System.
9. Provide the “Interface Design” of the new Systems including:
a. Provide all revisions to the existing Elementary System Drawing Package of the Generator Control and Voltage Regulator Systems.
b. Connection details for all new devices as supplied by contractor to be installed in the new Regulator Control Panel.
c. System Connection Drawings.
d. Wiring Lists of wires to be removed, wires to be reused and new wire to be added.
e. Interface details for direct connection of the new excitation equipment to the existing Control System and details on existing equipment to be removed from service.
f. Voltage Regulator Control System Settings.
g. Digital Documentation Package to include.
· a. Instruction Manuals for all equipment of the new Basler Electric Systems.
· b. As Built Digital Drawings (per above in items 9a – 9f), supplied in AutoCAD (dwg format).
· c. Startup Report, including all Software Settings.
10. Provide On-Site Turnkey Services by Basler factory trained Technical Expert with regard to the Installation, Connection and Interconnection of the new Basler Electric Systems.
a. Remove the ECS2100 equipment.
b. Install the new DECS-2100 Front-End retrofit in the existing exciter cabinet.
c. Interface with the existing Generator Control, Protection and Annunciator Systems.
d. Provide System Checkout / Testing of all new equipment, devices and interconnection cables.
11. Provide System Startup Services
a. Shut-down (Unit at standstill) checks with external equipment – DCS, Remote Switches, etc.)
b. Off-Line (Rated Speed No-Load) Set-Up and Testing of the new Voltage Regulator Control System.
c. On-Line (With Load) Set-Up and Testing of the new Voltage Regulator Control System
12. Provide the “final” System Startup Report with regard to the commissioning of the new Basler Electric Type DECS-2100 System.
13. On-Site Commissioning Tests
a. Pre-Excitation System Checks (Unit @ Standstill)
· Wire Checks / Ground Checks of the new System
· Control I/O Testing & Sequence Testing
· Loss of PT Signal Transfer Testing
· Excitation Simulation Checks (Dummy Load Test)
· Current & Voltage Signal Injection
· Unit Annunciation Alarm Checks
· DCS Interface Checks
· System “Trip” Tests
· DECS Module Software Setup
b. Off-Line, Full Speed No-Load System Checks
· AVR “Automatic Voltage Regulator” Start Sequence
· FCR “Field Current Regulator” Start Sequence
· AVR Step Response Testing & FCR Step Response Test
· Off-Line OEL Overexcitation Limiter Stability Step Test
· Saturation Curve Testing
c. On-Line System Tests
· AVR Step Response Test & FCR Step Response Test
· On-Line OEL Overexcitation Limiter Stability Step Test
· UEL Under-excitation Limiter Settings & Stability Step Test
14. In addition to the retrofit also include the replacement of the following devices, one for each unit (3 total each):
a. BCM-2, 2nd Generation Bridge Control Module
b. FGD-2, 2nd Generation Field Ground Detector Module
c. DXCB-2, 2nd Generation De-Excitation & Crowbar Module
d. AIOM-2, 2nd Generation Analog I/O Module
15. Include backups to all programs to include changes made during commissioning. Prior to leaving work site at project completion.
DELIVERABLES
The Contractor shall supply the Bureau of Reclamation with As-Built drawings for all work performed. These drawings shall be AutoCAD drawings in electronic format (.dwg file extension). Drawings shall be provided prior to Contractor leaving the site at the completion of the contract.
LOCATION
Delivery and installation will be at:
Elephant Butte Powerplant 4696 Hwy 51 Truth or Consequences, NM 87901
PERFORMANCE PERIOD
Contractor must provide lead time for all parts and estimated installation time.
Installation will occur during non-irrigation season, no sooner than October 1, 2023. Installation and commissioning must be completed before January 15, 2024.
WORK HOURS
Normal work hours are Monday through Thursday, except federal holidays, 7:00 a.m. to 4:30 p.m. If work needs to be done outside these hours the contractor must request for approval from the CO or COR in advance.
CLEANUP AND DISPOSAL OF WASTE MATERIAL
The contractor shall be responsible for all cleanup of waste materials or rubbish and will also be responsible for providing a dumpster and disposal of all waste materials. Disposal shall be in accordance with this paragraph and all applicable Federal, State, and local regulations, standards, codes and laws. Also, the requirements contained in the Bureau’s “Reclamation Safety and Health Standards” are applicable to clean up and to dispose waste materials and rubbish. In the event that there is a conflict between the requirements contained in this paragraph, the Bureau’s “Reclamation Safety and Health Standards”, and other Federal, State, or local regulations, standards, codes, and laws, the more stringent requirements shall prevail.
SITE CONDITIONS
Contractors will have access to water, electricity, and restrooms while on site. There will be no asbestos in any of the areas where the contractors will work.
SECURITY
All service locations under this contract are within secured areas. The COR will arrange for the Contractors entry into such areas and inform the Contractor of security procedures. The Contractor shall comply with all security procedures.
The Contractor shall supply the Bureau of Reclamation with the legal names of all employees who will be working under this contract. The Bureau of Reclamation reserves the right to run security checks on such employees. If, in the judgment of the Bureau of Reclamation, any employee fails to meet minimum security requirements or proves to be detrimental to the security of the Bureau of Reclamation facilities, the Contractor, upon request, shall remove such employee from any work under this contract.
Powerplant control room is a restricted access area and only can be entered if escorted by an authorized Reclamation employee.
CONTRACTOR QUALIFICATIONS
Must be Basler factory trained technicians to perform all work. The technicians should be able to provide Basler certifications or Basler Identification.
SUBMITTALS
· The offeror shall provide a complete data sheet of the product they are providing.
· Offeror shall provide a Delivery Schedule
· Offeror shall provide Warranty Details
· Offeror shall provide Past Performance examples. Minimum 5 references of similar projects completed.
QUOTE EVALUATION
Award will be made to the contractor offering the best value to the government considering Technical, warranty, delivery, and past performance.
Technical: Technical evaluations will include:
· Must use existing rectifier bridge
· All control loops must be capable of auto-tuning
· All equipment must fit within existing footprint
· Compatible with existing analog to digital I/O boards
Delivery: The best schedule for delivery of items under this quotation.
Warranty: Standard Manufacturer Warranty with stated items.
Past Performance: The quote will be evaluated to assess the experience of the Offeror with respect to projects similar in scope and size to the work described herein within the last (5) years.