Questions_and_Answers_0001.docx

DOCX document 13 KB Posted

Attached to
EB Voltage Regulator Board Replacement Federal contract opportunity
Solicitation number
140R4023Q0008
Issued by
Department of the Interior Bureau of Reclamation

About this file

This document contains questions and answers regarding a federal solicitation for voltage regulator board replacements on three electric generating units. The solicitation seeks to upgrade specific modules on each unit, with options available for additional digital and field transducer modules. Bidders must provide delivery timelines with equipment arriving by mid-November and all installation, commissioning, and verification work completed by February 29th. The Bureau of Reclamation will review bids submitted by June 9th and allow 30 days for evaluation, with purchase orders issued through a turnkey partner and an estimated 14-16 week lead time for equipment delivery thereafter.

View the file

Other files for this federal contract opportunity

Other files attached to EB Voltage Regulator Board Replacement, newest first.
File Type Posted
Sol_140R4023Q0008_Amd_0001.pdf PDF
Attachment_A_Statment_of_Work.docx DOCX document
Drawing_1_24-508-02864_01_00.pdf PDF
Schedule_B_Pricing.docx DOCX document
Drawing_2_24-508-02865_02_00.pdf PDF
Submission_Instructions_to_Offerors.docx DOCX document
Sol_140R4023Q0008.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation: 140R4023Q0008 Questions and Answers

1. There are modules listed to upgrade BCM-2, FGD-2, DXCB-2, and AIOM-2. There is no mention of the digital I/O module (DIO-2). There are four of these per unit. There is also not mention of the field transducer modules IT-2. There are two of those per unit. While these modules are NOT required they would be suggested if you are updating the rest. Should they just be listed as options? Yes lest list this as options. We also need to know how this will effect install and delivery time.

2. Can all three units be in outage at the same time? We would only do one unit at a time. Then do commissioning and verification of operation on that unit before moving on to the next one.

3. Just to let you know, if quotes are submitted by June 9 and BOR typically takes 30 days to review, and then it will typically take a couple of weeks for paperwork to filter thru our turnkey partner to get the PO to Basler for the equipment. Once Basler gets the PO for the equipment, the delivery lead time is 14-16 weeks. All of this will add up to equipment delivery early to mid November. This should still leave ample time for the install and commissioning. The deadline for all 3 units install, commissioning and verification of operation will be Feb. 29th. As long as they can meet this then we are good with this time frame.