RFQ # 140P8323Q0036
Attachment A: Statement of Work North Cascades National Park
Portable Water Tank
Cleaning and Video Inspection Service
PART 1: GENERAL
1-1 DESCRIPTION OF WORK
A. This contract provides services to inspect, clean, and repair minor leaks to the Parks six portable water tanks. The Environmental Learning Center water tank needs repair to fill pipe support. In service cleaning shall be performed prior to tank inspection.
B. The contract work includes:
1. Clean and inspect potable water tanks.
2. Video Inspection of potable water tanks. Video to be provided to Park.
3. Minor leak repairs, to include epoxy, gasket material or like materials/methods.
4. Waste material accumulated from tank cleaning will be disposed of at an approved facility or location pre-designated by COR.
5. Environmental Learning Center tank has broken supports that secure the fill pipe within the tank. At least two fiberglass Unistrut components will need to be repaired and/or replaced.
All six tanks will be kept in service while work is being done. Diving services will be necessary to ensure water services are not interrupted.
Identified repairs requiring more than the use of epoxy or like material will be approved by the
COR.
All sediment removed from the tanks will be disposed of in a location designated by COR.
Diving Technicians and associated in-tank equipment will be fully disinfected according to AWWA Standard C652-92
Work will be completed between the weekday hours of 7am and 4:30pm.
Contractor to provide the following:
1. Traffic Control in Park Roadways will be supplied by Contractor (if necessary).
2. Contractor will limit ‘off road’ use of equipment without COR approval.
3. Contractor will use Dive Maintenance Technicians certified in ASNT Non-Destructive testing.
4. Contractor is responsible for additional mobilization requirements to remote locations.
Attachment A: Statement of Work North Cascades National Park
5. Repair epoxy or like material.
6. Contractor will provide the Park with a viewable video inspection and a written report of findings, repairs, and any recommendations.
C. Delivery or Deliverables:
Video and written report shall be delivered to COR upon completion of project.
The report will include the following if applicable:
a. Nameplate Information.
b. Findings pertaining to condition of internal components (i.e., plumbing, vents, hatches, Cathodic system, etc.…).
c. Numeric representation of the percent of corrosion and/or damaged areas.
d. Color video illustrating each type of coating failure, the general condition of coating and substrate. video shall be clear, sharp, and definitive (interior video based on clarity of water in reservoir).
e. A report on coating failure analysis and the probable causes.
f. Report on pit depth and metal loss based on ASTM G 46-94 Standard Guide for Examination and Evaluation of Pitting Corrosion, measured in millimeters at significant corrosion modulation sites. Also calculated rate of metal loss and theoretical rate of penetration (if applicable).
g. A sample specification for repair or recoating of the interior and exterior if applicable.
h. Report referencing the various coating defects and causes reported.
i. Thickness and type of silt on the reservoir floor.
The Video shall be narrated with reference to the location of internal components and pertinent findings noted.
Final inspection will be conducted by COR to verify completion of service prior to invoicing.
All work will be performed under a single contract.
1-2 BACKGROUND
The mission of the National Park Service is to Preserve the Nations Parks and provide a quality experience for Park visitors. The goal of the Maintenance Department for North Cascades National Park is to ensure that Park infrastructure is maintained in a manor to support the Park Service Mission. This acquisition will ensure quality and safety of the Park’s potable water system for both the public and its employees.
Inspection, Cleaning, and Minor Repairs of the Park’s Six (6) Potable Water Tanks.
Preventive Maintenance to ensure that the Potable Water Tanks are clean and in proper working order.
1-3 LOCATION AND ACCESS
A. Location: The tanks are located in various sites within North Cascades to include:
Marblemount Administrative site, Newhalem Creek Campground, Colonial Creek Campground, ELC, Stehekin Landing, and Hozomeen Campground. Tank sizes include:
Attachment A: Statement of Work North Cascades National Park
1-4 PLACE OF PERFORMANCE
A. Four water storage tanks are located within the Ross Lake National Recreation Area along
Washington State Route 20:
a. Marblemount Water Tank: Turn north off SR 20 at Ranger Station Road near mile marker 105. Drive approximately 1 mile north to get to an administration area. The water tank is located beyond the admin site up a trail approximately ¼ mile. Park personnel will assist with powered toters to shuttle all necessary gear and equipment
b. Newhalem Water Tank: Turn south off SR 20 at milepost 120, just west of the town of
Newhalem. Drive approximately 0.6 miles toward the North Cascades Visitor Center, then turn left onto an unmarked gravel service road. The water tank is located approximately 0.3 miles from the turnoff. This water system is used seasonally, typically May through October.
c. Colonial Creek Campground: The unmarked gravel service road is located near SR 20 milepost 130, on the south side of the road between Colonial Creek crossing and the entrance to Colonial Creek Campground. The water tank is located approximately 0.2 miles from SR 20. A locked gate limits public access. This water system is used seasonally, typically May through October.
d. Environmental Learning Center: Turn north off SR 20 at milepost 127.5, drive across
Diablo Dam, then turn right and drive to the end of the road. The water tank is accessed by driving through the complex on a gravel service road approximately 0.4 miles from the main parking lot. The gate between the main parking lot and service road limits public access but is unlocked. This water system is used year-round.
B. There are two remote water storage tanks. One located in Hozomeen Campground which is at the northern end of Ross Lake next to the U.S./Canadian Border. The other is located within the Lake Chelan National Recreation Area, in the remote community of Stehekin:
Nominal Overflow Tank Location, Type Material Dimensions Height Capacity Level Area Marblemount Administrative Site
CIP reinforced concrete
13’-0” x 7’6” 13’-0” x 7’6” 10’- 0” 25,000
Gal 8.16 Ft 195 Sq Ft
Newhalem Creek Campground (2 Cells)
CIP reinforced concrete
28’-0” x 18’-0” 28’-0” x 18’-0” 12’- 0” 75,000
Gal
6.5 Ft
(49,012 Gal) 504 Sq Ft 504 Sq Ft
Colonial Creek Campground
Glass fused steel 25’-0” Diam 10’- 0” 36,000
Gal
9.3 Ft
(34,149 Gal) 491 Sq Ft
Environmental Learning Center
Glass Fused Steel 11’ Diam 56 41,000
Gal 55’ 6” 95 Sq Ft
Stehekin Landing CIP reinforced concrete 80’-6” x 20’-0” 11’- 0” 100,000
Gal
8.5 Ft
(102,371 Gal) 1610 Sq Ft
Hozomeen Campground
Glass Fused Steel 11.19’ Diam 33’ - 0” 23,000
Gal 98 Sq Ft
Attachment A: Statement of Work North Cascades National Park
Hozomeen:
a. Hozomeen Water Tank: From the upper loop of the Hozomeen campground there is a steep utility road the leads approximately 100 yards up to the water tank. This water system is used seasonally from May to September.
b. Hozomeen can be accessed via two routes. The first is to drive into Canada and up the
Trans-Canada Highway/BC-1 east to Hope, BC and then down the Silver Skagit Road and back into the U.S. Most of this road is dirt and is currently under construction due to flooding in 2021. The road will be intermittently closed due to construction needs so scheduling and communication will need to be done with the project contractor. The second way to access Hozomeen is via boat. This would require getting reservations with Ross Lake Resort and/or Seattle City Lights to get ferried across Diablo Lake, driven up the Ross Dam Road, and then ferried up Ross Lake (approximately 25 miles) to Hozomeen. It can not be counted on that there will be any vehicle support at Hozomeen to move gear/equipment the approximate 1 mile to the water tank from the dock. For closure information on Silver Skagit Road visit www.gov.bc.ca - Transportation and infrastructure projects - B.C. Highway Flood Recovery Projects - Silver Skagit Road - Province of British Columbia (gov.bc.ca).
c. Maps, description, accommodations, ferry rates and services may be viewed at www.nps.gov/noca/planyourvisit/hozomeen.htm, www.rosslakeresort.com, www.seattle.gov/city-light - In the community – Tours, Recreation, and Education – Skagit Tours and Recreation.
d. There is no cell coverage or internet in Hozomeen.
Stehekin:
a. Stehekin Landing: From the Stehekin Landing, which serves as the transportation hub for passenger ferries and barge transportation, take the gravel service road south. The water tank is located approximately 0.4 miles from the Landing, up the hill from the Golden West Visitor Center. This water system is used year-round.
b. Stehekin is completely disconnected from the national road network and is only accessible by boat, plane, barge, or trail. Maps, description, accommodations, and services may be viewed at http://www.nps.gov/noca/planyourvisit/stehekin.htm, www.lodgeatstehekin.com, www.stehekinvalley.com, and www.stehekin.com.
Passenger ferry rates and schedules can be found at www.ladyofthelake.com.
Information on barge transportation can be found by contacting Mountain Barge Services, LLC at (509) 682-2493.
c. Public phone service at Stehekin is limited to a single telephone requiring credit or calling card; cellular phone service is not available. Wi-Fi access can be purchased through the lodge.
See Figures 1 and 2 for water tank locations http://www.gov.bc.ca/ http://www.nps.gov/noca/planyourvisit/hozomeen.htm
Attachment A: Statement of Work North Cascades National Park
D. REQUIRED PERFORMANCE PERIOD
1. Project Completed No later than 9/30/23.
2. Submit project schedule for approval prior to mobilization.
3. Some scheduling may include working around different concessionaire operations to ensure their services do not impact the visiting public.
E. CONTRACTOR’S USE OF PREMISES
1. Confine on-site material storage, equipment and vehicle parking, and staging to areas specifically designated by the COR.
2. Keep job site clear of trash and debris. Dispose of any trash, debris and other unusable material legally at authorized facilities on non-Federal land.
3. On-site services such as electrical power, water, restrooms and telephones will be unavailable at the different project sites. Contractor shall make appropriate arrangements such as port-a-johns to accommodate their personnel.
4. Contractor shall make provisions to allow continued use of the general area outside the specific work zone.
5. Contractor shall comply with all applicable federal, state, and local requirements for protecting the safety of the Contractor’s employees, park staff, and the environment. In particular, all applicable OSHA standards shall be followed when working on the project site.
6. Contractor shall submit two (2) copies of the written safety plan to the CO prior to starting the job. The Safety Plan shall cover, at a minimum, safety procedures, identified hazardous conditions, and emergency contact information for all personnel on-site.
7. Preservation of Natural Features: Confine all operations to work limits of the project.
Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
a. Do not remove, injure, or destroy trees or other plants without prior approval.
b. Do not fasten ropes, cables, or guys to existing trees.
F. PARK-SPECIFIC CONDITIONS
1. Project-specific environmental compliance mitigations: The following items are required by the National Environmental Policy Act and shall be adhered to as applied to
Attachment A: Statement of Work North Cascades National Park this project. Other sections of this statement of work may describe these requirements in more detail.
a. Approval for any chemicals used for cleaning shall be approved by Lacey
Cunningham, Project Manager. Allow 14 days for review and approval.
b. Staging for equipment and materials shall be as designated by the COR.
c. All chlorinated water, sludge, debris and other waste generated by the cleaning and disinfecting methods shall be properly disposed of in accordance with current guidelines and regulations.
1-5 QUALITY ASSURANCE
1. All materials and methods used for this contract must meet or exceed the current local, state, and federal codes, standards, and regulations applicable to the contract work which includes American Water Works Association (AWWA) standard C652.
2. INDUSTRY STANDARDS/ CERTIFICATIONS
a. All work performed on this contract shall adhere to the most current standards of the following:
i. American Water Works Association (AWWA);
ii. U.S. Occupational Safety & Health Administration (OSHA);
iii. National Association of Corrosion Engineers International (NACE);
iv. Society for Protective Coatings (SSPC);
v. American Concrete Institute (ACI);
vi. Environmental Protection Agency (EPA);and,
vii. All State, local, and federal regulations related to the service performed.
3. All personnel performing work under this contract shall be trained and skilled in the trades required to complete the contract requirements. The Contractor shall meet the following minimum qualifications:
a. The Field Inspector shall have at least three (3) years of concrete water tank inspection experience.
4. The Contractor and/or subcontractor for this work shall demonstrate competence in water storage inspection cleaning and disinfection. All subcontractors shall be approved by the CO prior to starting work.
a. Contractor’s firm shall be an established Potable Water Tank Cleaning company
Attachment A: Statement of Work North Cascades National Park with a minimum of three (3) years’ experience with the preparation of specifications for tank rehabilitation and completely familiar with the specific requirements and methods needed for proper performance of this Contract.
b. Over the past three (3) years, Contractor shall have conducted a minimum of fifteen (15) inspections and cleanings of potable water tanks using those methods identified.
c. Contractor’s technical staff assigned to this Contract must have a minimum of one (1) year experience to perform any service under this contract.
d. Contractor shall provide project references for at least five (5) recent projects and the resumes of the field inspector and report preparer.
PART 2: MATERIAL
A. GENERAL
1. All cleaning compounds must be Environmental Protection Agency (EPA), Food and Drug Administration (FDA), and National Sanitation Foundation (NSF) approved.
2. Contractor will use environmentally preferred products whenever available, e.g.
Green Seal certified or equal.
3. Contractor will submit a list of the cleaning compounds, along with MSDS sheets, to the CO for review/approval prior to cleaning the tank(s).
PART 3: EXECUTION OF WORK
3-1 GENERAL
1. SERVICE INTERRUPTION
a. There are no utility services to the facilities.
2. SITE INVESTIGATION
The Contractor is responsible for investigating site conditions in the vicinity of the required work to ensure accessibility for required equipment, vehicles and personnel or any other obstacles or items which may increase time or cost of the work.
3. SERVICE WORK
Attachment A: Statement of Work North Cascades National Park
a. Service shall be performed in a professional manner in accordance with industry standard best practices.
b. All equipment introduced into the water shall be dedicated for potable water use only and must be disinfected in accordance with AWWA C652 standard and local codes.
3-1 INSPECTION AND EVALUATION OF WATER STORAGE FACILITIES
1. Contractor shall perform a comprehensive evaluation of the interior conditions of the tank:
a. Inspection(s) shall be conducted with each tank full and in service and shall be completed without causing disruption to the treatment or distribution system.
b. No confined space entry will be permitted without the CO’s or designee’s approval and an approved safety plan.
c. All equipment used in the tank must be sprayed with a chlorine solution, at a concentration of 200-mg/L, in accordance with AWWA C652.
d. Contractor shall provide high quality color (DVD) video/digital recording inspection of 100% of all internal surfaces, including the roof, walls, floor, hatches, joints, gaskets, etc. through closed circuit TV. Video recording shall have real time imprint. Video shall be taken within a timeframe of very low turbidity so as to get clearest picture.
e. Contractor shall provide adequate lighting to thoroughly document all surfaces with video under all conditions of water and surfaces.
f. The Field Inspector shall be on-site during the inspection and shall witness and narrate the underwater camera video footage.
g. The Field Inspector shall provide, recorded on the inspection video, any professional assessment and evaluation comments about the condition of the tank.
h. Contractor shall be able during the inspection to remove coatings and corrosion products on the internal submerged surfaces for direct examination of metal loss, pit depth and/or coating failure.
i. Contractor shall review, evaluate and provide a written report of any issues identified in the inspection.
2. The following items shall be inspected on each tank:
a. Condition of concrete or steel on the interior including approximate percent of cracking, corrosion, settling, type of failure, and locations of concentrated
Attachment A: Statement of Work North Cascades National Park spalling.
b. Corrosion of any exposed reinforcing materials.
c. Condition of any membrane covers, including flexibility and UV damage.
d. OSHA safety compliance of tank ladders and hatches.
e. Sanitary conditions of tank hatches, vents and other penetrations and interior plumbing.
f. Percentage of coating failure and corrosion on any coated surfaces.
g. Condition of foundation and anchors, visual inspection of obvious defects.
h. Water level sensors and associated wiring.
i. Seams, welds/bolted joints and integrity of previous repairs.
j. All other structural members not mentioned above.
k. Any other items required by the State of North Carolina potable water tank inspection codes.
3-2 CLEANING OF WATER STORAGE FACILITIES
1. Tank Cleaning
a. Contractor shall clean underwater surfaces to remove bio-growths, sediments, silt, sand, sludge buildup, etc.
b. Contractor shall thoroughly remove all accumulated bottom sediment and debris from all potable water storage water reservoirs.
c. All accumulated bottom sediment and debris shall be removed in a manner that does not compromise the tank integrity and/or coating system.
d. Cleaning work shall not cause disruption to the use or quality of the water.
e. The reservoir shall remain in operation while the cleaning is in progress. If shut down is necessary, it shall be for a minimal period.
f. Cleaning of the tank floor will be performed with a vacuum pump and rotary bristle brush or equal.
g. Cleaning shall remove the sediments while water system remains on-line.
h. Turbidity shall be minimal, preserving water quality.
Attachment A: Statement of Work North Cascades National Park
1. Disposal of Waste Materials
a. Contractor will coordinate with the COR to designate the appropriate discharge point for waste and debris material collected.
b. Sediment and water removed shall be pumped out of the structure to a COR designated discharge point.
c. Contractor must meet all EPA and OSHA guidelines in the proper handling and disposal of waste.
d. All debris removed from the tank(s) shall be disposed of in accordance with all applicable federal, state, and local requirements, including any de-chlorination requirements.
e. Neutralize all water-disposed from tanks being disinfected by treating with one of the chemicals listed in AWWA C652.
3-3 DIVER AND DIVING OPERATIONS
1. Any diving operations being proposed for this contract shall meet the following requirements:
a. All diving operations shall be conducted by certified commercial divers who have graduated from an Association of Commercial Diving Educators’ Approved Commercial Diving Course or equal. Alternatively, divers who have completed specialized military training i.e., Navy 1ST or 2nd Class Dive Courses or Master Dive School shall also qualify.
b. All dive team members shall have a current CPR & First Aid Card, 02
Administrator Card, and a complete diver physical within the past 24 months.
c. Contractor shall provide certificates of training for all personnel conducting diving operations.
d. All diving operations shall be conducted in accordance with OSHA 29 CFR.
e. All diving operations shall be conducted utilizing a totally encapsulated diving dress, diver hardhat with sealed neck dam, and a vulcanized rubber dry suit, all in good repair. A band mask shall be specifically prohibited for any instance but in an emergency.
f. The diver hard hat shall be equipped with operating voice communication to the surface.
g. All diver equipment and any other equipment introduced into the reservoir shall be dedicated for potable water operations, and further, shall be disinfected with no less than a 200 ppm chlorine scrub/spray prior to entry into the reservoir.
Attachment A: Statement of Work North Cascades National Park
h. Dive team shall be equipped with live color video with live voice recording (and associated lighting system) between diver and surface team, to allow for real-time surface monitoring of all diving activities and findings, as well as quality-control of the completed work.
3-4 ROV EQUIPMENT
1. Any Remotely Operated Vehicle (ROV) being proposed for this contract shall meet the following requirements:
a. Shall be dedicated for potable water use only and the Contractor shall provide a letter of certification stating the ROV is dedicated to potable water use inspection only.
b. ROV shall not contain any liquids that will contaminate the water. All thruster seal fluid shall be a food grade product.
c. Before placing ROV in potable water system, it shall be sanitized to meet AWWA Standard C652.
d. Shall be able to abrade the underwater surfaces to clean off corrosion products and loose concrete.
e. Shall be able to measure sediment depths on tank floor.
f. Shall have a zoom camera capable of extreme close up inspection as small as
1/32” and capability for long distance inspection of above water surfaces within the tank.
g. Shall be equipped with a vacuum pump and rotary bristle brush.
h. Shall be equipped with a power wire cleaning tool that can clean off all surface debris, corrosion products and failed coating to permit the inspector to see pits, cracks and weld corrosion.
i. Shall be equipped with adequate lighting for all conditions inside the tank.
3-5 PROJECT CLOSEOUT
A. CLEANUP
1. Remove all tools, equipment, excess materials, construction debris, and trash from the project site. Legally dispose of trash and debris at authorized facilities off Government property. Restore or refinish any surfaces damaged during performance of the contract work. Leave project site clean and ready for use at the time of final inspection.
2. Legally disposal of all excess and unusable materials at authorized disposal facilities.
B. FINAL INSPECTION AND ACCEPTANCE OF WORK
1. When all work including site restoration and cleanup has been completed, the Contractor
Attachment A: Statement of Work North Cascades National Park shall contact the COR to arrange the final inspection. The final inspection should be conducted by the COR within 5 working days after receipt of the Contractor’s request.
2. The Contractor will be notified of any deficiencies found during the final inspection.
After all deficiencies have been corrected and all required closeout submittals have been forwarded to the COR, the CO will issue a letter of final acceptance and request the release of claims.
3. Contractor shall supply a “Certificate of Performance” for each reservoir to the CO at the completion of the project. At a minimum, the Certificate will indicate the date of cleaning, the name of the servicing company, areas cleaned and those area(s) not cleaned.
4. Contractor shall submit four (4) copies of a detailed “Service Report” at the conclusion of the project to the CO (to include fully narrated DVD of the internal inspection). This Report shall indicate, but not be limited to, the following:
a. Job site location and address
b. Date and time of cleaning
c. Type of tank
d. Name and certificate number of the technician(s)
e. Measurements and recording of bottom sediment depth
f. A high resolution, DVD video/digital recording providing a detailed review of structural concrete, steel, landings, etc. of the interior of the structure
g. Digital photos of ladders, piping (above ground), hatches, vents and all other structural/ mechanical components
h. Recommended next service due date
i. Identify any mechanical, accessibility, and safety concerns
j. Identify any tank defects and recommendations for repair or upgrades
k. Identify in detail which component(s) is in need of repair/replacement/upgrade
l. Identify all repairs or upgrades needed to ensure the tank is in proper working order according to AWWA standards
m. A detailed cost estimate for any repair/upgrades found in the inspection/cleaning process.
Attachment A: Statement of Work North Cascades National Park
n. Contractor shall provide a schematic diagram of each tank showing the location of each problem area with corresponding still color image.
o. Contractor will provide detailed information and recommendations to maximize the serviceable life of each tank and provide information for possible modifications to improve operational effectiveness.
| 1-1 DESCRIPTION OF WORK |
| 1-2 BACKGROUND |
| 1-3 LOCATION AND ACCESS |
| 1-4 PLACE OF PERFORMANCE |
| A. Four water storage tanks are located within the Ross Lake National Recreation Area along Washington State Route 20: |
| a. Marblemount Water Tank: Turn north off SR 20 at Ranger Station Road near mile marker 105. Drive approximately 1 mile north to get to an administration area. The water tank is located beyond the admin site up a trail approximately ¼ mile. Park perso... |
| b. Newhalem Water Tank: Turn south off SR 20 at milepost 120, just west of the town of Newhalem. Drive approximately 0.6 miles toward the North Cascades Visitor Center, then turn left onto an unmarked gravel service road. The water tank is located app... |
| c. Colonial Creek Campground: The unmarked gravel service road is located near SR 20 milepost 130, on the south side of the road between Colonial Creek crossing and the entrance to Colonial Creek Campground. The water tank is located approximately 0.2... |
| d. Environmental Learning Center: Turn north off SR 20 at milepost 127.5, drive across Diablo Dam, then turn right and drive to the end of the road. The water tank is accessed by driving through the complex on a gravel service road approximately 0.4 m... |
| B. There are two remote water storage tanks. One located in Hozomeen Campground which is at the northern end of Ross Lake next to the U.S./Canadian Border. The other is located within the Lake Chelan National Recreation Area, in the remote community ... |
| Hozomeen: |
| a. Hozomeen Water Tank: From the upper loop of the Hozomeen campground there is a steep utility road the leads approximately 100 yards up to the water tank. This water system is used seasonally from May to September. |
| b. Hozomeen can be accessed via two routes. The first is to drive into Canada and up the Trans-Canada Highway/BC-1 east to Hope, BC and then down the Silver Skagit Road and back into the U.S. Most of this road is dirt and is currently under constructi... |
| c. Maps, description, accommodations, ferry rates and services may be viewed at www.nps.gov/noca/planyourvisit/hozomeen.htm, www.rosslakeresort.com, www.seattle.gov/city-light - In the community – Tours, Recreation, and Education – Skagit Tours and Re... |
| d. There is no cell coverage or internet in Hozomeen. |
| Stehekin: |
| a. Stehekin Landing: From the Stehekin Landing, which serves as the transportation hub for passenger ferries and barge transportation, take the gravel service road south. The water tank is located approximately 0.4 miles from the Landing, up the hill ... |
| b. Stehekin is completely disconnected from the national road network and is only accessible by boat, plane, barge, or trail. Maps, description, accommodations, and services may be viewed at http://www.nps.gov/noca/planyourvisit/stehekin.htm, www.lodg... |
| c. Public phone service at Stehekin is limited to a single telephone requiring credit or calling card; cellular phone service is not available. Wi-Fi access can be purchased through the lodge. |
| See Figures 1 and 2 for water tank locations |
| D. REQUIRED PERFORMANCE PERIOD |
| E. CONTRACTOR’S USE OF PREMISES |
| F. PARK-SPECIFIC CONDITIONS |
| 1-5 QUALITY ASSURANCE |
| A. GENERAL |
| 3-1 GENERAL |
| 2. SITE INVESTIGATION |
| 3. SERVICE WORK |
| 3-1 INSPECTION AND EVALUATION OF WATER STORAGE FACILITIES |
| 3-2 CLEANING OF WATER STORAGE FACILITIES |
| 3-3 DIVER AND DIVING OPERATIONS |
| 3-4 ROV EQUIPMENT |
| 3-5 PROJECT CLOSEOUT |
| B. FINAL INSPECTION AND ACCEPTANCE OF WORK |