Attachment_A_Specifications.pdf
PDF 2 MB Posted
- Solicitation number
- 140P8324R0008
About this file
This document is an attachment to a federal contract opportunity to replace a wastewater lift station at the Longmire Visitor's Center in Mount Rainier National Park.
The key details are:
- This is a project to replace an existing wet-well / dry-well style lift station with a new submersible style lift station to eliminate permit-required confined space entry.
- The work includes demolition and removal of the existing lift station, construction of the new lift station with associated electrical systems, valving, meter, pre-cast concrete vaults, and piping.
- The project is located within Mount Rainier National Park and the contractor must comply with park regulations regarding vehicle access, working hours, staging, resource protection, and safety requirements.
- The contractor must submit various plans and schedules for review, including a Construction Schedule, Quality Control Plan, Accident Prevention Plan, and Under-An-Acre Pollution Prevention Plan.
- Payment will be made on a lump sum basis for the complete lift station replacement.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment_F_site_visit_discussion_notes_140P8324R0008_0001.pdf | ||
| Sol_140P8324R0008_Amd_0001.pdf | ||
| Attachment_E_Form_4_Limitations_on_Subcontracting_Worksheet.xlsx | XLSX spreadsheet | |
| Sol_140P8324R0008.pdf | ||
| Attachment_C_DOL_Wage_Determination.pdf | ||
| Attachment_D_Forms_to_Return_with_Proposal.docx | DOCX document | |
| Attachment_B__Drawings.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MORA – 249788 TOC - 1
TABLE OF CONTENTS
DIVISION, SECTION & PARAGRAPH NUMBERING
Numbering and lettering of sections and paragraphs in this Project Manual are merely for identification.
Sections included are listed in this Table of Contents together with the number of pages in each section.
The Contractor shall check their copies of the Project Manual against this Table of Contents and confirm there are no missing pages or sections.
Number Title No. of Pages
00 00 20 Table of Contents
00 00 40 Contract Bid Schedule
DIVISION 01 - GENERAL REQUIREMENTS NO. OF PAGES
01 11 00 Summary of Work
01 11 40 Work Restrictions
01 27 00 Definition of Contract Price Items
01 31 00 Project Management & Coordination
01 32 16 Construction Schedule
01 33 23 Submittal Procedures
01 35 13.22 Archeological Protection
01 35 23 Safety Requirements
01 40 00 Quality Requirements
01 50 00 Temporary Facilities & Controls
01 57 23 Stormwater Pollution Prevention
01 73 40 Execution
01 74 19 Construction Waste Management & Disposal
01 77 00 Closeout Procedures
01 78 23 Operation & Maintenance Data
01 79 00 Demonstration & Training
Appendix A – Submittal List
Appendix B – Closeout List
DIVISION 02 – EXISTING CONDITIONS
02 05 00 General Site Construction Requirements
02 23 00 Clearing & Grubbing
02 41 00 Demolition & Abandonment
02 41 19 Selective Demolition
MORA – 249788 TOC - 2
DIVISION 03 - CONCRETE
03 11 13 Cast-In-Place Concrete Forms
03 15 10 Concrete Accessories – Epoxy Anchors
03 21 00 Concrete Reinforcing Steel
03 30 00 Cast-In-Place Concrete Site Elements
03 31 00 Normal Weight Structural Concrete
03 40 00 Precast Concrete Items
DIVISION 04 – MASONRY (Section not used)
DIVISION 05 – METALS (Section not used)
DIVISION 06 – WOOD, PLASTICS, & COMPONENTS (Section not used)
DIVISION 07 – THERMAL & MOISTURE PROTECTION (Section not used)
DIVISION 08 – OPENINGS
08 31 00 Access Doors & Frames
DIVISION 09 - FINISHES
09 90 00 General Painting & Coating Requirements
09 97 13.23 Exterior Painted Iron & Steel
DIVISION 10 – SPECIALTIES (Section not used)
DIVISION 11 – EQUIPMENT (Section not used)
DIVISION 12 – FURNISHINGS (Section not used)
DIVISION 13 – SPECIAL CONSTRUCTION (Section not used)
DIVISION 14 – CONVEYING EQUIPMENT (Section not used)
DIVISION 21 – FIRE SUPPRESSION (Section not used)
MORA – 249788 TOC - 3
DIVISION 22 - PLUMBING
22 00 00 Plumbing General Requirements
22 11 23.36 Pumps
DIVISION 26 - ELECTRICAL
26 00 00 Electrical General Requirements
26 05 00 Common Work Results for Electrical
26 05 19 Low Voltage Electrical Power Conductors & Cables
26 05 26 Grounding & Bonding for Electrical Systems
26 05 29 Hangers & Supports for Electrical Systems
26 05 33 Raceways & Boxes for Electrical Systems
26 05 48 Seismic Requirements for Electrical Systems
26 05 53 Identification for Electrical Systems
26 22 00 Low Voltage Transformers
26 24 16 Panelboards
26 27 26 Wiring Devices
26 28 13 Fuses
26 28 16 Enclosed Switches & Circuit Breakers
DIVISION 27 – COMMUNICATIONS (Section not used)
DIVISION 28 – ELECTRONIC SAFETY & SECURITY (Section not used)
DIVISION 31 – EARTHWORK
31 10 00 Site Clearing (general)
31 22 19 Finish Grading
31 23 16.10 Importing Soils & Fill Materials
31 23 16.13 Rock Removal
31 23 19 Dewatering
31 23 33 Utility Excavation & Backfill
31 23 33.20 Restoration of Surfaces
31 25 00 Erosion & Sediment Control
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 11 23 Aggregate Base Course
MORA – 249788 TOC - 4
DIVISION 33 – UTILITIES
33 00 00 Pipe & Pipe Fittings – General Statement
33 01 10.71 Emergency Overflow Wastewater Storage Tank
33 01 30.13 Sewer & Manhole Testing
33 01 30.63 Polyurea Interior Coating
33 05 13 Manhole Structures
33 05 26.16 Utility Line Identification Marking
33 09 30 Sewer Flow Measurement & Pressure Gauge
33 31 13 Sanitary Sewer Pipe
33 32 13.13B Sewage Lift Station Upgrade (Longmire)
DIVISION 34 – TRANSPORTATION (Section not used)
DIVISION 35 – WATERWAY & MARINE CONSTRUCTION (Section not used)
DIVISION 40 – PROCESS INTEGRATION (Section not used)
DIVISION 41 – MATERIAL PROCESSING & HANDLING EQUIPMENT (Section not used)
DIVISION 42 – PROCESS HEATING, COOLING, & DRYING EQUIPMENT (Section not used)
DIVISION 43 – PROCESS GAS & LIQUID HANDLING, PURIFICATION,
& STORAGE EQUIPMENT (Section not used)
DIVISION 44 – POLLUTION CONTROL EQUIPMENT (Section not used)
DIVISION 45 – INDUSTRY – SPECIFIC MANUFACTURING EQUIPMENT (Section not used)
DIVISION 46 – WASTEWATER EQUIPMENT (Section not used)
DIVISION 48 – ELECTRICAL POWER GENERATION (Section not used)
DIVISION 01
GENERAL REQUIREMENTS
MORA – 249788 01 11 00 - 1
SUMMARY OF WORK
SECTION 01 11 00
PART 1 – GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
Project Location: This project is located within the Mount Rainier National Park at the Longmire
Visitor’s Center.
A. The Work consists of the following: This project is to replace a wet-well / dry well style lift station (Longmire) in the Longmire Visitor’s Center. The existing lift station is located in permit-required confined spaces, with pumps and piping located in below ground vaults and controls located in NEMA enclosures on the surface. The existing lift station will be replaced with a new submersible style lift station that eliminate permit-required confined space entry for normal operations.
1.2 GOVERNMENT-FURNISHED ITEMS
A. The Government may furnish products and materials for incorporation into the work.
1. The government will arrange and pay for delivery of government furnished items to the project site based on the contractor’s approved construction schedule.
2. After delivery, the government will inspect delivered items for damage. If items are damaged, defective, or missing, the government will arrange for replacement.
3. The contractor is responsible for receiving, unloading, and handling government furnished items at project site for use in the work.
4. The contractor is responsible for protecting government furnished items during storage, handling, and the work, including damage from exposure to the elements.
5. If government furnished items are damaged as a result of the contractor’s operations, the contractor shall repair or replace the items in-kind.
B. Government-Furnished Items: The government will furnish the following products or materials for use on this contract: NONE ANTICPATED
1.3 PUBLIC USE OF THE SITE
A. General: The project site at Longmire Visitor’s Center will be not be closed to the public during the construction of this lift station. The sewer system will still be in use during the construction period. The contractor shall at all times conduct his operations to ensure the least inconvenience to the public. Temporary closures may be permitted upon specific written approval of the Contracting Officer (CO).
MORA – 249788 01 11 00 - 2
1.4 CONTRACTOR USE OF SITE
A. General: Limit use of the site during the construction period to the project area limits as outlined in the plans. Do not disturb portions of the site beyond the project area limits.
B. Park Entry: The contractor shall furnish a list of personnel with phone contact information.
Vehicles associated with the contractor shall be waived entrance fee upon entering in a marked company vehicle or by providing the names of employees entering in personal vehicles. The entrance fee is waived only for the purpose of reporting directly to a specific work location.
Any deviation for recreational purposes is subject to payment of required entrance fees.
C. Site Access: The contractor shall access the project site as outlined on the attached site map.
Do not drive vehicles off road or access non-project areas without permission from the
Contracting Officer or Park Superintendent.
D. Park Regulations: Ensure all personnel (contractors, subcontractors, and vendors) entering or working in the Park are familiar with and obey all Park regulations. Law enforcement rangers will intervene if they perceive any unsafe or unlawful activity.
E. Working Hours: Regular work hours shall be limited to daylight hours from 7:00 AM until
5:00 PM, Monday through Friday, excluding government holidays. Work outside regular hours requires approval from the CO.
F. No Smoking Policy: Smoking is prohibited inside or outside within twenty-five (25) feet of any buildings in the Park. This applies to existing buildings, buildings under construction, and buildings under renovation. Discarding of tobacco products or debris anywhere other than into designated tobacco receptacles is considered littering and subject to fines.
G. Staging and Storage: Confine storage of equipment and materials to the staging / lay-down / storage areas identified on the attached site map or as established at the preconstruction meeting.
H. Parking: The contractor shall park vehicles and heavy equipment in designated areas for contractor use or as established at the preconstruction meeting. Vehicles are not permitted within long-term or overnight parking along roads or in associated overlooks / pull-outs.
I. Driveways and Entrances: The contractor shall keep driveways and entrances serving the premises clear and available to the government, government employees, and emergency vehicles at all times.
J. Preservation of Natural Features: Prevent damage to natural surroundings. Restored damaged areas and replace damaged trees, vegetation, and grass at no expense to the government. Park service will remove any trees deemed necessary for project.
K. Refer also to Section 01 11 40 Work Restrictions and Section 01 50 00 Temporary Facilities &
Controls.
MORA – 249788 01 11 00 - 3
L. The contractor shall be allowed to use Longmire’s designated staging area for a staging/laydown area during construction of the lift station. The designated staging area will be determined by the Contracting Officer.
M. The contractor can use campsites across the river at Longmire for overnight camping. The use of the camping area needs to be coordinated with and approved by the Contracting Officer.
1.5 REFERENCE DOCUMENTS / REPORTS
A. General: The following reference documents / reports are available upon request to supplement the information specified in the contract documents: NOT APPLICABLE.
END OF SECTION
MORA – 249788 01 11 40 - 1
WORK RESTRICTIONS
SECTION 01 11 40
1.1 PARK REGULATIONS
A. General: The Contractor must comply with the following rules and conditions:
1. Ensure personnel (contractors or subcontractors) working in the Park become familiar with and obey all Park regulations, wear hard hats in designated areas, and do not enter any restricted areas unless required to do so and until cleared for such entry.
2. Ensure equipment is conspicuously marked for identification.
3. The Contractor shall restrict employees / representatives to the work site and control travel directly to and from the work site.
4. Restore all traffic / parking / security signs and markings, including space numbers, designations, and lines, to their original form if such signs / markings are defaced or deleted during construction / repair.
5. Control and provide security of Contractor-owned equipment and materials at the work site. Report immediately missing / lost / stolen property to the Park Dispatch / Law
Enforcement Rangers at 360-569-6600.
6. Vehicles associated with the Contractor shall be waived the entrance fee upon entering in a marked company vehicle or by providing the names of employees entering in personal vehicle(s). Please note that the entrance fee is waived only for the purpose of reporting directly to a specific work location. Any deviation for recreational purposes is subject to payment of required entrance fees.
a. Contractor will provide the Contracting Officer (CO) with a listing of its subcontractors and their associated vehicles and employees entering the Park on a daily basis.
b. Contractor will provide the CO with a listing of anticipated deliveries for each week.
7. Vehicles / Heavy Equipment:
a. Rules of the Road: All vehicles and heavy equipment will comply with posted traffic regulations, including speed limits and double-yellow center lane markings.
Vehicles and heavy equipment shall take every safe opportunity to use paved roadside pullouts in order to allow faster moving traffic to pass. Failure to comply with traffic regulations will result in a citation being issued to the driver.
b. Vehicle Parking: Vehicles are not permitted within long-term or overnight parking along Park roads or in associated overlooks / pullouts. Vehicles and heavy equipment will be permitted at designated parking areas only.
c. Vehicle Exhaust: All vehicles will be properly maintained to insure that the exhaust produced is within legal limits. Effects of excessive vehicle exhaust may be subject to enforcement of State and Federal laws regarding emissions as well as those regarding threatened and endangered species.
d. Spills: Contractor shall be responsible for any cleanup efforts required in accordance with 40 CFR and all applicable state environmental quality laws regarding disposal and cleanup of hazardous / industrial wastes. Contractor must immediately notify the CO of spills.
MORA – 249788 01 11 40 - 2
e. Commercial Vehicle Safety Inspections: The Contractor, employees, contractors, and subcontractors shall fully cooperate regarding safety inspections of commercial vehicles within the Park. Commercial vehicle safety inspections are conducted unannounced for employee and visitor safety. Vehicles are checked for safety and mechanical deficiencies and for compliance with current state and federal laws and regulations. Driver licenses and medical certificates are also checked.
f. Department of Transportation (DOT) Compliance: All vehicles are to be compliant with all DOT requirements including but not limited to driver with appropriate license class, medical examiner card as appropriate with license class, carrying three
(3) triangles or three (3) flares, mounted fire extinguisher, and valid DOT safety sticker.
g. Slow Vehicles: The Contractor is to notify the CO of slow vehicles that may cause traffic delays or extended traffic lines. Vehicles that are slow are requested to enter the Park AFTER 2:00 PM and exit the Park BEFORE sunset.
h. Oversized Vehicles: Oversized vehicles are defined as vehicles where the width of the vehicle or load exceeds one lane (i.e., beyond the center line of the paved road).
Oversized vehicles must not exceed the clearances along the Park road corridor.
Oversized vehicles will require an escort and drivers must avoid driving on the edges of the Park road. The Contractor is to notify the CO of oversized vehicles, scheduled dates and estimated arrival times at the Park entrance, and the identity of who is escorting the vehicle (e.g., police, contractor, etc.). Vehicles that are oversized are requested to enter the Park AFTER 2:00 PM and exit the Park BEFORE sunset.
i. Road Work: Contractor shall provide adequate traffic control, including flaggers on either side of any work performed on the road. Any workers on or near the road must wear highly visible, bright clothing. (See Section 01 50 00 for additional details).
j. Law Enforcement: Law Enforcement Rangers will intervene if they perceive any unsafe or unlawful activity. Contractor must immediately comply with any instructions issued by a Park Law Enforcement Ranger.
k. Road & Weight Restrictions: All vehicle load, weight and size limitations, as established by State law, apply to vehicles operated on the Park road (36 CFR §
4.11). No loads heavier than the current load rating for the historic Park bridge(s) will be permitted.
8. Emergency Medical and Accident Reporting:
a. The Contractor or subcontractor shall contact Park Dispatch for any medical emergency or traffic accident occurring within the Park.
1) Emergency number: Dial 911 as needed.
2) Park Dispatch: 360-569-6600
3) Park Dispatch is called so that the entrance station will be prepared should any emergency vehicles (e.g. ambulance) need to enter the Park and so that any available Emergency Medical Services personnel in the Park might respond until such time as the ambulance arrives.
b. The Contractor or subcontractor is required to report ANY personal injury and / or property damage incident occurring within the Park. This report must be made to a
Law Enforcement Ranger at the first available opportunity before leaving the Park:
1) Park Dispatch: 360-569-6600
MORA – 249788 01 11 40 - 3
1.2 RESOURCE PROTECTION
A. General: The Park is committed protecting natural and cultural resources found within the
Park and adjacent lands. The Contractor must comply with the following rules and conditions:
1. Invasive Species: The introduction of non-native invasive species can threaten rare and endangered species or can create new populations of non-native species not traditionally found in the Park. The contractor is required to inform personnel, subcontractors, and vendors to thoroughly clean all vehicles, equipment, tools, supplies, and materials prior to entrance into the Park.
2. Endangered Species: Endangered species are protected by Federal law. Obey all Park regulations. Drivers must obey all traffic laws and keep an eye out for animals on or alongside road. Contact Park Dispatch at 360-569-6600 immediately if animal is hit or injured or will not move off of the road.
3. Soundscape / Noise: The contractor shall minimize noise levels at the project site to protect the soundscape of the Park. Perform noise-producing work in less sensitive hours of the day or week or as directed by the CO.
MORA – 249788 01 27 00 - 1
DEFINITION OF CONTRACT PRICE ITEMS
SECTION 01 27 00
DEFINITION OF CONTRACT PRICE ITEMS
1.1 LIST OF CONTRACT LINE ITEMS
A. Contract Price Item No.1 – (Longmire Lift Station).
1. This price item consists of furnishing all materials, equipment and labor for the demolition and removal of the existing Longmire lift station, and construction of a new submersible lift station, with associated electrical systems, valving, meter, pre-cast concrete vaults, precast concrete emergency overflow tank and piping to connect to the existing gravity and pressure sewer systems. Installation involves open cut pit and trench work and associated excavation, rock excavation, tree stump removal and disposal, electrical, native soil surface restoration, debris removal and disposal.
2. Park Service will remove trees where necessary.
3. No separate measurement will be made.
4. Payment will be made per lump sum.
1.2 LIST OF CONTRACT BID OPTIONS
A. Not used.
MORA – 249788 01 31 00 - 1
PROJECT MANAGEMENT & COORDINATION
SECTION 01 31 00
1.1 SUBMITTALS
A. Division 01 documents: The following items shall be submitted a minimum of one week prior to the Preconstruction Conference. Contracting Officer (CO) will notify Contractor of tentative date for the Pre-Construction Conference.
1. Letter designating Project Superintendent.
2. Construction Schedule.
3. A comprehensive breakdown of the Schedule of Values.
4. Accident Prevention Plan.
5. A list of Subcontractors for this project.
6. Written statements from subcontractors certifying compliance with applicable labor standard clauses.
7. Satisfactory evidence of liability insurance coverage and workman’s compensation for the Contactor and all subcontractors.
B. All items listed must be provided to the CO before the Pre-Construction Conference is held. If all of these documents have not been received one week prior to the scheduled Pre-Construction
Conference date, the conference will be cancelled, Notice to Proceed will not be issued, and the CO will consider other contractual remedies. Work shall not commence until written
Notice to Proceed has been issued
1.2 REQUESTS FOR INFORMATION (RFIs)
A. General: On discovery of the need for additional information or interpretation of the Contract
Documents, the Contractor shall prepare and submit an RFI utilizing the form designated by the CO.
1. CO will not respond to RFIs submitted by other entities controlled by Contractor.
2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:
1. RFI number, numbered sequentially.
2. Date.
3. RFI subject.
4. Specification Section number and title and related paragraphs, as appropriate.
5. Drawing number and detail references, as appropriate.
MORA – 249788 01 31 00 - 2
6. Contractor's suggested resolution. If Contractor's suggested resolution impacts the
Contract Time or the Contract Sum, Contractor shall state impact in the RFI.
7. Contractor’s signature.
8. Requested date for response.
9. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop
Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, and details of affected materials, assemblies, and attachments on attached sketches.
C. Contracting Officer’s Action: CO will review each RFI, determine action required, and respond. CO will determine the critical nature of each RFI and issue a response accordingly.
1. The following are not considered to be RFIs and will receive no action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor's means and methods.
d. Requests for coordination information already indicated in the Contract
Documents.
e. Requests for adjustments in the Contract Time or the Contract Sum.
f. Requests for interpretation of Architect's/Engineer’s actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
2. Contracting Officer's action may include a request for additional information, in which case time for response will date from time of receipt of additional information.
3. Contracting Officer's action on RFIs may result in the need for a change to the Contract
Time or the Contract Sum. All contract changes will be processed following the terms and conditions of the contract.
MORA – 249788 01 31 00 - 3
REQUEST FOR INFORMATION # __
Project:
Contract No: Date:
To:
Cc:
From:
Subject:
Please provide the following information or clarification:
Response required by: ____\____\____
Date:
To:
From:
Subject:
MORA – 249788 01 32 16 - 1
CONSTRUCTION SCHEDULE
SECTION 01 32 16
PART 1 - GENERAL
1.1 SUMMARY
A. This Section consists of Construction Schedule requirements including but not limited to the following:
1. Schedule of Values
2. Construction Schedule Requirements.
3. Construction Schedule Updates.
B. Purpose: The purpose of the Construction Schedule is to ensure adequate planning, coordination, scheduling, and reporting during execution of the work by the Contractor. The
Construction Schedule will assist the Contractor and Contracting Officer (CO) in monitoring the progress of the work, evaluating proposed changes, and processing the Contractor's monthly progress payment.
1.2 SUBMITTALS
A. Schedule of Values: After contract award and before the Pre-Construction conference submit a schedule of dollar values based on the Contract Price Schedule.
B. Construction Baseline Schedule: After contract award and before the Pre-Construction conference, submit a baseline schedule, large enough to show entire schedule for entire construction period.
C. Construction Schedule Updates: Prior to the progress payment request date, submit estimates of the percent completion of each schedule activity and necessary supporting data.
1.3 COORDINATION
A. Coordinate Construction Baseline Schedule with the Schedule of Values, list of subcontracts, payment requests, and other required schedules and reports.
MORA – 249788 01 32 16 - 2
PART 2 - PRODUCTS
2.1 SCHEDULE OF VALUES
A. Breakdown each lump-sum item into component work activities used in the schedule, for which progress payments may be requested. The work activities broken out within the schedule of values shall be integrated into and made a logical part of the construction baseline schedule submitted under this specification. The total costs for the component work activities shall equal the contract price for that lump-sum item. The CO may request data to verify accuracy of dollar values. Include mobilization, general condition costs, overhead and profit in the total dollar value of unit price items and in the component work activities for each lump-sum item. Do not include mobilization, general condition costs, overhead or profit as a separate item.
B. Do not break down unit price items. Use only the contract price for unit price items.
C. The total cost of all items shall equal the contract price. The Schedule of Values will form the basis for progress payments.
D. An acceptable Schedule of Values shall be agreed upon by the Contractor and CO before the first progress payment is processed.
2.2 CONSTRUCTION SCHEDULE REQUIREMENTS
A. Construction Baseline Schedule: Prepare Construction Baseline Schedule using computerized scheduling software.
1. Construction Baseline Schedule shall show submittal review, construction start date, work activities / staff resources, activity durations, major milestones, inspection dates, closeout activities, and project end date.
2. Establish procedures for updating Construction Baseline Schedule and for reporting progress. Coordinate procedures with progress meeting and payment request dates.
3. CO may request an updated Construction Schedule at any time to confirm progress of the work.
MORA – 249788 01 33 23 - 1
SUBMITTAL PROCEDURES
SECTION 01 33 23
A. This Section includes administrative and procedural requirements for submitting Shop
Drawings, Product Data, Samples, and other submittals.
1.2 DEFINITIONS
A. Action Submittals: Written and graphic information that requires Government’s responsive action.
B. Informational Submittals: Written information that does not require Government’s responsive action. Submittals may be rejected for not complying with the requirements.
1.3 GENERAL SUBMITTAL PROCEDURES
A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities. Review them for legibility, accuracy, completeness, and compliance with Contract Documents.
1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.
2. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.
a. Contracting Officer reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.
B. Submittal List: A submittal list has been attached to the end of this Specification Section. The intent is to provide an overall summary of submittal requirements and not a comprehensive list.
The requirements of the individual Specification Sections, terms and conditions of the Contract still apply regardless of what is shown on the submittal list.
C. Processing Time: Allow enough time for submittal review, including time for re-submittals, as follows. Time for review shall commence on Contracting Officer’s receipt of submittal. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including re-submittals.
1. Action Submittals
a. Initial Review: Allow seven (7) days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required.
b. Re-submittal Review: Allow seven (7) days for review of each re-submittal.
MORA – 249788 01 33 23 - 2
2. Informational Submittals
a. Review: Allow seven (7) days for review of each submittal.
D. Approved Equals:
1. For each item proposed as an “approved equal,” submit supporting data, including:
a. Drawings and samples as appropriate.
b. Comparison of the characteristics of the proposed item with that specified.
c. Changes required in other elements of the work because of the substitution.
d. Name, address, and telephone number of vendor.
e. Manufacturer’s literature regarding installation, operation, and maintenance, including schematics for electrical and hydraulic systems, lubrication requirements, and parts lists. Describe availability of maintenance service, and state source of replacement materials.
2. A request for approval constitutes a representation that Contractor:
a. Has investigated the proposed item and determined that it is equal or superior in all respects to that specified.
b. Will provide the same warranties for the proposed item as for the item specified.
c. Has determined that the proposed item is compatible with interfacing items.
d. Will coordinate the installation of an approved item and make all changes required in other elements of the work because of the substitution.
e. Waives all claims for additional expenses that may be incurred as a result of the substitution.
E. Additional Copies: Unless additional copies are required for final submittal, and unless
Contracting Officer observes noncompliance with provisions in the Contract Documents, initial submittal may serve as final submittal.
1. Additional copies submitted for maintenance manuals will not be marked with action taken and will be returned.
F. Transmittal: Package each submittal individually and appropriately for transmittal and handling. Transmit each submittal using a transmittal form. Contracting Officer will discard submittals received from sources other than Contractor.
1. CM-16 Transmittal Form: All material submittals shall be transmitted using National
Park Service form CM-16. (This form can be downloaded from the Workflows website at http://www.nps.gov/dscw/con_subreview21.htm.) No action will be taken on a material submittal item unless accompanied by the transmittal form.
2. Documents required in Division 01 are to be delivered under separate cover letter. Do not use the CM-16 Transmittal form for these documents.
G. Identification: Place a permanent label one by four inches (1”x4”) on each submittal for identification.
1. Include the following information on label for processing and recording action taken:
a. Project name, Park, PMIS number, Contract number.
b. Date.
c. Submittal number or other unique identifier, including revision identifier.
1) Submittal number shall be a sequential number (e.g., 001). Re-submittals shall include an alphabetic suffix after another decimal point (e.g., 001.A).
http://www.nps.gov/dscw/con_subreview21.htm
MORA – 249788 01 33 23 - 3
H. Re-submittals: Make re-submittals in same form and number of copies as initial submittal.
1. Note date and content of previous submittal.
2. Note date and content of revision in label or title block and clearly indicate extent of revision.
3. Re-submit submittals until they are marked “Approved” or “Approved with notations”.
I. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.
J. Use for Construction: Use only final submittals with mark indicating “Approved” or
“Approved with notations.
1.4 CONTRACTOR’S USE OF CAD FILES
A. General: At Contractor’s written request, copies of CAD files will be provided to Contractor for Contractor’s use in connection with Project, subject to the following conditions:
1. Files will be provided as is; no format or other changes to files or changes to the objects in the drawing will be done by the Government.
2.1 ACTION SUBMITTALS
A. General: Prepare and submit Action Submittals required by individual Specification Sections.
1. Contracting Officer reserves the right to require submittals in addition to those called for in individual sections.
B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.
2. Mark each copy of each submittal to show which products and options are applicable.
3. Include the following information, as applicable:
a. Manufacturer’s written recommendations.
b. Manufacturer’s product specifications.
c. Manufacturer’s installation instructions: When Contract Documents require compliance with manufacturer’s printed instructions, provide one complete set of instructions to Contracting Officer and keep another complete set of instructions at the project site until substantial completion.
d. Manufacturer’s catalog cuts: Submit only pertinent pages; mark each copy of standard printed data to identify specific products proposed for use.
e. Wiring diagrams showing factory-installed wiring.
f. Printed performance curves.
g. Operational range diagrams.
MORA – 249788 01 33 23 - 4
h. Compliance with specified referenced standards.
i. Testing by recognized testing agency.
4. Number of Copies: Submit four (4) copies of Product Data, unless otherwise indicated.
Contracting officer will return one copy. Retain copy as a Project Record Document.
C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base
Shop Drawings on reproductions of the Contract Documents or standard printed data, unless submittal of CAD Drawings is otherwise permitted.
1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable:
a. Dimensions.
b. Identification of products.
c. Fabrication and installation drawings. d. Roughing-in and setting diagrams.
e. Wiring diagrams showing field-installed wiring, including power, signal, and control wiring.
f. Shopwork manufacturing instructions.
g. Templates and patterns.
h. Schedules.
i. Notation of coordination requirements.
j. Notation of dimensions established by field measurement.
k. Relationship to adjoining construction clearly indicated.
l. Seal and signature of professional engineer if specified.
m. Wiring Diagrams: Differentiate between manufacturer-installed and field-installed wiring.
2. Sheet Size: Except for templates, patterns, and similar full-size drawings, submit Shop
Drawings on sheets at least eight and one-half by eleven inches (8-1/2” x 11”) but no larger than thirty by forty inches (30” x 40”).
3. Number of Copies: Submit four (4) copies of each submittal. Contracting Officer will return one (1) copy.
D. Samples: Submit Samples for review of kind, color, pattern, and texture for a check of these characteristics with other elements and for a comparison of these characteristics between submittal and actual component as delivered and installed.
1. Transmit Samples that contain multiple related components such as accessories together in one (1) submittal package.
2. Identification: Attach label on unexposed side of Samples that includes the following:
a. Generic description of Sample.
b. Product name and name of manufacturer.
c. Sample source.
d. Submittal Number and title of appropriate Specification Section.
3. Disposition: Maintain sets of approved Samples at Project site, available for quality-control comparisons throughout the course of construction activity. Sample sets may be used to determine final acceptance of construction associated with each set.
4. Samples for Initial Selection: Submit manufacturer’s color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available.
a. Number of Samples: Submit two ( 2 ) full set(s) of available choices where color, pattern, texture, or similar characteristics are required to be selected from manufacturer’s product line. Contracting Officer will return submittal with options selected.
MORA – 249788 01 33 23 - 5
5. Samples for Verification: Submit full-size units or Samples of size indicated, prepared from same material to be used for the Work, cured and finished in manner specified, and physically identical with material or product proposed for use, and that show full range of color and texture variations expected.
a. Samples include, but are not limited to, the following: partial sections of manufactured or fabricated components; small cuts or containers of materials;
complete units of repetitively used materials; swatches showing color, texture, and pattern; color range sets; and components used for independent testing and inspection.
b. Number of Samples: Submit four (4) sets of Samples. Contracting Officer will retain three (3) Sample sets; remainder will be returned. Retain Sample set as a
Project Record Sample.
C. Construction Materials: The Contractor is encouraged to submit for approval products made out of recycled or environmentally responsible material. Every effort will be made by the
National Park Service to approve these materials.
2.2 INFORMATIONAL SUBMITTALS
A. General: Prepare and submit Informational Submittals required by other Specification Sections.
1. Number of Copies: Submit three (3) copies of each submittal, unless otherwise indicated.
Contracting Officer will not return copies.
2. Certificates and Certifications: Provide a notarized statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.
3. Informational submittals that do not comply with the requirements specified in the
Contract Documents will be rejected and one copy will be returned.
B. Coordination Drawings: Comply with the requirements specified in Section 01 31 00 “Project
Management & Coordination.”
C. Contractors Construction Schedule: Comply with the requirements specified in Section 01 32
16 “Construction Schedule.”
D. Accident Prevention Plan: Comply with the requirements specified in Section 01 35 23 “Safety
Requirements.”
E. Schedule of Values: Comply with the requirements specified in Section 01 32 16 “Construction
Schedule.”
F. Waste Recycling Plan: Comply with the requirements specified in Section 01 74 19
“Construction Waste Management & Disposal.”
G. Quality Control Plan: Comply with the requirements specified in Section 01 40 00 “Quality
Requirements.”
H. Storm Water Pollution Prevention Plan: Comply with the requirements specified in Section 01
57 23 “Storm Water Pollution Prevention.”
MORA – 249788 01 33 23 - 6
I. Qualification Data: Prepare written information that demonstrates capabilities and experience of firm or person. Include lists of completed projects with project names and addresses, names and addresses of architects and owners, and other information specified.
J. Welding Certificates: Prepare written certification that welding procedures and personnel comply with the requirements in the Contract Documents. Submit record of Welding
Procedure Specification (WPS) and Procedure Qualification Record (PQR) on AWS forms.
Include names of firms and personnel certified.
K. Installer Certificates: Prepare written statements on manufacturer’s letterhead certifying that
Installer complies with the requirements in the Contract Documents and, where required, is authorized by manufacturer for this specific Project.
L. Manufacturer Certificates: Prepare written statements on manufacturer’s letterhead certifying that manufacturer complies with the requirements in the Contract Documents. Include evidence of manufacturing experience where required.
M. Product Certificates: Prepare written statements on manufacturer’s letterhead certifying that product complies with the requirements in the Contract Documents.
N. Material Certificates: Prepare written statements on manufacturer’s letterhead certifying that material complies with the requirements in the Contract Documents.
O. Material Test Reports: Prepare reports written by a qualified testing agency, on testing agency’s standard form, indicating and interpreting test results of material for compliance with the requirements in the Contract Documents.
P. Product Test Reports: Prepare written reports indicating current product produced by manufacturer complies with the requirements in the Contract Documents. Base reports on evaluation of tests performed by manufacturer and witnessed by a qualified testing agency, or on comprehensive tests performed by a qualified testing agency.
Q. Research/Evaluation Reports: Prepare written evidence, from a model code organization acceptable to authorities having jurisdiction, that product complies with building code in effect for Project.
R. Pre-construction Test Reports: Prepare reports written by a qualified testing agency, on testing agency’s standard form, indicating and interpreting results of tests performed before installation of product, for compliance with performance requirements in the Contract Documents.
S. Compatibility Test Reports: Prepare reports written by a qualified testing agency, on testing agency’s standard form, indicating and interpreting results of compatibility tests performed before installation of product. Include written recommendations for primers and substrate preparation needed for adhesion.
T. Field Test Reports: Prepare reports written by a qualified testing agency, on testing agency’s standard form, indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with the requirements in the Contract Documents.
MORA – 249788 01 33 23 - 7
U. Maintenance Data: Prepare written and graphic instructions and procedures for operation and normal maintenance of products and equipment. Comply with the requirements specified in
Section 01 78 23 “Operation & Maintenance Data.”
V. Design Data: Prepare written and graphic information, including, but not limited to, performance and design criteria, list of applicable codes and regulations, and calculations.
Include list of assumptions and other performance and design criteria and a summary of loads.
Include load diagrams if applicable. Provide name and version of software, if any, used for calculations. Include page numbers.
W. Manufacturer’s Instructions: Prepare written or published information that documents manufacturer’s recommendations, guidelines, and procedures for installing or operating a product or equipment. Include name of product and name, address, and telephone number of manufacturer.
X. Manufacturer’s Field Reports: Prepare written information documenting factory-authorized service representative’s tests and inspections. Include the following, as applicable:
1. Statement on condition of substrates and their acceptability for installation of product.
2. Summary of installation procedures being followed, whether they comply with the requirements and, if not, what corrective action was taken.
3. Results of operational and other tests and a statement of whether observed performance complies with the requirements.
PART 3 - EXECUTION
3.1 CONTRACTOR’S REVIEW
A. Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents. Note corrections and field dimensions.
3.2 CONTRACTING OFFICER’S ACTION
A. General: Submittals will be returned disapproved without technical review if identification information is missing, not filled in, or if placed on the back of the submittal; an incorrect number or format of submittals is provided; the transmittal form is incorrectly filled out;
submittals are not coordinated; or submittals do not show evidence of Contractor’s approval.
1. Any work done or orders for materials or services placed before approval shall be at the
Contractor’s own risk.
B. Action Submittals: Contracting Officer will review each submittal, make marks to indicate corrections or modifications required, and return one copy. Contracting Officer will annotate the CM-16 Transmittal Form indicating the action taken, as follows:
1. The returned submittal will be marked in one of three ways as defined below:
a. APPROVED: Acceptable with no corrections.
b. APPROVED WITH NOTATIONS: Minor corrections or clarifications required.
All comments are clear and no further review is required. The Contractor shall address all review comments when proceeding with the work.
MORA – 249788 01 33 23 - 8
c. DISAPPROVED - RESUBMIT: Rejected as not in accordance with the contract or as requiring major corrections or clarifications. The Contracting Officer will identify the reasons for disapproval. The Contractor shall revise and resubmit with changes clearly identified.
C. Informational Submittals: Contracting Officer will review each submittal and will not return it, or will reject and return one (1) copy if it does not comply with the requirements. Contracting
Officer will forward each submittal to appropriate party.
D. Partial submittals are not acceptable, will be considered non-responsive, and will be returned without review.
MORA – 249788 01 33 23 - 9
Project:
A c ti o n S u b m it ta l
I n fo rm a ti o n a l S u b m it ta l
I te m N o
Specification
Section No.
P a ra g ra p h N o
Description of Item
(Size, Type, Name, Manufacturer, Use, Etc.)
N o o f
C o p ie s S u b m it te d
C o n tr ib u te s t o m e e ti n g L
E E
D a n d /o r F e d S u s t.
R e q
M e e ts
B u y A m e ri c a n A c t
R e q
A lt e rn a te
M a te ri a ls
P ro p o s e d
N o o f
C o p ie s R e tu rn e d
A p p ro v e d
A p p ro v e d w it h N o ta ti o n s
D is a p p ro v e d
R e s u b m it
A c c e p t
R e je c t
Date To Contractor: r03/10Date Received: Distribution: 1 copy each: CMR Interim, A/E, DSC, Contr.
Title: Date:
Title: Date:
Action by:
Approval of this submittal is subject to the provisions of the contract draw ings and specif ications. This action is for general concurrence only and the government is not responsible for errors or omissions
Title: Date:
Contractor's Signature:
I hereby certify that this submittal has been review ed for accuracy, completeness, and compliance w ith contract requirements (FAR 52.236-21)
Review Comments:
Action
Submittal
Informational
Submittal
Contractor: NPS ACTIONSubcontractor / Supplier:
Recommended by:
CM-16 TRANSMITTAL FORM - NATIONAL PARK SERVICE
Park: PMIS No.: Contract No.: Date: Transmittal No.:
Sheet: 1 of:
MORA – 249788 01 33 23 - 10
Project:
c t io n
S u b m it t l
I f o r m a t io n a l S u b m it t l
I t e m
N o
Specification
Section No.
P r a g r a p h
N o
Description of Item
(Size, Type, Name, Manufacturer, Use, Etc.)
o f
C o p ie s
S u b m it t d
C n t r ib u t e s t o m e e t in g
L E
E d o r
F e d
S u s t
R e q
M e t s
B u y
A m e r ic a n
A c t
R e q lt e r n a t e
M a t e r ia ls
P r o p o s o f
C o p ie s
R e t u r n p p r o v p r o v e d w it h
N o t a t io s is a p p r o v e d
R e s u b m it c c e t
R je c t r03/10
Contractor: Subcontractor / Supplier: NPS ACTION
Action
Submittal
Informational
Submittal
Review Comments
CM-16 TRANSMITTAL FORM CONTINUATION - NATIONAL PARK SERVICE
Park: PMIS No.: Contract No.: Date: Transmittal No.:
Sheet: of:
MORA – 249788 01 35 13.22 - 1
ARCHEOLOGICAL PROTECTION
SECTION 01 35 13.22
A. The work of this section consists of protecting archeological resources contained in soil deposits.
A. Archeological Resources: Archeological resources are the physical evidences of past human activity, including evidences of the effects of that activity on the environment. Archeological resources represent both prehistoric and historic time periods. They are found above and below ground and under water.
B. Archeologically Sensitive Areas: Areas that have the potential to contain significant (National
Register eligible) archeological resources. If National Register eligible or listed archeological resources could not be avoided, an appropriate mitigation strategy would be developed in consultation with the state historic preservation officer and, if necessary, associated American
Indian tribes.
C. Non-sensitive Areas: Areas with little, if any, potential of containing significant (National
Register eligible) archeological resources.
D. Archeological Monitor: Representative of the Government designated to oversee construction activities that could disturb archeological resources.
E. Archeological Resources Protection Act (ARPA) of 1979 (P.L. 96-95; 93 Stat. 712): defines archeological resources as any material remains of past human life or activities that are of archeological interest and at least 100 years old; Section 4 of the statute describes the requirements that must be met before Federal authorities can issue a permit to excavate or remove any archeological resource on Federal or Indian lands; the curatorial requirements of artifacts, and other materials excavated or removed.
1.3 SUBMITTALS
A. Daily Work Schedule; Submit a Daily work Schedule detailing construction work in archeologically sensitive areas. Submit to Contracting Officer 14 days before start of ground disturbing site work.
MORA – 249788 01 35 13.22 - 2
1.4 QUALITY ASSURANCE
A. At least 14 days before on-site work begins, Contractor shall meet with Contracting Officer and Archeological Monitor to discuss Daily Work Schedule and equipment and special methods to be used in archeologically sensitive areas. Contractor shall ensure that approved
Daily Work Schedule is followed throughout construction.
2.1 DAILY WORK SCHEDULE
A. A Daily Work Schedule is required for all work occurring within archeologically sensitive areas. Include all work that is to occur within the area and key the schedule to the drawings to include the following:
1. Starting and ending dates of ground-disturbing construction.
2. Locations of temporary facilities, such as barriers, field offices, staging areas, sanitary facilities, borrow pits, and haul and access roads.
3. Types of construction, such as clearing, topsoil stripping, structure or trench excavation, landscaping, and post construction clean-up.
4. Methods and equipment used for each type of construction.
5. Plan for relocating work in the event of temporary work stoppages at each archeologically sensitive area
3.1 BARRICADES
A. Comply with requirements specified in Division 01 Section “Temporary Facilities and
Controls.”
3.2 ARCHEOLOGICAL INVESTIGATION BY NON-NPS PERSONNEL
A. A permit is required for any archeological investigations (e.g. excavation, shovel testing, coring, pedestrian survey, underwater archeology, rock art documentation, or other types of reconnaissance including the archaeological monitoring of…