Attachment A is a Specialized Experience Supplemental Information document for a Naval Facilities Engineering Command (NAVFAC) Architect-Engineer Services contract. The template provides a structured format for documenting up to 10 example projects, requiring detailed information about project characteristics including professional services, design disciplines, project types, and technical system capabilities.

The document is part of a pre-solicitation for an Indefinite Delivery/Indefinite Quantity (IDIQ) contract for mechanical engineering projects at various locations under NAVFAC Hawaii's cognizance. Potential offerors must complete the template, highlighting their experience across disciplines such as civil, architectural, structural, electrical, mechanical, fire protection, and geotechnical engineering. The solicitation requires comprehensive documentation of relevant project experience, with specific emphasis on mechanical systems like HVAC, compressed air systems, ventilation, plumbing, and utility infrastructure. The response is due on Thursday, October 16, 2025 at 2:00 p.m. Hawaii Standard Time.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT (A)

SPECIALIZED EXPERIENCE

(a) SPECIALIZED EXPERIENCE
EXAMPLE PROJECT KEY NUMBER:
1
TITLE AND LOCATION (CITY & STATE)
DESIGN COMPLETED (YR)

(NOT INCLUDING PCAS)

EST. CONSTRUCTION COMPLETED (YR)

PROJECT ROLE: PRIME A/E, DB DESIGNER OF RECORD, OR SUB CONSULTANT
CONSTRUCTION COST (NOT AE DESIGN FEE):

AE FIRM NAME OR JV:

NEW CONSTRUCTION (NC) OR REPAIR (R):

PROFESSIONAL SERVICE (CHECK ALL THAT APPLIES)

DESIGN BID BUILD

D-B RFP

ENGINEERING STUDIES/ RPTS

DESIGN-BUILD DOR

FACD/ DESIGN CHARRETTE

DISCIPLINES INVOLVED IN PROJECT (CHECK ALL THAT APPLIES):

CIVIL

ARCHITECT

STRUCTURAL

ELECTRICAL

MECHANICAL

FIRE PROTECTION

GEOTECHNICAL

FUELS (POL)

VTE

CYBER-SECURITY

CxC

RELEVANT DESIGN PROJECT TYPES (CHECK ALL THAT APPLIES):

HVAC CHILLED WATER AND DIRECT EXPANSION SYS

SERVER ROOM HVAC SYS

BACnet DIRECT DIGITAL CONTROLS

LOW/HIGH PRESSURE COMPRESSED AIR SYS

INDUSTRIAL VENTILATION SYS

MECH SUPPLY/EXHAUST VENTILATION SYS

SERVICE WATER HEATING/ SOLAR HOT WATER HEATING

GENERAL PURPOSE PLUMBING SYS

HYDRONIC PUMPING SYS

WATERFRONT/DOCKSIDE UTILITIES

ELEVATOR/ VERTICAL TRANSPORTATION EQUIP

ABOVE/BELOW GROUND FUEL STORAGE/DISTRIBUTION SYS

POL RECEIVING/ STORAGE, DISTRIB/DISP SYS

(a) SPECIALIZED EXPERIENCE
EXAMPLE PROJECT KEY NUMBER:
2
TITLE AND LOCATION (CITY & STATE)
DESIGN COMPLETED (YR)

EST. CONSTRUCTION COMPLETED (YR)

PROJECT ROLE: PRIME A/E, DB DESIGNER OF RECORD, OR SUB CONSULTANT
CONSTRUCTION COST (NOT AE DESIGN FEE):

AE FIRM NAME OR JV:

NEW CONSTRUCTION (NC) OR REPAIR (R):

PROFESSIONAL SERVICE (CHECK ALL THAT APPLIES)

DESIGN BID BUILD

D-B RFP

ENGINEERING STUDIES/ RPTS

DESIGN-BUILD DOR

FACD/ DESIGN CHARRETTE

DISCIPLINES INVOLVED IN PROJECT (CHECK ALL THAT APPLIES):

CIVIL

ARCHITECT

STRUCTURAL

ELECTRICAL

MECHANICAL

FIRE PROTECTION

GEOTECHNICAL

FUELS (POL)

VTE

CYBER-SECURITY

CxC

RELEVANT DESIGN PROJECT TYPES (CHECK ALL THAT APPLIES):

HVAC CHILLED WATER AND DIRECT EXPANSION SYS

SERVER ROOM HVAC SYS

BACnet DIRECT DIGITAL CONTROLS

LOW/HIGH PRESSURE COMPRESSED AIR SYS

INDUSTRIAL VENTILATION SYS

MECH SUPPLY/EXHAUST VENTILATION SYS

SERVICE WATER HEATING/ SOLAR HOT WATER HEATING

GENERAL PURPOSE PLUMBING SYS

HYDRONIC PUMPING SYS

WATERFRONT/DOCKSIDE UTILITIES

ELEVATOR/ VERTICAL TRANSPORTATION EQUIP

ABOVE/BELOW GROUND FUEL STORAGE/DISTRIBUTION SYS

POL RECEIVING/ STORAGE, DISTRIB/DISP SYS

(a) SPECIALIZED EXPERIENCE
EXAMPLE PROJECT KEY NUMBER:
3
TITLE AND LOCATION (CITY & STATE)
DESIGN COMPLETED (YR)

EST. CONSTRUCTION COMPLETED (YR)

PROJECT ROLE: PRIME A/E, DB DESIGNER OF RECORD, OR SUB CONSULTANT
CONSTRUCTION COST (NOT AE DESIGN FEE):

AE FIRM NAME OR JV:

NEW CONSTRUCTION (NC) OR REPAIR (R):

PROFESSIONAL SERVICE (CHECK ALL THAT APPLIES)

DESIGN BID BUILD

D-B RFP

ENGINEERING STUDIES/ RPTS

DESIGN-BUILD DOR

FACD/ DESIGN CHARRETTE

DISCIPLINES INVOLVED IN PROJECT (CHECK ALL THAT APPLIES):

CIVIL

ARCHITECT

STRUCTURAL

ELECTRICAL

MECHANICAL

FIRE PROTECTION

GEOTECHNICAL

FUELS (POL)

VTE

CYBER-SECURITY

CxC

RELEVANT DESIGN PROJECT TYPES (CHECK ALL THAT APPLIES):

HVAC CHILLED WATER AND DIRECT EXPANSION SYS

SERVER ROOM HVAC SYS

BACnet DIRECT DIGITAL CONTROLS

LOW/HIGH PRESSURE COMPRESSED AIR SYS

INDUSTRIAL VENTILATION SYS

MECH SUPPLY/EXHAUST VENTILATION SYS

SERVICE WATER HEATING/ SOLAR HOT WATER HEATING

GENERAL PURPOSE PLUMBING SYS

HYDRONIC PUMPING SYS

WATERFRONT/DOCKSIDE UTILITIES

ELEVATOR/ VERTICAL TRANSPORTATION EQUIP

ABOVE/BELOW GROUND FUEL STORAGE/DISTRIBUTION SYS

POL RECEIVING/ STORAGE, DISTRIB/DISP SYS

(a) SPECIALIZED EXPERIENCE
EXAMPLE PROJECT KEY NUMBER:
4
TITLE AND LOCATION (CITY & STATE)
DESIGN COMPLETED (YR)

EST. CONSTRUCTION COMPLETED (YR)

PROJECT ROLE: PRIME A/E, DB DESIGNER OF RECORD, OR SUB CONSULTANT
CONSTRUCTION COST (NOT AE DESIGN FEE):

AE FIRM NAME OR JV:

NEW CONSTRUCTION (NC) OR REPAIR (R):

PROFESSIONAL SERVICE (CHECK ALL THAT APPLIES)

DESIGN BID BUILD

D-B RFP

ENGINEERING STUDIES/ RPTS

DESIGN-BUILD DOR

FACD/ DESIGN CHARRETTE

DISCIPLINES INVOLVED IN PROJECT (CHECK ALL THAT APPLIES):

CIVIL

ARCHITECT

STRUCTURAL

ELECTRICAL

MECHANICAL

FIRE PROTECTION

GEOTECHNICAL

FUELS (POL)

VTE

CYBER-SECURITY

CxC

RELEVANT DESIGN PROJECT TYPES (CHECK ALL THAT APPLIES):

HVAC CHILLED WATER AND DIRECT EXPANSION SYS

SERVER ROOM HVAC SYS

BACnet DIRECT DIGITAL CONTROLS

LOW/HIGH PRESSURE COMPRESSED AIR SYS

INDUSTRIAL VENTILATION SYS

MECH SUPPLY/EXHAUST VENTILATION SYS

SERVICE WATER HEATING/ SOLAR HOT WATER HEATING

GENERAL PURPOSE PLUMBING SYS

HYDRONIC PUMPING SYS

WATERFRONT/DOCKSIDE UTILITIES

ELEVATOR/ VERTICAL TRANSPORTATION EQUIP

ABOVE/BELOW GROUND FUEL STORAGE/DISTRIBUTION SYS

POL RECEIVING/ STORAGE, DISTRIB/DISP SYS

(a) SPECIALIZED EXPERIENCE
EXAMPLE PROJECT KEY NUMBER:
5
TITLE AND LOCATION (CITY & STATE)
DESIGN COMPLETED (YR)

EST. CONSTRUCTION COMPLETED (YR)

PROJECT ROLE: PRIME A/E, DB DESIGNER OF RECORD, OR SUB CONSULTANT
CONSTRUCTION COST (NOT AE DESIGN FEE):

AE FIRM NAME OR JV:

NEW CONSTRUCTION (NC) OR REPAIR (R):

PROFESSIONAL SERVICE (CHECK ALL THAT APPLIES)

DESIGN BID BUILD

D-B RFP

ENGINEERING STUDIES/ RPTS

DESIGN-BUILD DOR

FACD/ DESIGN CHARRETTE

DISCIPLINES INVOLVED IN PROJECT (CHECK ALL THAT APPLIES):

CIVIL

ARCHITECT

STRUCTURAL

ELECTRICAL

MECHANICAL

FIRE PROTECTION

GEOTECHNICAL

FUELS (POL)

VTE

CYBER-SECURITY

CxC

RELEVANT DESIGN PROJECT TYPES (CHECK ALL THAT APPLIES):

HVAC CHILLED WATER AND DIRECT EXPANSION SYS

SERVER ROOM HVAC SYS

BACnet DIRECT DIGITAL CONTROLS

LOW/HIGH PRESSURE COMPRESSED AIR SYS

INDUSTRIAL VENTILATION SYS

MECH SUPPLY/EXHAUST VENTILATION SYS

SERVICE WATER HEATING/ SOLAR HOT WATER HEATING

GENERAL PURPOSE PLUMBING SYS

HYDRONIC PUMPING SYS

WATERFRONT/DOCKSIDE UTILITIES

ELEVATOR/ VERTICAL TRANSPORTATION EQUIP

ABOVE/BELOW GROUND FUEL STORAGE/DISTRIBUTION SYS

POL RECEIVING/ STORAGE, DISTRIB/DISP SYS

(a) SPECIALIZED EXPERIENCE
EXAMPLE PROJECT KEY NUMBER:
6
TITLE AND LOCATION (CITY & STATE)
DESIGN COMPLETED (YR)

EST. CONSTRUCTION COMPLETED (YR)

PROJECT ROLE: PRIME A/E, DB DESIGNER OF RECORD, OR SUB CONSULTANT
CONSTRUCTION COST (NOT AE DESIGN FEE):

AE FIRM NAME OR JV:

NEW CONSTRUCTION (NC) OR REPAIR (R):

PROFESSIONAL SERVICE (CHECK ALL THAT APPLIES)

DESIGN BID BUILD

D-B RFP

ENGINEERING STUDIES/ RPTS

DESIGN-BUILD DOR

FACD/ DESIGN CHARRETTE

DISCIPLINES INVOLVED IN PROJECT (CHECK ALL THAT APPLIES):

CIVIL

ARCHITECT

STRUCTURAL

ELECTRICAL

MECHANICAL

FIRE PROTECTION

GEOTECHNICAL

FUELS (POL)

VTE

CYBER-SECURITY

CxC

RELEVANT DESIGN PROJECT TYPES (CHECK ALL THAT APPLIES):

HVAC CHILLED WATER AND DIRECT EXPANSION SYS

SERVER ROOM HVAC SYS

BACnet DIRECT DIGITAL CONTROLS

LOW/HIGH PRESSURE COMPRESSED AIR SYS

INDUSTRIAL VENTILATION SYS

MECH SUPPLY/EXHAUST VENTILATION SYS

SERVICE WATER HEATING/ SOLAR HOT WATER HEATING

GENERAL PURPOSE PLUMBING SYS

HYDRONIC PUMPING SYS

WATERFRONT/DOCKSIDE UTILITIES

ELEVATOR/ VERTICAL TRANSPORTATION EQUIP

ABOVE/BELOW GROUND FUEL STORAGE/DISTRIBUTION SYS

POL RECEIVING/ STORAGE, DISTRIB/DISP SYS

(a) SPECIALIZED EXPERIENCE
EXAMPLE PROJECT KEY NUMBER:
7
TITLE AND LOCATION (CITY & STATE)
DESIGN COMPLETED (YR)

EST. CONSTRUCTION COMPLETED (YR)

PROJECT ROLE: PRIME A/E, DB DESIGNER OF RECORD, OR SUB CONSULTANT
CONSTRUCTION COST (NOT AE DESIGN FEE):

AE FIRM NAME OR JV:

NEW CONSTRUCTION (NC) OR REPAIR (R):

PROFESSIONAL SERVICE (CHECK ALL THAT APPLIES)

DESIGN BID BUILD

D-B RFP

ENGINEERING STUDIES/ RPTS

DESIGN-BUILD DOR

FACD/ DESIGN CHARRETTE

DISCIPLINES INVOLVED IN PROJECT (CHECK ALL THAT APPLIES):

CIVIL

ARCHITECT

STRUCTURAL

ELECTRICAL

MECHANICAL

FIRE PROTECTION

GEOTECHNICAL

FUELS (POL)

VTE

CYBER-SECURITY

CxC

RELEVANT DESIGN PROJECT TYPES (CHECK ALL THAT APPLIES):

HVAC CHILLED WATER AND DIRECT EXPANSION SYS

SERVER ROOM HVAC SYS

BACnet DIRECT DIGITAL CONTROLS

LOW/HIGH PRESSURE COMPRESSED AIR SYS

INDUSTRIAL VENTILATION SYS

MECH SUPPLY/EXHAUST VENTILATION SYS

SERVICE WATER HEATING/ SOLAR HOT WATER HEATING

GENERAL PURPOSE PLUMBING SYS

HYDRONIC PUMPING SYS

WATERFRONT/DOCKSIDE UTILITIES

ELEVATOR/ VERTICAL TRANSPORTATION EQUIP

ABOVE/BELOW GROUND FUEL STORAGE/DISTRIBUTION SYS

POL RECEIVING/ STORAGE, DISTRIB/DISP SYS

(a) SPECIALIZED EXPERIENCE
EXAMPLE PROJECT KEY NUMBER:
8
TITLE AND LOCATION (CITY & STATE)
DESIGN COMPLETED (YR)

EST. CONSTRUCTION COMPLETED (YR)

PROJECT ROLE: PRIME A/E, DB DESIGNER OF RECORD, OR SUB CONSULTANT
CONSTRUCTION COST (NOT AE DESIGN FEE):

AE FIRM NAME OR JV:

NEW CONSTRUCTION (NC) OR REPAIR (R):

PROFESSIONAL SERVICE (CHECK ALL THAT APPLIES)

DESIGN BID BUILD

D-B RFP

ENGINEERING STUDIES/ RPTS

DESIGN-BUILD DOR

FACD/ DESIGN CHARRETTE

DISCIPLINES INVOLVED IN PROJECT (CHECK ALL THAT APPLIES):

CIVIL

ARCHITECT

STRUCTURAL

ELECTRICAL

MECHANICAL

FIRE PROTECTION

GEOTECHNICAL

FUELS (POL)

VTE

CYBER-SECURITY

CxC

RELEVANT DESIGN PROJECT TYPES (CHECK ALL THAT APPLIES):

HVAC CHILLED WATER AND DIRECT EXPANSION SYS

SERVER ROOM HVAC SYS

BACnet DIRECT DIGITAL CONTROLS

LOW/HIGH PRESSURE COMPRESSED AIR SYS

INDUSTRIAL VENTILATION SYS

MECH SUPPLY/EXHAUST VENTILATION SYS

SERVICE WATER HEATING/ SOLAR HOT WATER HEATING

GENERAL PURPOSE PLUMBING SYS

HYDRONIC PUMPING SYS

WATERFRONT/DOCKSIDE UTILITIES

ELEVATOR/ VERTICAL TRANSPORTATION EQUIP

ABOVE/BELOW GROUND FUEL STORAGE/DISTRIBUTION SYS

POL RECEIVING/ STORAGE, DISTRIB/DISP SYS

(a) SPECIALIZED EXPERIENCE
EXAMPLE PROJECT KEY NUMBER:
9
TITLE AND LOCATION (CITY & STATE)
DESIGN COMPLETED (YR)

EST. CONSTRUCTION COMPLETED (YR)

PROJECT ROLE: PRIME A/E, DB DESIGNER OF RECORD, OR SUB CONSULTANT
CONSTRUCTION COST (NOT AE DESIGN FEE):

AE FIRM NAME OR JV:

NEW CONSTRUCTION (NC) OR REPAIR (R):

PROFESSIONAL SERVICE (CHECK ALL THAT APPLIES)

DESIGN BID BUILD

D-B RFP

ENGINEERING STUDIES/ RPTS

DESIGN-BUILD DOR

FACD/ DESIGN CHARRETTE

DISCIPLINES INVOLVED IN PROJECT (CHECK ALL THAT APPLIES):

CIVIL

ARCHITECT

STRUCTURAL

ELECTRICAL

MECHANICAL

FIRE PROTECTION

GEOTECHNICAL

FUELS (POL)

VTE

CYBER-SECURITY

CxC

RELEVANT DESIGN PROJECT TYPES (CHECK ALL THAT APPLIES):

HVAC CHILLED WATER AND DIRECT EXPANSION SYS

SERVER ROOM HVAC SYS

BACnet DIRECT DIGITAL CONTROLS

LOW/HIGH PRESSURE COMPRESSED AIR SYS

INDUSTRIAL VENTILATION SYS

MECH SUPPLY/EXHAUST VENTILATION SYS

SERVICE WATER HEATING/ SOLAR HOT WATER HEATING

GENERAL PURPOSE PLUMBING SYS

HYDRONIC PUMPING SYS

WATERFRONT/DOCKSIDE UTILITIES

ELEVATOR/ VERTICAL TRANSPORTATION EQUIP

ABOVE/BELOW GROUND FUEL STORAGE/DISTRIBUTION SYS

POL RECEIVING/ STORAGE, DISTRIB/DISP SYS

(a) SPECIALIZED EXPERIENCE
EXAMPLE PROJECT KEY NUMBER:
10
TITLE AND LOCATION (CITY & STATE)
DESIGN COMPLETED (YR)

EST. CONSTRUCTION COMPLETED (YR)

PROJECT ROLE: PRIME A/E, DB DESIGNER OF RECORD, OR SUB CONSULTANT
CONSTRUCTION COST (NOT AE DESIGN FEE):

AE FIRM NAME OR JV:

NEW CONSTRUCTION (NC) OR REPAIR (R):

PROFESSIONAL SERVICE (CHECK ALL THAT APPLIES)

DESIGN BID BUILD

D-B RFP

ENGINEERING STUDIES/ RPTS

DESIGN-BUILD DOR

FACD/ DESIGN CHARRETTE

DISCIPLINES INVOLVED IN PROJECT (CHECK ALL THAT APPLIES):

CIVIL

ARCHITECT

STRUCTURAL

ELECTRICAL

MECHANICAL

FIRE PROTECTION

GEOTECHNICAL

FUELS (POL)

VTE

CYBER-SECURITY

CxC

RELEVANT DESIGN PROJECT TYPES (CHECK ALL THAT APPLIES):

HVAC CHILLED WATER AND DIRECT EXPANSION SYS

SERVER ROOM HVAC SYS

BACnet DIRECT DIGITAL CONTROLS

LOW/HIGH PRESSURE COMPRESSED AIR SYS

INDUSTRIAL VENTILATION SYS

MECH SUPPLY/EXHAUST VENTILATION SYS

SERVICE WATER HEATING/ SOLAR HOT WATER HEATING

GENERAL PURPOSE PLUMBING SYS

HYDRONIC PUMPING SYS

WATERFRONT/DOCKSIDE UTILITIES

ELEVATOR/ VERTICAL TRANSPORTATION EQUIP

ABOVE/BELOW GROUND FUEL STORAGE/DISTRIBUTION SYS

POL RECEIVING/ STORAGE, DISTRIB/DISP SYS

File details come from the government source that posted it. Updated .