This is a Statement of Work (SOW) for pavement improvement projects at two lock facilities operated by the Great Lakes St. Lawrence Seaway Development Corporation (GLS), a Department of Transportation entity. The work involves the complete removal and replacement of existing pavement and subbase on the north (operational) sides of both Eisenhower Lock (190A Barnhart Island Road, Massena, NY) and Snell Lock (145 Snell Lock Road, Massena, NY). The contractor must excavate and remove all existing asphalt pavement and subbase materials, prepare and compact the existing subgrade, install new geotextile fabric, place a minimum 12-inch depth of 2-inch crusher run subbase with compaction, and install 2½ inches of binder course and 1½ inches of top course asphalt. All work must maintain positive drainage away from lock walls and toward existing drainage structures, with crushed stone aprons installed where finished asphalt elevations exceed existing ground levels to prevent edge cracking.
The contract consists of three Contract Line Item Numbers (CLINs): CLIN 0001 covers mobilization/demobilization including pre-construction meetings, equipment and material mobilization, and demobilization; CLIN 0002 addresses paving at Eisenhower Lock North; and CLIN 0003 addresses paving at Snell Lock North. Performance must begin within 10 calendar days and be completed within 120 calendar days from the notice to proceed, expected on or about June 29, 2026. The contractor is responsible for all labor, equipment, materials, utilities, and project costs, and must submit a Health and Safety Plan (HASP) compliant with OSHA regulations (29 CFR 1926/1910) for GLS approval prior to work commencement. Constant coordination with GLS Operations personnel is required as work locations are within active lock operational areas. Applicable contract documents include eight utility maps, six paving plans, paving details, and technical specifications covering earthwork, gravel and crushed stone base/subbase courses, and hot-mixed asphalt paving.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 6923G526Q0063 QA (Rev1).xlsx | XLSX spreadsheet | |
| 6923G526Q0063A00001.pdf | ||
| 6923G526Q0063 QA.xlsx | XLSX spreadsheet | |
| SPOILS DISPOSAL AREA ORTHO.pdf | ||
| SLS-326-300-SPOILS DISPOSAL AREA.pdf | ||
| Attachment E_Specifications Combined.pdf | ||
| Attachment B_Pricing Sheet.xlsx | XLSX spreadsheet | |
| RFQ 6923G526Q0063.pdf | ||
| Attachment C_Davis Bacon Wage Determination.pdf | ||
| Attachment D_SLS-370-283_ Eisenhower and Snell Lock North Side Paving Improvements-full set.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work Eisenhower & Snell Lock North Side Paving Improvements
SECTION 1 – SCOPE
1.1 – Purpose/Introduction/Overview
The Great Lakes St. Lawrence Seaway Development Corporation (GLS) has a requirement for the installation of new pavement on the North (Operational) sides of both Eisenhower and Snell Locks. This includes the full removal of all existing pavement and subbase, and replacement with new subbase, binder course asphalt, and top course asphalt. Over time the existing parking areas and access roads have begun to show signs of wear and deterioration, thus prompting construction of new parking areas and access roads to rehabilitate the areas.
This work shall be completed at Eisenhower Lock and Snell Lock located at 190A Barnhart Island Road, Massena New York and 145 Snell Lock Road, Massena, NY, respectively.
1.2 – Background
Part of the Department of Transportation (DOT), the Great Lakes St. Lawrence Seaway
Development Corporation (GLS) is a wholly owned government corporation created by statute
May 13, 1954, to construct, operate and maintain the U.S. portion of the St. Lawrence Seaway between the Port of Montreal and Lake Erie. The mission of the GLS is to serve the U.S.
intermodal and international transportation system by improving the operation and maintenance of a safe, reliable, efficient, and environmentally responsible deep-draft waterway, in cooperation with its Canadian counterpart. The GLS also encourages the development of trade through the Great Lakes Seaway System, which contributes to the comprehensive economic development of the entire Great Lakes region.
SECTION 2 – APPLICABLE DOCUMENTS
The documents listed in this section, combined with the other sections of the SOW, form the contract requirements for the project. These documents are being furnished to the Contractor in electronic format only. References to Owner in the Technical Specifications shall mean GLS, and references to
Owner’s Representative shall mean the GLS appointed Contracting Officer’s Representative (COR).
Drawings:
SLS-370-283/1 – Cover Sheet
SLS-370-283/2 – Vicinity and Locality Maps
SLS-370-283/3 – Existing Site Utility Map – Eisenhower Lock 1
SLS-370-283/4 – Existing Site Utility Map – Eisenhower Lock 2
SLS-370-283/5 – Existing Site Utility Map – Eisenhower Lock 3
SLS-370-283/6 – Existing Site Utility Map – Snell Lock 1
SLS-370-283/7 – Existing Site Utility Map – Snell Lock 2
SLS-370-283/8 – Existing Site Utility Map – Snell Lock 3
SLS-370-283/9 – Site Paving Plan – Eisenhower Lock 1
SLS-370-283/10 – Site Paving Plan – Eisenhower Lock 2
SLS-370-283/11 – Site Paving Plan – Eisenhower Lock 3
SLS-370-283/12 – Site Paving Plan – Snell Lock 1
SLS-370-283/13 – Site Paving Plan – Snell Lock 2
SLS-370-283/14 – Site Paving Plan – Snell Lock 3
SLS-370-283/15 – Paving Details
Technical Specifications:
Section 02200 – Earthwork
Section 02505 – Gravel and Crush Stone Base and Subbase Course
Section 02511 – Hot-Mixed Asphalt Paving
SECTION 3 – REQUIREMENTS
3.1 – Scope Requirements
This SOW overall consists of the removal and replacement of existing pavement areas on the north (operational) sides of both Eisenhower and Snell Locks. These areas include access roads, parking areas, and operational pavement surfaces as indicated on the contract drawings.
The Contractor shall be responsible for the following:
- Removal and disposal of all existing asphalt pavement and subbase materials in areas delineated on Contract Drawings.
- Excavation to required depths in areas of new pavement.
- Preparation and compaction of existing subgrade. If the existing subgrade is unsuitable, notify the COR for corrective action to remove and replace if necessary.
- Placement of new geotextile fabric.
- Placement of new 2” crusher run subbase, minimum 12” depth, and compaction.
- Installation of 2 ½” of binder course and 1 ½” of top course asphalt.
The Contractor shall maintain or improve existing grades such that they promote positive drainage away from the lock walls and to existing drainage structures. Wherever the final elevation of finished asphalt is higher than the elevation of existing ground, the Contractor shall install a crushed stone apron to provide a smooth transition and to avoid edge cracking of the new asphalt (see note 9 on page 15 of the contract drawings).
All spoils and removed materials shall be transported off-site. Clean spoils may be disposed of at an on-site location as approved by the COR.
The Contractor shall be responsible for all labor, equipment, materials, utilities, and any other costs required to complete all requirements of this project. The Contractor shall perform all work in a safe manner in accordance with applicable OSHA regulations and shall submit a
Health and Safety Plan (HASP) for GLS approval prior to commencing work.
Work locations are within active lock operational areas. The Contractor shall coordinate all work activities with the COR and GLS Operations personnel to maintain safe and uninterrupted lock operations. Access to certain areas may require advance notice and scheduling restrictions as GLS personnel will frequently need to access the areas to perform operational work.
Advanced and constant coordination will be required when the Contractor is actively working in these sensitive areas.
3.2 – Task Requirements
CLIN 0001 – Mobilization/Demobilization
Task 1 – Attend pre-construction meeting. Review construction/installation with GLS, provide project schedule, schedule of values, Health and Safety Plan (HASP), and provide material submittals log.
Task 2 – Mobilize all construction equipment and materials to site.
Task 3 – Demobilize all construction equipment and remove excess materials from site after project completion.
CLIN 0002 – Paving Area 1 (Eisenhower Lock North)
Task 4 – Per the contract drawings and specifications, excavate the existing Eisenhower Lock North side pavement areas to the depth and limits indicated and remove all existing pavement and subbase. Compact existing subgrade as necessary.
Task 5 – Per the contract drawings and specifications, install new subbase, geotextile fabric, binder course, and top course pavement in all areas of the Eisenhower Lock North side pavement area as indicated. Ensure all site drainage is directed away from the lock walls and to the existing catch basins or drainage swales.
CLIN 0003 – Paving Area 2 (Snell Lock North)
Task 6 – Per the contract drawings and specifications, excavate the existing Snell Lock North side pavement areas to the depth and limits indicated, and remove all existing pavement and subbase. Compact existing subgrade as necessary.
Task 7 – Per the contract drawings and specifications, install new subbase, geotextile fabric, binder course, and top course pavement in all areas of the Snell Lock North side pavement area as indicated. Ensure all site drainage is directed away from the lock walls and to the existing catch basins or drainage swales.
3.3 – Deliverables
Tasks Deliverables Period of Performance
CLIN 0001 Mobilization/Demobilization IAW Contractors Project Plan
Task 1 Attend pre-construction meeting, review construction/installation with GLS, provide Construction Schedule, Schedule of Values, Within 15 days of Award
HASP and submittal log in accordance with Technical Specifications and SOW
Task 2 Mobilize equipment and materials to the site. IAW Contractors Project Plan
Task 3 Demobilize equipment and remove excess materials from the site.
IAW Contractors Project Plan
CLIN 0002 Paving Area 1 (Eisenhower Lock North Side) IAW Contractors Project Plan
Task 4 Excavate existing Eisenhower North pavement areas and remove existing pavement and subbase.
IAW Contractors Project Plan
Task 5 Install new subbase and pavement at the Eisenhower Lock North Side pavement areas.
IAW Contractors Project Plan
CLIN 0003 Paving Area 2 (Snell Lock North Side) IAW Contractors Project Plan
Task 6 Excavate existing Snell Lock North Side pavement areas and remove existing pavement and subbase.
IAW Contractors Project Plan
Task 7 Install new subbase and pavement at the Snell Lock North Side pavement areas.
IAW Contractors Project Plan
3.4 – General Conditions
3.4.1 – Period of Performance
The contractor shall begin performance within 10 calendar days and complete it within 120 calendar days after receiving the notice to proceed. It is expected that the notice to proceed will be issued on or about June 29, 2026.
3.4.2 – Place of Performance
All work shall take place at Eisenhower Lock, located at 190A Barnhart Island Road, and Snell
Lock, located at 145 Snell Lock Road, Massena New York.
3.4.3 – Government Furnished Equipment/Information
The Contractor shall supply all materials needed to complete the project.
3.4.4 – Facilities
GLS will provide access to all required areas to complete the project.
3.4.5 – Safety
The Williams-Steiger Occupational Safety and Health Act of 1970 (as amended) as set forth in 29 CFR 1926/1910, shall govern this contract. The Contractor shall be responsible for a safe work environment at all times. The Contractor shall comply with requirements of OSHA. The Contractor shall submit a Health and Safety Plan (HASP) for approval prior to commencing work.