6923G526Q0063 QA (Rev1).xlsx

XLSX spreadsheet 13 KB Posted

Attached to
Paving Improvements at Eisenhower and Snell Locks Federal contract opportunity
Solicitation number
6923G526Q0063
Issued by
Department of Transportation Saint Lawrence Seaway Development Corporation

About this file

This is a Questions and Answers (Q&A) document for solicitation 6923G526Q0063, addressing clarifications on paving improvements at Eisenhower and Snell Locks in Massena, New York.

Key clarifications provided include: (1) temporary access during phased construction must remain passable for Great Lakes Seaway (GLS) employees, with compacted subbase acceptable as a driving path; temporary pavement is not required; (2) GLS will disconnect existing loop detectors associated with gate systems, and the contractor may remove them during excavation; GLS will install and connect new loop detectors before new pavement placement; (3) pavement marking replacement is excluded from contractor scope and will be performed by GLS after construction completion; (4) excavated materials and clean spoils may be disposed of onsite at the Eisenhower Lock disposal area (location map provided), or contractors may choose to haul spoils offsite; no contaminated fill or metals are permitted at the onsite disposal location; (5) construction activities will rarely require pausing during vessel transits along the lock chamber wall between control towers at Snell Lock. The document emphasizes the requirement for advanced coordination with the GLS Contracting Officer's Representative to notify which areas will be disturbed daily, allowing employees to plan alternate access routes. This Q&A document is incorporated into the solicitation as Amendment A00001 and serves to clarify contractor responsibilities versus government responsibilities and resolve ambiguities in the original Statement of Work and drawings.

View the file

Other files for this federal contract opportunity

Other files attached to Paving Improvements at Eisenhower and Snell Locks, newest first.
File Type Posted
6923G526Q0063A00001.pdf PDF
6923G526Q0063 QA.xlsx XLSX spreadsheet
SPOILS DISPOSAL AREA ORTHO.pdf PDF
SLS-326-300-SPOILS DISPOSAL AREA.pdf PDF
Attachment A_SOW.pdf PDF
Attachment E_Specifications Combined.pdf PDF
Attachment B_Pricing Sheet.xlsx XLSX spreadsheet
RFQ 6923G526Q0063.pdf PDF
Attachment C_Davis Bacon Wage Determination.pdf PDF
Attachment D_SLS-370-283_ Eisenhower and Snell Lock North Side Paving Improvements-full set.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1 6923G526Q0063 - Paving Improvements at Eisenhower and Snell Lock(s) Questions & Answers

#QuestionAnswer
1Please clarify the govt's expectations regarding temp. access and/or temp. pavement during phased construction. At the Snell Lock location, particularly at the downhill approach near the lock and waterfront area, available space appears limited (approx. 10' wide), making it difficult to establish a temp. bypass route. Please advise how the govt. expects access to be maintained during construction activities in these areas.Construction will occur in active lock operational areas. Maintaining access for GLS employees will be required during construction. Temporary pavement is not required, as long as the material used to provide access to GLS employees is suitable to drive on. At the Snell Lock downhill approach, as long as the construction area is left passable by vehicle, this will suffice (i.e. leaving compacted subbase as a driving path to allow employees to access work areas until paving is completed.) In many locations there are alternate routes for GLS employees to access their work areas. Advanced coordination with the GLS COR will be required to notify which areas will be disturbed on a particular day so GLS employees can plan their access routes.
2Please confirm whether all exist. loop detectors associated with the gate systems are to be disconnected, removed, reinstalled, replaced, and/or commissioned by the govt. and are not part of the Contractor's scope.GLS will be responsible for disconnecting all existing loop detectors associated with the gate systems. After they are disconnected, the Contractor may remove them during excavation. GLS will install and connect new vehicle loop detectors prior to the placement of new pavement.
3Existing pavement markings were observed at both the Eisenhower and Snell Lock pavement areas. The drawings do not appear to identify replacement pavement markings or provide striping details. Please confirm whether pavement marking replacement is excluded from the Contractor's scope.GLS will be responsible for replacing pavement markings after the completion of construction.
4Drawing Note #3 indicates that project spoils shall be disposed of onsite, while the Statement of Work states that removed materials shall be transported offsite and that only clean spoils may be disposed of at an onsite location approved by the COR. Please clarify the govt's expectations regarding disposal of excavated materials, existing subbase, and other removed materials.
Additionally, during the site visit, an onsite disposal area near Eisenhower Lock was discussed. Please confirm whether this location may be used for disposal and whether all excavated materials or only clean spoils may be placed there. If possible, can the govt. provide the location map of the disposal area so contractors can accurately estimate hauling distances and logistics?Excavated materials may be disposed of onsite at the Eisenhower Lock disposal area (see attached map showing the location of the dump site). All clean fill may be disposed of at this site (including existing pavement), no contaminated fill, metals, etc. may be disposed here. It is up to the Contractors discretion whether they would like to utilize the on-site spoils disposal area or haul the spoils off-site.
5During the site visit, contractors were advised that construction operations may need to pause while vessels enter and exit the locks. Please clarify regarding these work interruptions, specifically: A) Will construction activities be required to stop during vessel movements? B) Approximately how many vessel transits occur daily at each lock? C) What is the typical duration of each lock operation and associated work interruption? D) Are there anticipated peak periods when interruptions occur more frequently? This will help us assist in evaluating production rates, scheduling, and anticipated downtime.Construction activities will rarely need to be paused while a ship is transiting the lock at Snell Lock along the lock chamber wall between the control towers. Ships requiring line handling (<1% of the transits) will require equipment and personnel to be away from the lock chamber walls during transit. Ships carrying certain hazardous cargo will require work to be paused until the ship leaves the lock. The Contractor shall coordinate by calling GLS's Vessel Traffic Control (VTC) each morning to get the estimated shipping schedule for ship ETAs for these types of ship transits. VTC can provide an approximate 12-hour look ahead. A typical lockage takes approximately 40 minutes. On average, there are six ships that transit the lock during a day shift. There are no "peak periods", but GLS will work with the Contractors to ensure minimal interruption to schedules so the work can be completed in a timely manner.
6Was the site visit mandatory to bid the project?No.
7Are we to assume a 5% Bid Bond and what type of Bid Bond Form is required?No, the performance and payment bonds shall be 100 percent of the original contract price. Performance bonds must be submitted on Standard Form 25 and payment bonds must be submitted on 25A.
8What are the insurance requirements? We did not see them in the project documents.The Contractor shall maintain, at a minimum, the following insurance coverages during the period of performance:

Workers' Compensation: As required by New York State law.

General Liability: $500,000 per occurrence for bodily injury.

Automobile Liability: $200,000 per person and $500,000 per occurrence for bodily injury, and $20,000 per occurrence for property damage

File details come from the government source that posted it. Updated .