This is a Request for Quote (RFQ) for runoff station concrete repairs at the USDA Agricultural Research Service Grassland Soil and Water Research Laboratory in Riesel, Texas.

The solicitation seeks bids for concrete repairs to restore critical research structures at the facility. The requirement includes three line items: a base contract for repairs to stations SW12, SW17, and W10, with two optional line items for repairs to additional stations (W6, W12, W13 under Option 1; Y2, Y6, Y8, Y10, Y13, Y14 under Option 2). All work is priced on a lump sum basis with a 300-day performance period from Notice to Proceed. Quotes must be submitted by email to Spencer Hamilton at spencer.hamilton@usda.gov by 12:00 p.m. Central Time on May 8, 2026, as stated on SAM.gov. The Government intends to make one award and requires pricing for all items to be considered responsive. A firm fixed-price contract is anticipated. Bid guarantee is not required for proposals under $150,000; proposals exceeding this threshold require a 20 percent bid guarantee not to exceed $3,000,000. Performance and payment bonds are required for awards over $35,000 within 10 days of award notification. An organized site visit is scheduled for April 28, 2026, at 9:00 a.m. Central Time, with RSVP required by April 27, 2026.

Evaluation will be conducted using lowest price technically acceptable criteria, where only the lowest-priced quote receives technical evaluation. If unacceptable, evaluation proceeds to the next lowest price. Technical acceptability is based on the quoter's ability to demonstrate understanding of requirements through three years of relevant past performance examples, technical experience with similar projects, and adequate project completion approach within the 300-day timeline. Quotes must include SAM.gov registration, completed representations and certifications, past performance references with contact information, and pricing for base and all option items. The solicitation incorporates numerous FAR clauses including construction wage rate requirements, labor standards compliance, buy American provisions for construction materials, and anti-discrimination certifications.

View the file

Other files for this federal contract opportunity

Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

PAGE OF PAGES

7. ISSUED BY CODE 8. ADDRESS OFFER TO

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION CALL

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

1165967

USDA ARS ACQUISITION AND PROPERTY D

5601 SUNNYSIDE AVENUE

RM 3-2102

BELTSVILLE MD 20705

ARS-1232SA

spencer.hamilton@usda.gov

Do not use regular mail to submit quotes

S HAMILTON 5105596338

104/14/2026

1232SA26Q0455

INVITATION FOR BID

REQUEST FOR PROPOSAL

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

Attachment A - SF 1442 & Solicitation Terms and Conditions_1232SA26Q0455 (this document)

Attachment B - Statement of Work

Attachment C - Dept of Labor General Decision Number TX20260007 01/02/2026

Attachment 1 - Temple Runoff Stations Specifications 2023-12_Riesel

Attachment 2 - Temple Runoff Stations Drawings 1 - For Base and Options

Attachment 3 - Temple Runoff Stations Drawings 2 - Base

Attachment 4 - Temple Runoff Stations Drawings 3 - Option-1

Attachment 5 - Temple Runoff Stations Drawings 4 - Option-2

11. The Contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

10 300 calendar days and complete it within ________________ ________________ calendar days after receiving

05/08/2026

NSN 7540-01-155-3212

x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________

STANDARD FORM 1442 (Rev. 12/2022)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d)

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14.)

CODE FACILITY CODE

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

OFFER (Must be fully completed by offeror)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES CODE AT

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this document solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE

BY

2PAGE OF

USDA ARS ACQUISITION AND PROPERTY D

5601 SUNNYSIDE AVENUE

RM 3-2102

BELTSVILLE MD 20705

ARS-1232SA

S S. HAMILTON

28. NEGOTIATED AGREEMENT 29. AWARD

and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations,certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.) Contractor agrees to furnish

10 U.S.C. 3204(a) 41 U.S.C. 3304(a)

STANDARD FORM 1442 (REV. 12/2022) BACK

Continued...

and return

(Contractor is not required to sign this document.) Your offer on this

ITEM NO.

(A)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

3 22

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

1232SA26Q0455

United States Department of Agriculture (USDA), Agricultural Research Service (ARS), Grassland

Soil and Water Research Laboratory (GSWRL) in

Riesel, TX has a requirement for runoff station concreate repairs to restore structures that are critical components of the research efforts at

GSWRL. See attached Statement of Work for a complete description of requirements.

Delivery Location Code: ARS-127D74

PA GRASSLAND, SOIL AND WATER RESEAR

808 EAST BLACKLAND ROAD

TEMPLE TX 76502 US

0001 Base - Runoff Stations Concrete Repairs - SW12, SW17, and W10

Delivery: 300 Days After Notice to Proceed

1001 Option 1: Station Repairs - W6, W12, and W13

(Option Line Item)

Product/Service Code: Z1PZ

Product/Service Description: MAINTENANCE OF OTHER

NON-BUILDING FACILITIES

Delivery: 300 Days After Award

2001 Option 2: Station Repairs - Y2, Y6, Y8, Y10, Y13, and Y14

(Option Line Item)

Product/Service Code: Z1PZ

Product/Service Description: MAINTENANCE OF OTHER

NON-BUILDING FACILITIES

Delivery: 300 Days After Award

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

Temple Riesel GSWRL Runoff Stations Concrete Repairs (Riesel, TX)

RFQ# 1232SA26Q0455

Statement of Requirement - United States Department of Agriculture (USDA), Agricultural Research Service (ARS), Grassland Soil and Water Research Laboratory (GSWRL) in Riesel, TX has a requirement for runoff station concreate repairs to restore structures that are critical components of the research efforts at GSWRL. See attached Statement of Work for a complete description of requirements.

Schedule of Items –

CLIN Description Estimated Quantity Pay Unit

Unit Cost Total

0001 Base - Runoff Stations Concrete Repairs - SW12, SW17, and W10

1 LS JB $ -

1001 Option 1: Station Repairs - W6, W12, and W13

1 LS JB $ -

2001 Option 2: Station Repairs - Y2, Y6, Y8, Y10, Y13, and Y14

1 LS JB $ -

TOTAL

Technical Data -

The following documents are included as attachments to this solicitation.

Attachment A – SF 1442 & Solicitation Terms and Conditions_1232SA26Q0455 (this document)

Attachment B – Statement of Work Attachment C – Dept of Labor General Decision Number TX20260007 01/02/2026 Attachment 1 - Temple Runoff Stations Specifications 2023-12_Riesel Attachment 2 - Temple Runoff Stations Drawings 1 - For Base and Options Attachment 3 - Temple Runoff Stations Drawings 2 – Base Attachment 4 - Temple Runoff Stations Drawings 3 - Option-1 Attachment 5 - Temple Runoff Stations Drawings 4 - Option-2

Project Location

United States Department of Agriculture (USDA) Agricultural Research Service (ARS) Grassland Soil and Water Research Laboratory (GSWRL) 1702 Blackland Rd.

Riesel, TX 76682

Bonding

Bid Guarantee: A bid guarantee is not required for proposals less than $150K.

If a proposal is above $150K, a bid guarantee is required in an amount not less than 20 percent of the proposed price but shall not exceed $3,000,000 (for proposals of $35,000 or more). Failure to furnish the required bid guarantee in the proper form and amount, by the time set for receipt of proposals, shall require rejection of the proposal in all cases except those listed in Federal Acquisition Regulation (FAR) 28.101-4. Bid Bonds must be provided using Standard Form 24 (see FAR 28.106-

1) electronic versions of Bid Guarantee will be accepted. Individual sureties have to be acceptable to the Contracting Officer (see FAR 28.203) and be accompanied by Standard Form 28 Affidavit of Individual Surety. Other forms of offer security are acceptable as denoted in solicitation provision FAR Part 28.203-2. The cost of a Bid Guarantees will not be reimbursed.

After award, in accordance with Contract Clause 52.228-15, and FAR 28.102, Contractors are reminded that any amount awarded over $35,000.00 shall require a Payment Bond (SF 25A), and awards exceeding $150,000.00 shall require both Payment and Performance Bonds (SF 25).

Payment and Performance bonds are due no later than 10 days after notification of award.

Federal Acquisition Regulation (FAR) and United States Department of Agriculture Acquisition Regulation (AGAR) Clauses and Provisions The clauses and provisions contained herein are applicable to any order awarded as a result of this solicitation. The terms and conditions set forth herein supersede all other terms and conditions.

Acceptance of the order in accordance with (IAW) FAR 12.201-1(b)(2) constitutes acceptance of all terms and conditions contained herein.

As part of the Revolutionary FAR Overhaul (RFO), system updates may lag policy updates. The System for Award Management (SAM) may continue to require entities to complete representations based on provisions that are not included in this solicitation. Contracting officers will rely on representations from offers based on provisions in the solicitation. Entities are not required to, nor are they able to, update their entity registration to remove these representations in SAM.

52.252-2 Clauses Incorporated by Reference Feb 1998 This solicitation incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also the full text of the clause may be accessed electronically at Internet address https://www.acquisition.gov/far-overhaul/far-part-deviation-guide/far-overhaul-part-52

52.212-4 Terms and Conditions—Commercial Products and Commercial Services (Nov 2025) ☐ Alternate I (Nov 2025) of 52.212-4

This is a commercial construction acquisition. FAR 52.212-4 is amended as follows:

(b) Inspection/Acceptance. Inspection and Acceptance will be conducted in accordance with FAR 52.246-12, Inspection of Construction (Aug 1996).

(d) Changes. Changes will be handled in accordance with the following FAR clause(s):

☐ FAR 52.243-4, Changes (Nov 2025) ☒ FAR 52.243-5, Changes and Changed Conditions (Nov 2025)

52.203-17 Contractor Employee Whistleblower Rights (Nov 2023)

52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (Jan 2017) 52.222-50 Combating Trafficking in Persons (Nov 2025)

☐ Alternate I (Nov 2025) of 52.222-50 52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving (May 2024) 52.232-39 Unenforceability of Unauthorized Obligations (Jun 2013) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (Mar 2023) 52.233-3 Protest After Award (Sep 2025) 52.233-4 Applicable Law for Breach of Contract Claim (Sep 2025) 52.240-91 Security Prohibitions and Exclusions (Nov 2025)

☐ Alternate I (Nov 2025) of 52.240-91 52.244-6 Subcontracts for Commercial Products and Commercial Services (Nov 2025)

The following clauses are applicable if checked:

☐ 52.203-6 Restrictions on Subcontractor Sales to the Government (Jun 2020) with Alternate I (Nov 2021) of 52.203-6 ☐ 52.203-13 Contractor Code of Business Ethics and Conduct (Nov 2021) ☐ 52.204-9 Personal Identity Verification of Contractor Personnel Jan 2011 ☒ 52.204-13 System for Award Management—Maintenance (Nov 2025) ☐ 52.204-91 Contractor identification (Nov 2025) ☒ 52.209-6 Protecting the Government’s Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (Sep 2025) ☐ 52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters (Sep 2025) ☒ 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (Sep 2025) ☐ 52.219-4 Notice of Price Evaluation Preference for HUBZone Small Business Concerns (Nov 2025) ☐ 52.219-6 Notice of Total Small Business Aside (Nov 2025)

☐ Alternate I (Mar 2020).

☐ 52.219-8 Utilization of Small Business Concerns (Nov 2025) ☐ 52.219-9 Small Business Subcontracting Plan (Nov 2025)

☐ Alternate III (Nov 2025) of 52.219-9.

☐ Alternate IV (Nov 2025) of 52.219-9

☐ 52.219-14 Limitations on Subcontracting (Nov 2025) ☐ 52.219-16 Liquidated Damages—Subcontracting Plan (Nov 2025) ☐ 52.219-33 Nonmanufacturer Rule (Nov 2025) ☒ 52.222-3 Convict Labor (June 2003) ☒ 52.222-19 Child Labor—Cooperation with Authorities and Remedies (Nov 2025) ☐ 52.222-35 Equal Opportunity for Veterans (Nov 2025)

☐ Alternate I (Jul 2014) of 52.222-35 ☒ 52.222-36 Equal Opportunity for Workers with Disabilities (Nov 2025)

☐ Alternate I (Jul 2014) of 52.222-36

☐ 52.222-37 Employment Reports on Veterans (Nov 2025) ☐ 52.222-40 Notification of Employee Rights Under the National Labor Relations Act (Dec 2010) ☐ 52.222-41 Service Contract Labor Standards (Aug 2018) ☐ 52.222-42 Statement of Equivalent Rates for Federal Hires (May 2014)

This Statement is for Information Only:

It is not a Wage Determination

Employee Class Monetary Wage -- Fringe Benefits

☐ 52.222-43 Fair Labor Standards Act and Service Contract Labor Standards -- Price Adjustment (Multiple Year and Option Contracts) (Aug 2018) ☐ 52.222-44 Fair Labor Standards Act and Service Contract Labor Standards -- Price Adjustment (May 2014) ☐ 52.222-51 Exemption from Application of the Service Contract Labor Standards to Contracts for Maintenance, Calibration, or Repair of Certain Equipment-Requirements (May 2014) ☐ 52.222-53 Exemption from Application of the Service Contract Labor Standards to Contracts for Certain Services-Requirements (Nov 2025) ☐ 52.222-54 Employment Eligibility Verification (Nov 2025) ☐ 52.222-62 Paid Sick Leave Under Executive Order 13706 (Jan 2022) ☐ 52.223-9 Estimate of Percentage of Recovered Material Content for EPA-Designated Items (May 2008)

☐ Alternate I (May 2008) of 52.223-9 ☐ 52.223-11 Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons (Nov 2025) ☐ 52.223-12 Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air Conditioners (Nov 2025) ☐ 52.223-23 Sustainable Products and Services ☐ 52.224-3 Privacy Training (Jan 2017)

☐ Alternate I (Jan 2017) of 52.224-3 ☒ 52.225-1 Buy American-Supplies (Nov 2025)

☐ Alternate I (Oct 2022) of 52.225-1 ☐ 52.225-3 Buy American--Free Trade Agreements--Israeli Trade Act (Nov 2025)

☐ Alternate II (Nov 2025) of 52.225-3.

☐ Alternate III (Nov 2025) of 52.225-3.

☐ Alternate IV (Oct 2022) of 52.225-3

☐ 52.225-5 Trade Agreements (Nov 2023) ☐ 52.225-19 Contractor Personnel in a Designated Operational Area or Supporting a Diplomatic or Consular Mission outside the United States (May 2020) ☐ 52.225-26 Contractors Performing Private Security Functions Outside the United States (Oct 2016)

☐ 52.226-4 Notice of Disaster or Emergency Area Set-Aside (Nov 2007) ☐ 52.226-5 Restrictions on Subcontracting Outside Disaster or Emergency Area (Aug 2025) ☐ 52.229-12 Tax on Certain Foreign Procurements ☐ 52.232-29 Terms for Financing of Purchases of Commercial Products and Commercial Services (Nov 2021) ☐ 52.232-30 Installment Payments for Commercial Products and Commercial Services (Nov 2021) ☒ 52.232-33 Payment by Electronic Funds Transfer— System for Award Management (Oct 2018) ☐ 52.232-34 Payment by Electronic Funds Transfer—Other Than System for Award Management (Jul 2013) ☐ 52.232-36 Payment by Third Party (Nov 2025) ☐ 52.240-92 Security Requirements (Nov 2025)

☐ Alternate II (Nov 2025) of 52.240-92 ☐ 52.240-93 Basic Safeguarding of Covered Contractor Information Systems (No 2025) ☐ 52.247-64 Preference for Privately Owned U.S.-Flag Commercial Vessels (Nov 2025)

☐ Alternate I (Apr 2023) of 52.247-64.

☐ Alternate II (Nov 2021) of 52.247-64

The Contractor shall comply with the following FAR Clauses for Commercial Construction.

52.222-6 Construction Wage Rate Requirements 52.222-7 Withholding of Funds 52.222-8 Payrolls and Basic Records 52.222-9 Apprentices and Trainees 52.222-10 Compliance with Copeland Act Requirements 52.222-11 Subcontracts (Labor Standards) 52.222-12 Contract Termination-Debarment 52.222-14 Disputes Concerning Labor Standards 52.222-15 Certificate of Eligibility 52.236-5 Material and Workmanship

The following clauses are applicable when checked:

☐ 52.222-30 Construction Wage Rate Requirements-Price Adjustment (None or Separately Specified Pricing Method (Aug 2018) ☐ 52.222-31 Construction Wage Rate Requirements-Price Adjustment (Percentage Method) (Aug 2018) ☐ 52.222-32 Construction Wage Rate Requirements-Price Adjustment (Actual Method) (Nov 2025) ☒ 52.225-9 Buy American-Construction Materials (Nov 2025) ☐ Alternate I (Oct 2022) of 52.25-9 ☐ 52.225-11 Notice of Buy American Requirement-Construction Materials under Trade Agreements (Nov 2025) ☐ Alternate I (Nov 2025) (of 52.225-11

☐ Alternate II (Oct 2022) of 52.225-11 ☒ 52.228-2 Additional Bond Security (Oct 1997) ☐ 52.228-5 Insurance-Work on Government Installation (Jan 1997) ☒ 52.228-11 Individual Surety-Pledge of Assets (Feb 2021) ☒ 52.228-13 Alternative Payment Protections (Jul 2020) ☐ 52.228-14 Irrevocable Letter of Credit (Nov 2014) ☐ 52.228-15 Performance and Payment Bonds-Construction (Jun 2020) ☐ 52.228-17 Individual Surety-Pledge of Assets (Bid Guarantee) (Feb 2021) ☒ 52.236-2 Differing Site Conditions (Jul 2025) ☒ 52.236-3 Site Investigation and Conditions Affecting the Work (Jul 2025) ☒ 52.236-6 Superintendent by the Contractor (Jul 2025) ☒ 52.236-7 Permits and Responsibilities (Jul 2025) ☒ 52.236-8 Other Contracts (Jul 2025) ☒ 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (Jul 2025) ☒ 52.336-10 Operations and Storage Areas (Jul 2025) ☒ 52.236-11 Use and Possession Prior to Completion (Jul 2025) ☒ 52.236-12 Cleaning Up (Jul 2025) ☒ 52.236-13 Accident Prevention (Jul 2025) ☐ Alternate I (Nov 1991) of 52.236-13 ☒ 52.236-14 Availability and Use of Utility Services (Jul 2025) ☐ 52.236-15 Schedules for Construction Contracts (Jul 2025) ☐ 52.236-16 Quantity Surveys (Jul 2025) ☐ Alternate I (Apr 1984) of 52.236-16 ☒ 52.236-17 Layout of Work (Jul 2025) ☐ 52.236-21 Specifications and Drawings for Construction (Jul 2025) ☐ Alternate I (Apr 1984) of 52.236-21 ☐ Alternate II (Apr 1984) of 52.236-21 ☒ 52.242-14 Suspension of Work (Apr 1984) ☐ 52.248-3 Value Engineering (Oct 2025) ☐ Alternate I (Apr 1984) of 52.248-3

Other Applicable Clauses

52.247-34 F.O.B. Destination (Jan 1991)

AGAR Clauses

452.203-71 Anti-Discrimination and Diversity, Equity, and Inclusion (DEI) Compliance (Dec 2025)

(a) By entering into this contract, the Contractor certifies that:

1. It is compliant with all applicable Federal anti-discrimination laws and the Equal Protection principles of the U.S. Constitution, and it will remain compliant for the duration of the contract.

2. Neither it nor any subcontractor or teaming partner operates or funds any program, policy, or initiative that promotes DEI in a manner that violates any applicable Federal anti-discrimination laws, including but not limited to Title VI and VII of the Civil Rights Act of 1964, or the Equal Protection principles of the U.S. Constitution, and the Contractor and any subcontractor or teaming partner will not do so for the duration of the contract.

(b) If the Contractor participates in, facilitates, or funds programs that implicate Title VI of the Civil Rights Act of 1964 or Title IX of the Education Amendments of 1972, as amended, including but not limited to grants to or for schools, colleges, universities, 4-H programs, non-governmental organization (NGO) programs, sports programs, and education-related grants to prisons or other detention facilities, the Contractor certifies that it will remain compliant with those laws, including the requirements set forth in Executive Order 14168, Defending Women from Gender Ideology Extremism and Restoring Biological Truth to the Federal Government, and Executive Order 14173, Ending Illegal Discrimination and Restoring Merit-Based Opportunity.

(c) The Contractor affirms that the above requirements are conditions of payment that go to the essence of the contract and are therefore material terms of the contract. Payments under the contract are predicated on compliance with the above requirements, and therefore the Contractor is not eligible for funding under the contract or to retain any funding under the contract absent compliance with the above requirements.

(d) This certification reflects a change in the Government’s position regarding the materiality of the foregoing requirements and therefore any prior payment of similar claims does not reflect the materiality of the foregoing requirements to this contract.

(e) Submission of a knowing false statement relating to Contractor’s compliance with the above requirements and/or eligibility for the contract may subject the Contractor to liability under the False Claims Act, 31 U.S.C. § 3729, and/or criminal liability, including under 18 U.S.C. §§ 287 and 1001.

(f) The Contractor must include the provisions of this clause in all subcontract solicitations.

(g) Failure on the part of the Contractor or its subcontractors to comply with the terms of this clause may be grounds for the Contracting Officer to terminate this contract for default.

(End of Clause)

452.204–70 Modification for Contract Closeout (Nov 2025)

(a) If unliquidated funds in the amount of $1000 or less remain on the contract, the Contracting Officer (Contracting Officer) shall issue a unilateral modification for deobligation. The contractor will receive a copy of the modification but will not be required to provide a signature. The Contracting Officer shall immediately proceed with contract closeout upon completion of the period of performance, receipt and acceptance of supplies or services, and final payment.

(b) Upon contract closeout for contracts utilizing SAP: if unliquidated funds of more than $1000 remain on the contract, the Contracting Officer shall issue a bilateral modification for deobligation.

The contractor will receive a copy of the modification and will be required to provide a signature.

(The Contracting Officer may also request a “Contractor Release of Claims” be completed by the contractor, although not required for contracts and orders using SAP.) If the bilateral modification and Release of Claims are not returned to the Contracting Officer within 60 days, the Contracting Officer shall release the modification as unilateral and proceed with contract closeout upon completion of the period of performance, receipt and acceptance of supplies or services, and final payment.

(c) Upon contract closeout for contracts utilizing anything other than cost reimbursement, if unliquidated funds of more than $1000 remain on the contract, the Contracting Officer shall issue a bilateral modification for deobligation. The contractor will receive a copy of the modification and a ‘‘Contractor Release of Claims’’ and will be required to provide a signature on both forms. If the bilateral modification and Release of Claims are not returned to the Contracting Officer within 120 days, the Contracting Officer shall release the modification as unilateral and proceed with contract closeout upon completion of the period of performance, receipt and acceptance of supplies or services, and final payment.

(End of Clause)

452.232-71 Progress Payments for Commercial Construction Contracts (Dec 2025)

(a) Contractor entitlement to progress payments. The Contractor may request progress payments monthly as the work proceeds, or at more frequent intervals as determined by the Contracting Officer, on estimates of work accomplished that meets the standards of quality established under the contract, as approved by the Contracting Officer.

(b) Computation of amounts. Progress payments will be authorized when the payment requested is properly due in accordance with this contract; the work will be performed in accordance with the contract; and there has been no impairment or diminution of the Government’s security under this contract. The Contracting Officer may authorize consideration of:

3. Materials delivered on site and preparatory work;

4. Materials delivered to the Contractor at locations other than the site, if:

i. Specifically authorized by the contract; and

ii. The Contractor provides satisfactory evidence of title and intended use in the contract.

(c) Contractor request for progress payments. The Contractor’s request for progress payments shall include the following:

1. An itemization of the amounts requested, related to the various elements of work required by the contract;

2. A listing of the amount included for work performed by each subcontractor;

3. A listing of the total amount of each subcontract;

4. A listing of the amounts previously paid to each subcontractor; and

5. Additional supporting data in a form and detail required by the Contracting Officer.

(d) Contractor Certification. Each request for progress payment shall be accompanied by the following certification:

I hereby certify, to the best of my knowledge and belief, that—

1. The amounts requested are only for performance in accordance with the specifications, terms, and conditions of the contract;

2. All payments due to subcontractors and suppliers from previous payments received under the contract have been made, and timely payments will be made from the proceeds of the payment covered by this certification, in accordance with subcontract agreements and the requirements of Chapter 39 of Title 31, United States Code;

3. This request for progress payments does not include any amounts which the prime contractor intends to withhold or retain from a subcontractor or supplier in accordance with the terms and conditions of the subcontract; and

4. This certification is not to be construed as final acceptance of a subcontractor’s performance.

________________________________________________(name) ________________________________________________(title) ________________________________________________(date)

(e) Access for verification of payment entitlement. To verify the Contractor’s entitlement to progress payments under this contract, the Contractor shall provide the Government, upon request and during normal business hours, access to the following:

1. Records and Documentation:

(i) Certified progress payment requests and supporting documentation;

(ii) Subcontractor and supplier invoices, payment records, and lien waivers;

(iii)Updated schedule of values and progress schedules;

(iv) Quality assurance and inspection reports;

(v) Payroll records, if applicable under labor provisions.

2. Facilities and Worksite Access:

(i) Physical access to the construction site for inspection of work progress;

(ii) Access to off-site storage locations for materials billed but not yet incorporated into the work; or (iii)Access to any fabrication facilities where contract-related work is being performed.

3. Access to electronic invoicing or project management systems used to track progress and payments, if such systems are used in contract performance.

(f) Dates for payment. A progress payment under this clause is a contract progress payment under the Prompt Payment clause of this contract, and except as provided in paragraph (g) of this clause, approved requests shall be paid within 30 days of submittal of a proper request for payment.

(g) Liquidation of progress payments. Progress payments shall be liquidated by deducting from the payment of each item the total unliquidated amount of progress payments made for that separately priced unit of that line item. The liquidation amounts for each line item shall be clearly delineated in each request for progress payment submitted by the Contractor.

(h) Security for progress payments. In the event the Contractor fails to provide adequate security as required in this contract, no progress payment shall be made under this contract. Upon receipt of adequate security, progress payments shall be made, including all previous payments to which the Contractor is entitled, in accordance with the terms of the contract. If at any time the Contracting Officer determines that the security provided by the Contractor is insufficient, the Contractor shall promptly provide such additional security as the Contracting Officer determines necessary. In the event the Contractor fails to provide such additional security, the Contracting Officer may collect or liquidate such security that has been provided, and suspend further payments to the Contractor; the Contractor shall repay to the Government the amount of unliquidated progress payments as the Contracting Officer at his sole discretion deems repayable.

(i) Special terms regarding termination for cause. If this contract is terminated for cause, the Contractor shall, on demand, repay to the Government the amount of unliquidated progress payments. The Government shall be liable for no payment except as provided by the Termination for Cause paragraph of the clause at Federal Acquisition Regulation 52.212-4, Contract Terms and Conditions—Commercial Products and Commercial Services.

(j) Reservation of rights.

1. No payment, vesting of title under this clause, or other action taken by the Government under this clause shall-

(i) Excuse the Contractor from performance of obligations under this contract; or

(ii) Constitute a waiver of any of the rights or remedies of the parties under the contract.

2. The Government’s rights and remedies under this clause-

(i) Shall not be exclusive, but rather shall be in addition to any other rights and remedies provided by law or this contract; and

(ii) Shall not be affected by delayed, partial, or omitted exercise of any right, remedy, power, or privilege, nor shall such exercise or any single exercise preclude or impair any further exercise under this clause or the exercise of any other right, power, or privilege of the Government.

(k) Refund of unearned amounts. If the Contractor, after making a certified request for progress payments, discovers that a portion or all of such request constitutes a payment for performance by the Contractor that fails to conform to the specifications, terms, and conditions of this contract (hereinafter referred to as the "unearned amount"), the Contractor shall-

1. Notify the Contracting Officer of such performance deficiency; and

2. Be obligated to pay the Government an amount (computed by the Contracting Officer in the manner provided in paragraph (j) of this clause) equal to interest on the unearned amount from the 8th day after the date of receipt of the unearned amount until-

(i) The date the Contractor notifies the Contracting Officer that the performance deficiency has been corrected; or

(ii) The date the Contractor reduces the amount of any subsequent certified request for progress payments by an amount equal to the unearned amount.

(l) Retainage. If the Contracting Officer finds that satisfactory progress was achieved during any period for which a progress payment is to be made, the Contracting Officer shall authorize payment to be made in full. However, if satisfactory progress has not been made, the Contracting Officer may retain a maximum of 10 percent of the amount of the payment until satisfactory progress is achieved. When the work is substantially complete, the Contracting Officer may retain from previously withheld funds and future progress payments that amount the Contracting Officer considers adequate for protection of the Government and shall release to the Contractor all the remaining withheld funds. Also, on completion and acceptance of each separate building, public work, or other division of the contract, for which the price is stated separately in the contract, payment shall be made for the completed work without retention of a percentage.

(m) Title, liability, and reservation of rights. All material and work covered by progress payments made shall, at the time of payment, become the sole property of the Government, but this shall not be construed as-

1. Relieving the Contractor from the sole responsibility for all material and work upon which payments have been made or the restoration of any damaged work; or

2. Waiving the right of the Government to require the fulfillment of all the terms of the contract.

3. The Government’s rights and remedies under this clause-

(i) Shall not be exclusive, but rather shall be in addition to any other rights and remedies provided by law or this contract; and

(ii) Shall not be affected by delayed, partial, or omitted exercise of any right, remedy, power, or privilege, nor shall such exercise or any single exercise preclude or impair any further exercise under this clause or the exercise of any other right, power, or privilege of the Government.

(n) Reimbursement for bond premiums. In making these progress payments, the Government shall, upon request, reimburse the Contractor for the amount of premiums paid for performance and payment bonds (including coinsurance and reinsurance agreements, when applicable) after the Contractor has furnished evidence of full payment to the surety. The retainage provisions in paragraph (l) of this clause shall not apply to that portion of progress payments attributable to bond premiums.

(o) Final payment. The Government shall pay the amount due the Contractor under this contract after-

1. Completion and acceptance of all work;

2. Presentation of a properly executed voucher; and

3. Presentation of release of all claims against the Government arising by virtue of this contract, other than claims, in stated amounts, that the Contractor has specifically excepted from the operation of the release. A release may also be required of the assignee if the Contractor’s claim to amounts payable under this contract has been assigned under the Assignment of Claims Act of1940 ( 31 U.S.C.3727 and 41 U.S.C. 6305).

(p) Limitation because of undefinitized work. Notwithstanding any provision of this contract, progress payments shall not exceed 80 percent on work accomplished on undefinitized contract actions. A "contract action" is any action resulting in a contract, as defined in FAR subpart 2.1, including contract modifications for additional supplies or services, but not including contract modifications that are within the scope and under the terms of the contract, such as contract modifications issued pursuant to the Changes clause, or funding and other administrative changes.

(End of clause)

Solicitation Information

Award Type

It is anticipated that a Firm Fixed price Contract will be awarded as a result of this synopsis/solicitation.

The Government intends to make one award from this solicitation. Therefore, to be considered responsive, contractors must submit pricing for all items.

Period of Performance

300 days from Notice to Proceed (NTP)

Organized Site Visit

(a) A single organized site visit has been scheduled for 09:00 a.m. Central Time on Tuesday April 28, 2026.

Vendors are urged and expected to inspect the site where services are to be performed and to satisfy themselves as to all general and local conditions which may affect the cost of performance of the contract, to the extent such information is reasonably available. In no event will a failure to inspect the site constitute grounds for a claim after award of contract.

For the site visit, we ask the following:

• Visitors bring photo identification. Non-US citizens should bring a passport.

• Visitors must sign-in and out.

(b) All individuals interested in attending the site visit must RSVP by emailing spencer.hamilton@usda.gov and kyle.tiner@usda.gov, no later than 12:00 p.m. Central Time on Monday April 27, 2026, with a list of names of attendees. This is necessary to ensure that the site is prepared for the number of visitors expected.

(c) Participants will meet at:

United States Department of Agriculture (USDA), Agricultural Research Service (ARS) Grassland Soil and Water Research Laboratory (GSWRL) 1702 Blackland Rd.

Riesel, TX 76682

Attendees will meet at the main entrance to sign-in. Mud boots are recommended.

Questions

All questions pertaining to this solicitation, including questions that arise during the site visit, must be submitted to spencer.hamilton@usda.gov by 12:00 p.m. Central Time, Friday, May 1, 2026.

Questions that are not submitted in writing or that are not submitted by this deadline above may not receive a response. Questions/answers discussed at the site visit will not be binding on the resultant contract unless submitted in writing and incorporated into the solicitation by amendment.

Quote Submission Instructions

(a) To be considered for award, quotes must be submitted by email to Spencer Hamilton at spencer.hamilton@usda.gov. Any other method of submitting your quote will result in your quote not being considered. Quote submission date and time is stated on https://sam.gov/contracting for subject solicitation number 1232SA26Q0455.

(b) quote submission must include:

(1) Email quote as described above including pricing, signatures, SAM Unique Entity Identifier (UEI) # on the SF-1442 form

(2) Acknowledgement of any solicitation amendment(s) on SF-30.

(3) Active registration at SAM.gov (required at quote submission or your quote will not be accepted).

(4) Completed electronic annual representations and certifications at SAM.gov. No separate submission required if reps and certs are already completed at SAM.gov. The government will validate this is completed at time of quote receipt. If reps and certs are not filled out in SAM.gov, these shall be filled out and accompanied with your quote.

(5) Technical Experience: Quote shall adequately describe your company’s technical experience in performing similar projects. Quote shall include a detailed descriptive listing of three (3) projects performed within the past five (5) years that are similar in nature to the one described in this solicitation. “Similar” is defined as projects comparable in terms of such factors as duration, dollar value, installation, replacement, and repair for types of services performed or level of Contractor responsibility and authority. The quote shall adequately describe how the project will be completed within the period of performance.

(6) Past Performance:

a. Provide relevant examples of Past Performance for three (3) previous projects that the offeror has performed within the previous 5 years. The projects should be similar to the requirements of this project in terms of scope, dollar value, and level of complexity and nature of effort. The examples must include: (a) a detailed explanation of the complexity and nature of effort; (b) the dollar value;

(c) period of performance;(d) project location; and (e) valid email address; point of contact and telephone number.

b. Contractor Performance Assessment Reporting System (CPARS) evaluations may be submitted by the offeror to satisfy the requirement. The offeror is responsible for ensuring each CPARS evaluation submitted meets the criteria of “similar (in terms of dollar value, type of work performed, and level of complexity) contracts in which it has participated during the past 5 years.”

c. The Government reserves the right to contact references for verification or additional information.

d. The Government reserves the right to determine whether an example of past performance is relevant to the requirement. If an example of past performance submitted is determined to be non-relevant, it will not be further evaluated for quality of performance.

e. The Government reserves the right to use past performance information obtained from sources other than those identified by the offeror, including but not limited to past performance information located in the Contractor Performance Assessment Reporting System (CPARS). When problems were encountered briefly describe the problem areas and the steps taken to resolve or correct. For those contracts with less than positive performance, you are encouraged to provide a description of the problems and the efforts made to correct and to prevent future occurrences.

(7) Price: Pricing for Base Item and all Option Items.

Evaluation and Basis for Award

The provision at Federal Acquisition Regulation (FAR) 52.212-2 Evaluation of Commercial Items is not applicable to this solicitation. In lieu of this provision, quotes will be evaluated in accordance with FAR 12.203 based on the criteria listed below. Award will be made to the quoter representing the best value to the Government.

Evaluation Method

The Government will evaluate quotations based on the lowest price technically acceptable criteria.

Only the lowest priced quote will be evaluated for Technical Acceptability. Should the lowest priced quote not receive an acceptable technical rating, the process will continue in order of lowest priced quote until the lowest price, technically acceptable quote is identified.

Technical Acceptability:

Technical Acceptability will be evaluated to receive an overall rating of "acceptable" or "unacceptable." This will be based on the quoter's ability to provide a sound and compliant approach that meets all requirements and shows a thorough understanding of them. It is the quoter’s responsibility to ensure their quotation clearly demonstrates their capability to meet these requirements. All quoters must provide the above-referenced minimum information and documentation with their quotations to be considered responsive and have their quotes evaluated.

The Government will evaluate the quoter’s ability to meet all the requirements identified in the

SOW.

Technical Experience – The Government will evaluate the extent of recent, relevant experience of the quoter (including subcontractors) regarding their role on this project. Federal Government project experience will not be rated inherently more important than non-Federal Government project experience. The Government will evaluate the experience submitted to see that it demonstrates capability to execute projects that are similar in size, scope, and complexity to this requirement.

Specialized experience will be rated to the extent the quoter can clearly and fully demonstrate that it has a thorough understanding of the requirements and can successfully meet the requirements.

Past Performance – Past Performance evaluation considers each offeror’s demonstrated recent and relevant record in performing similar project work. Past performance is a measure of the degree to which an offeror satisfied its customers in the past, complied with contract schedule, and adherence to the contract specifications. Past performance is also a measure of the risk of performance associated with the offeror. The Government will assess the offeror’s record of past performance on similar contracts as an indicator of success under this requirement.

For an quoter to be eligible for award, it must have either a “acceptable” or neutral past performance.

Offers with negative past performance information from any source may not be considered for award. Lack of relevant and recent past performance information shall be rated as a “Neutral.” When performance is evaluated, the outcome is either Acceptable or Unacceptable. Unacceptable performance will disqualify a quoter from award. Acceptable or neutrally rated past performance will be rated as Acceptable. The Government may utilize any references provided by the Contractor, along with information available from past contracts/orders with the USDA and any information found using sources such as Federal Government sources, Past Performance Information Retrieval System (PPIRS)/Contractor Performance Assessment Reporting System (CPARS) to determine if the Contractor has acceptable or neutral Past Performance. The Government reserves the right to limit or expand the number of references it decides to contact and to contact references other than those provided by the offeror.

Price:

The quoter shall provide pricing as requested in the schedule of items. Any quantity price discounts and discounts for prompt payment should be included in this section. The quotation will be evaluated in accordance with FAR 12.204, to determine if it is fair and reasonable.

52.252-1 Solicitation Provisions Incorporated by Reference Feb 1998 This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es): https://www.acquisition.gov/far-overhaul/far-part-deviation-guide/far-overhaul-part-52

52.212-1 Instructions to Offerors - Commercial Products and Commercial Services (Nov 2025)

FAR 52.212-1 is amended as follows:

Period for acceptance of offers.

The Offeror agrees to hold the prices in its offer firm for 120 calendar days from the date specified for receipt of offers.

52.203-18 Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements-Representation (Jan 2017) 52.209-2 Prohibition on Contracting with Inverted Domestic Corporations - Representation (Sep 2025) 52.209-11 Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law (Sep 2025) 52.240-90 Security Prohibitions and Exclusions Representations and Certifications (Nov 2025)

The following provisions are applicable if checked:

☐ 52.203-11 Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions (Sep 2024) ☒ 52.204-7 System for Award Management—Registration (Nov 2025)

☐ Alternate I (Nov 2025) to 52.204-7 ☐ 52.204-90 Offeror Identification (Nov 2025) ☐ 52.207-6 Solicitation of Offers from Small Business Concerns and Small Business Teaming Arrangements or Joint Ventures (Multiple-Award Contracts) (Aug 2024) ☐ 52.209-12 Certification Regarding Tax Matters (Oct 2025) ☐ 52.219-2 Equal Low Bids (Nov 2025) ☐ 52.222-5 Construction Wage Requirements, Secondary Site of the Work (Nov 2025) ☐ 52.222-18 Certification Regarding Knowledge of Child Labor for Listed End Products (Feb 2021) ☐ 52.222-48 Exemption from Application of the Service Contract Labor Standards for Maintenance, Calibration, or Repair of Certain Equipment–Certification (Nov 2025) ☐ 52.222-52 Exemption from Application of the Service Contract Labor Standards for Certain Services-Certification (Nov 2025) ☐ 52.222-56 Certification Regarding Trafficking in Persons Compliance Plan (Oct 2020) ☐ 52.223-4 Recovered Material Certification (May 2008) ☒ 52.225-2 Buy American Certificate (Oct 2022) ☐ 52.225-4 Buy American-Free Trade Agreements-Israeli Trade Act Certificate (Nov 2025)

☐ 52.225-6 Trade Agreements-Certificate (Feb 2021) ☒ 52.225-10 Notice of Buy American Requirement- Construction Materials (May 2014) ☐ Alternate I (May 2014) of 52.225-10 ☐ 52.225-12 Notice of Buy American Requirement-Construction Materials under Trade Agreements (May 2014) ☐ Alternate I (May 2014) of 52.225-12 ☐ Alternate II (Nov 2023) of 52.225-12

☐ 52.226-3 Disaster or Emergency Area Representation (Nov 2007) ☐ 52.228-1 Bid Guarantee (Sep 1996) ☐ 52.229-11 Tax on Certain Foreign Procurements—Notice and Representation (Jul 2025)

Other Applicable FAR Provisions

52.233-2 Service of Protest (Sep 2025)

AGAR Provisions

452.203-70 Anti-Discrimination and Diversity, Equity, and Inclusion (DEI) Certification (Dec 2025)

(a) By submission of its offer, the offeror certifies that:

1. It is compliant with all applicable Federal anti-discrimination laws and the Equal Protection principles of the U.S. Constitution.

2. Neither it nor any proposed subcontractor or teaming partner operates or funds any program, policy, or initiative that promotes DEI in a manner that violates any applicable Federal anti-discrimination laws, including but not limited to Title VI and VII of the Civil Rights Act of 1964, or the Equal Protection principles of the U.S. Constitution.

(b) If the offeror participates in, facilitates, or funds programs that implicate Title VI of the Civil Rights Act of 1964 or Title IX of the Education Amendments of 1972, as amended, including but not limited to grants to or for schools, colleges, universities, 4-H programs, non-governmental organization (NGO) programs, sports programs, and education-related grants to prisons or other detention facilities, by submission of its offer, the offeror certifies that it is compliant with those laws, including the requirements set forth in Executive Order 14168, Defending Women from Gender Ideology Extremism and Restoring Biological Truth to the Federal Government, and Executive Order 14173,…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .