ATTACHMENT A-S-62900-0014548_ODF_FG_Exterior Rehab Specifications.pdf

PDF 7 MB Posted

Attached to
Forest Grove Warehouse & Fire Cache Siding & Windows ReplacementWindows and Siding
Solicitation number
S-62900-00014548
Issued by
Washington County, Oregon

About this file

This file is a comprehensive Project Specification document for the Oregon Department of Forestry's Forest Grove District Buildings Siding and Window Rehabilitation Project (Project Number 25-095), involving two operational buildings located at 801 Gales Creek Rd, Forest Grove, Oregon. The project scope includes repairing and replacing exterior wall systems, windows, and associated components for the Warehouse and Fire Cache Buildings. Specifically, the work involves removing and replacing 100% of existing siding, trim, windows, gutters, downspouts, and roof overhang components. The project is scheduled for implementation in 2025, with an issue date of August 4, 2025, and requires comprehensive documentation, quality control, and adherence to specified installation standards.

The project will be executed using James Hardie fiber cement siding and trim products, with Milgard V250 Style Line Series windows, and will include specialized treatments for asbestos and lead paint. The contractor must be a licensed Commercial General Contractor with specific qualifications, including 10 years of reclad experience and successful completion of similar renovation projects. Financial terms include stainless steel fasteners, specific installation requirements, and warranties covering workmanship (2 years) and products (30-year transferable limited warranty). The project emphasizes moisture control, proper installation techniques, and compliance with Oregon State Building Code requirements, with a focus on maintaining the existing buildings' functionality and aesthetic qualities during renovation.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Oregon Department of Forestry Forest Grove District Buildings

SI

D

IN

G

W

IN

D

O W

R

EH

A

B

IL

IT

A

TI

N

PR

JE

C

T

SP

EC

IF

IC

A

TI

O

N S

PDFPREPARED FOR: Oregon Department of

Forestry 2600 State Street, Salem, OR 97310

PROJECT ADDRESS: 801 Gales Creek Rd, Forest Grove, OR 97116

PROJECT NUMBER: 25-095

ISSUE DATE: 08.04.2025

REVISION DATE(S):

Permit Issue Set

PREPARED BY:

12901 SE 97TH AVE SUITE 310

CLACKAMAS, OR 97015

www.forensicbuilding.com http://www.forensicbuilding.com/

Oregon Department of Forestry 2025.08.04 Forest Grove District Buildings PROJECT SPECIFICATIONS Siding & Window Rehabilitation (25-095)

FBC TABLE OF CONTENTS 00 01 10 - 1

SECTION 00 01 10

TABLE OF CONTENTS

1.01 DIVISION 00 -- PROCUREMENT AND CONTRACTING REQUIREMENTS

A. 00 01 10 - Table of Contents

2.01 DIVISION 01 -- GENERAL REQUIREMENTS

A. 01 00 00 - General Requirements B. 01 10 00 - Summary of Work C. 01 31 00 - Project Management and Coordination D. 01 33 00 - Submittal Procedures E. 01 40 00 - Quality Requirements F. 01 42 00 - References G. 01 50 00 - Temporary Facilities and Controls H. 01 60 00 - Product Requirements I. 01 73 00 - Execution J. 01 74 19 - Construction Waste Management and Disposal K. 01 77 00 - Closeout Procedures L. 01 78 00 – Closeout Submittals M. 01 78 23 - Operation and Maintenance Data

2.02 DIVISION 02 -- EXISTING CONDITIONS (NOT USED)

2.03 DIVISION 03 -- CONCRETE (NOT USED)

2.04 DIVISION 04 -- MASONRY (NOT USED)

2.05 DIVISION 05 -- METALS

2.06 DIVISION 06 -- WOOD, PLASTICS, AND COMPOSITES

A. 06 10 00 - Rough Carpentry B. 06 16 00 – Wood Sheathing C. 06 45 50 – Fiber Cement Trim

2.07 DIVISION 07 -- THERMAL AND MOISTURE PROTECTION

A. 07 21 00 - Thermal Insulation B. 07 25 00 – Weather Barriers C. 07 46 46 – Fiber Cement Siding D. 07 62 00 – Sheet Metal Flashing and Trim E. 07 65 00 – Flexible Flashing

FBC TABLE OF CONTENTS 00 01 10 - 2

F. 07 71 23 – Gutters and Downspouts G. 07 90 05 – Joint Sealants

2.08 DIVISION 08 – OPENINGS

A. 08 14 36 – Hinged Entry Doors B. 08 53 13 – Vinyl Windows

2.09 DIVISION 09 – FINISHES

A. 09 90 00 – Painting and Coating

2.10 DIVISION 26 – ELECTRICAL (NOT USED)

DIVISIONS 11-25, 27-33 NOT USED

END OF SECTION

FBC GENERAL REQUIREMENTS 01 00 00 - 1

SECTION 01 00 00

GENERAL REQUIREMENTS

PART 1 GENERAL: Must conform to the conditions of Exhibit 6 and Exhibit 7 of the State of Oregon General conditions section. If any conflicts exist compliance with Exhibit 6 General Conditions and Exhibit 7 will be the guiding requirement.

1.01 DESCRIPTION

A. Contracts:

1. It is assumed that Exhibit 6 of the ITB, is the basis for the General Conditions between the Owner and Contractor.

a. The Building Envelope Consultant is represented by Forensic Building

Consultants.

b. Forensic Building Consultants is not an Architectural Firm (see ORS 606-010-

0078.2.d) B. Project Parameters: The Work described in the Contract Documents does not include the following (see ORS 671.030):

1. Alterations or repair to the structural parts of the building, including but not limited to the foundation walls, floors, roof, footings, bearing partitions, beams, columns and joists

2. Changing the building code classification of the building’s Use or Occupancy

3. Changing the building code classification of the building’s Type.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION

A. Responsible Person in Charge:

1. Mr. Jerry Wyatt

2. Email: jwyatt@forensicbuilding.com

3. Phone: (503) 989-9950

4. Mr. Toby White

5. Email: toby@forensicbuilding.com

6. Phone: (503) 772-1114 mailto:jwyatt@forensicbuilding.com mailto:toby@forensicbuilding.com

FBC SUMMARY OF WORK 01 10 00 - 1

SECTION 01 10 00

SUMMARY OF WORK

PART 1 GENERAL INFORMATION

1.01 SECTION INCLUDES

A. General Information B. General Description of the Work C. Project Requirements

1.02 PROJECT INFORMATION

A. Project Name:

1. Oregon Department of Forestry Forest Grove District Buildings Siding and Window

Rehabilitation (25-095)

B. Project Location:

1. Oregon Department of Forestry

801 Gales Creek Rd, Forest Grove, OR 97116

C. Owner:

1. Oregon Department of Forestry 2600 State Street, Building F Salem, OR 97301

Wayne Newman, Northwest Area Facilities Operations Specialist Phone: 971.446.0891 Email: Wayne.L.Newman@odf.oregon.gov

1.03 PROJECT DESCRIPTION

A. The Oregon Department of Forestry Siding and Window Replacement (Project) is to repair and/or replace portions of the building envelope’s existing exterior wall system which are determined to have deficiencies. The project includes replacement of the existing exterior wall systems and windows at (2) operations buildings: the Forest Grove Warehouse & Fire Cache Buildings as more fully detail below.

B. The Oregon Department of Forestry Forest Grove district campus in Forest Grove Oregon is a compound of nine (9) facility operations buildings. Buildings within the compound have varied years of development with limited documentation relating to original design and construction.

C. Warehouse Building: The proposed building enclosure rehabilitation shall consist of removal, disposal, and replacement of all existing siding, trim and windows along each elevation and include concealed weather-resistive barrier (“WRB”) and flashings. Removal, disposal, and replacement of the existing swing door unit on the north elevation and sliding barn-style door on the east elevation. Removal, safe storage, and reinstallation of remaining existing swing door units. Removal, disposal, and replacement of 100% gutters and downspouts. Removal and replacement of 100% existing gable roof overhang barge boards. Installation of new eave overhang roof fascia boards. Note: Existing roofing is not within the project scope and shall mailto:Wayne.L.Newman@odf.oregon.gov

FBC SUMMARY OF WORK 01 10 00 - 2

require removal and replacement of existing shingles as necessary to incorporate roof edge fascia and flashing components

D. Fire Cache Building: The proposed building enclosure rehabilitation shall consist of removal, disposal, and replacement 100% of all existing siding, trim and windows along each elevation and include concealed WRB (as occurs) and utility penetrations. Where single-wall construction occurs at existing T1-11 and cedar panels, if deemed appropriate, panels may be used as wall sheathing. Removal, disposal, and replacement of all existing window units and associated trims.

At identified rear window location (refer to elevations on detail set) the B.O.D shall be to infill window R.O. with 2x wood stud framing, exterior and interior sheathing, and installation of a “new” through-wall PTAC cooling and heating unit. Removal, safe storage, and reinstallation of all swing doors. Flash in place existing roll-up garage style doors. Removal, disposal, and replacement of 100% gutters and downspouts. Removal and replacement of 100% existing gable roof overhang barge boards. Installation of new eave overhang roof fascia boards. Note:

Existing roofing is not within the project scope and shall require removal and replacement of existing shingles as necessary to incorporate roof edge fascia and flashing components.

E. Select windows tested positive for Asbestos containing materials on both buildings within the scope of service and therefore all windows should be treated as, assumed to be positive for Asbestos containing materials. Test results attached in the ITB as Attachment C Asbestos Testing Results.

F. The buildings withing the scope of service have tested positive for lead paint. While these buildings are not subject to some Oregon lead based paint rules, others may apply. It will be the contractor’s sole responsibility to perform all necessary testing and comply with applicable federal, state, and local regulations related to lead paint as it applies to this project.

1.04 BUILDING ENVELOPE CONSULTANT

A. Consultant Name:

1. Forensic Building Consultants B. Consultant Address:

1. 12901 SE 97th Ave Suite 310, Clackamas, Oregon, 97015 C. Contact:

1. Project Manager: Jerry Wyatt

2. E-mail: jwyatt@forensicbuilding.com

3. Phone: 503.772.1114

4. Technical Design: Michael Green

5. E-mail: michaelg@forensicbuilding.com

6. Phone: 503.772.1114

1.05 DEFINITIONS

A. Definitions of terms throughout the Project documents are as follows:

1. Project Team: The Project team consists of the Owner’s authorized representative, the Building Envelope Consultant, and the Contractor mailto:michaelg@forensicbuilding.com

FBC SUMMARY OF WORK 01 10 00 - 3

2. Primary Quality Assurance: It is the Contractor’s responsibility to employ its own system of primary quality assurance, which for the purposes of this Project is defined as the prevention and detection of defects in workmanship and verification of proper installation of building components for the Project.

3. Supplemental Quality Assurance: It is the Building Envelope Consultant’s role during construction to provide supplemental quality assurance, which for the purposes of this Project is defined as periodic inspections of a sample of the work completed by the Contractor or its subcontractors to review compliance with regard to the Project’s contract documents, specifications, and details.

4. Quality Control: It is the product installers’ responsibility to employ it own system of Quality Control, which for the purposes of this Project is defined as employing a system for verifying and maintaining an acceptable level of quality during installation of the Work by careful planning, use of proper equipment, continued inspection, and corrective action as required to achieve compliance with the Contract Documents.

B. Definitions of typical acronyms used throughout the Project documents are as follows:

1. FBC: Forensic Building Consultants

2. OSB: Oriented Strand Board

3. PT: Pressure-Treated

4. SAM: Self-Adhered Membrane

5. SS: Stainless Steel

6. WRB: Water-Resistive Barrier

7. BOD: Basis-of-Design

8. R&R: Remove and Reinstall

9. FIP: Flash-in-Place

10. Code: The most recent building code enforced by the jurisdiction and state of Oregon.

1.06 RELATED REQUIREMENTS

A. Section 01 00 00 - General Requirements B. Section 01 31 00 – Project Management and Coordination C. Section 01 33 00 – Submittal Procedures and Section B of Exhibit 6 of the ITB D. Section 01 40 00 - Quality Requirements E. Section 01 42 00 - References F. Section 01 50 00 - Temporary Facilities and Controls G. Section 01 60 00 - Product Requirements H. Section 01 73 00 - Execution I. Section 01 74 19 - Construction Waste Management and Disposal J. Section 01 77 00 – Closeout Procedures K. Section 01 78 00 – Closeout Submittals L. Section 01 78 23 – Operation and Maintenance Data

FBC SUMMARY OF WORK 01 10 00 - 4

1.07 OWNER OCCUPANCY

A. Owner intends to continuously occupy all portions of the existing buildings during the entire construction period.

B. Contractor shall schedule the work to accommodate continuous Owner occupancy.

C. Contractor shall cooperate with the Owner to minimize conflict and to facilitate the Owner’s operations.

1.08 CONTRACTOR USE OF SITE

A. Construction Operations are limited to the areas noted on Design Package Drawings.

B. Provide access to and from site as required by law or by the Owner.

C. Emergency Building Exits During Construction:

1. Keep all exits open as required by code during construction period.

2. Provide temporary signs if exit routes are temporarily altered or impeded.

D. Do not obstruct roadways, sidewalks, or public rights of way without permit.

1.09 CONSULTANT ROLE AND DISCLAIMER

A. Building Envelope Consultant is not, nor does it claim to be, a building inspector.

B. Building Envelope Consultants’ previous work at the Project was limited to visual review and destructive testing of a portion of the installed building envelope assemblies as part of an investigative process including an appropriate repair protocol for the Project.

C. Because no investigation was conducted that included the complete removal of the Project’s exterior cladding, roofing, and fenestration systems, there remains the possibility of concealed property damage, water leakage, and/or nonconforming conditions that Consultant could neither detect, document, nor report on.

D. Consultant reserves the rights to amend, modify, and/or re-issue this document as previously concealed building envelope conditions are revealed during the rehabilitation process, as more information is made available and reviewed, or as the Work proceeds.

E. This document is intended solely for the use by the Owner for this Project, and should, in any event, be reproduced only in its entirety, with this disclaimer included.

PART 2 GENERAL DESCRIPTION OF THE WORK

2.01 SCOPE OF WORK

A. All activities described in this Summary of Work are to be conducted in conformance with the Project Manual Specifications, Drawings, Details, and incorporated contract documents, which constitute the complete Scope of Work for the Project.

B. All activities described in this Summary of Work are to be conducted in conformance with current laws and Oregon State Building Code requirements adopted, implemented, and amended by the local jurisdiction of the Project.

C. If damage is discovered at or extending beyond areas of limits of Work, contractor shall notify Building Envelope Consultant of location and extent of damage by marking up the unit elevation photo sheet provided or creating a sketch of the area(s) in question and establish a written description of the area to provide a record of where damage was discovered. All additional work will constitute a change order.

D. Provide pricing according to the Basis-of-Design described in the individual Sections contained within this Summary of Work document.

FBC SUMMARY OF WORK 01 10 00 - 5

2.02 EXTERIOR WALL ASSEMBLIES (BUILDINGS B & E)

A. Schedule

1. Remove and dispose of 100% existing siding, wood trim and all associated components.

2. Install fiber cement siding & fixture blocks with James Hardie HZ 10 Color Plus or owner approved equal.

3. Install Hardie Color Plus fiber cement trim and all associated components or owner approved equal.

4. Remove and replace existing WRB, SAM, metal flashings, sealant joints and all associated products. Quickflash panels at all MEP penetrations. Install ½ inch dynamic sealant with backer rod.

5. All associated products per the Project Design Details and Specifications.

B. Related Requirements

1. Section 06 10 00 – Rough Carpentry

2. Section 06 16 00 – Wood Sheathing

3. Section 07 21 00 – Thermal Insulation

4. Section 07 25 00 – Weather Barriers

5. Section 07 46 46 – Fiber Cement Siding

6. Section 07 62 00 – Sheet Metal Flashing and Trim

7. Section 07 65 00 – Flexible Flashing

8. Section 07 71 23 – Gutters and Downspouts

9. Section 07 90 05 – Joint Sealants

10. Section 08 14 36 – Hinged Entry Doors

11. Section 08 53 13 – Vinyl Windows

12. Section 09 90 00 – Painting and Coating

C. Inspection

1. Inspect all existing wood sheathing for signs of water damage, deterioration, microbial growth, and/or other nonconforming conditions.

2. Inspect all sheathing, and any exposed framing components for damage and structural integrity. Structural Engineers, contracted separately by the Owner, shall determine the protocol for treatment and/or replacement of such components.

D. Repairs

1. Install new cladding materials and associated components in accordance with the project documents. Detail all parts of the assembly in conformance with Project Design Document Drawings, Details and Specifications.

2. It is anticipated that removal of elements of the building envelopes may reveal moisture-related damage. Should contractor encounter such damage on this project, the change order process should be used to add remediation to these areas before any work is performed.

3. Contractor is to chase and remediate all property damage and nonconforming conditions, including (but not limited to) the following: water leakage, deterioration, and microbial growth at all exterior building envelope wall.

FBC SUMMARY OF WORK 01 10 00 - 6

a. Damaged plywood sheathing is to be replaced with new exterior plywood sheathing per Project specifications. New sheathing shall consist of a moisture-tolerant material.

4. Where plywood sheathing is removed, install new sheathing to match thickness of existing sheathing; new sheathing shall be exterior-grade cdx plywood sheathing. Ensure continuous blocking to support new sheathing at all edges.

5. At all sheathing replacement/remediation areas, install new sheathing with corrosion-resistant metal accessories and fasteners that are chemically and physically compatible with adjacent building components; stainless steel (SS) accessories, SS connectors, and SS metal flashing shall be used when in contact with pressure-treated (PT) materials.

6. Treat or replace damaged wood stud framing members per structural engineer’s protocol.

7. Replace wet or microbial-affected batt insulation in “like-kind” and in conformance with applicable codes.

8. At insulation removal areas, install new insulation to match R-Value of existing insulation.

a. New insulation shall feature a continuous vapor retarder on the warm-in-winter side.

b. Seal new vapor retarder to adjacent framing members and at overlaps in order to achieve a monolithic air barrier.

9. Remediate all encountered interior microbial growth as determined by a licensed industrial hygienist (to be contracted directly by the Owner).

a. The remediation of all areas affected by microbial growth shall be conducted under the direction of a Special Inspector in accordance with industry-recognized abatement protocols.

10. Install new complete water-resistive barrier (WRB) system per Project details and specifications for an air-barrier installation.

a. BOD Product: Fortifiber WeatherSmart® Drainable by Henry® Includes air barrier installation, Foritflex, Fortiflash Butyl and all related components. Or owner approved equal.

b. Properly integrate and seal WRB with existing entry ways WRB as required and per the manufacturer’s installation requirements for lapping and air-sealing, notify Consultant if existing conditions do not allow conformance.

c. Use corrosion-resistant cap fasteners to secure the WRB in conformance with the manufacturer’s air barrier installation instructions.

d. Terminate WRB to the sheathing and to existing WRB at boundaries of Deferred areas of work, along bottom and top of walls in general accordance with the project details, specifications, and manufacturer requirements.

e. Install self-adhered membrane (SAM) flashing extending a minimum 2” past all trim-to-siding transitions in all locations regardless of dimensions or locations identified in the Attachment B Design Documents.

11. Install hose bibbs mounting blocks.

a. Extend plumbing as needed to accommodate new mounting block. Contractor is to coordinate flashing panel installation at the time of the bibb installation to allow for the integration of the properly sized Quickflash Plumbing Panel. Verify flashing panel for correct pipe diameter.

b. Pipe penetration flashing to be installed in an air-barrier fashion.

c. BOD Product – Quickflash Panel (P-Series sized for pipe diameter). Or owner approved equal.

FBC SUMMARY OF WORK 01 10 00 - 7

d. Install flashed 5/4 mounting block. Seal around pipe penetration. Two-piece blocks are permissible and should be weather-cut with the joint embedded in sealant.

Flashing to be 24-Gauge with upturned end dams set on a continuous bead of sealant.

e. Install flashed 5/4 mounting block. Install dynamic sealant joint around penetration.

Two-piece blocks are permissible, and should be weather-cut with the joint embedded in sealant. Flashing to be 24-Gauge with upturned end dams set on a continuous bead of sealant.

12. Existing exterior outlet junction boxes and covers.

a. At all exterior electrical outlet locations provide, quickflash panel, and code compliant exterior bubble cover. Modify sheathing as necessary for junction box installation.

b. BOD Quickflash Panel Product – E-SGB-C 1 /38” for single gang outlets. Or owner approved equal.

c. BOD Quickflash Panel Product – E-DGB-C 1 /38” for double gang outlets. Or owner approved equal.

d. BOD Junction Box Product – Carlon Adjustable Electrical Single Gang Box Part

# B121ADJ for single gang outlets. Or owner approved equal.

e. BOD Junction Box Product – Carlon Adjustable Electrical Single Gang Box Part

# B234ADJ for double gang outlets. Or owner approved equal.

f. At electrical penetrations (exterior light and sensors) with no junction box or round install a 3” round fiberglass exterior mounted junction box and Quickflash Panel.

g. BOD Quickflash Panel Product – E-3/0 B-A 1 /38”. Or owner approved equal.

h. BOD Junction Box Product – Allied Molded Products, Inc. Part # 9338-E. Or owner approved equal.

13. Install utility mounting blocks.

a. At coax cable locations coordinate with the owner’s service provider to install coax through a Quickflash Panel.

b. BOD Product – Quickflash Panel P-25. Or owner approved equal.

c. At each unit install a non-penetration mounting block for installation of a hose reel.

Location to be determined by owner.

d. Install Quickflash Panels at all applicable utilities, fixtures, and penetrations. At locations that are not suitable for Quickflash Panels, install flexible SAM flashing per the manufacturer’s installation instructions.

e. Install flashed 5/4 mounting block. Ensure mounting block extends a minimum of 2” around perimeter of component mounted to block. Seal around penetration.

Two-piece blocks are permissible, and should be weather-cut, primed, and with the joint embedded in sealant. Weather cuts are to be horizontal. Flashing to be 24-Gauge pre-finished with upturned end dams set on a continuous bead of sealant.

14. Remove exterior light fixtures for reinstallation.

a. Install Quickflash Panels at all applicable reinstalled light fixture junction box penetrations. At locations that are not suitable for Quickflash Panels, install flexible SAM flashing per the manufacturer’s installation instructions.

b. Install flashed 5/4 fiber cement mounting block. Ensure mounting block extends a minimum of 2” around perimeter of fixture mounted to block. Seal around penetration.

Two-piece blocks are permissible, and should be weather-cut, primed, and with the

FBC SUMMARY OF WORK 01 10 00 - 8

joint embedded in sealant. Weather cuts are to be horizontal. Flashing to be 24-Gauge pre-finished with upturned end dams set on a continuous bead of sealant.

15. Along identified exterior elevation walls and adjacent walls and deck perimeters per the design documents, install cladding with manufacturer recommended stainless steel fasteners per the manufacturer’s most recently published best practices installation guide.

a. Siding BOD Product to be Color Plus HZ10 Hardie lap siding by James Hardie per design document dated 7.27.2025- pages A2.02- A2.04. Or owner approved equal.

b. Siding BOD Product to be Color Plus Smooth Panel w/ Batten Trim by James Hardie per design document dated 7.27.2025- pages A2.02- A2.04. Or owner approved equal.

c. Prime all field cut edges with manufacturer recommended primer. Back prime as well.

d. Install with a 1/8” gap at trim transitions.

e. Install manufacturer recommended sheet metal joint flashing at siding butt joints.

Note: DO NOT CAULK SIDING BUTT JOINTS.

16. Install Hardie fiber cement trim to replace existing trim per project details and specifications.

a. No miter cuts except at vertical joints where trim shall be mitered and constructed in a weatherboard fashion to shed water away from the building.

b. Outside corner trim shall be rabbeted with a 1/2” by 1/2” rabbet sawn at one piece of trim. Trim board cut to be pre-primed and joint to be sealed prior to assembly with static fillet joint at exterior.

c. All cut ends to be primed and cured prior to joining. Install sealant bedding joint at all trim joints.

d. Apply sealant between adjoining trim sections during assembly, after the edge cut primer has dried.

e. Secure trim using stainless steel fasteners with staggered spacing of 16" on center (maximum) and 3" from each end.

f. Do not fasten closer than 3/4" from sides of trim or through window mounting flanges.

g. Account for additional trim where present on site but not shown in drawings.

17. Flash all exposed projecting horizontal trim with galvanized pre-finished flashing, positively sloped for drainage away from the structure. Horizontal projecting trim less than 1 1/2” to have 10 degrees of positive slope to drain, projects greater than 1 1/2” to receive 5 degrees positive slope to drain.

a. Exposed Flashing is to be minimum 24-Gauge thickness. Concealed flashing shall be

24-Gauge or 26-Gauge in thickness or as otherwise specified in the project design documents.

b. Secure flashing through vertical surfaces only unless indicated otherwise.

c. Provide watertight up-turned end dams at horizontal terminations per project details and specifications.

d. Inside and outside corners and transitions to be fabricated watertight.

e. All lap joints to be joined in a “bayonet” joint with a minimum 4” lap, bed in three beads of 3/8” diameter sealant.

18. Flashing installed in contact with non-borate pressure-treated framing or concrete shall be

24-Gauge stainless steel unless indicated otherwise.

FBC SUMMARY OF WORK 01 10 00 - 9

19. Install sealants as specified by Building Envelope Consultant, and as indicated in the Project details and specifications.

a. All horizontal trim to receive sheet metal flashing will be set in a 3/8” bead of sealant on the top of the trim.

20. Remove, dispose and replace all downspouts with appropriately sized downspouts

2.03 WINDOW AND SWING DOOR ASSEMBLIES

1. The design intent is for all serviceable windows to be removed, disposed of, and replaced.

2. The design intent is for the north elevation door at the Warehouse Building to be remove, disposed of, and replaced. All other swing doors to be removed, flashed, and reinstalled.

3. All roll-up garage style doors to be flashed in place.

4. The sliding barn-style door is to be removed, flashed, and reinstalled.

B. Related Requirements

1. Section 06 10 00 – Rough Carpentry

2. Section 06 16 00 – Wood Sheathing

3. Section 06 45 50 – Fiber Cement Trim

4. Section 07 21 00 – Thermal Insulation

5. Section 07 25 00 – Weather Barriers

6. Section 07 46 46 – Fiber Cement Siding

7. Section 07 62 00 – Sheet Metal Flashing and Trim

8. Section 07 65 00 – Flexible Flashing

9. Section 07 90 05 – Joint Sealants

10. Section 08 14 36 – Hinged Entry Doors

11. Section 08 53 13 – Vinyl Windows

C. Inspection

1. Upon removal of all components, inspect all sheathing, framing, and insulation components for damage and signs of moisture intrusion, deterioration, microbial growth, and/or other nonconforming conditions. Chase and remediate all damage to extinction upon completion and authorization of a change order.

2. A licensed structural engineer, contracted separately by the Owner, shall determine the protocol for treatment and/or replacement of such components.

D. Repairs – Windows & Doors

1. Remove, flash, and replace (100%) windows in accordance with the project design documents and specifications.

2. Remove and safely store swing doors.

3. Replace all windows with new. Replacement windows to match the existing in dimension and function.

a. B.O.D. Product: Milgard V250 Style Line Series or owner approved equal.

4. All replacement swing doors shall receive new hardware.

FBC SUMMARY OF WORK 01 10 00 - 10

5. Install swing door with new metal sill pan fully welded and soldered, sloped to drain to the exterior. Coordinate detailing and installation of swing door with Project design documents and per component manufactures installation instructions.

6. Install windows with a back dam and end dams.

7. Install new SAM flashing at the rough openings in accordance with the Project design documents.

a. BOD Product System is, Fortiflash Butyl, by Henry®. Or owner approved equal.

8. Install windows and SGD/swing doors. Contractor shall use corrosion-resistant fasteners and decay resistant shims.

9. Install minimally expanding foam around the perimeter of the door per the Project design documents.

10. Install SAM flashing to windows and doorframe at the jambs and head.

11. Install exterior trim and sealant per the Project design documents and specifications.

install with a minimum of ½ inch space between the trim and the fenestration in order to have a dynamic sealant joint.

a. BOD Product: Color Matched- Sikafelx HY 150 sealant by Sika or Quad Max by

OSI at window and door trim (install trims using square cuts, prime all sides, and adjoin with sealant). Or owner approved equal.

11. Install 24-Gauge pre-finished metal flashing with upturned end dams atop head trim.

12. Interior finishes at the perimeter of the windows and doors are to be removed and reinstalled as needed.

2.04 EXTERIOR FINISHES

1. Paint un-finished cladding materials

B. Related Requirements

1. Section 07 62 00 - Sheet Metal Flashing and Trim

2. Section 09 90 00 - Painting and Coating

C. Inspection

1. Inspect all exterior elevation surfaces and sealant joints in order to document and correct conditions that may require special or additional preparation for paint application.

D. Repairs

1. Clean and prep all surfaces as required by the paint manufacturers and Design Documents.

2. Coordinate selection of final paint colors with the Owner. Trim paint to be included at window, door, barge, and fascia trim.

a. B.O.D. Product: SuperPaint by Sherwin Williams Or owner approved equal.

3. Spray and brush all un-finished exposed cladding surfaces with two (2) coats of approved paint product per Project details and specifications.

FBC SUMMARY OF WORK 01 10 00 - 11

PART 3 PROJECT REQUIREMENTS

3.01 GENERAL PROJECT REQUIREMENTS: Must conform with Exhibit 6 of the ITB

A. Refer to related Sections for complete Project specifications B. All work to be performed under this Scope of Work (Work) shall be conducted in full compliance with all applicable local, state (OSSC), and federal laws and regulations.

1. It is the general contractor’s (Contractor) duty to be familiar with all such applicable local, state, and federal laws and regulations, which include the current edition of the Oregon Structural Specialty Code (OSSC) and related Standards. Furthermore, the Contractor shall ensure that all activities performed by the Contractor’s personnel, subcontractors, and suppliers comply with these laws and regulations throughout the course of the Work.

C. In the preparation of their bid and the performance of the Work, the Contractor shall:

1. Review the Project’s existing site conditions to become familiar with the site environment that may be affected by the required Work.

2. Document the Project’s existing site conditions (interior & exterior conditions) in order to properly restore the Project in accordance to the contract documents.

3. Note that some building components or systems adjacent to repaired areas covered by the Work may require partial removal, replacement, temporary storage and/or reinstallation in order to accomplish the Work.

D. The Contractor is responsible for acquiring all required permits necessary to perform the Work in a timely manner.

1. Additionally, the Contractor is responsible for any necessary follow-up with the Building

Official throughout the repair process. If changes to the original design are made, the Contractor is responsible for re-submitting all necessary documentation to the Building Official and ensuring that the design changes have been approved prior to the (re) commencement of the Work.

E. The Contractor is responsible for the payment of all sales taxes associated with the Work in states where applicable.

F. The Contractor and the Owner shall agree upon a designated area within the Project to be used for temporary construction, office, and material and equipment storage areas prior to the commencement and throughout the duration of the Work.

1. Security provisions for this designated area and stored products and equipment shall be the responsibility of the Contractor and their subcontractors, in accordance with the contract documents.

G. The Contractor shall engage appropriate local utility companies to implement necessary temporary facilities and/or arrange with The Owner to connect to existing services at the Project in order to perform the required Work.

1. Additionally, the Contractor is responsible for the connection fee for temporary facilities or services.

a. The Contractor is not to use individual owner power unless approved by owner.

2. The Contractor shall be responsible for providing sanitary facilities, drinking water, telephone services, email, and fax capabilities to be used by the Contractor and their subcontractors throughout the course of the Work.

H. The Contractor shall maintain a clean site and all trash and debris shall be removed on a daily basis to maintain a clean appearance and safe access for occupants of the Project and their visitors.

FBC SUMMARY OF WORK 01 10 00 - 12

I. All Work shall be performed during normal business hours (set as 7:00 A.M. to 4:30 P.M.

Monday through Friday), unless arrangements are made with the Owner at least seventy-two

(72) hours beforehand and are in accordance with the regulations of the local jurisdiction.

1. Staging of the daily Work can commence thirty (30) minutes prior to the agreed time, without disrupting the ingress and egress of the Project’s occupants.

J. The Project will remain occupied throughout the course of the Work. The Contractor is required to maintain a clear and safe environment for Occupants with unobstructed pathways to all sidewalks, entry walkways, doors, and driveways. Overhead protection from falling debris is required at the entry door specific to the repairs.

K. In situations where completion of the Work disrupts the ingress and egress of the Project’s occupants from their individual residences, temporary ingress and egress provisions must be provided by the Contractor until pre-construction ingress and egress conditions are restored.

1. Similarly, in situations where the Work affects the security of the residence(s) the

Contractor shall provide a temporarily secure environment during times when work is not being performed.

L. Coordinate with Building Envelope Consultant to develop an appropriate method for communication and documentation during the construction process, in accordance with the contract documents

M. Contractor shall designate a single individual as project foreman who shall be on site at all times during building envelope installation.

1. The designated foreman shall be responsible for supplying applicable Reference

Standards and product manufacturer’s installation instructions to installers, maintaining Quality Control of the installation and shall ensure that deficient construction assemblies and open Action Items (documented in Building Envelope Consultant site visit reports) are corrected and memorialized in the following manner:

a. Building Envelope Consultant is onsite during a regularly scheduled site visit after correction of the Action Item and the corrected assembly or condition is visible for examination, in which case Consultant will document the corrected item, or;

b. The Action Item has been corrected while Consultant was offsite, between one of Consultant's regularly scheduled site visits, in which case, the Contractor may photograph the corrected Action Item in a manner that clearly demonstrates and memorializes the correction and do one of the following:

i. Send the photographs of the corrected condition(s) to Consultant, which certifies that the condition was corrected per the Construction Documents, and/or;

ii. Send Consultant written verification that the Action Item has been corrected per the Construction Documents.

N. During the reconstruction process, the Contractor shall create the necessary documentation to complete the Work, in accordance with the contract documents. Provide copies of such documentation for review and approval by Forensic and the Owner. Such documentation includes, but is not necessarily limited to, the following:

1. All necessary permit(s) to perform the intended Work, obtained from the applicable building authority and paid for by the Contractor;

2. Provide proof of valid insurance;

3. Create a plan describing the locations and extent of the intended Work along with an associated construction schedule;

4. Product submittals, samples, MSDS and other product and material data sheets, etc., available for review;

FBC SUMMARY OF WORK 01 10 00 - 13

5. Maintain a marked-up and updated set of as-built drawings on site, accurately depicting construction changes as they are made during the course of the Work.

a. This includes marking on the elevations locations where damage is discovered during the Work.

O. Plan and stage construction and staging areas associated with the Work in coordination with the Owner to be the least disruptive to the normal operation of the Project’s residents as possible. Where disruption is unavoidable, the Contractor shall coordinate with the Owner at least seventy-two (72) hours prior to commencement of the disruptive activities.

P. Provide the appropriate means and methods to complete the required Work in a timely, non-disruptive, non-destructive, and professional manner, in accordance with the contract documents. Means and methods include, but are not necessarily limited to, the following:

1. Full weather protection for parts of the Project affected by the work

2. Scaffolding and/or boom lifts (as determined by Project Team)

3. Pump jacks

4. OSHA-compliant Safety equipment for all parties, including subcontractors, Building

Envelope Consultant and Owner upon request.

5. Security fencing

6. All necessary mechanisms to create an environment conducive to installation of the intended building components and systems

7. Provisions safeguarding adjacent building components, interior finishes, private property, and site elements (such as stairs, walkways, driveways, landscape, irrigation systems, etc.) throughout the course of the Work.

8. Temporary toilet facilities per OSHA requirements.

9. Task lighting and/or temporary lighting

Q. Provide all demolition, temporary bracing, construction techniques, materials, and construction sequences and assemblies in conjunction with properly performing the required Work.

R. Provide dumpster(s) throughout the course of the Work as necessary and dispose of refuse in appropriate and lawful manner. Recycle all salvageable materials whenever possible.

S. In place mockups of the initial assemblies at the beginning of the Project for Consultant’s review and approval. Consultant may require mockups to be re-built if deficiencies are found in initial mockups.

T. Install all new building components in a manner compliant with product manufacturers’ most recently published installation requirements/recommendations, applicable industry association standards, prevailing building codes, zoning requirements, and sound weatherproofing and waterproofing principles. In instances where conflicts may arise between such entities, notify Consultant as soon as possible, and clarification will be provided prior to commencement of the Work.

1. ALL manufacturer installation literature must be onsite during the course of remediation.

U. Repair or replace any building components or systems that are damaged throughout the course of the Work, as well as any building components or systems, affected by the Work, that do not conform with the Project’s prevailing building code requirements or fail to meet the standards of care expected from such work.

V. Clean, replace, and/or properly restore the Project site to pre-construction state at the completion of the Work, in accordance to the contract documents.

FBC SUMMARY OF WORK 01 10 00 - 14

W. At time of Project Completion, the Contractor shall participate in a final walk-through with the Owner and Consultant to evaluate the Work performed and to assemble a final punch list of items to be corrected.

1. The Contractor shall perform the work associated with the punch list items within a specified amount of time, in accordance with the contract documents.

2. Similarly, all open Action Items contained within the Consultant’s Action Item Log shall be corrected.

3. Final payments will not be issued until the completion of the Work and correction of all

Action Items and punch list items, in accordance with the contract documents.

X. The Contractor shall guarantee all Workmanship for a period of two (2) years from the date of the letter of Project Substantial Completion, or as required by law. Material warranties provided by each manufacture.

4.01 RESPONSIBILITIES OF THE OWNER DURING CONSTRUCTION

A. The Owner shall provide the Contractor with access to the site during working hours and working days, for the purposes of conducting the Work, in accordance with the contract documents.

B. The Owner shall provide the Contractor designated area(s) within the Project site to be used for temporary construction, office, and material and equipment storage areas prior to the commencement and throughout the duration of the work.

1. Security and safety provisions for the designated area(s) and stored products and equipment shall be the responsibility of the Contractor and their subcontractors, in accordance with the contract documents.

C. The Owner shall provide the Contractor with access to unit interiors during working hours and working days, for the purposes of conducting the Work, in accordance with the contract documents.

D. The Owner shall provide the Contractor with access to Owner-controlled water and electrical power sources, for the Contractor’s use during the Project.

1. The Owner will pay for all power and water usage from these sources throughout the project.

2. Unless otherwise negotiated, electricity and/or water service shall not be used from individual units.

E. The Owner shall require and be responsible for the removal of all personal items from site areas as needed to accommodate the Work.

F. The Owner shall require that occupants temporarily remove items attached to the interior of exterior walls affected by the Work, in order to avoid breakage or damage to personal items.

G. The Owner will remove obstructions inhibiting work, contractor has responsibility for damages as described in Section G.1 of Exhibit 6 if the ITB.

FBC PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 1

SECTION 01 31 00

PROJECT MANAGEMENT AND COORDINATION

PART 1 GENERAL: Must conform to the conditions of Exhibit 6 and Exhibit 7 of the State of Oregon General conditions section. If any conflicts exist compliance with Exhibit 6 General Conditions and Exhibit 7 will be the guiding requirement.

1.01 SECTION INCLUDES

A. Preconstruction Meeting B. Progress Meetings C. Construction Progress Schedule D. Requests for Interpretation (RFIs).

1.02 RELATED REQUIREMENTS

A. Section 01 10 00 - Summary of Work B. Section 01 73 00 - Execution C. Section 01 77 00- Closeout Procedures D. Section 01 40 00 – Quality Requirements

1.03 DEFINITIONS

A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.

1. Critical activities are activities on the critical path. They must start and finish on the planned early start and finish times.

2. Predecessor Activity: An activity that precedes another activity in the network.

3. Successor Activity: An activity that follows another activity in the network.

B. CPM: Critical path method, which is a method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.

C. Critical Path: The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no float.

D. Float: The measure of leeway in starting and completing an activity.

1. Float time is not for the exclusive use or benefit of either Owner or Contractor, but is a jointly owned, expiring Project resource available to both parties as needed to meet schedule milestones and Contract completion date.

1.04 SUBMITTALS

A. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design.

B. Key Personnel Names: Within 15 days of starting construction operations, submit a list of key personnel assignments, including superintendent and other personnel in attendance at Project site. Identify individuals and their duties and responsibilities; list addresses and telephone

FBC PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 2

numbers, including home, office, and cellular telephone numbers and e-mail addresses.

Provide names, addresses, and telephone numbers of individuals assigned as alternates in the absence of individuals assigned to Project.

1.05 COORDINATION

A. Coordinate construction operations included in different Sections to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections that depend on each other for proper installation, connection, and operation.

1. Schedule construction operations, in sequence required, to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components with other contractors to ensure maximum accessibility for required maintenance, service and repair.

3. Make adequate provisions to accommodate items scheduled for later installation.

4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.

5. Coordinate construction of Mockups to comply with construction Schedule.

B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports and list of attendees at meetings.

1. Prepare similar memoranda for Owner and separate contractors if coordination of their

Work is required.

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:

1. Preparation of Contractor's Construction Schedule and related updates during construction.

2. Preparation of the Schedule of Values and related updates during construction as outlined in Section E of Exhibit 6 of the ITB.

3. Ensure construction personnel and subcontractors possess copies of the Contract

Documents and applicable product manufacturer’s installation instructions and Reference Standards that provide instructions related to the quality of the intended work.

4. Installation and removal of temporary facilities and controls.

5. Delivery and processing of submittals in conformance to section B.18 of Exhibit 6 of the

ITB and section 01 33 00.

6. Performance of mockups.

7. Progress meetings (weekly during periods when the Work is performed).

8. Pre-installation conferences.

9. Startup and adjustment of systems.

10. Project closeout activities (including course of construction corrections, completed

Action Items, and punchlist items) as specified in Section K of Exhibit 6 of the ITB.

D. Conservation: Coordinate construction activities to ensure that operations are carried out with consideration given to conservation of energy, water, and materials. Coordinate use of temporary utilities to minimize waste.

1. Salvage materials and equipment involved in performance of, but not actually incorporated into, the Work. See other Sections for disposition of salvaged materials that are designated as Owner's property.

FBC PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 3

3.01 PRECONSTRUCTION MEETING

A. Contractor will schedule a meeting at a time convenient to the Owner and Building Envelope Consultant, but no later than 7 business days after execution of the Agreement.

B. Conduct the conference to review responsibilities and personnel assignments.

C. Schedule and conduct meeting at Project site unless otherwise authorized by the Owner.

D. Attendance Required: All participants shall be familiar with the Project and authorized to conclude matters relating to the Work.

1. Owner's designated representative.

2. Building Envelope Consultant.

3. Contractor.

4. Contractor's Superintendent.

5. Major subcontractors, suppliers, and third party consultants may attend if necessary.

E. Agenda:

1. Tentative construction schedule.

2. Phasing, if applicable.

3. Critical work sequencing and long-lead items.

4. Designation of personnel representing the parties to Contract, inspecting agencies and

Building Envelope Consultant and their duties.

5. Lines of communication.

6. Procedures for processing field decisions and Change Orders.

7. Procedures for RFIs.

8. Procedures for testing and inspecting.

9. Procedures for processing Applications for Payment.

10. Submission of executed bonds and insurance certificates.

11. Distribution of Contract Documents.

12. Submittal procedures.

13. Performance of mockups:

a. Locations and time of installation.

b. Testing and evaluation.

14. Use of premises and existing buildings, including:

a. Parking availability.

b. Office, work and storage areas.

c. Working hours.

15. Work restrictions.

16. Owner's occupancy requirements.

17. Submission of list of Subcontractors, list of Products, schedule of values, and progress schedule.

18. Procedures for weather protection to prevent exposure to moisture.

19. Procedures for correcting construction conditions identified on Building Envelope

Consultant's site visit reports.

FBC PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 4

20. Scheduling activities of Special Inspectors.

21. Responsibility for temporary facilities and controls.

22. Construction waste management and recycling.

23.…