Attachment A - Quality Control Plan Guide.pdf

PDF 159 KB Posted

Attached to
FY22 USACE Nashville District Environmental Services MATOC
Solicitation number
W912P522B0013
Issued by

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment A- Quality Control Plan Guide

1. Master File. Certify that a master file (record File) has been established. Give project name, location, file number, control and access details. USACE will provide the Master File number and maintain the file; the AE will be responsible for providing pertinent information (QCP, critical correspondence, review documentation) to keep the file up to date.

2. Scope of Work. Define the task. Designate project team. Assign responsibilities. Address budget and schedule. Discuss CRUCIAL design parameters.

3. Specify the review process. Designate the review team, checking of comps, verification of CRUCIAL design parameters, review by specialists, supervisory review, use of interim reviews, and the Independent Technical Review (ITR).

4. Use of checklists. Identify applicable references and guidance. Discuss design checklists, environmental checklist, others. Show copies.

5. Coordination. Tell who is in the coordination loop. Who needs to know your results? Whose input do you need? How does the USACE fit in? Describe provisions for estimating, specifications, and printing (where applicable).

6. Plan for customer involvement. Show where the USACE customer(s) fits into your planning, review, changes, etc.

7. Analyze CRUCIAL design features. Describe what must not be allowed to go wrong and what steps will be taken to be sure it doesn’t.

8. Site visits. Describe how site visits will be used to insure good design. Detail frequency, coordination, use of photos, field data. Identify any special equipment needed for site visits.

9. Quality indicators. Tell what you will use to monitor budget, schedule, technical quality, and responsiveness.

10. Describe your R&D plan. Be sure your design/study incorporates the latest technical developments.

11. Signature blocks for Principal, Project Engineer.

File details come from the government source that posted it. Updated .