Attachment A_Project Charter_Final.docx

DOCX document 77 KB Posted

Attached to
IQMS for DMV DL/ID System Replacement Project
Solicitation number
S-73000-00017868
Issued by
Oregon

About this file

This is a Project Charter document for the Driver License and Identification System Replacement (DISR) project, submitted by the Oregon Department of Transportation (ODOT) Department of Motor Vehicles (DMV). The project scope encompasses the evaluation, procurement, and implementation of a new Digital Photo Licensing (DPL) solution to replace the existing Veridos system, which expires December 30, 2027, with an optional three-year extension available through December 30, 2030. The new system must provide end-to-end functionality for capturing customer information and photographic images, performing biometric identity verification, and producing AAMVA-compliant driver licenses and identification cards, with centralized production and distribution services. Key project objectives include ensuring service continuity, improving customer experience through single-workstation transactions, evaluating vendor capabilities for enhanced security features, and implementing operational efficiencies. The project charter identifies a projected implementation timeline spanning from Q1 2026 procurement planning through Q4 2030 project closure, with critical deployment occurring by Q4 2029 to ensure continuity before the legacy contract expiration.

Project costs total an estimated $2,292,548 for implementation, comprised of $1,154,200 in ODOT Information Services Branch technical resources, $169,818 in Independent Quality Management Services (IQMS), $447,700 in project management costs, and $520,830 in business resources. Ongoing operational costs are projected at $13,141,500 over five years, based on the existing cost model of $2.88 per card produced for approximately 900,000 driver licenses and identification cards annually, with the vendor responsible for hardware, software, ongoing maintenance, upgrades, and operations. Funding is provided through the Field Services Group using State Highway Funds, with DMV and Information Services staff costs covered by their operational units. The project assumes a potential multi-vendor solution arrangement, with the Request for Proposal (RFP) structured to allow contracting with up to three vendors for distinct aspects: image capture and biometric identity verification, biometric checks against existing records, and card production and distribution services. The project team comprises approximately 9,450 work hours across eight functional roles, including project management, technical leadership, business analysis, and vendor implementation services.

View the file

Other files

File Type Posted
DMV IQMS RFQ_Final.docx DOCX document
Exhibit 3_Statement of Work_Final.docx DOCX document
Attachment B_Business Case_Final.docx DOCX document
17868_Q and A_Vol.1.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Charter Driver License and Identification System Replacement Project

DISR Project Charter

VERSION 1.4

PATRICK MARCINKO

Attachment A to OregonBuys Bid #S-73000-00007868

Project Description
The Oregon Department Of Transportation’s (ODOT), Department of Motor Vehicles (DMV) has a legislative mandate to issue driver licenses and Identification cards. In order to fulfil this mandate, ODOT utilizes a Digital Photo Licensing (DPL) solution. The current DPL vendor (Veridos) has a services contract that expires on 12/30/27.

The purpose of this project is to evaluate vendor(s) products and services, procure products and services then implement a new DPL solution/system to replace the existing system and provide “end to end” continuity for this mission critical process of taking customer photos, performing biometric identity checks, and applying data to an American Association of Motor Vehicle Administrators (AAMVA) compliant Driver Licenses/Identification (DL/ID) cards. Services will also include the production and distribution of DL/ID cards from a centralized location to the DMV customer(s).

The contract with the current vendor (Veridos) is set to expire on December 30, 2027. There is an option in the current contract to extend this mission critical service for up to three years to December 30, 2030; however, beyond this date there is no guarantee service will be provided by the vendor. Without contracted services the DMV will not be able to fulfil the legislative mandate for issuing driver licenses or ID cards.

Project Scope:

The scope of this project is to ensure continuity of services for the DPL system by:

· Engage effective business project stakeholders for the following:

· Develop “As-Is” and “To-Be” Business Process Maps

· Develop Use Case Diagrams – functional requirements of the system from a user’s perspective

· Develop Detailed List of Requirements

· Identifying a vendor/vendors solution(s) to provide basic critical end-to-end functionality for capturing information and photographic images of a customer required to produce a driver license or Identification card and its delivery to Oregonians applying for a driver license or ID card. Any vendor(s) selected will need to meet or exceed the current standards used by the existing DPL system as well as provide the service levels customers experience today. Any system chosen to replace the current DPL system must also meet the AAMVA standards.

· Prepare facial recognition data to be migrated from the current platform to the new platform (if needed)

· Configure the Commercial Off The Shelf (COTS) solution hosted in the “Vendor(s) Cloud” to align with current policy and business processes or modify existing policy or processes if needed

· Develop test scripts for testing end-to-end integration and User Acceptance Testing

· Develop training for end users in how to operate a new DPL system

· Develop training for technical users in how to trouble shoot any production issues that may occur after the DPL system has been transitioned to production

· Develop data security positions for the new DPL system

· Integration of the new DPL Solution with the existing “Core System” (OLIVR)

Project Scope To Be Determined:

· Any office modifications needed to accommodate new photo capture equipment.

Out of scope items include:

· Computer hardware, software or processes developed that are not directly associated with the process to capture information/data/images required for creating an Oregon driver license or Identification card

· Any use of information/data/images, captured by the DPL system, to be used outside the DMV driver license or Identification card process

Project Objectives

Objective
Success Criteria
Provide the continuity of services for driver licenses and identification cards to Oregonians
Evaluate vendors, services, choose and negotiate a contract with the vendor and implement a new DPL solution/system
Improve the DMV experience for new and renewed driver license customers as well as identification card customers by completing their transaction at a single workstation
Select a vendor that can preferably provide image capture at each workstation in a DMV office
Take advantage of enhanced American Association of Motor Vehicle Administrators (AAMVA) security features that have evolved since the implementation of the current DPL solution, used by Oregon’s DMV
· Evaluate and implement additional security features available in the vendor’s system that DMV does not have with the current system

· Evaluate and implement system capabilities that would provide operational efficiencies and improved performance for issuing a driver license of Identification card.

Budget
This project is fully funded by the Field Services Group, using State Highway Funds. DMV and IS staff will continue to be paid by their operational units. This procurement is for selecting a vendor or vendors with the intention they (the vendor(s)) provide hardware for photo capture, software services for facial recognition and production printing and distribution services for the card produced.

This table represents the projected costs for this project’s implementation. There is no upfront cost for DMV to procure hardware or software, in the current contract, it is the vendor’s responsibility, and they get paid per card produced. The costs for ongoing support (maintenance, upgrades) and operations are also covered by the cost of each card produced. Currently, each card costs $2.88 to produce. Oregon DMV issued approximately 900,000 driver licenses and identification cards for approximately $2,592,000 in 2024. The intent is to continue using this type of model for this project.

Estimated cost summary for acquiring a new DPL solution:

ODOT ISB Resource
In-House Subtotal
Total
Tech Team Leadership
$363,000
$363,000
Technical Analysis
$36,300
$36,300
Technical Design/Arch
$84,700
$84,700
Technical Dev/Support
$121,000
$121,000
Technical Testing
$121,000
$121,000
Technical Documentation
$30,250
$30,250
Security/Firewall
$30,250
$30,250
Networking
$60,500
$60,500
EDIT and FSU
$121,000
$121,000
Server and Access management
$30,250
$30,250
Technical Resource Center
$82,500
$82,500
IT Technical Training
$24,200
$24,200
SDC*
$49,250
$49,250
Total Technical Costs
$1,154,200
$1,154,200

IQMS

Total

IQMS Costs
$169,818
$169,818
Total IQMS Costs
$169,818
$169,818
ODOT ISB Resource
In-House Subtotal
Total
Project Manager
$447,700
$447,700
Total Project Mgt Costs
$447,700
$447,700
ODOT Business Resource
In-House Subtotal
Total
Business Guide
$272,430
$272,430
Business Systems Analyst
$248,400
$248,400
Total Business Costs
$520,830
$520,830

Total Project Estimates

$2,292,548

*Note State Data Center (SDC) consulting external connectivity costs are based on the current hosting model and may change

Estimated 5-year operational costs

Contracts/Services
Total
900K DL/ID cards produced/yr @ $2.88/card
$12,960,000
ODOT Personnel
$181,500
Total 5-year operational Estimates
$13,141,500
Resources
The estimated number of resources needed to support this project is 8 functional roles and approximately 9,450 work hours. The functional roles include:
Name - Title
Role
· Patrick Marcinko – Project Manager
· Provide project management services on behalf of ODOT and oversight of delivery of the COTS vendor’s project management and implementation professional services.

· Submit required Stage Gate project deliverables to Enterprise Information Services (EIS).

· Bala Kothandapani – Business Relationship Manager
· Coordinates with PM and EIS to help ensure EIS-required Stage Gate project deliverables are reviewed and submitted in a timely and proper manner.

· Provides an IS-level of review of drafts of EIS-required Stage Gate project deliverables.

Provides direction to the project team to ensure project management processes, procedures, and best practices are being followed to ensure the project is successful.

· Alex Wyatt - Technical Lead
· Lead all IS resources in coordinating with the ODOT/DMV Units for the analysis, design, development, and implementation of any ODOT/DMV systems integration with the COTS vendor’s asset management system.

· Coordinate with the ODOT Enterprise Technology (ET) Security Team and ODOT ET Network Team to review and approve the COTS vendor’s cloud-based asset management application environment architecture, ensuring it’s in conformance with ODOT ET’s architectural and security standards.

· Coordinate with IS and the COTS vendor on the development and execution of plans to migrate from existing legacy data sources to the COT vendor’s system.

Provide general technical oversight of the implementation of the COTS vendor’s system.

· Responsible for assigning development resources for:

· Technical Analysis

· Technical Design & Architecture

· Technical Development & Support

· Technical Testing

· Technical Documentation

· TBD - Enterprise Technology (ET) Security Team
· Coordinate with ODOT IS Technical Lead and ODOT ET Network Team to review and approve the COTS vendor’s cloud-based asset management application environment architecture, ensuring it’s in conformance with ODOT ET’s architectural and security standards.

Work with the project team to develop the System Security Plan and with the vendor(s) to develop the Cloud Work Book for the COTS solution in the “Vendor(s) Cloud” .

· TBD – Enterprise Network Team
· Coordinate with ODOT IS Technical Lead and ET Security Team to review and approve the COTS vendor’s cloud-based asset management application environment architecture, ensuring it’s in conformance with ODOT ET’s architectural and security standards.
· TBD - Enterprise Desktop Infrastructure Team (EDIT)
· Develops the standards executed by the Field Services Unit
· TBD - Field Services Unit (FSU)
· Creates and maintains ODOT Desktop operating system and modern work environment models.

· 1st & 2nd Level support services for IT Devices (Print Servers, Desktop, Laptop, Smartphone, etc).

· Resolves most server-to-PC or Laptop connectivity issues.

· Configures client software, i.e., ODBC drivers, e-mail access, protocol adapters, etc.

· Performs initial installs of new software including configuration, testing and troubleshooting.

· Provides customers with information that would lead to efficient solutions for business needs.

· Responsible for ODOT office on-site hardware problem evaluation, analysis of error codes, physical repair, and replacement of PC, Server and network components.

· TBD, COTS Vendor
Provide project Implementation services, in coordination with the ODOT Project Manager, and IT professional services for ODOT to implement the new solution/system.
· TBD, Subject Matter Experts (SMEs)
· Work with the Business Guide to define As-Is and To-Be business process maps and flows.

· Work with the Business Guide to define Business Requirements.

· With assistance and support from the COTS vendor, perform business functional configuration of the solution/system to meet business needs.

· Work with the Business Guide and COTS vendor to develop, approve and execute a Test Plan for the implementation of the COTS vendor’s solution/system.

· Upon full implementation of the COTS vendor’s solution/system, work with the Business Guide to implement the previously anticipated and any newly identified business process changes that emerged during implementation.

A designated subset of the SMEs participates in the Train-the-Trainer sessions with the COTS vendor.

· Douglas Hermann – Business Guide
· Coordinate with the Business Subject Matter Experts (SMEs) to:

· Develop As-Is and To-Be Business Process Maps and Flows

· Define Business Requirements

· Identify and assist Business Staff to implement new business process changes that emerge upon implementation of the COTS vendor’s asset management system

· Coordinate with the vendor(s) to develop, approve and execute a Test Plan for the COTS solution in the “Vendor(s) Cloud”.

· TBD – Business Systems Analyst
· Participate in the developing the “As Is” and “To Be” Business Process Maps and Flows

· Develops User Acceptance Test (UAT) scripts

· Executes the UAT scripts

· Participates in the resolution of defects found during UAT

Summary Schedule

Milestone
Projected Quarter
Procurement Planning Completed
Q1 2026
Solicitation Planning Completed
Q2 2026
Solicitation Completed
Q4 2026
Vendor Selection Completed – negotiated and signed contract, planning documentation completed
Q4 2027
Implementation Planning with ODOT and vendor(s) completed
Q4 2027
Build Phase Completed – Gap and Design, test plans and scripts developed by ODOT and vendor(s).
Q3 2028
Test Phase Completed – Integration and UAT by ODOT and vendor(s) completed
Q4 2028
Deployment Completed – Pilot deployment and stabilization, Statewide rollout by ODOT and vendor(s).
Q4 2029
Warranty Period Completed (agreement by ODOT and vendor(s))
Q4 2030
Project Closed
Q4 2030

Project Risks

The risks listed below are perceived risks this project could experience. They include and are not limited to:

· Potential for the contract negations take longer than expected.

· Resources (technical and business) available when needed during project execution.

· The project solution may be a multi-vendor solution vs. a single vendor solution requiring more time during the contract negotiation, implementation & integration, test and rollout phases.

· Technical experience and knowledge leave the agency due to resources retiring or resources moving on to other career positions.

· The solutions provided by vendors today may be very different from what DMV has today.

· Changes in policy, process or procedures resulting from the implementation of legislation and IT projects.

· Key business not available needed as Subject Matter Experts (SMEs)

· The solution may have embedded AI components that require more review prior to implementation.

· IT resource contention with other IT projects.

· May need to have the field offices modified to address any issues adding photo capture at each workstation location

Assumptions

The project team is proceeding under the following assumptions.

· The solicitation and implementation of the new solution will take place prior to the expiration of the legacy DPL contract.

· The new system must integrate with existing DMV OLIVR system.

· Over 21 million photos in the DMV DL/ID Issuance database will need to be migrated to the new solution to create the baseline for the facial recognition processes.

· The selected solution could be Software as a Services (SaaS) or cloud-based solution instead of being hosted in the State Data Center (SDC).

· The workstations may not need to be in the current production network domain.

· The Request for Proposal (RFP) will be drafted so that up to three vendors can be contracted to provide one or more of the three DPL solution aspects: 1) image capture and identity verification biometric checks; 2) biometric checks comparing a new photo against all photos stored in DMV records; and 3) card production and distribution.

Constraints
There is a project resource constraint in that DMV business and IS technical resources are utilized across all division projects.

· The project will be assigned resources according to the project priority assigned by the DMV User Council.

· The legacy contract has an expiration date of December 31, 2027. If ODOT leverages the full three-year extension option, the DPL solution must still be replaced by March 2028 to ensure continuity of service for issuing driver licenses and identification cards.

Stakeholders

Below is a high-level list of the stakeholders for this project. This list will be reviewed and updated as the project moves forward to ensure appropriate engagement and communication with ODOT Departments and if needed departments external to ODOT.

ODOT/DMV/Customer Services (CSG) - TBD ODOT/DMV/Field Services (FSG) – David McKay, Field Services Manager ODOT/DMV/Innovation and Planning (IAPG) - TBD ODOT/DMV/Program Services (PGSG) -TBD Department of Transportation (ODOT) Central Support Area(s) - TBD Other ODOT Divisions - TBD ODOT/Information Service Branch – Patrick Marcinko, Project Manager

Steering Committee

The Steering Committee for this project will be the DMV User Council and includes the following:

Shamus Hannan – Enterprise Applications Services - ODOT Jason Young – Information Systems Manager/ Information System - ODOT Bala Kothandapani – IT Business Relationship Manager – ODOT Susan Anderson – Business Continuity Manager Field Services – ODOT David McKay – Licensing and Permit Administrator – ODOT Stephanie Zellner – Business Operations Manager – ODOT

Project Sponsor

David Mckay - Driver & Motor Vehicle Services - ODOT

Project Manager

Patrick Marcinko Project Manager – Information Services Branch – ODOT

Sponsor Approval Signature

Name Date

Approved Project Charter Change Requests (Require approval of Steering Committee):

Change #
Date
Person
Change Description
####-###
mm/dd/yy
<requestor>

Driver License & Identification System Replacement (DISR) Project image1.jpeg