This is a Pricing Table attachment for an Interconnection Study contract opportunity with the Illinois Commerce Commission (ICC). The project encompasses annual reporting cycles from 2027 through 2030, with each cycle requiring five primary deliverables: project plan updates, research and analysis, stakeholder and ICC staff coordination, draft report submission, and final report submission. Vendor responsibilities include conducting kickoff meetings, reviewing Illinois' existing interconnection rules and tariffs, evaluating industry practices in comparable jurisdictions, facilitating monthly status meetings with stakeholders through the Interconnection Working Group, and presenting findings to ICC staff and potentially to the Commission. The contract term spans multiple years with deliverables structured across four consecutive annual reporting cycles.
Pricing for this contract utilizes a firm fixed price model, with vendors required to submit individual prices for each of the 24 identified milestones and deliverables across all four reporting years. All service costs must be included in the fixed prices, which remain firm throughout the contract term without escalation. Vendors must also provide a labor rate schedule identifying proposed labor categories including Project Director/Principal, Project Manager, Senior Analyst/Modeler, Analyst, and Research/Support Staff; however, these hourly rates are for contract administration purposes only and cannot be used to calculate or adjust the fixed prices. Travel expenses are reimbursable up to a maximum of $2,000 during the entire contract term and must be pre-approved by ICC Staff. The total evaluated contract price is $2,000, representing only the authorized travel allowance, as all service deliverables require fixed pricing from the vendor.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| BEP Utilization Plan v.26.1~1.pdf | ||
| c2d-vendor-answer-sheet-v-26-2~1.pdf | ||
| ipg-active-registered-vendor-disclosure-formerly-forms-b~1.docx | DOCX document | |
| c2d-vendor-guidance-v.24.4~2.pdf | ||
| c2d-offeror-job-aid-v.24.2~2.jpg | JPG image | |
| request-for-proposal-offer-to-the-state-of-illinois-7-29-2025-v-26-1~1.pdf | ||
| BEP_WaiverRequest.pdf | ||
| Interconnection RFP Final.docx | DOCX document | |
| vendor-disclosure-formerly-forms-a~1.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Fixed Price
| Milestone | Milestone / Deliverable | Deliverable Description | Firm Fixed Price | |
| 1 | Project Kickoff & Project Plan | Conduct the kickoff meeting and submit the Project Plan, including the project schedule, research and analytical framework, stakeholder-input approach, and draft report outline, | Offeror shall provide a labor rate schedule identifying all proposed labor categories anticipated to support performance of the Contract. Vendor shall enter rates in the Tab titled: Rate Schedule | |
| 2 | Research, Review & Analysis | Perform the research, review, and analysis required by the Scope of Work, including review of Illinois' existing interconnection rules, tariffs, policies, and procedures; evaluation of the topics identified in the Scope of Work; review of relevant stakeholder input and Interconnection Working Group discussions; research of applicable industry practices and comparable approaches used in other jurisdictions, where appropriate; and documentation of assumptions, analytical methods, and supporting rationale | ||
| 3 | Stakeholder & ICC Staff Coordination | Perform stakeholder and ICC Staff coordination, including monthly status meetings and Monthly Status Reports, Interconnection Working Group and subgroup participation as requested, consideration of stakeholder input, and documentation of areas of stakeholder agreement and disagreement | ||
| 4 | Draft 2027 Report Submission | Prepare and submit the Draft 2027 Report | ||
| 5 | Final 2027 Report Submission | Revise the Draft 2027 Report based on ICC Staff comments and direction and submit the Final 2027 Report | ||
| 6 | 2027 Presentation of Findings | Present findings and recommendations to ICC Staff. If requested by ICC Staff, the Vendor shall also present the findings and recommendations to the Commission at no additional cost | ||
| TOTAL 2027 REPORT SERVICES | $ - 0 |
| 7 | 2028 Project Plan Update | Submit the Project Plan Update for the 2028 reporting cycle | |
| 8 | 2028 Research, Review & Analysis | Perform the research, review, and analysis required for development of the 2028 Report consistent with the applicable requirements | |
| 9 | 2028 Stakeholder & ICC Staff Coordination | Perform stakeholder and ICC Staff coordination for the 2028 reporting cycle, including monthly status meetings and Monthly Status Reports, Working Group and subgroup participation as requested, and consideration and documentation of stakeholder input | |
| 10 | Draft 2028 Report Submission | Prepare and submit the Draft 2028 Report | |
| 11 | Final 2028 Report Submission | Revise the Draft 2028 Report based on ICC Staff comments and submit the Final 2028 Report | |
| 12 | 2028 Presentation of Findings | Present findings and recommendations to ICC Staff. If requested by ICC Staff, the Vendor shall also present the findings and recommendations to the Commission at no additional cost | |
| TOTAL 2028 REPORT SERVICES | $ - 0 |
| 13 | 2029 Project Plan Update | Submit the Project Plan Update for the 2029 reporting cycle | ||
| 14 | 2029 Research, Review & Analysis | Perform the research, review, and analysis required for development of the 2029 Report | ||
| 15 | 2029 Stakeholder & ICC Staff Coordination | Perform stakeholder and ICC Staff coordination for the 2029 reporting cycle, including monthly status meetings and Monthly Status Reports, Working Group and subgroup participation as requested, and consideration and documentation of stakeholder input | ||
| 16 | Draft 2029 Report Submission | Prepare and submit the Draft 2029 Report | ||
| 17 | Final 2029 Report Submission | Revise the Draft 2029 Report based on ICC Staff comments and submit the Final 2029 Report | ||
| 18 | 2029 Presentation of Findings | Present findings and recommendations to ICC Staff. If requested by ICC Staff, the Vendor shall also present the findings and recommendations to the Commission at no additional cost | ||
| TOTAL 2029 REPORT SERVICES | $ - 0 | |||
| 19 | 2030 Project Plan Update | Submit the Project Plan Update for the 2030 reporting cycle | ||
| 20 | 2030 Research, Review & Analysis | Perform the research, review, and analysis required for development of the 2030 Report | ||
| 21 | 2030 Stakeholder & ICC Staff Coordination | Perform stakeholder and ICC Staff coordination for the 2030 reporting cycle, including monthly status meetings and Monthly Status Reports, Working Group and subgroup participation as requested, and consideration and documentation of stakeholder input | ||
| 22 | Draft 2030 Report Submission | Prepare and submit the Draft 2030 Report | ||
| 23 | Final 2030 Report Submission | Revise the Draft 2030 Report based on ICC Staff comments and submit the Final 2030 Report | ||
| 24 | 2030 Presentation of Findings | Present findings and recommendations to ICC Staff. If requested by ICC Staff, the Vendor shall also present the findings and recommendations to the Commission at no additional cost | ||
| TOTAL 2030 REPORT SERVICES | $ - 0 | |||
| Travel expenses shall be reimbursed only as permitted under Section F.5.3 and shall not exceed $2,000.00 without prior approval of ICC Staff. Travel shall not be guaranteed and shall be reimbursed only for pre-approved, necessary travel. | $ 2,000.00 | |||
| TOTAL EVALUATED CONTRACT PRICE | $ 2,000.00 | Offeror should enter the total evaluated contract price into BidBuy Line Item #1. |
Travel expenses shall be reimbursed only as permitted under Section F.5.3. Travel must be necessary for Contract performance and approved in writing by ICC Staff prior to travel. Total reimbursable travel shall not exceed $2,000 during the Contract term.
The Offeror shall provide a firm fixed price for each service or deliverable identified in the RFP. The firm fixed prices shall include all costs necessary to perform the applicable requirements of the Scope of Work, except reimbursable travel expressly permitted by the Contract.
Prices shall remain firm throughout the Contract term and shall not be subject to escalation or adjustment except as expressly authorized by the Contract and applicable procurement requirements.
Offeror shall provide a price for every item. If a required service or deliverable will be provided at no additional charge, Offeror shall enter "$0.00." A blank pricing field shall not be interpreted as $0.00.
| Pricing for each item shall reasonably reflect the anticipated level of effort and value of the applicable service or deliverable. Each individual firm fixed price shall become part of the resulting Contract. |
| The Total Evaluated Contract Price shall be calculated by the State as the sum of Items 1 through 24 and travel cost. Annual subtotals are provided for informational and contract-administration purposes and will not be separately scored. |
Offeror shall provide a labor rate schedule identifying all proposed labor categories anticipated to support performance of the Contract. Vendor shall enter rates in the Tab titled: Rate Schedule
Rate Schedule
| Labor Category | Role Description | Hourly Rate |
| Project Director / Principal | Executive oversight, strategic direction, expert testimony, senior regulatory guidance | |
| Project Manager | Day-to-day project management, coordination with ICC Staff, schedule and deliverable oversight | |
| Senior Analyst / Modeler | Leads modeling, technical analysis, scenario development, and interpretation of results | |
| Analyst | Supports modeling, data analysis, research, and documentation | |
| Research / Support Staff | Data collection, administrative support, formatting, and documentation support |
| The Offeror may propose its own internal staff titles; however, all proposed personnel must be mapped to the Agency-defined labor categories above. |
| The Offeror shall provide hourly rate for each labor Category. Hourly rates are requested for contract administration purposes. Hourly rates can not be used to calculate or adjust the fixed prices. |