Price Sheet Summary

This is a price sheet attachment for the East Central Canal Priority Navigational Dredging Project solicitation issued by Brevard County Purchasing Services on behalf of the Natural Resource Management Department in Florida. The project involves maintenance dredging services for the East Central Canal, with bidders required to provide pricing for general items, temporary handling site work, dredging and material handling operations, and offsite disposal services. The estimated dredging quantity is 3,200 cubic yards, with the same volume applicable to towing, offloading, dewatering, and final transport/disposal activities. The price sheet is structured to accommodate both lump sum fixed costs and estimated measured quantity costs, allowing contractors to bid on mobilization and demobilization, maintenance of traffic, surveys with photographic and video documentation, erosion controls, site preparation and restoration, turbidity barriers, environmental and hydrographic monitoring, and mechanical dredging operations.

The bid format requires licensed and qualified marine contractors to submit unit costs and lump sum amounts for each line item, with all costs to be consolidated into a total bid amount. The price sheet presents all bid items with blank cost fields, indicating this is a template for solicitation purposes rather than a completed bid. No specific pricing information, set-asides, contract term details, award dates, or response deadlines are included in this attachment. Contractors are expected to complete the pricing based on their proposed unit rates and lump sum estimates for the fixed and measured quantity work items.

View the file

Other files

File Type Posted
Notice_of_Award.pdf PDF
Bid_Tabulation.pdf PDF
Bid_Tabulation__Names_Only.pdf PDF
2__Revised_Project_Plans_Sheets_G001_C301.pdf PDF
Addendum_3.pdf PDF
1__Revised_Project_Plans_Sheets_G001_C301.pdf PDF
Addendum_2.pdf PDF
Addendum_1.pdf PDF
Addendum_1__Response.pdf PDF
B-8-26-19_INV_&_SPECS.pdf PDF
Attachment_B_-Tech_Specs_with_Permits.pdf PDF
Attachment_C_-_Construction_Plans.pdf PDF
Attachment_D_-_Draft_Contract.pdf PDF
Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Price Sheet East Central Canal Priority Navigational Dredging Project Attachment A - Price Sheet

Lump Sum Fixed Costs
Bid ItemItem DescriptionEst Qty.UnitUnit CostLump Sum Total
General Items
A1Mobilization and Demobilization1LS$ - 0
A2Maintenance of Traffic1LS$ - 0
Temporary Handling Site
B1Surveys (Pre/Post, with Photo & Video)2LS$ - 0
B2Erosion Controls and Devices1LS$ - 0
B3Site Preparation1LS$ - 0
B4Site Restoration1LS$ - 0
Dredging and Material Handling
C1Floating Turbitidy Barrier and Monitoring1LS$ - 0
C2Environmental Monitoring1LS$ - 0
C3Hydrygraphic Survey (Pre/Post)2LS$ - 0
C4As-Built Survey1LS$ - 0
Estimated Measured Quantity Costs
Bid ItemItem DescriptionEst Qty.UnitEstimated Total
Dredging and Material Handling
C5Mechanical Dredging3,200CY$ - 0
C6Tow to Shore and Offloading3,200CY$ - 0
C7Dewatering3,200CY$ - 0
Offsite Disposal
D1Final Transport of Sediment/Disposal3,200CY$ - 0
Summary of Costs
TOTAL LUMP SUM FIXED COSTS:$0.00
ESTIMATED MEASURED QUANTITY COSTS:$0.00

TOTAL BID: $0.00