Attachment A Original SOW.pdf
PDF 187 KB Posted
- Attached to
- 437-22-108 Place Chilled Water Pumps on Epower
- Solicitation number
- 36C26326B0013
About this file
This is a Statement of Work (SOW) for Project 437-22-108 at the Fargo VA Healthcare System to place chilled water pumps on emergency power. The construction cost estimate ranges from $250,000 to $500,000, with a 270-day period of performance beginning approximately 61 days after contract award. The contractor must furnish all labor, materials, and equipment to convert the existing chilled water pump electrical systems from normal power to emergency equipment branch power while maintaining minimal disruption to hospital operations. Work must comply with the National Electrical Code (NEC), VHA Directive 1028, NFPA requirements, and applicable federal, state, and local codes. All electrical work must be performed by certified electricians, and off-hours shift work (5 PM–10 PM or 5 AM–8 AM) is preferred and required whenever possible. All electrical shutdowns require three-week advance notification and approval, completion of Job Safety Analysis worksheets, and facility director acceptance of risk for live electrical work. Arc Flash and Electrical Safety compliance per NEC and NFPA 70E is mandatory.
The project involves installing a new 600A automatic transfer switch (01_AT_EB10E6P) in room 2D-12 to serve five 40hp chilled water pumps (CHWP #1–5) in building 01, converting panelboard 01_PB_10E6P to equipment branch status, and relocating feeder circuits. For pumps #8 and #9 in building 46, the contractor must swap motor control center buckets to relocate power from 46_MC_MCC-46 to 46_MC_MCC-3B. For pumps #12–#19 located in various mechanical rooms across buildings 01 and 09, the contractor must reroute conduit and wire, install new circuit breakers in equipment branch panelboards and switchboards, and decommission existing normal power circuits. The contractor must submit a phasing plan for approval before work begins, maintain daily logs, and provide comprehensive submittals including product data, as-built drawings, certification reports, testing reports per NETA and IEEE standards, progress documentation, warranties, and operation manuals using a digital construction application such as Procore. A completed progress document detailing all new and removed connections with equipment labels must be provided before work is considered concluded. The contract cannot be closed until after the station's go-live date, and any additional equipment needs identified through coordination with the Contracting Officer's Representative shall be negotiated as modifications.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project # 437-22-108 Fargo VA Healthcare System
Scope of Work
Project Number: 437-22-108 Project Title: PLACE CHILLED WATER PUMPS ON EMERGENCY POWER
Construction Cost Estimate Range: $250,000 - $500,000
A. General Intention
The Contractor shall furnish all labor, materials, and equipment to place the chilled water pumps on emergency equipment branch power on the Fargo VA campus in accordance with this Statement of Work, all contract documents including drawings and specifications, and in compliance with federal, state, and local codes and law. If there are conflicts between the codes, contact the VA Contracting Officer (CO) and the VA Contracting Officer’s Representative (COR) for resolution.
B. Statement of Work
Description of Work: Work shall include, but shall not be limited to providing all labor, materials, equipment, etc necessary to complete Fargo VA Health Care System project 437-22-108, Place Chilled Water Pumps on Emergency Power, in accordance with this Scope of Work, NEC, VHA Directive 1028 (Electrical Power Distribution Systems), the contract documents, all applicable federal, state and local codes as well as all NFPA requirements.
The construction work shall account for and ensure that the VA is minimally impacted in terms of services provided to our customers, as well as any coordination with other contractors on site.
Offerors will verify field conditions in a pre-bid site walk.
Normal business hours for the hospital are 8am to 5pm. Off-hours shift work (i.e.
shifts between 5 PM – 10PM or 5 AM – 8 AM) shall be preferred and required whenever possible to minimize disruptions to hospital services.
All electrical shutdowns shall have 3-week notification and approval prior to date of shutdown to allow for notification of affected staff. No live electrical work shall be performed without express written acceptance of risk by facility director per instance of live electrical work. All electrical shutdowns shall require completion of Job Safety Analysis (JSA) Worksheet prior to start of specific work on the date of the shutdown; see attachment for blank and sample completed JSAs.
Lock Out Tag Out (LOTO) procedures shall be required for all electrical and utility work, and some work may require confined/enclosed space work conditions and training.
Arc Flash and Electrical Safety shall be required per NEC and NFPA 70E for all work around electrical equipment.
All electrical work shall be performed by a certified electrician. Modification of procedures shall not be permitted unless authorized via notification and approval via express written acceptance of risk by facility director prior to date of performance of modified work.
See project specifications for additional information.
Work shall include, but shall not be limited to, installation and commissioning of a new automatic transfer switch for the five (5) 40 hp chilled water pumps (CHWP #1-5) in BE-27 mechanical room to maintain an emergency equipment branch power path (from panel in ) and a normal branch power path (from panel in), as well as breaker location switching and replacement for pumps 8, 9, 12, 13, 14, 15, 16, 17, 18, and 19, with Motor Control Center (MCC) bucket swapping and relocation for pumps 8 and 9, with all necessary conduit and wire demolition, intercepting, rerouting, and installation to bring them onto emergency equipment branch power.
Some pieces of electrical distribution equipment will require commissioning services to be obtained by the Contractor and include at a minimum, the automatic transfer switch. The Contractor shall account for and be prepared to replace all necessary devices, cabling, and conduit as needed and per specifications. As part of commissioning, the Contractor shall be responsible for testing all equipment installed per NEC, and the best practices and standards issued by the National Electrical Testing Association (NETA), and the Institute of Electrical and Electronics Engineers (IEEE).
The Contractor shall be responsible for submitting a phasing plan to accomplish all work within the period of performance, for review and approval by the VA CO and VA COR before the start of work.
Infection control PCRA (Pre-Construction Risk Assessment), ICRA Level II (Infection Control Risk Assessment) and ILSM (Interim Life Safety Measures) procedures shall always be followed at a minimum.
A completed progress document detailing all new connections, all removed connections, and a table of all new labels of all equipment shall be provided to the VA prior to work being considered concluded.
ICRA level 2 will be implemented in all mechanical spaces. Higher ICRA will be required in spaces outside of mechanical rooms in close proximity to clinical spaces.
C. Period of Performance
Coordinate work times with the COR. Submit daily logs to COR for progress tracking, see attachment for sample daily log reporting.
Below represents an approximate schedule for the Period of Performance.
Duration of Work: 270 days for all construction
D. Key Tasks
a. CHWP #1, #2, #3, #4, #5:
i. All five pumps are 40hp and are controlled by VFDs.
ii. They are all currently powered by panelboard 01_PB_10E6P, which is an 800A, 208Y/120V normal power panelboard located in the same room, BE-27, of Building 01. 01_PB_10E6P is fed from switchboard 46_SB_46-W, which is one of the two main switchboards in Building 46.
iii. The service load calculation for these five pumps is as follows:
114A*1.25 (largest motor) + 114A*4 (other remaining motors) = 598.5A
iv. It was determined that there were no existing equipment branch panelboards or switchboards that could accommodate this additional load.
v. Panelboard 01_PB_10E6P shall be converted to an equipment branch panelboard and would be renamed 01_PB_EB10E6P.
1. The feeder from 46_SB_46-W to 01_PB_10E6P shall be disconnected and removed.
2. The 60A, 208V, 1Ø feeder that feeds Building 53 from circuits 2 and 4 in panelboard 01_PB_10E6P will have to be relocated to be fed out of panelboard 01_PB_10E7, which is located in the same room (BE-27) as 01_PB_10E6P.
a. The 30A, 3 pole spare breaker in circuits 35, 37, 39 will have to be removed.
b. A new 60A, 2 pole breaker will have to be installed in
01_PB_10E7.
Item Day
Contract Award D
Pre-construction Conference D+10
Notice to Proceed
• Badging/Background Check Start
• Submittals Due
• Long-Lead Items Ordered (e.g. ATS)
• Badging/Background Check Completion
D+10 D+10 D+10 D+10 D+10
Construction Start D+61
Construction Completion D+270
c. The 60A feeder conduit and conductors will have to be intercepted and re-routed to terminate at 01_PB10E7, which is located about 3 feet on center from 01_PB_10E6P.
3. A new 208Y/120V, 600A automatic transfer switch, 01_AT_EB10E6P, shall be installed to feed the converted equipment branch panelboard 01_PB_EB10E6P.
a. 01_AT_EB10E6P shall be installed in room 2D-12, oriented so its back is to the metal grate mezzanine and between the two flights of stairs connected to the mezzanine. 2D-12 was selected because the ATS must be located in a room that sits above the flood plain.
b. The normal power source of the ATS will be from 46_SB_46-W. The existing breaker 46_FB_10E6P shall be relabeled as 46_FB_ATS-EB10E6P. The existing breaker’s long-time pickup shall be adjusted from 1.0 to 0.75, or the next lowest setting, to account for the new feeder being rated 600A rather than 800A.
The feeder shall be (2) parallel 3” conduits, each carrying 4 #350 (3 hot and a neutral), and a #1 ground conductor.
c. The emergency power source of the ATS will be from 46_SB_46-EE. A new 600A, 3 pole breaker will need to be installed. The feeder shall be (2) parallel 3” conduits, each carrying 4 #350 (3 hot and a neutral), and a #1 ground conductor.
4. A new 600A feeder shall be installed between the new transfer switch, 01_AT_EB10E6P and the converted panelboard, 01_PB_EB10E6P. The feeder shall be (2) parallel 3” conduits, each carrying 4 #350 (3 hot and a neutral), and a #1 ground conductor.
b. Pumps #8/#9:
i. Both pumps are located in BA-01 Mechanical Room of Building 46.
ii. Both are powered by motor control center 46_MC_MCC-46, which is rated for 800A, 208Y/120V and is located in BA-01 Mechanical Room. 46_MC_MCC-46 is fed from switchboard 46_SB_46-W, which is one of the two main switchboards in Building 46.
iii. The nearest equipment branch power source is 46_MC_MCC-3B.
46_MC_MCC-3B is located immediately adjacent to 46_MC_MCC- 46 in the BA-01 Mechanical Room and is rated for 800A, 208Y/120V.
iv. Pumps #8 and #9 shall be powered from 46_MC_MCC-3B.
1. 46_MC_MCC-3B and 46_MC_MCC-46 are identical make and model motor control centers. Therefore, the two buckets that contain the circuit breakers for Pump #8 and Pump #9 can be swapped with two spare buckets of equal size in 46_MC_MCC-3B, which would leave 46_MC_MCC-46 with two additional spare buckets.
2. The conduit and wire that powers Pump #8 and Pump #9 shall be intercepted and rerouted to terminate at 46_MC_MCC-3B. Any unused conduit and wire leftover shall be disconnected and removed.
c. Pumps #12/#13:
i. Both pumps are 40hp and are controlled by VFDs. The pumps are located in BA-65A Mechanical Room.
ii. Both pumps are powered from main switchboard 09_SB_9-E via a
200A circuit breaker, 09_FB_CWP-12-13. 09_SB_9-E is located in room BA-01B.
iii. The service load calculation for these two pumps is as follows:
114A*1.25 (largest motor) = 142.5A. We don’t need to account for both pumps since they run in a primary/backup configuration.
iv. Pumps #12 and #13 shall be powered from a spare 200A breaker in switchboard 09_SB_EB-2.
1. The conduit running from the VFDs that control pumps #12 and #13 shall be intercepted in room BA-01B and then re-routed to switchboard 09_SB_EB-2. The existing conductors and any additional unused conduit shall be disconnected and removed.
2. Existing circuit breaker 09_FB_CWP-12-13 in switchboard 09_SB_9-E shall be turned off and relabeled as “Spare”.
3. New conductors shall be pulled from 09_SB_EB-2 to the VFDs that control pumps #12 and #13.
4. The conductors shall be terminated at one of the available 200A spare breakers, and the breaker shall be re-labeled as
09_FB_CWP-12-13.
d. Pumps #14/#15:
i. Both pumps are 20hp and are controlled by VFDs. The pumps are located in BA-65A Mechanical Room.
ii. Both pumps are powered from panelboard 09_PB_90S2, which is a normal power panelboard that is also located in BA-65A Mechanical Room, via a 90A circuit breaker.
iii. The service load calculation for these two pumps is as follows:
59.4A*1.25 (largest motor) = 74.25A. We don’t need to account for both pumps since they run in a primary/backup configuration.
iv. Pumps #14 and #15 shall be powered from a spare 100A breaker in switchboard 09_SB_EB-2.
1. The conduit and wire running from the VFDs that control pumps #14 and #15 back to panelboard 09_PB_90S2 shall be disconnected and removed.
2. The existing 90A circuit breaker in panelboard 09_PB_90S2, circuits 25, 27, 29 shall be turned off and relabeled as “Spare”.
3. New conductors shall be pulled from 09_SB_EB-2 to the VFDs that control pumps #14 and #15. The conductors shall be terminated at the available 100A spare breaker, and the breaker shall be re-labeled as 09_FB_CWP-14-15
4. The new circuit shall consist of 1-1/2” conduit with 3 #1, and 1 #8 ground.
e. Pumps #16 and #17
i. Both pumps are located in room 3E-08 Mechanical Room of
Building 01 and are powered from panelboard 01_PB_12E5P, which is a normal power panelboard that is located in room 2E-40, via a 90A circuit breaker.
ii. Pumps #16 and #17 shall be powered via two new 90A circuits from panelboard 01_PB_EB13.
1. The conduit and wire running from panelboard 01_PB_12E5P to the non-fused disconnects that provide local disconnecting means for pumps #16 and #17 in room 3E-08 shall be disconnected and removed.
2. The existing 90A circuit breaker in panelboard 01_PB_12E5P shall be turned off and relabeled as “Spare”.
3. Two (2) new 90A, 3 pole circuit breakers shall be installed in panelboard 01_PB_EB13C1’s available space.
4. New conduit and wire shall be provided from 01_PB_EB13C1 to pump #16 and #17’s non-fused disconnects. The conductors shall be terminated at the two new circuit breakers. The new circuit breakers shall be labeled “01_MO_CWP-16” and “01_MO_CWP-17”, respectively. v.
5. Each circuit shall consist of 1-1/4” conduit with 3 #2, 1 #8 ground.
f. Pumps #18/#19:
i. Both pumps are 15hp and are located in BD-70 Mechanical Room.
ii. Both pumps are powered from panelboard 01_PB_10S4, which is a normal power panelboard that is also located in BD-70 Mechanical Room, each via an 80A circuit breaker.
iii. The service load calculation for these two pumps is as follows:
46.2A*1.25 (largest motor) = 57.75A. We don’t need to account for both pumps since they run in a primary/backup configuration.
1. Pumps #18 and #19 shall be powered via two new 80A circuits from panelboard 01_PB_EB10S2. The conduit and wire running from panelboard 01_PB_10S4 to pumps #18 and #19 shall be intercepted and re-routed to terminate at panelboard 01_PB_EB10S2. Any unused conduit and wire leftover shall be disconnected and removed.
2. The existing 80A circuit breaker in panelboard 01_PB_10S4 shall be turned off and relabeled as “Spare”.
3. An existing 20A, 3 pole spare breaker in spaces 7, 9, 11 shall be disconnected and removed.
4. Two (2) new 80A, 3 pole circuit breakers shall be installed in panelboard 01_PB_EB10S2’s spaces 1, 3, 5, and 7, 9, 11.
The new breakers shall be labeled as “01_MO_CWP-18” and “01_MO_CWP-19” respectively.
E. Submittals Contractor to provide a digital construction application for tracking all construction activities, such as Procore or equivalent. Software must provide access to mobile devices through an application. The Digital construction application must provide space for tracking, including the following (list is not exclusive): 1. Submittals/Testing Report VA Project #437-22-108 placed chilled water pumps on emergency power. Agency-specific requirements
a. Daily Logs
b. Submittals for all associated scope of work
i. Product Data
ii. Product Samples (e.g. cables, fuses, breakers)
iii. As-built drawings (e.g. one-line diagrams, locations, and labels for equipment)
iv. Certification Report(s)
v. Testing Reports (including deficiencies)
vi. Progress Documentation (see example below)
vii. Warranties of installation and equipment
viii. Operation and Maintenance Manuals
F. Project Completion
The contract shall not be closed by the Contracting Officer until after the station’s go-live date if additional equipment or needs are identified through coordination with the COR.
If additional equipment or needs are identified, a modification shall be negotiated for the additional work.
End of SOW