Attachment_A_-_C106467_SOW_-_Data_Cable_Installation.docx
DOCX document 40 KB Posted
- Attached to
- Structured Network Cabling Services
- Solicitation number
- 75N99026R00002
About this file
This document is a Statement of Work (SOW) for a data cable installation task order (C106467) at the National Institute of Environmental Health Sciences (NIEHS) Research Triangle Park, NC. The project involves installing and terminating new CAT 6A data cables in multiple rooms (F062, F068-F079) within Building 101, with a 14-calendar day completion period following the Notice to Proceed. Specific installation requirements include demolishing existing cables, installing white, pink, and blue CAT6A cables with varied termination points, replacing data jacks and faceplates, and reinstalling a digital antenna system. The contractor must comply with NIH Design Requirements Manual and FMB-RTP Engineering Standards, provide comprehensive project management, submit detailed schedules and submittals, and ensure all cables are labeled, tested, and warranted for one calendar year from beneficial occupancy date.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work Task Order C106467 Building 101, F Module, Integrated Physiological Initiative Suite – Data Cable Installation National Institute of Environmental Health Sciences Research Triangle Park, NC COR: Kyle Askins Date: November 21, 2025
This Scope of Work details requirements for the installation and termination of new CAT 6A data cables in renovated rooms in Building 101 which includeF062, F068, F069, F070, F071, F072, F073, F074, F075, F076A, F076B, F076C, F076D, F076E, F077, and F079. The Contractor is to provide all services for review of existing conditions; preparation of required submittals; and construction in accordance with this Statement of Work and contract requirements.
I. GENERAL:
A. The Contractor shall provide all services necessary to complete the project as stated in Section III, Scope of Work (SOW). The Contractor is responsible for providing demolition/construction, temporary contractor access, and maintaining functionality of the existing facility as required.
B. Period of performance: Following Notice to proceed, the contractor will have 14 calendar days to complete the work.
C. The Technical Foreman will serve as the site Safety Officer for work covered in this task order.
D. The Contractor shall provide all project management personnel necessary per their approved quality control and safety plans to properly oversee the construction of this project. Project Manager/ Quality Control Manager, and Foreman roles may be performed by the same individual as deemed appropriate by the Contractor for this task order provided the designated personnel are qualified and meet the requirements set forth in the Contractor’s approved Site-Specific Safety Plan and Site Specific Quality Control Plan. The Contractor shall provide for review and acceptance the resume and qualifications of any key personnel performing the tasks identified above that have not been previously approved by the Government.
E. The attached submittal register (Attachment C) details the minimum number of items to be submitted for Government review and acceptance. The updated submittal register shall include submission dates coordinated with the construction schedule. The construction schedule shall provide a minimum of 5 business days for Government review of each submittal package.
F. Within 5 calendar days of task order Notice to Proceed (NTP) the Contractor shall provide an updated submittal register and preliminary schedule for approval.
G. Within 5 calendar days of task order NTP the Contractor shall provide a detailed construction schedule identifying all major and minor features of work including all closeout documentation required in Section IV of this SOW. The schedule shall be updated and submitted with each pay request or every month, whichever comes first.
H. To avoid unexpected material delivery delays ALL material shall be on the job site or stored locally and readily available. A preparatory inspection may not be scheduled until the material is made available for inspection. No work shall be performed without a preparatory inspection.
II. CONSTRUCTION:
A. The Contractor shall construct the project in accordance with the 2016 NIH Design Requirements Manual for Biomedical Laboratories and Animal Research Facilities and in accordance with the FMB-RTP Engineering Standards and Material Requirements (Revision K). Attachment B is provided as a reference for the installation of the data cables denoted by different shapes and colors.
B. The Contractor shall comply with the quality control requirements for construction in accordance with the Contractor’s Quality Control Plan and approved task order specific supplements.
C. The Contractor shall comply with the safety requirements for construction in accordance with the Contractor’s Accident Prevention Plan and approved task order specific supplements.
III. SCOPE OF WORK
The Contractor shall provide the following:
1. Demolition
a. F062:
i. The corridor has 10 existing pink cables coiled above the ceiling near the door marked with the purple square in Attachment B. Demolish these cables in their entirety back to Communication Room F003.
2. New Work
i. Install 1 white CAT6A cable at each location marked with a red circle on Attachment B and terminate in Communication Room F003.
ii. Install 1 white CAT6A cable at each location marked with an orange circle on Attachment B and terminate in Communication Room F003. Replace the 1 ft blank raceway cover with a 1 ft aluminum raceway cover with a rectangular cutout for a data jack from Post Glover. Provide a two port data jack at each location.
iii. Install 6 white CAT6A cables at each location marked with a yellow circle on Attachment B and terminate in Communication Room F003. Replace the data jacks and faceplate cover with a 6 port data faceplate
iv. Install 1 pink CAT6A cable at each location marked with a blue square in Attachment B and terminate in Communication Room F003. Terminate at each Government provided wireless access point (moved to camera locations on Attachment B).
v. Install 1 blue CAT6A cable at each location marked with a green circle on Attachment B and run the cable to NAE-101-F05 located in the Ground Floor Mechanical Room in F Module.
vi. Re-install the Government provided digital antennae system cabling and install exposed in the corridor at the ceiling. Connect to the existing digital antennae cabling in the F062 corridor near the door on Attachment B. Install the two Government provided Digital Antenna devices shown in Attachment B in Corridor F078 represented by the light blue squares.
b. General Requirements:
i. All cables and terminations shall be labeled and tested with a report submitted.
ii. Cable colors shall meet ESMR requirements.
A. Prior to the start of construction, the Contractor shall submit at minimum the material indicated on the attached submittal register (Attachment C)
B. All equipment and workmanship shall have a warranty period of at least 1 calendar year(s) from the beneficial occupancy date.
IV. ATTACHMENTS
· Submittal Register
· Data Drawing
NOVEMBER 21, 2025 18 of 18 Task Order C106467-Data Only