Attachment A - Approved for Const Project Manual - 03.17.26.pdf
PDF 5 MB Posted
- Attached to
- Enterprise Hall Elevator Modernization
- Solicitation number
- IFB-127890
- Issued by
- Fairfax County, Virginia
About this file
This is a Project Manual for construction of the George Mason University Enterprise Hall Elevator Modernization, a state and local contract opportunity located in Fairfax, Virginia. The project involves modernization of two hydraulic elevators in Enterprise Hall at George Mason University (4400 University Dr, Fairfax, VA 22030), including renovations of the elevator pit, replacement of elevator doors, upgrades with new interior stainless steel panels, lighting, and call buttons, and all necessary modifications to bring the elevators to current code compliance. The project is designated as GMU PC No. 247-242012 and C&DA Project No. 20011.22. The construction documents received approval for construction on March 17, 2026, following revisions submitted on December 9, 2025, and November 20, 2025. The project will be constructed under a single prime contract with the building remaining occupied during construction. The Architect of record is Cole & Denny Architects (Alexandria, VA), with MEP engineering by Potomac Energy Group, Inc., fire protection by GHD, and elevator consulting by Walker Consultants. The project includes comprehensive specifications divided into multiple divisions covering selective demolition, masonry, finishes, conveying equipment, fire suppression, plumbing, HVAC, electrical, and electronic safety systems.
The Contract Documents require compliance with the 2021 Virginia Uniform Statewide Building Code and referenced standards including NFPA 241, the Virginia Rehabilitation Code, and the Virginia Statewide Fire Prevention Code. Contractor must provide a full-time on-site construction superintendent and coordinate all work to minimize disruption to Owner operations, with work limited to normal business hours Monday through Friday unless otherwise approved. The contract specifies submittal procedures requiring 15-day review periods for initial and resubmittal actions, coordination with subcontractors and suppliers, and preparation of comprehensive record documents including marked-up drawings and specifications. Construction waste management must comply with recycling and disposal regulations, with combustible waste materials not held more than seven days during normal weather conditions. Final cleaning and project closeout procedures require Contractor compliance with all manufacturer's instructions, removal of temporary facilities, completion of punch list items, and submission of warranties and project record documents prior to issuance of Substantial Completion and Final Completion certificates. The project is subject to Virginia prevailing wage and employment regulations as indicated by reference to standard forms DGS-30-256, DGS-30-220, and DGS-30-054.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project Manual for construction of
George Mason University Enterprise Hall Elevator Modernization
4400 University Dr Fairfax, VA 22030
GMU PC No.: 247-242012
C&DA Project No.: 20011.22
OUBO Permit Submission
20 Nov 2025
NOT APPROVED,
REVISE & RESUBMIT
Date = 12/09/2025
NOT APPROVED,
REVISE & RESUBMIT
Date = 03/09/2026
APPROVED FOR
CONSTRUCTION
Date = 03/17/2026
These construction documents have been examined in accordance with the 2021 Virginia Uniform Statewide Building Code (USBC). Submittals and/or shop drawings have not been provided or reviewed as part of this process.
The Registered Design Professional and/or Building/Tradesman Contractor shall be solely responsible for the correct installation and construction of all required systems in compliance with Federal, State, Local codes and manufacturing installation instructions. Request required special inspections and provide to A&E for review. Request inspections required by OUBO in accordance with OUBO policies and procedures. Any revisions that occur during the course of construction shall not be made to this set without the explicit permission of the OUBO in accordance with OUBO policies and procedures.
George Mason University Cole & Denny Architects
Enterprise Hall Elevator Modernization Project No.: 20011.22
Project No.: 247-242012
Architect Cole & Denny Architects
277 S. Washington St., Suite 385
Alexandria, VA 22314
Phone: (703) 684-5994
MEP Potomac Energy Group, Inc
2901 Telestar Court, Suite 400
Falls Church, VA 22042
Phone: (703) 683-5000
Fire Protection GHD
14501 George Carter Way, Suite 102
Chantilly, VA 20151
Phone: (571) 325-5032
Elevator Consultant Walker Consultants
2000 Tower Oaks Boulevard, Suite 350
Rockville, MD 20852
202.510.9366
Seal
CO
MM
ONWEALTH OF VIRGINI A
PROFESSIONAL ENGIN
EE
R
FAROOQ M. AHMADZAI
Lic. No. 23837
09-26-202511/20/25
11/20/25
11/20/25
Project No.: 247-242012
TABLE OF CONTENTS TOC - 1
TABLE OF CONTENTS
BIDDING INFORMATION DGS FORM HECO FORM
Notice of Invitation for Bids DGS-30-256 Instructions to Bidders N/A
N/A
HECO-7A-EB
Standard Bid Form DGS-30-220 N/A
GENERAL CONDITIONS & FORMS
All project-required forms can be found on Mason's Facilities Website by utilizing this link -https://facilities.gmu.edu/resources/heco-dgs-forms/
General Conditions of the Construction Contract DGS-30-054 CO-7 Contract Between George Mason University and Contractor N/A HECO-9 Workers Compensation Certificate of Coverage N/A HECO-9A Standard Performance Bond N/A HECO-10 Standard Labor and Material Payment Bond N/A HECO-10.1 Construction Change Order and Justification N/A HECO-11 General Contractor Estimate for Change Order N/A HECO-GC-1 Subcontractor Estimate for Change Order N/A HECO-SC-1 Sub-Subcontractor Estimate for Change Order N/A HECO-SS-1 Schedule of Values and Certificate for Payment N/A HECO-12 Affidavit of Payment of Claims N/A HECO-13 Certificate of CompletionbyA/E of Record N/A HECO-13.1 Certificate of Partial or Substantial Completion by A/E N/A HECO-13.1a Final Report of Structural & Special Inspections N/A HECO-13.1b Certificate of Substantial Completion by Construction N/A HECO-13.1c Inspector ,Manager ,or Administrator Certificate of Completion by Contractor N/A HECO-13.2 Certificate of partial or Substantial Completion by Contractor N/A HECO-13.2a Checklist for Beneficial Occupancy N/A HECO-13.2b Project Completion Report N/A HECO-14 Submittal Register Format DGS-30-364 N/A Statement of Structural and Special Inspections N/A HECO-6a-6b
SPECIFICATIONS
DIVISION 0 – PROCUREMENT AND CONTRACTING REQUIREMENTS
000115 List of Drawing Sheets
DIVISION 1 – GENERAL REQUIREMENTS
011000 Summary 013300 Submittal Procedures 017300 Execution 017419 Construction Waste Management and Disposal
TABLE OF CONTENTS TOC - 2
017700 Closeout Procedures 017839 Project Record Documents
DIVISION 2 – EXISTING CONDITIONS
024119 Selective Demolition
DIVISION 4 – Masonry
040120.65 Masonry Repair & Cleaning
DIVISION 9 – FINISHES
092216 Non-Structural Metal Framing 092900 Gypsum Board 095113 Acoustical Panel Ceilings 096516 Resilient Sheet Flooring 099123 Interior Painting
DIVISION 14 – CONVEYING EQUIPMENT
142401 Hydraulic Elevators
DIVISION 21 – FIRE SUPPRESSION
211313 Wet-Pipe Sprinkler Systems
DIVISION 22 – PLUMBING
220517 Sleeves and Sleeve Seals for Plumbing Piping 220529 Hangers and Supports for Plumbing Piping and Equipment 220553 Identification for Plumbing Piping and Equipment 221429 Sump Pumps
DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
230517 Sleeves and Sleeve Seals for HVAC Piping 230518 Escutcheons for HVAC Piping 230529 Hangers and Supports for HVAC Piping and Equipment
230548.13 Vibration Controls for HVAC
230553 Identification for HVAC Piping and Equipment 230719 HVAC Piping Insulation 232300 Refrigerant Piping 238126 Split-System Air-Conditioners
DIVISION 26 – ELECTRICAL
260519 Low-Voltage Electrical Power Conductors and Cables 260526 Grounding and Bonding for Electrical Systems 260529 Hangers and Supports for Electrical Systems
TABLE OF CONTENTS TOC - 3
260533 Raceways and Boxes for Electrical Systems 260544 Sleeves and Sleeve Seals for Electrical Raceways and Cabling 262726 Wiring Devices 262813 Fuses 262816 Enclosed Switches and Circuit Breakers 265119 LED Interior Lighting
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
283111 Addressable Fire Alarm
LIST OF DRAWING SHEETS 000115 - 1
DOCUMENT 000115 - LIST OF DRAWING SHEETS
1.1 LIST OF DRAWINGS
Drawings: Drawings consist of the Contract Drawings and other drawings listed on the Table of Contents page of the separately bound drawing set titled George Mason University Enterprise Hall Elevator Modernization (Project No.: 247-242012), as modified by subsequent Addenda and Contract modifications.
A. List of Drawings: GMU Enterprise Hall Elevator Modernization
G0.01 Cover Sheet
G1.01 Egress, Occupancy & Fire Resistance Rating Plan
G1.02 Phasing Plan
AD1.01 Partial Demolition Floor Plan – Elevator #1 & #2
AD1.02 Partial Demolition Floor Plan - Elevator #3
AD4.01 Demolition Interior Elevations, Wall Sections and Details - Elevator #1 & #2
AD4.02 Demolition Interior Elevations, Wall Sections and Details - Elevator #3
A1.01 Partial Floor Plans - Elevator #1 & #2
A1.02 Partial Floor Plans - Elevator #3
A4.01 Interior Elevations, Wall Sections and Details - Elevator #1 & #2
A4.02 Interior Elevations, Wall Sections and Details – Elevator #3
A5.01 Partition Types & UL Details
M-001 Cover Sheet – Mechanical
M-101 Partial Demolition Floor Plans Elevator #1 & #2 – Mechanical
M-102 Partial Demolition Floor Plans Elevator #3 – Mechanical
M-201 Partial New Work Floor Plans Elevator #1 & #2 – Mechanical
M-202 Partial Demolition Floor Plan Elevator #3 – Mechanical
M-203 Site Plan New Work, Mechanical
LIST OF DRAWING SHEETS 000115 - 2
M-301 Details – Mechanical
M-401 Schedules – Mechanical
P-001 Cover Sheet – Plumbing
P-201 Partial New Work Floor Plans – Elevator #1 & #2
P-202 Partial New Work Floor Plans – Elevator #3
E-001 Cover Sheet – Electrical
E-101 Partial Demolition Floor Plans – Elevator #1 & #2
E-102 Partial Demolition Floor Plans – Elevator #3
E-201 Partial Lighting Floor Plans – Elevator #1 & #2
E-202 Partial Power Floor Plans – Elevator #1 & #2
E-203 Partial Lighting Floor Plans – Elevator #3
E-204 Partial Power Floor Plans – Elevator #3
E-205 Site Plan – Electrical
E-401 Power Riser Diagram
E-501 Panel Schedules – Electrical
T-001 Cover Sheet – Telecom
T-201 Partial First Floor New Work Plans – Elevator #1 & #2
T-202 Partial First Floor New Work Plans – Elevator #3
FA0.01 Reference Sheet - Fire Alarm
FA1.00 Elev #1 & #2 Lower Floor Plans - Fire Alarm
FA1.01 Elev & #2 Level 1-4 Floor Plans - Fire Alarm
FA1.02 Elev #3 Lower Level Floor Plans - Fire Alarm
FA1.03 Elev #3 First Floor Plans - Fire Alarm
FA1.04 Elev #3 Second Floor Plans - Fire Alarm
FA5.01 Detail Sheet - Fire Alarm
LIST OF DRAWING SHEETS 000115 - 3
FX0.01 Reference Sheet – Sprinkler
FX1.00 Elev #1 & #2 Lower Floor Plans – Sprinkler
FX 1.01 Elev & #2 Level 1-4 Floor Plans – Sprinkler
FX 1.02 Elev #3 Lower Level Floor Plans – Sprinkler
FX 1.03 Elev #3 First Floor Plans – Sprinkler
FX 1.04 Elev #3 Second Floor Plans – Sprinkler
FX 5.01 Detail Sheet - Sprinkler
END OF DOCUMENT 000115
SUMMARY 011000 - 1
SECTION 011000 - SUMMARY
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Project information.
2. Work covered by Contract Documents.
3. Access to site.
4. Coordination with occupants.
5. Work restrictions.
6. Specification and Drawing conventions.
7. Miscellaneous provisions.
1.3 PROJECT INFORMATION
A. Project Identification: George Mason University Enterprise Hall Elevator Modernization.
Project No.:247-242012
1. Project Location: 4400 University Dr Fairfax, Virginia 22030
B. Owner: George Mason University.
C. Architect: Cole & Denny Architects, 277 S. Washington Street Suite 385, Alexandria, Virginia 22314.
1.4 WORK COVERED BY CONTRACT DOCUMENTS
A. The project consists of the modernization of two hydraulic elevators in the Enterprise Hall of the George Mason University. Modernization consists of renovations of the elevator pit and replacing elevator doors. The elevator will also be upgraded with new interior stainless steel interior panels, lighting, and call buttons. All necessary modifications shall be made to bring the elevator up to current code. The building will remain occupied during construction.
B. Type of Contract:
SUMMARY 011000 - 2
1. Project will be constructed under a single prime contract.
1.5 ACCESS TO SITE
A. General: Contractor shall have limited use of Project site for construction operations as directed and approved by the Owner.
B. Use of Site: Limit use of Project site to work in areas indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. Driveways, Walkways and Entrances: Keep driveways loading areas, and entrances serving premises clear and available to Owner, Owner's employees, students and visitors, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
a. Schedule deliveries to minimize use of driveways and entrances by construction operations.
b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
C. Protection of Entrances and Exits:
1. Provide temporary protection, including overhead protection, for persons at all building entrances and exits when work is being performed above and around each entrance and exit. Maintain required egress widths at all times.
1.6 COORDINATION WITH OCCUPANTS
A. Full Owner Occupancy: Owner will occupy site and existing building during entire construction period. Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform the Work so as not to interfere with Owner's day-to-day operations. Maintain existing exits unless otherwise indicated.
1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Owner and approval of authorities having jurisdiction.
2. Notify Owner not less than 72 hours in advance of activities that will affect Owner's operations.
1.7 WORK RESTRICTIONS
A. Work Restrictions, General: Comply with restrictions on construction operations.
1. Comply with limitations on use of public streets and with other requirements of authorities having jurisdiction.
SUMMARY 011000 - 3
2. On-Site Work Hours: Limit work in and on the existing building to normal business working hours on Monday through Friday, except as otherwise approved by Owner.
B. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after providing temporary utility services.
1. Notify Owner not less than two days in advance of proposed utility interruptions.
2. Obtain Owner's written permission before proceeding with utility interruptions.
C. Noise, Vibration, and Odors: Coordinate operations that may result in high levels of noise and vibration, odors, or other disruption to building occupancy and surrounding buildings and sites with Owner.
1. Notify Owner not less than two days in advance of proposed disruptive operations.
2. Obtain Owner's written permission before proceeding with disruptive operations.
D. Nonsmoking Building: Smoking is not permitted within the building or within 50 feet of entrances, operable windows, or outdoor air intakes of any buildings on site.
1.8 SPECIFICATION AND DRAWING CONVENTIONS
A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:
1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.
2. Specification requirements are to be performed by Contractor unless specifically stated otherwise.
3. Unless otherwise noted, the term “days” shall mean calendar days.
B. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.
C. Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the Specifications. One or more of the following are used on Drawings to identify materials and products:
1. Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections.
2. Abbreviations: Materials and products are identified by abbreviations published as part of the U.S. National CAD Standard and scheduled on Drawings.
3. Keynoting: Materials and products are identified by reference keynotes referencing Specification Section numbers found in this Project Manual.
SUMMARY 011000 - 4
1.9 GENERAL SEQUENCE OF WORK
A. Obtain Owner’s approval of all submittals related to exterior work before beginning any exterior work on site.
B. To the extent practical, complete each interior work area fully as soon as possible to avoid the need to return to that area.
1.10 CONSTRUCTION SUPERINTENDENT
A. Provide full time on-site construction superintendent qualified and available to supervise all construction trades and coordinate the work with the Owner and Owner's operations.
1.11 INDUSTRY STANDARDS
A. Applicability of Standards: Unless the Contract Documents include more stringent requirements, applicable construction industry standards have the same force and effect as if bound or copied directly into the Contract Documents to the extent referenced. Such standards are made a part of the Contract Documents by reference.
B. Publication Dates: Comply with standards in effect as of date of the Contract Documents unless otherwise indicated.
C. Copies of Standards: Each entity engaged in construction on Project should be familiar with industry standards applicable to its construction activity. Copies of applicable standards are not bound with the Contract Documents.
1. Where copies of standards are needed to perform a required construction activity, obtain copies directly from publication source.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 011000
SUBMITTAL PROCEDURES 013300 - 1
SECTION 013300 - SUBMITTAL PROCEDURES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Submittal schedule requirements.
2. Administrative and procedural requirements for submittals.
B. Related Requirements:
1. General Conditions of the Construction Contract for additional requirements.
2. Division 1 Section 017839 "Project Record Documents" for submitting record
Drawings, record Specifications, and record Product Data.
1.3 DEFINITIONS
A. Action Submittals: Written and graphic information and physical samples that require Architect's responsive action. Action submittals are those submittals indicated in individual Specification Sections as "action submittals."
B. Informational Submittals: Written and graphic information and physical samples that do not require Architect's responsive action. Submittals may be rejected for not complying with requirements. Informational submittals are those submittals indicated in individual Specification Sections as "informational submittals."
1.4 SUBMITTAL SCHEDULE
A. Submittal Schedule: Submit, as an action submittal, a list of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, ordering, manufacturing, fabrication, and delivery when establishing dates.
Include additional time required for making corrections or revisions to submittals noted by Architect and additional time for handling and reviewing submittals required by those corrections.
1. Coordinate submittal schedule with list of subcontracts, the schedule of values, and Contractor's construction schedule.
SUBMITTAL PROCEDURES 013300 - 2
2. Initial Submittal: Submit concurrently with startup construction schedule. Include submittals required during the first 60 days of construction. List those submittals required to maintain orderly progress of the Work and those required early because of long lead time for manufacture or fabrication.
3. Final Submittal: Submit concurrently with the first complete submittal of Contractor's construction schedule.
a. Submit revised submittal schedule to reflect changes in current status and timing for submittals.
4. Format: Arrange the following information in a tabular format:
a. Scheduled date for first submittal.
b. Specification Section number and title.
c. Submittal Category: Action; informational.
d. Name of subcontractor.
e. Description of the Work covered.
f. Scheduled date for Architect's final release or approval.
g. Scheduled dates for purchasing.
h. Scheduled date of fabrication.
i. Scheduled dates for installation.
j. Activity or event number.
1.5 SUBMITTAL FORMATS
A. Submittal Information: Include the following information in each submittal:
1. Project name.
2. Date.
3. Name of Architect.
4. Name of Contractor.
5. Name of firm or entity that prepared submittal.
6. Names of subcontractor, manufacturer, and supplier.
7. Unique submittal number, including revision identifier. Include Specification
Section number with sequential alphanumeric identifier; and alphanumeric suffix for resubmittals.
8. Category and type of submittal.
9. Submittal purpose and description.
10. Number and title of Specification Section, with paragraph number and generic name for each of multiple items.
11. Drawing number and detail references, as appropriate.
12. Indication of full or partial submittal.
13. Location(s) where product is to be installed, as appropriate.
14. Other necessary identification.
15. Remarks.
16. Signature of transmitter.
B. Options: Identify options requiring selection by Architect.
SUBMITTAL PROCEDURES 013300 - 3
C. Deviations and Additional Information: On each submittal, clearly indicate deviations from requirements in the Contract Documents, including minor variations and limitations; include relevant additional information and revisions, other than those requested by Architect on previous submittals. Indicate by highlighting on each submittal or noting on attached separate sheet.
D. PDF Submittals: Prepare submittals as PDF package, incorporating complete information into each PDF file. Name PDF file with submittal number.
1.6 SUBMITTAL PROCEDURES
A. Prepare and submit submittals required by individual Specification Sections. Types of submittals are indicated in individual Specification Sections.
1. Email: Prepare submittals as PDF package, and transmit to Architect by sending via email. Include PDF transmittal form. Include information in email subject line as requested by Architect.
a. Architect will return annotated file. Annotate and retain one copy of file as a digital Project Record Document file.
B. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.
1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.
2. Submit all submittal items required for each Specification Section concurrently unless partial submittals for portions of the Work are indicated on approved submittal schedule.
3. Submit action submittals and informational submittals required by the same Specification Section as separate packages under separate transmittals.
4. Coordinate transmittal of submittals for related parts of the Work specified in different Sections so processing will not be delayed because of need to review submittals concurrently for coordination.
a. Architect reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.
C. Processing Time: Allow time for submittal review, including time for resubmittals, as follows. Time for review shall commence on Architect's receipt of submittal. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including resubmittals.
1. Initial Review: Allow 15 days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required. Architect will advise Contractor when a submittal being processed must be delayed for coordination.
2. Intermediate Review: If intermediate submittal is necessary, process it in same manner as initial submittal.
3. Resubmittal Review: Allow 15 days for review of each resubmittal.
SUBMITTAL PROCEDURES 013300 - 4
4. Concurrent Consultant Review: Where the Contract Documents indicate that submittals may be transmitted simultaneously to Architect and to Architect's consultants, allow 15 days for review of each submittal. Submittal will be returned to Architect before being returned to Contractor.
D. Resubmittals: Make resubmittals in same form and number of copies as initial submittal.
1. Note date and content of previous submittal.
2. Note date and content of revision in label or title block and clearly indicate extent of revision.
3. Resubmit submittals until they are marked with approval notation from Architect's action stamp.
E. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.
F. Use for Construction: Retain complete copies of submittals on Project site. Use only final action submittals that are marked with approval notation from Architect's action stamp.
1.7 SUBMITTAL REQUIREMENTS
A. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
1. If information must be specially prepared for submittal because standard published data are unsuitable for use, submit as Shop Drawings, not as Product Data.
2. Mark each copy of each submittal to show which products and options are applicable.
3. Include the following information, as applicable:
a. Manufacturer's catalog cuts.
b. Manufacturer's product specifications.
c. Standard color charts.
d. Statement of compliance with specified referenced standards.
e. Testing by recognized testing agency.
f. Application of testing agency labels and seals.
g. Notation of coordination requirements.
h. Availability and delivery time information.
4. For equipment, include the following in addition to the above, as applicable:
a. Wiring diagrams that show factory-installed wiring.
b. Printed performance curves.
c. Operational range diagrams.
SUBMITTAL PROCEDURES 013300 - 5
d. Clearances required to other construction, if not indicated on accompanying Shop Drawings.
5. Submit Product Data before Shop Drawings, and before or concurrent with Samples.
B. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.
1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable:
a. Identification of products.
b. Schedules.
c. Compliance with specified standards.
d. Notation of coordination requirements.
e. Notation of dimensions established by field measurement.
f. Relationship and attachment to adjoining construction clearly indicated.
g. Seal and signature of professional engineer if specified.
2. Paper Sheet Size: Except for templates, patterns, and similar full-size Drawings, submit Shop Drawings on sheets at least 11 by 17 inches, but no larger than 24 by 36 inches.
a. Two opaque (bond) copies of each submittal. Architect will return one copy.
C. Product Schedule: As required in individual Specification Sections, prepare a written summary indicating types of products required for the Work and their intended location.
Include the following information in tabular form:
1. Type of product. Include unique identifier for each product indicated in the Contract Documents or assigned by Contractor if none is indicated.
2. Manufacturer and product name, and model number if applicable.
3. Number and name of room or space.
4. Location within room or space.
D. Qualification Data: Prepare written information that demonstrates capabilities and experience of firm or person. Include lists of completed projects with project names and addresses, contact information of architects and owners, and other information specified.
E. Design Data: Prepare and submit written and graphic information indicating compliance with indicated performance and design criteria in individual Specification Sections.
Include list of assumptions and summary of loads. Include load diagrams if applicable.
Provide name and version of software, if any, used for calculations. Number each page of submittal.
F. Certificates:
SUBMITTAL PROCEDURES 013300 - 6
1. Certificates and Certifications Submittals: Submit a statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity. Provide a notarized signature where indicated.
2. Installer Certificates: Submit written statements on manufacturer's letterhead certifying that Installer complies with requirements in the Contract Documents and, where required, is authorized by manufacturer for this specific Project.
3. Manufacturer Certificates: Submit written statements on manufacturer's letterhead certifying that manufacturer complies with requirements in the Contract Documents. Include evidence of manufacturing experience where required.
4. Material Certificates: Submit written statements on manufacturer's letterhead certifying that material complies with requirements in the Contract Documents.
5. Product Certificates: Submit written statements on manufacturer's letterhead certifying that product complies with requirements in the Contract Documents.
6. Welding Certificates: Prepare written certification that welding procedures and personnel comply with requirements in the Contract Documents. Submit record of Welding Procedure Specification and Procedure Qualification Record on AWS forms. Include names of firms and personnel certified.
G. Test and Research Reports:
1. Compatibility Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of compatibility tests performed before installation of product. Include written recommendations for primers and substrate preparation needed for adhesion.
2. Field Test Reports: Submit written reports indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements in the Contract Documents.
3. Material Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements in the Contract Documents.
4. Preconstruction Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of tests performed before installation of product, for compliance with performance requirements in the Contract Documents.
5. Product Test Reports: Submit written reports indicating that current product produced by manufacturer complies with requirements in the Contract Documents. Base reports on evaluation of tests performed by manufacturer and witnessed by a qualified testing agency, or on comprehensive tests performed by a qualified testing agency.
6. Research Reports: Submit written evidence, from a model code organization acceptable to authorities having jurisdiction, that product complies with building code in effect for Project. Include the following information:
a. Name of evaluation organization.
b. Date of evaluation.
c. Time period when report is in effect.
SUBMITTAL PROCEDURES 013300 - 7
d. Product and manufacturers' names.
e. Description of product.
f. Test procedures and results.
g. Limitations of use.
1.8 CONTRACTOR'S REVIEW
A. Action Submittals and Informational Submittals: Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to Architect.
B. Contractor's Approval: Indicate Contractor's approval for each submittal with a uniform approval stamp. Include name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.
1. Architect will not review submittals received from Contractor that do not have Contractor's review and approval.
1.9 ARCHITECT'S REVIEW
A. Action Submittals: Architect will review each submittal, indicate corrections or revisions required, and return it.
1. PDF and Paper Submittals: Architect will indicate, via markup on each submittal, the appropriate action.
B. Informational Submittals: Architect will review each submittal and will not return it, or will return it if it does not comply with requirements. Architect will forward each submittal to appropriate party.
C. Incomplete submittals are unacceptable, will be considered nonresponsive, and will be returned for resubmittal without review.
D. Architect will discard submittals received from sources other than Contractor.
E. Submittals not required by the Contract Documents will be returned by Architect without action.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 013300
EXECUTION 017300 - 1
SECTION 017300 - EXECUTION
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes general administrative and procedural requirements governing execution of the Work including, but not limited to, the following:
1. Construction layout.
2. Installation of the Work.
3. Cutting and patching.
4. Progress cleaning.
5. Protection of installed construction.
6. Correction of the Work
B. Related Requirements:
1. Section 011000 "Summary" for limits on use of Project site.
2. Section 017700 "Closeout Procedures" for submitting final property survey with
Project Record Documents, recording of Owner-accepted deviations from indicated lines and levels, replacing defective work, and final cleaning.
3. Section 024119 "Selective Demolition" for demolition and removal of selected portions of the building.
1.3 DEFINITIONS
A. Cutting: Removal of in-place construction necessary to permit installation or performance of subsequent work.
B. Patching: Fitting and repair work required to restore construction to original conditions after installation of subsequent work.
EXECUTION 017300 - 2
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 EXAMINATION
A. Existing Conditions: The existence and location of underground and other utilities and construction indicated as existing are not guaranteed. Before beginning sitework, investigate and verify the existence and location of underground utilities, and other construction affecting the Work.
3.2 PREPARATION
A. Fire Hazards during demolition and construction: VCC Section 33309.2 and Virginia Rehabilitation Code Section 1504.2 require the provisions of the Virginia Construction Code, and Virginia Rehabilitation Code, and the Virginia Statewide Fire Prevention Code (Chapter 33) strictly observed. In addition the Virginia Statewide Fire Prevention Code Chapter 33 also requires compliance with NFPA 241-2009 for conditions not covered by the Virginia Statewide Fire Prevention Code.
B. Field Measurements: Take field measurements as required to fit the Work properly.
Recheck measurements before installing each product. Where portions of the Work are indicated to fit to other construction, verify dimensions of other construction by field measurements before fabrication. Coordinate fabrication schedule with construction progress to avoid delaying the Work.
C. Space Requirements: Verify space requirements and dimensions of items shown diagrammatically on Drawings.
D. Review of Contract Documents and Field Conditions: Immediately on discovery of the need for clarification of the Contract Documents caused by differing field conditions outside the control of Contractor, submit a request for information to Architect.
3.3 INSTALLATION
A. General: Locate the Work and components of the Work accurately, in correct alignment and elevation, as indicated.
1. Make vertical work plumb and make horizontal work level.
2. Where space is limited, install components to maximize space available for maintenance and ease of removal for replacement.
3. Conceal pipes, ducts, and wiring in finished areas unless otherwise indicated.
B. Comply with manufacturer's written instructions and recommendations for installing products in applications indicated.
EXECUTION 017300 - 3
C. Install products at the time and under conditions that will ensure the best possible results. Maintain conditions required for product performance until Substantial Completion.
D. Conduct construction operations so no part of the Work is subjected to damaging operations or loading in excess of that expected during normal conditions of occupancy.
E. Sequence the Work and allow adequate clearances to accommodate movement of construction items on site and placement in permanent locations.
F. Tools and Equipment: Where possible, select tools or equipment that minimize production of excessive noise levels.
G. Templates: Obtain and distribute to the parties involved templates for work specified to be factory prepared and field installed. Check Shop Drawings of other portions of the Work to confirm that adequate provisions are made for locating and installing products to comply with indicated requirements.
H. Attachment: Provide blocking and attachment plates and anchors and fasteners of adequate size and number to securely anchor each component in place, accurately located and aligned with other portions of the Work. Where size and type of attachments are not indicated, verify size and type required for load conditions.
1. Mounting Heights: Where mounting heights are not indicated, mount components at heights directed by Architect.
2. Allow for building movement, including thermal expansion and contraction.
3. Coordinate installation of anchorages. Furnish setting drawings, templates, and directions for installing anchorages, including sleeves, concrete inserts, anchor bolts, and items with integral anchors, that are to be embedded in concrete or masonry. Deliver such items to Project site in time for installation.
I. Joints: Make joints of uniform width. Where joint locations in exposed work are not indicated, arrange joints for the best visual effect. Fit exposed connections together to form hairline joints.
J. Repair or remove and replace damaged, defective, or nonconforming Work.
1. Comply with Section 017700 "Closeout Procedures" for repairing or removing and replacing defective Work.
3.4 CUTTING AND PATCHING
A. Cutting and Patching, General: Employ skilled workers to perform cutting and patching.
Proceed with cutting and patching at the earliest feasible time, and complete without delay.
EXECUTION 017300 - 4
1. Cut in-place construction to provide for installation of other components or performance of other construction, and subsequently patch as required to restore surfaces to their original condition.
B. Existing Warranties: Remove, replace, patch, and repair materials and surfaces cut or damaged during installation or cutting and patching operations, by methods and with materials so as not to void existing warranties.
C. Temporary Support: Provide temporary support of work to be cut.
D. Protection: Protect in-place construction during cutting and patching to prevent damage. Provide protection from adverse weather conditions for portions of Project that might be exposed during cutting and patching operations.
E. Adjacent Occupied Areas: Where interference with use of adjoining areas or interruption of free passage to adjoining areas is unavoidable, coordinate cutting and patching according to requirements in Section 011000 "Summary."
F. Existing Utility Services and Mechanical/Electrical Systems: Where existing services/systems are required to be removed, relocated, or abandoned, bypass such services/systems before cutting to prevent interruption to occupied areas.
G. Cutting: Cut in-place construction by sawing, drilling, breaking, chipping, grinding, and similar operations, including excavation, using methods least likely to damage elements retained or adjoining construction. If possible, review proposed procedures with original Installer; comply with original Installer's written recommendations.
1. In general, use hand or small power tools designed for sawing and grinding, not hammering and chopping. Cut holes and slots neatly to minimum size required, and with minimum disturbance of adjacent surfaces. Temporarily cover openings when not in use.
2. Finished Surfaces: Cut or drill from the exposed or finished side into concealed surfaces.
3. Concrete and Masonry: Cut using a cutting machine, such as an abrasive saw or a diamond-core drill.
4. Excavating and Backfilling: Comply with requirements in applicable Sections where required by cutting and patching operations.
5. Mechanical and Electrical Services: Cut off pipe or conduit in walls or partitions to be removed. Cap, valve, or plug and seal remaining portion of pipe or conduit to prevent entrance of moisture or other foreign matter after cutting.
6. Proceed with patching after construction operations requiring cutting are complete.
H. Patching: Patch construction by filling, repairing, refinishing, closing up, and similar operations following performance of other work. Patch with durable seams that are as invisible as practicable. Provide materials and comply with installation requirements specified in other Sections, where applicable.
1. Inspection: Where feasible, test and inspect patched areas after completion to demonstrate physical integrity of installation.
EXECUTION 017300 - 5
2. Exposed Finishes: Restore exposed finishes of patched areas and extend finish restoration into retained adjoining construction in a manner that will minimize evidence of patching and refinishing.
a. Clean piping, conduit, and similar features before applying paint or other finishing materials.
b. Restore damaged pipe covering to its original condition.
3. Exterior Building Enclosure: Patch components in a manner that restores enclosure to a weathertight condition and ensures thermal and moisture integrity of building enclosure.
I. Cleaning: Clean areas and spaces where cutting and patching are performed. Remove paint, mortar, oils, putty, and similar materials from adjacent finished surfaces.
3.5 PROGRESS CLEANING
A. General: Clean Project site and work areas continuously and at the completion of each work day, including common areas. Enforce requirements strictly. Dispose of materials lawfully.
1. Comply with Chapter 33 of the 2018 International Fire code and compliance with NFPA 241 for conditions not covered by the International Fire Code for removal of combustible waste materials and debris.
2. Do not hold waste materials more than seven days during normal weather or three days if the temperature is expected to rise above 80 deg F.
3. Containerize hazardous and unsanitary waste materials separately from other waste. Mark containers appropriately and dispose of legally, according to regulations.
a. Use containers intended for holding waste materials of type to be stored.
4. Coordinate progress cleaning for joint-use areas where Contractor and other contractors are working concurrently.
B. Site: Maintain Project site free of waste materials and debris.
C. Work Areas: Clean areas where work is in progress to the level of cleanliness necessary for proper execution of the Work.
1. Remove liquid spills promptly.
2. Where dust would impair proper execution of the Work, broom-clean or vacuum the entire work area, as appropriate.
D. Installed Work: Keep installed work clean. Clean installed surfaces according to written instructions of manufacturer or fabricator of product installed, using only cleaning materials specifically recommended. If specific cleaning materials are not recommended, use cleaning materials that are not hazardous to health or property and that will not damage exposed surfaces.
EXECUTION 017300 - 6
E. Concealed Spaces: Remove debris from concealed spaces before enclosing the space.
F. Exposed Surfaces in Finished Areas: Clean exposed surfaces and protect as necessary to ensure freedom from damage and deterioration at time of Substantial Completion.
G. Waste Disposal: Do not bury or burn waste materials on-site. Do not wash waste materials down sewers or into waterways.
H. During handling and installation, clean and protect construction in progress and adjoining materials already in place. Apply protective covering where required to ensure protection from damage or deterioration at Substantial Completion.
I. Clean and provide maintenance on completed construction as frequently as necessary through the remainder of the construction period. Adjust and lubricate operable components to ensure operability without damaging effects.
J. Limiting Exposures: Supervise construction operations to ensure that no part of the construction, completed or in progress, is subject to harmful, dangerous, damaging, or otherwise deleterious exposure during the construction period.
3.6 PROTECTION OF INSTALLED CONSTRUCTION
A. Provide final protection and maintain conditions that ensure installed Work is without damage or deterioration at time of Substantial Completion.
B. Protection of Existing Items: Provide protection and ensure that existing items to remain undisturbed by construction are maintained in condition that existed at commencement of the Work.
C. Comply with manufacturer's written instructions for temperature and relative humidity.
3.7 CORRECTION OF THE WORK
A. Repair or remove and replace defective construction. Restore damaged substrates and finishes.
1. Repairing includes replacing defective parts, refinishing damaged surfaces, touching up with matching materials, and properly adjusting operating equipment.
B. Restore permanent facilities used during construction to their specified condition.
C. Remove and replace damaged surfaces that are exposed to view if surfaces cannot be repaired without visible evidence of repair.
D. Repair components that do not operate properly. Remove and replace operating components that cannot be repaired.
EXECUTION 017300 - 7
E. Remove and replace chipped, scratched, and broken glass or reflective surfaces.
END OF SECTION 017300
CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL 017419 - 1
SECTION 017419 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for the following:
1. Recycling nonhazardous demolition and construction waste.
2. Disposing of nonhazardous demolition and construction waste.
B. Related Requirements:
1. Section 024119 "Selective Demolition" for disposition of waste resulting from partial demolition of buildings, structures, and site improvements.
1.3 DEFINITIONS
A. Construction Waste: Building and site improvement materials and other solid waste resulting from construction, remodeling, renovation, or repair operations. Construction waste includes packaging.
B. Demolition Waste: Building and site improvement materials resulting from demolition or selective demolition operations.
C. Disposal: Removal off-site of demolition and construction waste and subsequent sale, recycling, reuse, or deposit in landfill or incinerator acceptable to authorities having jurisdiction.
D. Recycle: Recovery of demolition or construction waste for subsequent processing in preparation for reuse.
CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL 017419 - 2
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 PLAN IMPLEMENTATION
A. General: Provide handling, containers, storage, signage, transportation, and other items as required to implement waste management plan during the entire duration of the Contract.
B. Site Access and Temporary Controls: Conduct waste management operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.
1. Designate and label specific areas on Project site necessary for separating materials that are to be recycled.
3.2 RECYCLING DEMOLITION AND CONSTRUCTION WASTE, GENERAL
A. General: Recycle paper and beverage containers used by on-site workers.
B. Preparation of Waste: Prepare and maintain recyclable waste materials according to recycling or reuse facility requirements. Maintain materials free of dirt, adhesives, solvents, petroleum contamination, and other substances deleterious to the recycling process.
C. Procedures: Separate recyclable waste from other waste materials, trash, and debris.
Separate recyclable waste by type at Project site to the maximum extent practical according to approved construction waste management plan.
1. Provide appropriately marked containers or bins for controlling recyclable waste until removed from Project site. Include list of acceptable and unacceptable materials at each container and bin.
a. Inspect containers and bins for contamination and remove contaminated materials if found.
2. Stockpile processed materials on-site without intermixing with other materials.
Place, grade, and shape stockpiles to drain surface water. Cover to prevent windblown dust.
3. Stockpile materials away from construction area. Do not store within drip line of remaining trees.
4. Store components off the ground and protect from the weather.
5. Remove recyclable waste from Owner's property and transport to recycling receiver or processor.
CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL 017419 - 3
3.3 RECYCLING DEMOLITION WASTE
A. Wood Materials: Sort and stack members according to size, type, and length. Separate lumber, engineered wood products, panel products, and treated wood materials.
3.4 RECYCLING CONSTRUCTION WASTE
A. Packaging:
1. Cardboard and Boxes: Break down packaging into flat sheets. Bundle and store in a dry location.
2. Polystyrene Packaging: Separate and bag materials.
3. Pallets: As much as possible, require deliveries using pallets to remove pallets from Project site. For pallets that remain on-site, break down pallets into component wood pieces and comply with requirements for recycling wood.
4. Crates: Break down crates into component wood pieces and comply with requirements for recycling wood.
3.5 DISPOSAL OF WASTE
A. General: Except for items or materials to be salvaged, recycled, or otherwise reused, remove waste materials from Project site and legally dispose of them in a landfill or incinerator acceptable to authorities having jurisdiction.
1. Except as otherwise specified, do not allow waste materials that are to be disposed of accumulate on-site.
2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.
B. Burning: Do not burn waste materials.
C. Burning: Burning of waste materials is permitted only at designated areas on Owner's property, provided required permits are obtained. Provide full-time monitoring for burning materials until fires are extinguished.
D. Disposal: Remove waste materials and dispose of at designated spoil areas on Owner's property.
E. Disposal: Remove waste materials from Owner's property and legally dispose of them.
END OF SECTION 017419
CLOSEOUT PROCEDURES 017700 - 1
SECTION 017700 - CLOSEOUT PROCEDURES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for contract closeout, including, but not limited to, the following:
1. Substantial Completion procedures.
2. Final completion procedures.
3. Warranties.
4. Final cleaning.
5. Repair of the Work.
B. Related Requirements:
1. Section 017839 "Project Record Documents" for submitting Record Drawings, Record Specifications, and Record Product Data.
1.3 SUBSTANTIAL COMPLETION PROCEDURES
A.