Attachment 9 - 663A4-23-201 - Division Cost Breakout.xls
XLS spreadsheet 316 KB Posted
- Solicitation number
- 36C26026R0035_1
About this file
This is a Construction Cost Estimate template in CSI (Construction Specifications Institute) format for federal construction project 663A4-23-201, "Replace 40 Ton Condenser Bldg 200" at VA Puget Sound Medical Center - AMLK Campus in Tacoma, Washington. The spreadsheet is designed for contractors to submit detailed cost breakdowns organized by 50 CSI divisions, with prefilled divisions serving as examples that contractors may modify or supplement with additional line items as needed.
The template includes a summary page where contractors must fill in company name, date, and overhead/profit percentages for both prime contractors (with placeholder rates of 10% overhead and 10% profit) and subcontractors (5% overhead and 11% profit), along with sales tax (6%) and builder's risk/performance bonds (2%). The three sample divisions provided show cumulative costs: Division 1 (General Requirements) at $50.00, Division 2 (Existing Conditions) at $59.48 with subcontractor markups applied, and Division 3 (Concrete Work) at $64.45 with different subcontractor rates, resulting in a hard cost total of $173.93 and a final contract total of $214.66. All other divisions (5, 6, 7, 10, 13, 22, 23, 26) are currently empty, allowing contractors to populate costs as required. The spreadsheet contains automated formulas that self-populate the summary page and all division tabs based on individual division entries and the overhead/profit rates established on the summary page, with exceptions for cases where different subcontractors have varying rates or when the prime performs work directly.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Instructions
Use the information from the prefilled division sheets below to complete the 50 Divisions Cost Estimate CSI* Format tool to build your proposal. The information from the prefilled division sheets may not be all inclusive. The contractor is allowed to include any missing items from each division and is allowed to fill in other divisions that are not listed in the prefilled division sheets. If there is a disagreement with the prefilled division sheets, the contractor should not delete the element(s), but instead leave it blank and then include their suggested element(s) at the bottom of that division tab. Please note that on the summary page there is a place to fill in overhead and profit percentages for both the prime and the subcontractor that will self-populate the summary page and all the division tabs.
Exceptions:
(1) if each subcontractor has a different overhead and profit rates than the percentage placed on the summary page, an adjustment will have to be made to that specific division page. The spreadsheet will still calculate correctly.
(2) If the prime is self-performing the work for that division then the profit and overhead will need to be zeroed for that particular division, because the primes overhead and profit is already captured on the summary page.
| The ktr is required to complete the areas marked "Fill Here" in the summary tab. The rest of the information in the summary tab will automatically tabulate from the individual division tabs except for the few exceptions listed above. |
| Divisions 1, 2, and 3 show sample inputs to illustrate how the spreadsheet works. |
| * CSI = Construction Specifications Institute |
&L&"Verdana,Bold"Construction Cost Estimate &R&P of &N
Summary
| CONSTRUCTION COST ESTIMATE | Date: | |||||
| Fill Here | ||||||
| COMPANY | ||||||
| Fill Here | ||||||
| PROJECT | ||||||
| 663A4-23-201 - Replace 40 Ton Condenser Bldg 200 | ||||||
| LOCATION | PROJECT NO. | 663-21-100 | ||||
| VA Puget Sound Medical Center - AMLK Campus, Tacoma, WA | ||||||
| DIVISION | DESCRIPTION | % by | ||||
| Division | Division Total | |||||
| DIVISION 01 | GENERAL REQUIREMENTS | 28.7% | 50.00 | |||
| DIVISION 02 | EXISTING CONDITIONS | 34.2% | 59.48 | |||
| DIVISION 03 | CONCRETE WORK | 37.1% | 64.45 | FILL IN AS REQUIRED (this will link to the entire document) | ||
| DIVISION 05 | METALS | - 0 | ||||
| DIVISION 06 | WOOD, PLASTICS AND COMPOSITES | 0.0% | - 0 | |||
| DIVISION 07 | THERMAL AND MOISTURE PROTECTION | 0.0% | - 0 | GC Overhead | 10.00% | |
| DIVISION 10 | SPECIALTIES | 0.0% | - 0 | GC Profit | 10.00% | |
| DIVISION 13 | SPECIAL CONSTRUCTION | - 0 | Sub Overhead | 5.00% | ||
| DIVISION 22 | PLUMBING | 0.0% | - 0 | Sub Profit | 11.00% | |
| DIVISION 23 | HEATING, VENTILATING AND A/C | 0.0% | - 0 | Sales Tax | 6.00% | |
| DIVISION 26 | ELECTRICAL | 0.0% | - 0 | Risk/Bonding | 2.00% | |
| HARD COST TOTAL | 100% | 173.93 | This spreadsheet contains many formulas... please save a copy prior to editting in case you make a mistake. All shaded areas are either linked or contain formulas | |||
| PRIME GENERAL CONTRACT OFFICE OVERHEAD (Fill in%) | 10% | 17.39 | ||||
| SUBTOTAL | 191.32 | |||||
| PRIME GENERAL CONTRACTOR'S PROFIT(Fill in%) | 10% | 19.13 | ||||
| SUBTOTAL | 210.45 | |||||
| BUILDER'S RISK / PERFORMANCE BONDS (Fill in%) | 2% | 4.21 | ||||
| CONTRACT TOTAL | $ 214.66 |
&L&"Verdana,Bold"Construction Cost Estimate &R&P of &N davisjam:
Percentages listed are place fillers. Please complete as required
Div1
| CONSTRUCTION COST ESTIMATE | DATE | ||||||
| Fill Here | |||||||
| PROJECT | BASIS FOR ESTIMATE | ||||||
| 663A4-23-201 - Replace 40 Ton Condenser Bldg 200 | CODE A (No design completed) | ||||||
| LOCATION | CODE B (Preliminary design) | ||||||
| VA Puget Sound Medical Center - AMLK Campus, Tacoma, WA | CODE C (Final design) | ||||||
| COMPANY | PROJECT NO. | OTHER (Specify) | |||||
| Fill Here | 663-21-100 | ||||||
| DRAWING NO. | ESTIMATOR | CHECKED BY | |||||
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| GENERAL REQUIREMENTS | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| Sample Input | 2 | - 0 | 10.00 | 20.00 | 20.00 | ||
| Sample Input | 3 | 1.00 | 10.00 | 30.00 | - 0 | 30.00 | |
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | 30.00 | 20.00 | |||||
| SUBTOTAL | 50.00 | ||||||
| Sub-Contractor's Overhead | 0.00% | - 0 | |||||
| Sub-Contractor's Profit | 0.00% | - 0 | |||||
| FL State Sales Tax | 0.00% | - 0 | |||||
| TOTAL | $ 50.00 |
&L&"Verdana,Bold"Construction Cost Estimate &R&P of &N
Div2
| CONSTRUCTION COST ESTIMATE | DATE | ||||||
| Fill Here | |||||||
| PROJECT | BASIS FOR ESTIMATE | ||||||
| 663A4-23-201 - Replace 40 Ton Condenser Bldg 200 | CODE A (No design completed) | ||||||
| LOCATION | CODE B (Preliminary design) | ||||||
| VA Puget Sound Medical Center - AMLK Campus, Tacoma, WA | CODE C (Final design) | ||||||
| COMPANY | PROJECT NO. | OTHER (Specify) | |||||
| Fill Here | 663-21-100 | ||||||
| DRAWING NO. | ESTIMATOR | CHECKED BY | |||||
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| EXISTING CONDITIONS | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| Sample Input | 2 | - 0 | 10.00 | 20.00 | 20.00 | ||
| Sample Input | 3 | 10.00 | 30.00 | - 0 | 30.00 | ||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | 30.00 | 20.00 | |||||
| SUBTOTAL | 50.00 | ||||||
| Sub-Contractor's Overhead | 5.00% | 2.50 | |||||
| Sub-Contractor's Profit | 11.00% | 5.78 | |||||
| FL State Sales Tax | 6.00% | 1.20 | |||||
| TOTAL | $ 59.48 |
&L&"Verdana,Bold"Construction Cost Estimate &R&P of &N
Div3
| CONSTRUCTION COST ESTIMATE | DATE | ||||||
| Fill Here | |||||||
| PROJECT | BASIS FOR ESTIMATE | ||||||
| 663A4-23-201 - Replace 40 Ton Condenser Bldg 200 | CODE A (No design completed) | ||||||
| LOCATION | CODE B (Preliminary design) | ||||||
| VA Puget Sound Medical Center - AMLK Campus, Tacoma, WA | CODE C (Final design) | ||||||
| COMPANY | PROJECT NO. | OTHER (Specify) | |||||
| Fill Here | 663-21-100 | ||||||
| DRAWING NO. | ESTIMATOR | CHECKED BY | |||||
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| CONCRETE WORK | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| Sample Input | 2 | - 0 | 10.00 | 20.00 | 20.00 | ||
| Sample Input | 3 | 10.00 | 30.00 | - 0 | 30.00 | ||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | 30.00 | 20.00 | |||||
| SUBTOTAL | 50.00 | ||||||
| Sub-Contractor's Overhead | 10.00% | 5.00 | |||||
| Sub-Contractor's Profit | 15.00% | 8.25 | |||||
| FL State Sales Tax | 6.00% | 1.20 | |||||
| TOTAL | $ 64.45 |
&L&"Verdana,Bold"Construction Cost Estimate &R&P of &N
Div5
| CONSTRUCTION COST ESTIMATE | DATE | ||||||
| Fill Here | |||||||
| PROJECT | BASIS FOR ESTIMATE | ||||||
| 663A4-23-201 - Replace 40 Ton Condenser Bldg 200 | CODE A (No design completed) | ||||||
| LOCATION | CODE B (Preliminary design) | ||||||
| VA Puget Sound Medical Center - AMLK Campus, Tacoma, WA | CODE C (Final design) | ||||||
| COMPANY | PROJECT NO. | OTHER (Specify) | |||||
| Fill Here | 663-21-100 | ||||||
| DRAWING NO. | ESTIMATOR | CHECKED BY | |||||
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| METALS | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| Sub-Contractor's Overhead | 10.00% | - 0 | |||||
| Sub-Contractor's Profit | 15.00% | - 0 | |||||
| FL State Sales Tax | 6.00% | - 0 | |||||
| TOTAL | $ - 0 |
Div6
| CONSTRUCTION COST ESTIMATE | DATE | ||||||
| Fill Here | |||||||
| PROJECT | BASIS FOR ESTIMATE | ||||||
| 663A4-23-201 - Replace 40 Ton Condenser Bldg 200 | CODE A (No design completed) | ||||||
| LOCATION | CODE B (Preliminary design) | ||||||
| VA Puget Sound Medical Center - AMLK Campus, Tacoma, WA | CODE C (Final design) | ||||||
| COMPANY | PROJECT NO. | OTHER (Specify) | |||||
| Fill Here | 663-21-100 | ||||||
| DRAWING NO. | ESTIMATOR | CHECKED BY | |||||
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| WOOD, PLASTICS AND COMPOSITES | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| Sub-Contractor's Overhead | 5.00% | - 0 | |||||
| Sub-Contractor's Profit | 11.00% | - 0 | |||||
| FL State Sales Tax | 6.00% | - 0 | |||||
| TOTAL | $ - 0 |
&L&"Verdana,Bold"Construction Cost Estimate &R&P of &N
Div7
| CONSTRUCTION COST ESTIMATE | DATE | ||||||
| Fill Here | |||||||
| PROJECT | BASIS FOR ESTIMATE | ||||||
| 663A4-23-201 - Replace 40 Ton Condenser Bldg 200 | CODE A (No design completed) | ||||||
| LOCATION | CODE B (Preliminary design) | ||||||
| VA Puget Sound Medical Center - AMLK Campus, Tacoma, WA | CODE C (Final design) | ||||||
| COMPANY | PROJECT NO. | OTHER (Specify) | |||||
| Fill Here | 663-21-100 | ||||||
| DRAWING NO. | ESTIMATOR | CHECKED BY | |||||
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| THERMAL AND MOISTURE PROTECTION | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| Sub-Contractor's Overhead | 5.00% | - 0 | |||||
| Sub-Contractor's Profit | 11.00% | - 0 | |||||
| FL State Sales Tax | 6.00% | - 0 | |||||
| TOTAL | $ - 0 |
&L&"Verdana,Bold"Construction Cost Estimate &R&P of &N
Div10
| CONSTRUCTION COST ESTIMATE | DATE | ||||||
| Fill Here | |||||||
| PROJECT | BASIS FOR ESTIMATE | ||||||
| 663A4-23-201 - Replace 40 Ton Condenser Bldg 200 | CODE A (No design completed) | ||||||
| LOCATION | CODE B (Preliminary design) | ||||||
| VA Puget Sound Medical Center - AMLK Campus, Tacoma, WA | CODE C (Final design) | ||||||
| COMPANY | PROJECT NO. | OTHER (Specify) | |||||
| Fill Here | 663-21-100 | ||||||
| DRAWING NO. | ESTIMATOR | CHECKED BY | |||||
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| SPECIALTIES | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | $ - 0 | ||||||
| Sub-Contractor's Overhead | 5.00% | - 0 | |||||
| Sub-Contractor's Profit | 11.00% | - 0 | |||||
| FL State Sales Tax | 6.00% | - 0 | |||||
| TOTAL | $ - 0 |
&L&"Verdana,Bold"Construction Cost Estimate &R&P of &N
Div13
| CONSTRUCTION COST ESTIMATE | DATE | ||||||
| Fill Here | |||||||
| PROJECT | BASIS FOR ESTIMATE | ||||||
| 663A4-23-201 - Replace 40 Ton Condenser Bldg 200 | CODE A (No design completed) | ||||||
| LOCATION | CODE B (Preliminary design) | ||||||
| VA Puget Sound Medical Center - AMLK Campus, Tacoma, WA | CODE C (Final design) | ||||||
| COMPANY | PROJECT NO. | OTHER (Specify) | |||||
| Fill Here | 663-21-100 | ||||||
| DRAWING NO. | ESTIMATOR | CHECKED BY | |||||
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| SPECIAL CONSTRUCTION | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | $ - 0 | ||||||
| Sub-Contractor's Overhead | 5.00% | - 0 | |||||
| Sub-Contractor's Profit | 11.00% | - 0 | |||||
| FL State Sales Tax | 6.00% | - 0 | |||||
| TOTAL | $ - 0 |
Div22
| CONSTRUCTION COST ESTIMATE | DATE | ||||||
| Fill Here | |||||||
| PROJECT | BASIS FOR ESTIMATE | ||||||
| 663A4-23-201 - Replace 40 Ton Condenser Bldg 200 | CODE A (No design completed) | ||||||
| LOCATION | CODE B (Preliminary design) | ||||||
| VA Puget Sound Medical Center - AMLK Campus, Tacoma, WA | CODE C (Final design) | ||||||
| COMPANY | PROJECT NO. | OTHER (Specify) | |||||
| Fill Here | 663-21-100 | ||||||
| DRAWING NO. | ESTIMATOR | CHECKED BY | |||||
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| PLUMBING | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | $ - 0 | ||||||
| Sub-Contractor's Overhead | 5.00% | - 0 | |||||
| Sub-Contractor's Profit | 11.00% | - 0 | |||||
| FL State Sales Tax | 6.00% | - 0 | |||||
| TOTAL | $ - 0 |
&L&"Verdana,Bold"Construction Cost Estimate &R&P of &N
Div23
| CONSTRUCTION COST ESTIMATE | DATE | ||||||
| Fill Here | |||||||
| PROJECT | BASIS FOR ESTIMATE | ||||||
| 663A4-23-201 - Replace 40 Ton Condenser Bldg 200 | CODE A (No design completed) | ||||||
| LOCATION | CODE B (Preliminary design) | ||||||
| VA Puget Sound Medical Center - AMLK Campus, Tacoma, WA | CODE C (Final design) | ||||||
| COMPANY | PROJECT NO. | OTHER (Specify) | |||||
| Fill Here | 663-21-100 | ||||||
| DRAWING NO. | ESTIMATOR | CHECKED BY | |||||
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| HEATING, VENTILATING AND A/C | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | $ - 0 | ||||||
| Sub-Contractor's Overhead | 5.00% | - 0 | |||||
| Sub-Contractor's Profit | 11.00% | - 0 | |||||
| FL State Sales Tax | 6.00% | - 0 | |||||
| TOTAL | $ - 0 |
&L&"Verdana,Bold"Construction Cost Estimate &R&P of &N
Div26
| CONSTRUCTION COST ESTIMATE | DATE | ||||||
| Fill Here | |||||||
| PROJECT | BASIS FOR ESTIMATE | ||||||
| 663A4-23-201 - Replace 40 Ton Condenser Bldg 200 | CODE A (No design completed) | ||||||
| LOCATION | CODE B (Preliminary design) | ||||||
| VA Puget Sound Medical Center - AMLK Campus, Tacoma, WA | CODE C (Final design) | ||||||
| COMPANY | PROJECT NO. | OTHER (Specify) | |||||
| Fill Here | 663-21-100 | ||||||
| DRAWING NO. | ESTIMATOR | CHECKED BY | |||||
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| ELECTRICAL | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| Sub-Contractor's Overhead | 5.00% | - 0 | |||||
| Sub-Contractor's Profit | 11.00% | - 0 | |||||
| FL State Sales Tax | 6.00% | - 0 | |||||
| TOTAL | $ - 0 |
&L&"Verdana,Bold"Construction Cost Estimate &R&P of &N
File details come from the government source that posted it. Updated .