Attachment 9 - 663A4-23-201 - Division Cost Breakout.xls
XLS spreadsheet 316 KB Posted
- Solicitation number
- 36C26026R0035
About this file
This is a Construction Cost Estimate template in CSI (Construction Specifications Institute) format for federal contracting purposes. The document is a spreadsheet-based tool designed to estimate costs for Project 663A4-23-201, which involves replacing a 40-ton condenser in Building 200 at VA Puget Sound Medical Center - AMLK Campus in Tacoma, Washington. The template is structured with individual division tabs corresponding to CSI divisions, including General Requirements (Division 01), Existing Conditions (Division 02), Concrete Work (Division 03), Metals (Division 05), Wood/Plastics/Composites (Division 06), Thermal and Moisture Protection (Division 07), Specialties (Division 10), Special Construction (Division 13), Plumbing (Division 22), HVAC (Division 23), and Electrical (Division 26).
The spreadsheet includes prefilled division sheets with sample inputs to illustrate functionality, though contractors are permitted to modify, delete, or add line items as necessary. Key features include automated calculation fields for labor and material costs, with subcontractor overhead and profit percentages applied at the division level (5-11 percent overhead, 11-15 percent profit depending on division). The summary page consolidates all division costs and applies prime contractor overhead (10 percent), profit (10 percent), sales tax (6 percent), and builder's risk/performance bonds (2 percent) to arrive at the contract total. The document explicitly notes that the spreadsheet contains formulas and recommends saving a copy before editing. All shaded areas are either linked to formulas or linked to other sections, requiring careful attention when making modifications. Contractors must complete designated "Fill Here" fields including company name, date, basis for estimate code, and drawing numbers.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Instructions
Use the information from the prefilled division sheets below to complete the 50 Divisions Cost Estimate CSI* Format tool to build your proposal. The information from the prefilled division sheets may not be all inclusive. The contractor is allowed to include any missing items from each division and is allowed to fill in other divisions that are not listed in the prefilled division sheets. If there is a disagreement with the prefilled division sheets, the contractor should not delete the element(s), but instead leave it blank and then include their suggested element(s) at the bottom of that division tab. Please note that on the summary page there is a place to fill in overhead and profit percentages for both the prime and the subcontractor that will self-populate the summary page and all the division tabs.
Exceptions:
(1) if each subcontractor has a different overhead and profit rates than the percentage placed on the summary page, an adjustment will have to be made to that specific division page. The spreadsheet will still calculate correctly.
(2) If the prime is self-performing the work for that division then the profit and overhead will need to be zeroed for that particular division, because the primes overhead and profit is already captured on the summary page.
| The ktr is required to complete the areas marked "Fill Here" in the summary tab. The rest of the information in the summary tab will automatically tabulate from the individual division tabs except for the few exceptions listed above. |
| Divisions 1, 2, and 3 show sample inputs to illustrate how the spreadsheet works. |
| * CSI = Construction Specifications Institute |
&L&"Verdana,Bold"Construction Cost Estimate &R&P of &N
Summary
| CONSTRUCTION COST ESTIMATE | Date: | |||||
| Fill Here | ||||||
| COMPANY | ||||||
| Fill Here | ||||||
| PROJECT | ||||||
| 663A4-23-201 - Replace 40 Ton Condenser Bldg 200 | ||||||
| LOCATION | PROJECT NO. | 663-21-100 | ||||
| VA Puget Sound Medical Center - AMLK Campus, Tacoma, WA | ||||||
| DIVISION | DESCRIPTION | % by | ||||
| Division | Division Total | |||||
| DIVISION 01 | GENERAL REQUIREMENTS | 28.7% | 50.00 | |||
| DIVISION 02 | EXISTING CONDITIONS | 34.2% | 59.48 | |||
| DIVISION 03 | CONCRETE WORK | 37.1% | 64.45 | FILL IN AS REQUIRED (this will link to the entire document) | ||
| DIVISION 05 | METALS | - 0 | ||||
| DIVISION 06 | WOOD, PLASTICS AND COMPOSITES | 0.0% | - 0 | |||
| DIVISION 07 | THERMAL AND MOISTURE PROTECTION | 0.0% | - 0 | GC Overhead | 10.00% | |
| DIVISION 10 | SPECIALTIES | 0.0% | - 0 | GC Profit | 10.00% | |
| DIVISION 13 | SPECIAL CONSTRUCTION | - 0 | Sub Overhead | 5.00% | ||
| DIVISION 22 | PLUMBING | 0.0% | - 0 | Sub Profit | 11.00% | |
| DIVISION 23 | HEATING, VENTILATING AND A/C | 0.0% | - 0 | Sales Tax | 6.00% | |
| DIVISION 26 | ELECTRICAL | 0.0% | - 0 | Risk/Bonding | 2.00% | |
| HARD COST TOTAL | 100% | 173.93 | This spreadsheet contains many formulas... please save a copy prior to editting in case you make a mistake. All shaded areas are either linked or contain formulas | |||
| PRIME GENERAL CONTRACT OFFICE OVERHEAD (Fill in%) | 10% | 17.39 | ||||
| SUBTOTAL | 191.32 | |||||
| PRIME GENERAL CONTRACTOR'S PROFIT(Fill in%) | 10% | 19.13 | ||||
| SUBTOTAL | 210.45 | |||||
| BUILDER'S RISK / PERFORMANCE BONDS (Fill in%) | 2% | 4.21 | ||||
| CONTRACT TOTAL | $ 214.66 |
&L&"Verdana,Bold"Construction Cost Estimate &R&P of &N davisjam:
Percentages listed are place fillers. Please complete as required
Div1
| CONSTRUCTION COST ESTIMATE | DATE | ||||||
| Fill Here | |||||||
| PROJECT | BASIS FOR ESTIMATE | ||||||
| 663A4-23-201 - Replace 40 Ton Condenser Bldg 200 | CODE A (No design completed) | ||||||
| LOCATION | CODE B (Preliminary design) | ||||||
| VA Puget Sound Medical Center - AMLK Campus, Tacoma, WA | CODE C (Final design) | ||||||
| COMPANY | PROJECT NO. | OTHER (Specify) | |||||
| Fill Here | 663-21-100 | ||||||
| DRAWING NO. | ESTIMATOR | CHECKED BY | |||||
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| GENERAL REQUIREMENTS | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| Sample Input | 2 | - 0 | 10.00 | 20.00 | 20.00 | ||
| Sample Input | 3 | 1.00 | 10.00 | 30.00 | - 0 | 30.00 | |
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | 30.00 | 20.00 | |||||
| SUBTOTAL | 50.00 | ||||||
| Sub-Contractor's Overhead | 0.00% | - 0 | |||||
| Sub-Contractor's Profit | 0.00% | - 0 | |||||
| FL State Sales Tax | 0.00% | - 0 | |||||
| TOTAL | $ 50.00 |
&L&"Verdana,Bold"Construction Cost Estimate &R&P of &N
Div2
| CONSTRUCTION COST ESTIMATE | DATE | ||||||
| Fill Here | |||||||
| PROJECT | BASIS FOR ESTIMATE | ||||||
| 663A4-23-201 - Replace 40 Ton Condenser Bldg 200 | CODE A (No design completed) | ||||||
| LOCATION | CODE B (Preliminary design) | ||||||
| VA Puget Sound Medical Center - AMLK Campus, Tacoma, WA | CODE C (Final design) | ||||||
| COMPANY | PROJECT NO. | OTHER (Specify) | |||||
| Fill Here | 663-21-100 | ||||||
| DRAWING NO. | ESTIMATOR | CHECKED BY | |||||
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| EXISTING CONDITIONS | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| Sample Input | 2 | - 0 | 10.00 | 20.00 | 20.00 | ||
| Sample Input | 3 | 10.00 | 30.00 | - 0 | 30.00 | ||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | 30.00 | 20.00 | |||||
| SUBTOTAL | 50.00 | ||||||
| Sub-Contractor's Overhead | 5.00% | 2.50 | |||||
| Sub-Contractor's Profit | 11.00% | 5.78 | |||||
| FL State Sales Tax | 6.00% | 1.20 | |||||
| TOTAL | $ 59.48 |
&L&"Verdana,Bold"Construction Cost Estimate &R&P of &N
Div3
| CONSTRUCTION COST ESTIMATE | DATE | ||||||
| Fill Here | |||||||
| PROJECT | BASIS FOR ESTIMATE | ||||||
| 663A4-23-201 - Replace 40 Ton Condenser Bldg 200 | CODE A (No design completed) | ||||||
| LOCATION | CODE B (Preliminary design) | ||||||
| VA Puget Sound Medical Center - AMLK Campus, Tacoma, WA | CODE C (Final design) | ||||||
| COMPANY | PROJECT NO. | OTHER (Specify) | |||||
| Fill Here | 663-21-100 | ||||||
| DRAWING NO. | ESTIMATOR | CHECKED BY | |||||
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| CONCRETE WORK | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| Sample Input | 2 | - 0 | 10.00 | 20.00 | 20.00 | ||
| Sample Input | 3 | 10.00 | 30.00 | - 0 | 30.00 | ||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | 30.00 | 20.00 | |||||
| SUBTOTAL | 50.00 | ||||||
| Sub-Contractor's Overhead | 10.00% | 5.00 | |||||
| Sub-Contractor's Profit | 15.00% | 8.25 | |||||
| FL State Sales Tax | 6.00% | 1.20 | |||||
| TOTAL | $ 64.45 |
&L&"Verdana,Bold"Construction Cost Estimate &R&P of &N
Div5
| CONSTRUCTION COST ESTIMATE | DATE | ||||||
| Fill Here | |||||||
| PROJECT | BASIS FOR ESTIMATE | ||||||
| 663A4-23-201 - Replace 40 Ton Condenser Bldg 200 | CODE A (No design completed) | ||||||
| LOCATION | CODE B (Preliminary design) | ||||||
| VA Puget Sound Medical Center - AMLK Campus, Tacoma, WA | CODE C (Final design) | ||||||
| COMPANY | PROJECT NO. | OTHER (Specify) | |||||
| Fill Here | 663-21-100 | ||||||
| DRAWING NO. | ESTIMATOR | CHECKED BY | |||||
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| METALS | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| Sub-Contractor's Overhead | 10.00% | - 0 | |||||
| Sub-Contractor's Profit | 15.00% | - 0 | |||||
| FL State Sales Tax | 6.00% | - 0 | |||||
| TOTAL | $ - 0 |
Div6
| CONSTRUCTION COST ESTIMATE | DATE | ||||||
| Fill Here | |||||||
| PROJECT | BASIS FOR ESTIMATE | ||||||
| 663A4-23-201 - Replace 40 Ton Condenser Bldg 200 | CODE A (No design completed) | ||||||
| LOCATION | CODE B (Preliminary design) | ||||||
| VA Puget Sound Medical Center - AMLK Campus, Tacoma, WA | CODE C (Final design) | ||||||
| COMPANY | PROJECT NO. | OTHER (Specify) | |||||
| Fill Here | 663-21-100 | ||||||
| DRAWING NO. | ESTIMATOR | CHECKED BY | |||||
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| WOOD, PLASTICS AND COMPOSITES | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| Sub-Contractor's Overhead | 5.00% | - 0 | |||||
| Sub-Contractor's Profit | 11.00% | - 0 | |||||
| FL State Sales Tax | 6.00% | - 0 | |||||
| TOTAL | $ - 0 |
&L&"Verdana,Bold"Construction Cost Estimate &R&P of &N
Div7
| CONSTRUCTION COST ESTIMATE | DATE | ||||||
| Fill Here | |||||||
| PROJECT | BASIS FOR ESTIMATE | ||||||
| 663A4-23-201 - Replace 40 Ton Condenser Bldg 200 | CODE A (No design completed) | ||||||
| LOCATION | CODE B (Preliminary design) | ||||||
| VA Puget Sound Medical Center - AMLK Campus, Tacoma, WA | CODE C (Final design) | ||||||
| COMPANY | PROJECT NO. | OTHER (Specify) | |||||
| Fill Here | 663-21-100 | ||||||
| DRAWING NO. | ESTIMATOR | CHECKED BY | |||||
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| THERMAL AND MOISTURE PROTECTION | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| Sub-Contractor's Overhead | 5.00% | - 0 | |||||
| Sub-Contractor's Profit | 11.00% | - 0 | |||||
| FL State Sales Tax | 6.00% | - 0 | |||||
| TOTAL | $ - 0 |
&L&"Verdana,Bold"Construction Cost Estimate &R&P of &N
Div10
| CONSTRUCTION COST ESTIMATE | DATE | ||||||
| Fill Here | |||||||
| PROJECT | BASIS FOR ESTIMATE | ||||||
| 663A4-23-201 - Replace 40 Ton Condenser Bldg 200 | CODE A (No design completed) | ||||||
| LOCATION | CODE B (Preliminary design) | ||||||
| VA Puget Sound Medical Center - AMLK Campus, Tacoma, WA | CODE C (Final design) | ||||||
| COMPANY | PROJECT NO. | OTHER (Specify) | |||||
| Fill Here | 663-21-100 | ||||||
| DRAWING NO. | ESTIMATOR | CHECKED BY | |||||
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| SPECIALTIES | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | $ - 0 | ||||||
| Sub-Contractor's Overhead | 5.00% | - 0 | |||||
| Sub-Contractor's Profit | 11.00% | - 0 | |||||
| FL State Sales Tax | 6.00% | - 0 | |||||
| TOTAL | $ - 0 |
&L&"Verdana,Bold"Construction Cost Estimate &R&P of &N
Div13
| CONSTRUCTION COST ESTIMATE | DATE | ||||||
| Fill Here | |||||||
| PROJECT | BASIS FOR ESTIMATE | ||||||
| 663A4-23-201 - Replace 40 Ton Condenser Bldg 200 | CODE A (No design completed) | ||||||
| LOCATION | CODE B (Preliminary design) | ||||||
| VA Puget Sound Medical Center - AMLK Campus, Tacoma, WA | CODE C (Final design) | ||||||
| COMPANY | PROJECT NO. | OTHER (Specify) | |||||
| Fill Here | 663-21-100 | ||||||
| DRAWING NO. | ESTIMATOR | CHECKED BY | |||||
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| SPECIAL CONSTRUCTION | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | $ - 0 | ||||||
| Sub-Contractor's Overhead | 5.00% | - 0 | |||||
| Sub-Contractor's Profit | 11.00% | - 0 | |||||
| FL State Sales Tax | 6.00% | - 0 | |||||
| TOTAL | $ - 0 |
Div22
| CONSTRUCTION COST ESTIMATE | DATE | ||||||
| Fill Here | |||||||
| PROJECT | BASIS FOR ESTIMATE | ||||||
| 663A4-23-201 - Replace 40 Ton Condenser Bldg 200 | CODE A (No design completed) | ||||||
| LOCATION | CODE B (Preliminary design) | ||||||
| VA Puget Sound Medical Center - AMLK Campus, Tacoma, WA | CODE C (Final design) | ||||||
| COMPANY | PROJECT NO. | OTHER (Specify) | |||||
| Fill Here | 663-21-100 | ||||||
| DRAWING NO. | ESTIMATOR | CHECKED BY | |||||
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| PLUMBING | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | $ - 0 | ||||||
| Sub-Contractor's Overhead | 5.00% | - 0 | |||||
| Sub-Contractor's Profit | 11.00% | - 0 | |||||
| FL State Sales Tax | 6.00% | - 0 | |||||
| TOTAL | $ - 0 |
&L&"Verdana,Bold"Construction Cost Estimate &R&P of &N
Div23
| CONSTRUCTION COST ESTIMATE | DATE | ||||||
| Fill Here | |||||||
| PROJECT | BASIS FOR ESTIMATE | ||||||
| 663A4-23-201 - Replace 40 Ton Condenser Bldg 200 | CODE A (No design completed) | ||||||
| LOCATION | CODE B (Preliminary design) | ||||||
| VA Puget Sound Medical Center - AMLK Campus, Tacoma, WA | CODE C (Final design) | ||||||
| COMPANY | PROJECT NO. | OTHER (Specify) | |||||
| Fill Here | 663-21-100 | ||||||
| DRAWING NO. | ESTIMATOR | CHECKED BY | |||||
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| HEATING, VENTILATING AND A/C | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | $ - 0 | ||||||
| Sub-Contractor's Overhead | 5.00% | - 0 | |||||
| Sub-Contractor's Profit | 11.00% | - 0 | |||||
| FL State Sales Tax | 6.00% | - 0 | |||||
| TOTAL | $ - 0 |
&L&"Verdana,Bold"Construction Cost Estimate &R&P of &N
Div26
| CONSTRUCTION COST ESTIMATE | DATE | ||||||
| Fill Here | |||||||
| PROJECT | BASIS FOR ESTIMATE | ||||||
| 663A4-23-201 - Replace 40 Ton Condenser Bldg 200 | CODE A (No design completed) | ||||||
| LOCATION | CODE B (Preliminary design) | ||||||
| VA Puget Sound Medical Center - AMLK Campus, Tacoma, WA | CODE C (Final design) | ||||||
| COMPANY | PROJECT NO. | OTHER (Specify) | |||||
| Fill Here | 663-21-100 | ||||||
| DRAWING NO. | ESTIMATOR | CHECKED BY | |||||
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| ELECTRICAL | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| Sub-Contractor's Overhead | 5.00% | - 0 | |||||
| Sub-Contractor's Profit | 11.00% | - 0 | |||||
| FL State Sales Tax | 6.00% | - 0 | |||||
| TOTAL | $ - 0 |