This is Amendment 0007 to Solicitation 36C26026R0035 for the replacement of a 40-ton condenser in Building 200 at the VA Puget Sound Medical Center, American Lake Campus in Tacoma, Washington. The amendment extends the receipt deadline for offers to Monday, April 27, 2026 at 10:00 AM PDT and provides government clarification regarding temporary cooling requirements during construction.
The amendment addresses a contractor question about the sizing requirements for temporary cooler and freezer units needed during the condenser replacement work. The government clarified that while the minimum reference size should be based on the 60-square-foot exterior cooler being demolished, contractors must phase their work to minimize disruptions to the medical center's operations. If a contractor cannot phase the work to keep cooling and freezing functions operational using a smaller temporary unit, they must provide a temporary unit large enough to accommodate the loss of all interior cooling and refrigeration units (refrigerators #2, 3, 4, 5, 6, and 8, plus freezers #1 and #7) during construction. The work is being administered by the Network Contracting Office at the Department of Veterans Affairs Veterans Integrated Service Network 20, located in Vancouver, Washington.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO:
Specify authority)
THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 04-23-2026 663A4-23-201 36C260 NCO 20 Network Contracting Office
ATTN: V4CONT
1601 E. Fourth Plain Blvd Bldg.17, Suite B428 Vancouver WA 98661
To all Offerors/Bidders
36C26026R0035 02-24-2026
X X X ** HOUR & DATE for Receipt of Offers is EXTENDED to: 04-27-2026 10:00 am PDT Construction NRM Project 663A4-23-201 - Replace 40 Ton Condenser Bldg 200 Located at the VA Puget Sound Medical Center, American Lake Campus, Tacoma, WA
The purpose of this amendment is to provide a response to an additional clarification regarding the Temporary Cooler requirement as well extend the response due date to Monday, April 27, at 10:00 am PST.
Solicitation 36C26026R0035 – Replace 40 Ton Condenser, Bldg 200 – AMD 0007
Q. Contractor Question Amendment 0006 is calling for “Temporary Cooler should have the same volume, or greater, than the exterior cooler which is to be demolished.” The issue is that the outside freezer is only 60 sq ft and the understanding is that the freezer is not operational.
Shouldn’t the temporary freezer be big enough to accommodate the loss of Freezer #1 and #7 during construction? Shouldn’t we be providing a temporary cooler as well that is big enough to accommodate the loss of Refrigerator #2, 3, 4, 5, 6 and 8?
A. Government Response Reference item 16 of the solicitation SOW that reads:
“All work shall be phased to limit disruptions to the station. Specifically, if a freezer or refrigerating unit is to be disabled, it should first be ensured that temporary means to replace the respective function(s) are established.”
The idea is that a contractor should optimally phase outages/closures, so that any outage/closure can be accommodated by the temporary unit. The contractor should consider their capability to phase while creating a cost estimate and determining what size temporary unit is necessary. Consider the exterior unit to be demolished, to be a minimum reference size for this work. If the Contractor can not phase the work a temporary unit large enough to cover the entire interior cooling/freezing section would be necessary.
File details come from the government source that posted it. Updated .