Attachment 8_Specifications.pdf
PDF 6 MB Posted
- Solicitation number
- 36C78623B0011
About this file
This presolicitation notice announces the Department of Veterans Affairs' intent to issue a small business set-aside invitation for bid for construction services. The solicitation will be posted on August 25, 2022 for the construction of a new rural initiative cemetery in Cedar City, Utah. The contractor shall complete all work including site preparation, demolition, labor, materials, and services in accordance with provided drawings and specifications within four hundred and eighty calendar days from notice to proceed for a fixed price between $5-10 million. Firms must be registered in SAM and have completed online representations and certifications to receive consideration for this Davis-Bacon Act acquisition. The NAICS code is 237990 and size standard is $39.5 million. Offers from other than small businesses shall not be considered. Amendments will be posted to SAM and acknowledgement is required. The point of contact is Shane Hilts.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF VETERANS AFFAIRS
NATIONAL CEMETERY ADMINISTRATION OFFICE
OF DESIGN AND CONSTRUCTION
WASHINGTON, D.C.
BID DOCUMENTS
VOLUME -1
NATIONAL CEMETERY DEVELOPMENT
CEDAR CITY RURAL INITIATIVE
CEDAR CITY, UT
IFB NUMBER VA-XXXXXXXX
PROJECT NO. 942CM3001
BID DOCUMENT SUBMITTAL
22 July 22
THIS SHEET INTENTIONALLY LEFT BLANK
ARCHITECT: Sean Fitzpatrick
SECURITY: Sina Saboktakin gTRUc
Z mna
6754098-2203
DON WADE
tN
2 /z?
SIGNATURE PAGE
Architect & Security:
VALI COOPER INTERNATIONAL
Sections covered by these seals include:
Divisions: 00, 01, 03 (except 03 30 53 & 03 4821), 04 (except 04 20 00), 05, 07,09, 10,28,3231 13 &32 31 19.
Electrical Engineer:
VALI COOPER INTERNATIONAL
Sections covered by these seals include Divisions: 28
Civil & Structural Engineer:
WOOD
Sections covered by these seals include.
Divisions: 02,03 30 53, 03 48 21,04 20 00, 31,32 05 23, 32 12 16 & 33.
CIVIL: Don Dotson
56436
7/29/2022
C O
L
O
R
A
D
O
L
I
C
E
N
S
E
D
A
R
C
H
I T
E
C
T
S E A
N
M
F
IT
Z
P
A
T
R
I C K
7/22/22
Electrical Engineer:
WOOD
Sections covered by these seals include:
Divisions: 26
ELECTRICAL:
STRUCTURAL:
Landscape Architect/Irrigation Planner:
MRWM
Sections covered by this seal include:
32 33 00, 32 84 00 & 32 90 00
LANDSCAPE: Brian Verardo
DEPARTMENT OF VETERANS AFFAIRS
NATIONAL CEMETERY ADMINISTRATION OFFICE
OF DESIGN AND CONSTRUCTION
WASHINGTON, D.C.
BID DOCUMENTS
VOLUME -2
NATIONAL CEMETERY DEVELOPMENT
CEDAR CITY RURAL INITIATIVE
CEDAR CITY, UT
IFB NUMBER VA-XXXXXXXX
PROJECT NO. 942CM3001
BID DOCUMENT SUBMITTAL
22 JULY 22
BID DOCUMENT Submittal Project No. 942CM3001 National Cemetery Development 22 July 2022 Cedar City Rural Initiative
TABLE OF CONTENTS
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
NCA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
DIVISION 00 - SPECIAL SECTIONS
00 01 15 List of Drawing Sheets
DIVISION 01 - GENERAL REQUIREMENTS
01 00 02 General Requirements (Minor NCA Projects) 01 32 17 Network Analysis Schedules (Microsoft Project Gantt Chart) 01 33 23 Shop Drawings, Product Data, and Samples 01 42 19 Reference Standards 01 45 00 Quality Control 01 45 29 Testing Laboratory Services 01 45 35 Special Inspections 01 57 19 Temporary Environmental Controls 01 74 19 Construction Waste Management
DIVISION 02 – EXISTING CONDITIONS
02 41 10 Demolition and Site Clearing
DIVISION 03 – CONCRETE
03 30 53 (Short-Form) Cast-in-Place Concrete 03 45 00 Precast Architectural Concrete 03 48 21 Precast Concrete Burial Crypts (Double Depth Lawn Crypt) 03 48 24 Precast Concrete Columbarium Units 03 48 26 Concrete Memorial Wall Units
DIVISION 04 – MASONRY
04 05 13 Masonry Mortaring 04 05 16 Masonry Grouting 04 20 00 Unit Masonry 04 43 00 Natural Stone Veneer 04 72 10 Stone Masonry (ALL CAPS AND NUMBER PLAQUES) 04 73 00 Columbarium Niche Covers 04 73 10 Memorial Wall Markers
DIVISION 05 – METALS
05 50 00 Metal Fabrications
DIVISION 06 – WOOD, PLASTICS AND COMPOSITES
Cedar City Rural Initiative
TABLE OF CONTENTS
00 01 10-2
DIVISION 07 – THERMAL AND MOISTURE
07 92 00 Joint Sealants
DIVISION 08 - OPENINGS
08 35 13 Folding Glass Doors
DIVISION 09 – FINISHES
09 06 00 Schedule for Finishes
DIVISION 10 – SPECIALTIES
10 14 00 Exterior Signage 10 73 46 Pre-Fabricated Site Shelters 10 73 47 Pre-Fabricated Concrete Site Buildings 10 75 00 Flagpoles
DIVISION 11 - EQUIPMENT
DIVISION 12 – FURNISHINGS
DIVISION 13 - SPECIAL CONSTRUCTION
DIVISION 22 – PLUMBING
DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
DIVISION 25 – INTEGRATED AUTOMATION
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 26 05 19 Low-Voltage Electrical Power Conductors and Cables 26 05 26 Grounding and Bonding for Electrical Systems 26 05 33 Raceway and Boxes for Electrical Systems 26 05 41 Underground Electrical Construction 26 05 73 Overcurrent Protective Device Coordination Study 26 24 16 Panelboards 26 27 26 Wiring Devices 26 29 21 Enclosed Switches and Circuit Breakers 26 41 00 Facility Lightning Protection 26 51 00 Interior Lighting 26 56 00 Exterior Lighting
DIVISION 27 – COMMUNICATIONS
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 05 00 Common Work Results for Electronic Safety and Security 28 05 13 Conductors and Cables for Electronic Safety and Security
Cedar City Rural Initiative
TABLE OF CONTENTS
00 01 10-3
28 05 26 Grounding and Bonding for Electrical Safety and Security 28 05 18.33 Conduits and Backboxes 28 23 00 Video Surveillance
DIVISION 31 – EARTHWORK
31 05 19 Geotextile 31 11 00 Clearing and Grubbing 31 20 00 Earth Moving and Geo Tech Appendix
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 05 23 Cement and Concrete for Exterior Improvements 32 12 16 Asphalt Paving 32 31 13 Chain Link Fences and Gates 32 31 19 Decorative Metal Fences and Gates 32 33 00 Site Furnishings 32 84 00 Planting Irrigation 32 90 00 Planting
DIVISION 33 – UTILITIES
33 10 00 Water Utilities 33 30 00 Sanitary Sewer Utilities 33 40 00 Storm Sewer Utilities 33 46 13 Foundation Drainage
Cedar City Rural Initiative
TABLE OF CONTENTS
00 01 10-4
Cedar City Rural Initiative
LIST OF DRAWING SHEETS
00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
G-001 COVER SHEET
G-101 FENCING AND CONSTRUCTION STAGING PLAN
V-101 TOPOGRAPHIC / UTILITY SURVEY
V-102 TOPOGRAPHIC / UTILITY SURVEY W/O TREES
D-101 DEMOLITION PLAN
C-101 SITE PLAN
C-102 GRADING & UTILITY PLAN
C-103 INITIAL EROSION & SEDIMENTATION CONTROL PLAN
C-104 INTERMEDIATE EROSION & SEDIMENTATION CONTROL PLAN
C-201 ROADWAY PLAN AND PROFILE
C-202 STORM DRAIN PROFILES
C-203 SANITARY SEWER PLAN AND PROFILE
C-401 ENLARGED SITE PLAN
C-402 ENLARGED GRADING PLAN
C-403 GRAVESITE NUMBERING PLAN – SECTIONS 1, 2, 3 AND 4
C-404 GRAVESITE NUMBERING PLAN – SECTIONS 5 AND 6
C-501 GRAVESITE DETAILS 1 OF 2
C-502 GRAVESITE DETAILS 2 OF 2
C-503 SITE DETAILS 1 OF 2
C-504 SITE DETAILS 2 OF 2
C-505 EROSION CONTROL DETAILS
C-506 UTILITY DETAILS 1 OF 2
C-507 UTILITY DETAILS 2 OF 2
C-511 UNDERGROUND DETENTION FACILITY 1 OF 2
C-512 UNDERGROUND DETENTION FACILITY 2 OF 2
LI101 IRRIGATION PLAN
LI501 IRRIGATION DETAILS 1
LI502 IRRIGATION DETAILS 2
LI502 IRRIGATION DETAILS 3
LP101 PLANTING PLAN
A-101 COMMITTAL SHELTER & PUMP HOUSE FLOOR & ROOF PLANS AND PLAZA LAYOUT
A-201 COMMITTAL SHELTER AND PUMP HOUSE EXTERIOR ELEVATIONS
A-202 COLUMBARIUM & MEMORIAL WALL ELEVATIONS
A-301 COMMITTAL SHELTER & PUMP HOUSE BUILDING & WALL SECTIONS
A-401 COLUMBARIUM & MEMORIAL WALL ENLARGED PLANS, CAPS & DETAILS
A-501 COLUMBARIUM AND MEMORIAL WALL SECTIONS
Cedar City Rural Initiative
LIST OF DRAWING SHEETS
00 01 15 - 2
A-502 MEMORIAL WALL DETAILS 1
A-503 MEMORIAL WALL DETAILS 2
A-504 COLUMBARIUM DETAILS 1
A-505 COLUMBARIUM DETAILS 2
A-506 COMMITTAL SHELTER & PUMP HOUSE DETAILS
A-507 SITE AMENITY DETAILS
A-508 SIGNAGE ELEVATION DETAILS
A-509 SIGNAGE PANEL DETAILS & CONSTRUCTION SIGNAGE
A-510 SIGNAGE STRUCTURAL DETAILS
A-511 FENCING DETAILS 1
A-512 FENCING DETAILS 2
A-513 MISC. SITE DETAILS
E-001 ELECTRICAL NOTES & LEGENDS
E-101 ELECTRICAL SITE PLAN
E-102 ELECTRICAL PLANS – RESTROOM AND PUMP HOUSE
E-601 ELECTRICAL SCHEDULES
S-001 STRUCTURAL GENERAL NOTES
S-101 COMMITTAL SHELTER FOUNDATION PLAN
S-102 COLUMBARIUM, MEMORIAL WALL, AND ORNAMENTAL FENCE FDN. PLANS
S-201 ORNAMENTAL FENCE ELEVATION
S-501 COMMITTAL SHELTER FOUNDATION DETAILS
S-502 COLUMBARIUM AND WALLS STRUCTURAL DETAILS
S-503 ORNAMENTAL FENCE STRUCTURAL DTLS
S-504 TYPICAL MASONRY DETAILS
T-101 TELECOMMUNICATIONS PLANS AND DETAILS
- - - END - - -
Cedar City Rural Initiative
GENERAL REQUIREMENTS
i
SECTION 01 00 02
GENERAL REQUIREMENTS (MINOR NCA PROJECTS)
TABLE OF CONTENTS
1.1 GENERAL INTENTION
1.2 STATEMENT OF BID ITEM(S)
1.3 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
1.4 CONSTRUCTION SECURITY REQUIREMENTS
1.5 FIRE SAFETY
1.6 OPERATIONS AND STORAGE AREAS
1.7 ALTERATIONS (NOT USED)
1.8 ENVIRONMENTAL CONTROLS
1.9 DISPOSAL AND RETENTION
1.10 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,
UTILITIES, AND IMPROVEMENTS
1.11 RESTORATION
1.12 PHYSICAL DATA
1.13 PROFESSIONAL SURVEYING SERVICES
1.14 LAYOUT OF WORK
1.15 AS-BUILT DRAWINGS
1.16 USE OF ROADWAYS
1.17 RE/COTR'S FIELD OFFICE (NOT USED)
1.18 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
1.19 TEMPORARY TOILETS
1.20 AVAILABILITY AND USE OF UTILITY SERVICES
1.21 NEW TELEPHONE EQUIPMENT (NOT USED)
1.22 TESTS
1.23 INSTRUCTIONS
1.24 GOVERNMENT-FURNISHED PROPERTY
1.25 RELOCATED ITEMS (NOT USED)
1.26 CONSTRUCTION SIGN
1.27 SAFETY SIGN
1.28 CONSTRUCTION DIGITAL IMAGES
1.29 FINAL ELEVATION PHOTOGRAPHS
1.30 HISTORIC PRESERVATION
1.31 PROJECT HEALTH AND SAFETY PLAN
Cedar City Rural Initiative
GENERAL REQUIREMENTS
ii
This page intentionally blank
CD2 Submittal Project No. 942CM3001 National Cemetery Development 20 June 2022 Cedar City Rural Initiative
GENERAL REQUIREMENTS
01 00 02 - 1
SECTION 01 00 02
GENERAL REQUIREMENTS (MINOR NCA PROJECTS)
1.1 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor, materials, equipment and services and perform and complete all work for Cedar City National Cemetery Rural Initiative Cemetery
Development as required by drawings and specifications. The Period of
Performance for this contract shall be 18 months.
B. Visits to the site by Bidders may be made only by appointment with the
Cemetery Director.
C. All Testing Laboratory services will be retained and paid for by the
Contractor (see Section 01 45 29, Testing Laboratory Services).
However, the Department of Veterans Affairs may elect to retain its own
Testing Laboratory for any purpose. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three work days unless otherwise designated by the COR.
D.All employees of general contractor and subcontractors shall comply with security requirements as established by the COR, be identified by name and employer. They shall be restricted from unauthorized access.
E. Prior to commencing work, general contractor shall provide proof that a
30-hour OSHA certified “competent person” (CP) (29 CFR 1926.20(b)(2) will maintain a presence at the work site whenever the general or subcontractors are present.
F. Training:
1. All employees of general contractor or subcontractors shall, at the minimum, have successfully completed the 10-hour OSHA certified
Construction Safety course and/or other relevant competency training, as determined by VA CP.
2. Submit OSHA training records of all employees for approval before the start of work.
1.2 STATEMENT OF BID ITEM(S)
A. CLIN 0001, GENERAL CONSTRUCTION: Installation of all work shown on the plans and described in the specifications.
Cedar City Rural Initiative
GENERAL REQUIREMENTS
01 00 02 - 2
B. CLIN 0002, Provide the cost for the removal and disposal of 700CY of bed rock. Rock removed over or under the 700CY will be added or removed by Contract Modification based on the unit price cost of the
700CY pricing provided.
C. CLIN 0003, Manufacture and delivery of crypts. Installation of crypts to be included in CLIN 0001.
1.3 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. AFTER AWARD OF CONTRACT, one electronic set of specifications and drawings will be furnished to the contractor.
1.4 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the site without following the procedures approved by the COR. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. For working outside the “regular hours” as defined in the contract, The General Contractor shall give 3 days’ notice to the COR. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the COR.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the COR.
C. Guards:
1. No guards are required onsite unless requested by the COR.
D. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the COR for the purpose of security inspections of
Cedar City Rural Initiative
GENERAL REQUIREMENTS
01 00 02 - 3 every area of project including toolboxes and parked machines, and to take any necessary emergency action.
E. Document Control:
1. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
2. All electronic information shall be stored in a specified location following VA standards and procedures using an Engineering Document
Management Software (EDMS).
a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the
EDMS system.
1.5 FIRE SAFETY
A. Applicable Publications: Publications listed below form part of this
Article to the extent referenced. Publications are referenced in text by basic designations only.
1. American Society for Testing and Materials (ASTM):
E84-2009a ...........Surface Burning Characteristics of Building
Materials
2. National Fire Protection Association (NFPA):
10-2010 .............Standard for Portable Fire Extinguishers
30-2008 .............Flammable and Combustible Liquids Code
51B-2009 ............Standard for Fire Prevention During Welding, Cutting and Other Hot Work
70-2008 .............National Electrical Code
241-2009 ............Standard for Safeguarding Construction, Alteration, and Demolition Operations
3. Occupational Safety and Health Administration (OSHA):
29 CFR 1926 .........Safety and Health Regulations for Construction
B. Fire Safety Plan: Establish and maintain a fire protection program in accordance with 29 CFR 1926. Prior to start of work, prepare a plan detailing project-specific fire safety measures, including periodic status reports, and submit to COR/Cemetery Director for review for compliance with contract requirements in accordance with Section 01 33
23, SHOP DRAWINGS, PRODUCT DATA AND SAMPLES. Prior to any worker for the contractor or subcontractor’s beginning work, they shall undergo a
Cedar City Rural Initiative
GENERAL REQUIREMENTS
01 00 02 - 4 safety briefing provided by the General Contractor’s competent person per OSHA requirements. This briefing shall include information on the construction limits, safety guidelines, means of egress, break areas, work hours, locations of restrooms, use of NCA equipment, etc.
Documentation shall be provided to the COR that individuals have undergone the Contractor’s safety briefing.
C. Site and Building Access: Maintain free and unobstructed access to emergency services and for fire, police and other emergency response forces in accordance with NFPA 241.
D. Separate temporary facilities, such as trailers, storage sheds, and dumpsters, from existing buildings and new construction by distances in accordance with NFPA 241. For small facilities with less than 6 m (20 feet) exposing overall length, separate by 3m (10 feet).
E. Temporary Heating and Electrical: Install, use and maintain installations in accordance with 29 CFR 1926, NFPA 241 and NFPA 70.
F. Flammable and Combustible Liquids: Store, dispense and use liquids in accordance with 29 CFR 1926, NFPA 241 and NFPA 30.
G. Hot Work: Perform and safeguard hot work operations in accordance with
NFPA 241 and NFPA 51B. Coordinate with COR.
H. Fire Hazard Prevention and Safety Inspections: Inspect entire construction areas weekly. Coordinate with, and report findings and corrective actions weekly to COR.
I. Smoking: Smoking is prohibited in and adjacent to construction areas inside existing buildings and additions under construction. In separate and detached buildings under construction, smoking is prohibited except in designated smoking rest areas.
J. Dispose of waste and debris in accordance with NFPA 241. Remove from site weekly.
K. Perform other construction, alteration and demolition operations in accordance with 29 CFR 1926.
1.6 OPERATIONS AND STORAGE AREAS
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the COR. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
Cedar City Rural Initiative
GENERAL REQUIREMENTS
01 00 02 - 5
B. Temporary buildings (e.g., storage trailers, office trailers) and utilities may be erected by the Contractor only with the approval of the COR and shall be built with labor and materials furnished by the
Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work.
C. The Contractor shall, under regulations prescribed by the COR, use only established roadways, or use temporary roadways constructed by the
Contractor when and as authorized by the COR. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the
Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D. Working space and space available for storing materials shall be as shown on the drawings. Contractor parking will be only in areas and on roadways designated and agreed to by the COR in agreement of the
Cemetery.
E. Workmen are subject to rules of the Cemetery applicable to their conduct.
F. Execute work so as to interfere as little as possible with normal functioning of Cemetery as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others.
1. Do not store materials and equipment in other than assigned areas.
G. Phasing: To ensure such executions, the Contractor shall furnish the
COR with a schedule of approximate dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, the Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof.
H. Construction Privacy Fence: Before construction operations begin, the
Contractor shall provide a chain link construction fence, six feet minimum height, around the construction area indicated on the drawings.
Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension
Cedar City Rural Initiative
GENERAL REQUIREMENTS
01 00 02 - 6 bands and to line posts and top and bottom rails with tie wires spaced at maximum 375 mm (15 inches). Bottom of fences shall extend to 25 mm
(one inch) above grade. Install PVC privacy slats for entire length of fence. The temporary fencing shall encompass the construction work area(s) to serve as a pedestrian barrier to alert cemetery patrons of the construction site. Remove the fence when directed by COR.
I. Utilities Services:
1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, electricity, site access, etc., payment of such fee shall be the responsibility of the Government, the Contractor will pay the fee and the government will reimburse
(with no markups) the contractor for the cost of the connection fees.
J. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.
1.7 ALTERATIONS (NOT USED)
1.8 ENVIRONMENTAL CONTROLS
A. In general, following preventive measures shall be adopted during construction to keep down dust.
1. Dampen debris to keep down dust.
B. Final Cleanup:
1. Upon completion of the project, or as work progresses, remove all construction debris.
1.9 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of the site, or parts thereof, shall be disposed of as follows:
1. Reserved items: There are no reserved items for the government.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from the Cemetery.
1.10 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS
A. The Contractor shall preserve and protect all vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging
Cedar City Rural Initiative
GENERAL REQUIREMENTS
01 00 02 - 7 vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workmen, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the COR.
B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the
Contractor fails or refuses to repair the damage promptly, the COR may have the necessary work performed and charge the cost to the
Contractor.
(FAR 52.236-9)
C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Article 1.11 "Restoration", and Article 1.6
"Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.
D. Refer to FAR clause 52.236-7, "Permits and Responsibilities," which is included in General Conditions. A National Pollutant Discharge
Elimination System (NPDES)permit is required for this project. The
Contractor is considered an "operator" under the permit and has extensive responsibility for compliance with permit requirements. VA will make the permit application available at the (appropriate NCA
Central/Cemetery) office. The contractor and affected subcontractors shall furnish all information and certifications that are required to comply with the permit process and permit requirements. Many of the permit requirements will be satisfied by completing construction as shown and specified. Some requirements involve the Contractor's method of operations and operations planning and the Contractor is responsible for employing best management practices. The affected activities often include, but are not limited to the following:
1. Designating areas for equipment maintenance and repair;
Cedar City Rural Initiative
GENERAL REQUIREMENTS
01 00 02 - 8
2. Providing waste receptacles at convenient locations and provide regular collection of wastes;
3. Locating equipment wash down areas on site, and provide appropriate control of wash-waters;
4. Providing protected storage areas for chemicals, paints, solvents, fertilizers, and other potentially toxic materials; and
5. Providing adequately maintained sanitary facilities.
1.11 RESTORATION
A. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged.
C. At the Contractor's own expense, the Contractor shall immediately restore to service and repair any damage caused by the Contractor's workmen to existing piping and conduits, wires, cables, etc., of utility services which are indicated on drawings and which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"
(FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE CONDITIONS" (FAR
52.236-2).
1.12 PHYSICAL DATA
A. Data and information furnished or referred to below is for the
Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
1. The indications of physical conditions on the drawings and in the specifications are the result of site investigations by GEM
Engineering and survey by Platt & Platt, INC.
B. Subsurface conditions have been developed by core borings and test pits. Logs of subsurface exploration conducted by GEM Engineering are in the geotechnical report.
C. A copy of the geotechnical report is an Appendix to these specifications and shall be considered part of the contract documents.
Cedar City Rural Initiative
GENERAL REQUIREMENTS
01 00 02 - 9
D. The Government does not guarantee that other materials will not be encountered, nor that proportions, conditions or character of several materials will not vary from those indicated by explorations. Bidders are expected to examine the site of work and logs of borings and, after investigation, decide for themselves the character of materials and make their bids accordingly. Upon proper application to the Department of Veterans Affairs, including approved scheduling bidders will be permitted to make subsurface explorations of their own at site.
1.13 PROFESSIONAL SURVEYING SERVICES
A registered professional land surveyor or registered civil engineer whose services are retained and paid for by the Contractor shall perform services specified herein and in other specification sections.
The Contractor shall certify that the land surveyor or civil engineer is not one who is a regular employee of the Contractor, and that the land surveyor or civil engineer has no financial interest in this contract.
1.14 LAYOUT OF WORK
A. The Contractor shall lay out the work from Government established base lines and benchmarks indicated on the drawings and shall be responsible for all measurements in connection with the layout. The Contractor shall furnish, at the Contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work. The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the COR. The Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the COR until authorized to remove them. If such marks are destroyed by the
Contractor or through Contractor's negligence before their removal is authorized, the COR may replace them and deduct the expense of the replacement from any amounts due or to become due to the Contractor.
(FAR 52.236-17)
B. Establish and plainly mark center lines for each building, lines for each gravesite control monument, and such other lines and grades that are reasonably necessary to properly assure that location, orientation, and elevations established for each such structure, roads, gravesite control monuments, are in accordance with lines and elevations shown on contract drawings.
Cedar City Rural Initiative
GENERAL REQUIREMENTS
01 00 02 - 10
C. Following completion of general mass excavation and before any other permanent work is performed, establish and plainly mark (through use of appropriate batter boards or other means) sufficient additional survey control points or system of points as may be necessary to assure proper alignment, orientation, and grade of all major features of work. The
Survey shall include, but not be limited to, location of lines and grades of footings, exterior walls, center lines of columns in both directions, major utilities and elevations of floor slabs:
1. Such additional survey control points or system of points thus established shall be checked and certified by a registered land surveyor or registered civil engineer. Furnish such certification to the COR before any work (such as footings, floor slabs, columns, walls, utilities and other major controlling features) is placed.
D. During progress of work, the Contractor shall have lines, grades, locations and plumbness of all major form work checked and certified by a registered land surveyor or registered civil engineer as meeting requirements of contract drawings. Furnish such certification to the
COR before any major items of concrete work are placed. In addition, furnish to the COR certificates from a registered land surveyor or registered civil engineer that the following work is complete in every respect as required by contract drawings.
1. Lines of each building.
2. Elevations of bottoms of footings and tops of floors of each building.
3. Lines and elevations of sewers and of all outside distribution systems.
4. Lines of grave plot documentation.
5. Lines of elevations of all swales and interment areas.
6. Lines and elevations of roads and streets.
7. Lines and elevations and location of top of pre-placed crypts within their respective plots.
8. Lines and elevations of grade over pre-placed crypts.
9. Northing/Easting coordinate locations and elevation depth below finished grade of all water, storm and irrigation structures, directional fittings, control wire and lines.
10. Northing/Easting coordinate locations and elevation for each gravesite grid monument.
Cedar City Rural Initiative
GENERAL REQUIREMENTS
01 00 02 - 11
E. Upon completion of the work, the Contractor shall obtain the services of a register professional land surveyor to conduct a final survey of all construction and furnish the COR with reproducible drawings, in
AutoCAD form, at the scale of the contract drawings, showing the finished grade on the grid developed for constructing the work. These drawings shall bear the seal of the registered land surveyor or registered civil engineer.
F. The Contractor shall perform the surveying and layout work of this and other articles and specifications in accordance with the provisions of
Article "Professional Surveying Services".
1.15 AS-BUILT DRAWINGS
A. The Contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, which will include all contract changes, modifications and clarifications.
B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR's review, as often as requested.
C. At substantial completion, the Contractor shall secure the services of a professional land surveyor, as defined in Section 1.10, to perform a site survey within the project limits in accordance with the NCA Site, Topographic, Utility, Landscape & Soil Survey scope of services, as listed in the appendix of this specification. Elements to be surveyed include, but are not limited to:
1. Location, alignment, and dimension of roads, curbs, walks, parking, and paved areas. Indicate road centerlines with true bearings and lengths by 15 m (50') stationing. Describe curves by designating the points of curvature and tangency by station. Include all curve data as well as location of radius and vertex points. Designate roads with curbs by double lines. Show equalities for intersecting roads by station.
2. Crown, grade, and climb of curb at road crossings contours.
3. Elevations on 50' centers on centerline of roads, edges of roads, and top and bottom of curbs.
4. Type of pavement of roads.
5. Surface elevations on a 50' grid pattern, except where terrain features require greater detail. At abrupt changes in grade, show elevations at the tops and bottoms of slopes to the nearest 0.1'.
Cedar City Rural Initiative
GENERAL REQUIREMENTS
01 00 02 - 12
6. Site features of every character identified and located with exact measurements. Include fences, walls, areaways, steps, ramps, railings, gratings, flumes, pads, sprinkler heads, telephone poles, signage, and site furnishings.
7. All underground, overhead, and surface electrical utilities and structures. Show size, depth, and top elevation of all electrical structures, based on actual site investigation.
8. All underground and surface civil and mechanical utilities and structures. Show size depth, invert and top elevation of all utility structures, such as manholes, catch basins and headwalls, based on actual site investigation. Indicate direction of flow and size of pipe for all sewers drains and connecting lines between manholes.
9. Grid monuments.
D. The Contractor shall deliver two approved completed sets of as-built drawings to the COR within 15 calendar days after acceptance of the project by the COR.
E. Paragraphs A, B, C & D shall also apply to all shop drawings.
1.16 USE OF ROADWAYS
A. For hauling, use only established public roads and designated permanent roads on Cemetery property when indicated or authorized by the COR.
Temporary roads shall be constructed or modified by the Contractor at the Contractor's expense following approved plans that include:
construction, operation, maintenance and restoration. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.
B. When new permanent roads are to be a part of this contract, the
Contractor may construct them immediately to facilitate building operations. These roads may be used by all who have business thereon within zone of building operations.
1.17 RE/COTR'S FIELD OFFICE (NOT USED)
1.18 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to compliance with the following provisions:
Cedar City Rural Initiative
GENERAL REQUIREMENTS
01 00 02 - 13
1. Permission to use each unit or system must be given by COR. If the equipment is not installed and maintained in accordance with the following provisions, the COR will withdraw permission for use of the equipment.
2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, and their overload elements shall be properly sized, coordinated and adjusted. Voltage supplied to each item of equipment shall be verified to be correct and it shall be determined that motors are not overloaded. The electrical equipment shall be thoroughly cleaned before using it and again immediately before final inspection including vacuum cleaning and wiping clean interior and exterior surfaces.
3. Units shall be properly lubricated, balanced, and aligned.
Vibrations must be eliminated.
4. All components of heat production, metering equipment, and other auxiliary facilities used in temporary service shall be cleaned prior to use; maintained to prevent corrosion internally and externally during use; and cleaned, maintained and inspected prior to acceptance by the Government.
B. Prior to final inspection, the equipment or parts used which show wear and tear beyond normal, shall be replaced with identical replacements, at no additional cost to the Government.
C. This paragraph shall not reduce the requirements of the mechanical and electrical specifications sections.
1.19 TEMPORARY TOILETS
A. Provide where directed, (for use of all Contractor's workers) ample temporary sanitary toilet accommodations with suitable sewer and water connections, or when approved by COR provide suitable dry closets where directed. Keep such places clean and free from flies, and all connections and appliances connected therewith are to be removed prior to completion of contract, and premises left perfectly clean.
1.20 AVAILABILITY AND USE OF UTILITY SERVICES
A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The amount to be paid by the Contractor for
Cedar City Rural Initiative
GENERAL REQUIREMENTS
01 00 02 - 14 chargeable electrical services shall be the prevailing rates charged to the Government. The Contractor shall carefully conserve any utilities furnished without charge.
B. The Contractor, at Contractor's expense and in a workmanlike manner satisfactory to the COR, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of electricity used for the purpose of determining charges. Before final acceptance of the work by the
Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia.
C. The Contractor shall install meters at the Contractor's expense and furnish the Cemetery a monthly record of the Contractor's usage of electricity as hereinafter specified.
D. Heat: Furnish temporary heat necessary to prevent injury to work and materials through dampness and cold. Use of open salamanders or any temporary heating devices which may be fire hazards or may smoke and damage finished work, will not be permitted. Maintain minimum temperatures as specified for various materials:
E. Electricity (for Construction and Testing): Furnish all temporary electric services.
1. Obtain electricity by connecting to the Cemetery electrical distribution system. The Contractor shall meter and pay for electricity required for electric cranes and hoisting devices, electrical welding devices and any electrical heating devices providing temporary heat. Where not available or not convenient to connect to the Cemetery distribution system, the contractor shall supply power via portable generators at own expense.
F. Water (for Construction and Testing): Furnish temporary water service.
1. Obtain water by connecting to the Cemetery irrigation distribution system. Backflow preventer may not be required at connections to the irrigation system. Water is available at no cost to the Contractor.
2. Maintain connections, pipe, fittings and fixtures and conserve water-use so none is wasted. Failure to stop leakage or other wastes will be cause for revocation (at COR's discretion) of use of water from the Cemetery's system.
Cedar City Rural Initiative
GENERAL REQUIREMENTS
01 00 02 - 15
3. Where not available or not convenient to connect to the Cemetery distribution system, the Contractor shall supply water via portable/temporary means at his own expense.
1.21 NEW TELEPHONE EQUIPMENT (NOT USED)
1.22 TESTS
A. Pre-test mechanical and electrical equipment and systems and make corrections required for proper operation of such systems before requesting final tests. Final test will not be conducted unless pre-tested.
B. Conduct final tests required in various sections of specifications in presence of an authorized representative of the COR. Contractor shall furnish all labor, materials, equipment, instruments, and forms, to conduct and record such tests.
C. Mechanical and electrical systems shall be balanced, controlled and coordinated. A system is defined as the entire complex which must be coordinated to work together during normal operation to produce results for which the system is designed.
D. All related components as defined above shall be functioning when any system component is tested. Tests shall be completed within a reasonably short period of time during which operating and environmental conditions remain reasonably constant.
E. Individual test result of any component, where required, will only be accepted when submitted with the test results of related components and of the entire system.
1.23 INSTRUCTIONS
A. The Contractor shall furnish Maintenance and Operating manuals and verbal instructions when required by the various sections of the specifications and as hereinafter specified.
B. Manuals: Maintenance and operating manuals (four copies each) for each separate piece of equipment shall be delivered to the COR coincidental with the delivery of the equipment to the job site. Manuals shall be complete, detailed guides for the maintenance and operation of equipment. They shall include complete information necessary for starting, adjusting, maintaining in continuous operation for long periods of time and dismantling and reassembling of the complete units and sub-assembly components. Manuals shall include an index covering all component parts clearly cross-referenced to diagrams and
Cedar City Rural Initiative
GENERAL REQUIREMENTS
01 00 02 - 16 illustrations. Illustrations shall include "exploded" views showing and identifying each separate item. Emphasis shall be placed on the use of special tools and instruments. The function of each piece of equipment, component, accessory and control shall be clearly and thoroughly explained. All necessary precautions for the operation of the equipment and the reason for each precaution shall be clearly set forth. Manuals must reference the exact model, style and size of the piece of equipment and system being furnished. Manuals referencing equipment similar to but of a different model, style, and size than that furnished will not be accepted.
C. Instructions: The Contractor shall provide qualified, factory-trained manufacturers' representatives to give detailed instructions to assigned Department of Veterans Affairs personnel in the operation and complete maintenance for each piece of equipment. All such training will be at the job site. These requirements are more specifically detailed in the various technical sections. Instructions for different items of equipment that are component parts of a complete system; shall be given in an integrated, progressive manner. All instructors for every piece of component equipment in a system shall be available until instructions for all items included in the system have been completed.
This is to assure proper instruction in the operation of inter-related systems. All instruction periods shall be at such times as scheduled by the RE/COR and shall be considered concluded only when the COR is satisfied in regard to complete and thorough coverage. The Department of Veterans Affairs reserves the right to request the removal of, and substitution for, any instructor who, in the opinion of the COR, does not demonstrate sufficient qualifications in accordance with requirements for instructors above.
1.24 GOVERNMENT-FURNISHED PROPERTY
A. The Government shall deliver to the Contractor, the
Government-furnished property shown on drawings.
B. Materials furnished by the Government to be installed by the Contractor will be furnished to the Contractor at the Cemetery.
C. Storage space for materials will be provided by the Contractor and the
Contractor shall be prepared to unload and store such equipment therein upon its receipt at the Cemetery.
Cedar City Rural Initiative
GENERAL REQUIREMENTS
01 00 02 - 17
D. Notify COR in writing, 60 days in advance, of date on which Contractor will be prepared to receive materials furnished by Government.
Arrangements will then be made by the Government for delivery of materials.
1. Immediately upon delivery of materials, the Contractor shall arrange for a joint inspection thereof with a representative of the
Government. At such time the Contractor shall acknowledge receipt of materials described, make notations, and immediately furnish the
Government representative with a written statement as to its condition or shortages.
2. The Contractor thereafter is responsible for such material until such time as acceptance of contract work is made by the Government.
E. Equipment furnished by the Government, if any, will be delivered in a partially assembled (knock down) condition in accordance with existing standard commercial practices.
F. Completely assemble and install the Government furnished equipment in place ready for proper operation in accordance with specifications and drawings.
G. Furnish supervision of installation of equipment at construction site by qualified factory trained technicians regularly employed by the equipment manufacturer.
1.25 RELOCATED ITEMS (NOT USED)
1.26 CONSTRUCTION SIGN
A. Provide a Construction Sign where directed by the COR. All wood members shall be of framing lumber. Cover sign frame with 0.7 mm (24 gage) galvanized sheet steel nailed securely around edges and on all bearings. Sign face shall be 4 feet x 5 feet and 6 inches. Provide two 100 by 100 mm (4-inch by 4-inch) posts (or equivalent round posts) set 900 mm (three feet) into ground. Set bottom of sign level at 900 mm (three feet) above ground and secure to posts with through bolts.
Make posts full height of sign. Brace posts with 50 mm x 100 mm (two by four inch) material as directed.
B. Paint all surfaces of sign and posts two coats of white semi-gloss paint. Border and letters shall be of black gloss paint, except project title which shall be blue gloss paint.
C. Maintain sign and remove it when directed by the COR.
Cedar City Rural Initiative
GENERAL REQUIREMENTS
01 00 02 - 18
D. Detail Drawing of construction sign showing required legend and other characteristics of sign is a part of the drawings.
1.27 SAFETY SIGN
A. Provide a Safety Sign where directed by COR. Signboard shall be three feet x four feet, 19 mm (3/4-inch) thick exterior grade plywood.
Provide two 100 mm by 100 mm (four by four inch) posts extending full height of sign and 900 mm (three feet) into ground. Set bottom of sign level at 1200 mm (four feet) above ground.
B. Paint all surfaces of Safety Sign and posts with one prime coat and two coats of white gloss paint. Letters and design shall be painted with gloss paint of colors noted.
C. Maintain sign and remove it when directed by COR.
D. Detail Drawing of safety sign showing required legend and other characteristics of sign is included in the drawings.
E. Post the number of accident free days on a daily basis.
1.28 CONSTRUCTION DIGITAL IMAGES
A. During construction period through completion, furnish Department of
Veterans Affairs weekly color digital photographs of construction progress (8 to 10 images per week.) Photographs of the reinforcing steel shall be taken after all reinforcing steel, sleeves, inserts, etc. are in place. Photographs must show distinctly, at as large a scale as possible, all parts of work embraced in picture.
B. Photographs are to be taken with a high-resolution digital camera, minimum 6 megapixels, with good wide-angle capability. The images shall be recorded in JPEG format with a minimum of 24-bit color and no reduction in actual picture size.
1. Compressed size of the file shall be no less than 80% or the original with no loss of information.
2. File names shall contain the Project number, the date the image was taken, and a unique sequential identifier, for example:
101CM3202_10-01-2013_0001. Use underscore, not spaces in digital file names.
C. The digital photo files shall become property of Government and will be both e-mailed and submitted on CD-ROM.
1. The images shall be forwarded electronically to the COR via email to
NAME@va.gov within 2 days of when the photo was taken. Identify the content of each picture by a caption incorporated in the photo.
Cedar City Rural Initiative
GENERAL REQUIREMENTS
01 00 02 - 19
2. The digital photo files shall also be submitted on CD-ROM to the COR at the conclusion of the project. The CD-ROM shall also contain an index of all the images contained therein in either a TXT or
Microsoft Word format.
1.29 FINAL ELEVATION PHOTOGRAPHS
A. Final photographs shall be taken by a commercial/professional photographer. They shall be taken upon completion, including landscaping. They shall be taken on a clear sunny day at as large a scale as possible to obtain sufficient detail to show depth and to provide clear, sharp pictures. All images shall become property of the Government.
B. Photographs shall be artistically composed showing full front elevations of new columbarium court(s), memorial wall, site features and surrounding landscapes. A minimum of thirty six (36) images shall be taken as per these specifications.
C. Minimum digital photo file size for final photos is 20 mb un-interpolated, preferably 52 mb. Submit proofs, via e-mail or web photo gallery, from which the COR will select the final images for printing.
D. Pictures selected by the COR for printing shall be printed on regular weight paper, matte finish archival grade photographic paper and produced by a RA4 process from the digital image with a minimum
300 PPI. Photographs shall have full picture print with no margin.
E. Submit two (2) 400 mm x 500 mm (16 x 20) framed prints and three (3)
8 x 10 prints of the final selected photos. Deliver to the
COR/Project Manager, in boxes suitable for shipping, F. Submit a CD-ROM to the COR containing all (minimum 36) final digital photo files.
1. Images on CD-ROM shall be recorded in JPEG format with a minimum of 24 bit color and no reduction in actual picture size.
Compressed size of the file shall be no less than 80% of the original with no loss of information.
Cedar City Rural…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .