About this file
This is a Contractor Work Surveillance Checklist for monitoring the placement or removal of empty rented rolloff boxes (ROB) or vacuum boxes related to hazardous waste removal services in Alaska. The checklist is designed to verify contractor compliance with delivery requirements and equipment specifications.
The checklist evaluates several key aspects of the contractor's performance, including: timely arrival at the scheduled location, delivery of appropriately sized containers with required components (plastic liners and watertight tarp covers for ROBs), provision of approved weight tickets showing container tare weight, condition of containers (minimal corrosion, no waste residue, free of offensive graffiti), and overall equipment functionality. The form requires sign-off from a Designated Government Representative and includes space to document any defects or damages that must be acknowledged by the driver, noting that failure to acknowledge defects can result in rejection of the ROB and liner.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Picture1.jpg | JPG image | |
| Attachment 1 Alaska PWS.pdf | ||
| Attachment 2 Alaska Price Schedule.xlsx | XLSX spreadsheet | |
| Attachment 1 Alaska PWS.pdf | ||
| Attachment 3 Alaska Pick Up Locations.xlsx | XLSX spreadsheet | |
| Attachment 5 - KTR Work Surveillance Checklist - Placement or Removal Empty of ROB or Vac Box.pdf | ||
| Attachment 12 - Provision Fill-ins.pdf | ||
| Attachment 6 DLA Form 2505.xlsx | XLSX spreadsheet | |
| Attachment 8 - Form 2593_Verifcation of W. Removal.pdf | ||
| Attachment 9 Addenda to 52.212-1 Instructions to Offerors.pdf | ||
| Attachment 1 Alaska PWS.pdf | ||
| Attachment 4 - PPI Questionnaire - Alaska HW.pdf | ||
| Attachment 10 Addenda to 52.212-2 Evaluation.pdf | ||
| Attachment 11 Contract Terms and Conditions.pdf | ||
| Attachment 2 Alaska Price Schedule.xlsx | XLSX spreadsheet |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Contractor Work Surveillance Checklist
Placement or Removal of Empty Rented Rolloff Box (ROB) or Vacuum Box
Date(s) of Work Surveillance: _________________ Start Time: ___________ Stop Time: ___________
Contract Number: SP4500-______-D-___________ TO #: ________________ CLIN: ______________
Name of Designated Government Representative: ___________________________________________
Title of Designated Government Representative: ____________________________________________
Phone Number of Designated Government Representative: (______) _______-___________ Ext.______
Yes No N/A Description of Contractor Work Surveillance: [ROB] or [Vac Box] (Circle one)
Did the Contractor arrive on site at the scheduled time and date?
Did the Contractor arrive on site with all of the requisite equipment, including
- One ROB or Vacuum Box container of the appropriately ordered size, with
- One plastic liner of sufficient size and thickness to adequately contain the waste for which it was intended (ROB only), and
- One watertight tarp cover that was generally free of rips and tears (ROB only)?
Does the Contractor have an approved weight ticket showing the empty (tare) weight of the container?
Was the container inspected by a Designated Government Representative upon arrival at the designated location?
Was the container of acceptable appearance and integrity, with minimal evidence of corrosion, visibly void of waste residue and legible/offensive graffiti upon delivery?
Was the ROB, bows and cover free of any defects or damage, other than those attributable to normal wear and tear, and determined acceptable for Government use? Please document below any noteworthy defects or damage and have driver initial for acknowledgment.
Note: Failure of the driver to acknowledge any existing noteworthy defects or damage will be cause for rejection of the ROB and liner.
Did the equipment operate properly without causing a delay in work?
Was the work performed safely and did the equipment meet the satisfaction of the Designated Government Representative?
Comments:
Signature of Designated Government Representative Date