Attachment 7 - CECC Form 3052.xls
XLS spreadsheet 31 KB Posted
- Attached to
- Replace FCU & AHU B1317 Federal contract opportunity
- Solicitation number
- FA252125B0001
About this file
This is Air Force Form 3052, a Construction Cost Estimate Breakdown template used for contractors to submit detailed cost estimates for construction projects. The form requires itemized breakdowns of material costs, labor costs (including manhours and rates), and other direct costs, with columns for unit measures, quantities, and line item totals. The template includes fields for contract number, project number, work location, and contractor information.
The form is meant to be used in conjunction with construction contract FA252125B0001 for replacing fan coil units and air handler units at Patrick Space Force Base, FL. While the template itself is blank, it provides instructions for contractors to document their cost estimates in a standardized format, including requirements for supporting documentation and the right of government review of contractor cost data. The final page requires calculation of total material costs, labor costs, overhead, profit and total price.
View the file
Other files for this federal contract opportunity
Show all 21
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AF3052
| CONSTRUCTION COST ESTIMATE BREAKDOWN | ||||||||||
| CONTRACTOR | ADDRESS | |||||||||
| CONTRACT FOR | PROPOSED TOTAL CONTRACT PRICE | |||||||||
| Contract No. | $0 | |||||||||
| PURCHASE REQUEST FORM | PROJECT NUMBER | WORK LOCATION | ||||||||
| MATERIAL COST | LABOR COST | |||||||||
| UNIT | OTHER | |||||||||
| LINE | ITEM | OF | QUANTITY | MANHOURS | AVERAGE | TOTAL | DIRECT | LINE | ||
| NO. | MEASURE | UNIT | TOTAL | MANDAYS | RATE | COSTS | TOTAL | |||
| (1) | (2) | (3) | (4) | (5) | (6) | (7) | (8) | (9) | (10) | |
| 0.00 | 0.00 | 0.00 | 0.00 | |||||||
| 0.00 | 0.00 | 0.00 | ||||||||
| 0.00 | 0.00 | 0.00 | ||||||||
| 0.00 | 0.00 | 0.00 | ||||||||
| 0.00 | 0.00 | 0.00 | ||||||||
| 0.00 | 0.00 | 0.00 | ||||||||
| 0.00 | ||||||||||
| 0.00 | ||||||||||
| 0 | 0.00 | |||||||||
| 0.00 | 0.00 | 0.00 | ||||||||
| 0.00 | 0.00 | 0.00 | ||||||||
| 0.00 | 0.00 | 0.00 | ||||||||
| 0.00 | 0.00 | 0.00 | ||||||||
| 0.00 | 0.00 | 0.00 | ||||||||
| 0.00 | 0.00 | 0.00 | ||||||||
| 0.00 | ||||||||||
| 0.00 | 0.00 | 0.00 | ||||||||
| 0.00 | 0.00 | 0.00 | ||||||||
| CECC FORM 3052 | PAGE 1 | |||||||||
| INSTRUCTIONS FOR COMPLETING AF FORM 3052 | ||||||||||
| Col 1 Item. Description of materials required, work to be done, special equipment needed, etc. Breakdown should be in sufficient | ||||||||||
| detail to permit itemizing of all direct costs. | ||||||||||
| Col 2 Unit of Measure. Description of the unit in which each item is to be estimated (examples--square yards--SY, cubic yards-- | ||||||||||
| CY, square feet--SF, linear feet--LF, board feet--BF, each--EA, pound--LB). | ||||||||||
| Col 3 Quantity. Constractor's estimate of quantity required in terms of unit of measure (couldmn 2). Itms and units of measure will | ||||||||||
| be furnished by the Government. Quantity estimates will be furnished by the Government only when it is anticipated that a unit price | ||||||||||
| contract will be issued. Otherwise, the contractor is responsible for determining quantity estimates. | ||||||||||
| Col 4 and 5 Material Costs. Enter unit cost (Col 4) of material to be supplied and total costs (Col 5) for items listed in column 1. | ||||||||||
| Col 6, 7 and 8 Labor Costs. Enter in col 6 the estimated number of manhours or mandays needed to perform the work listed in | ||||||||||
| column 1. Enter in col 7 the average rate per manhour (manday) and in col 8 the total labor cost. | ||||||||||
| Col 9 Other Direct Costs. Enter estimated costs of special equipment and other items (listed in column 1) which are special to the | ||||||||||
| contract and of significant dollar value. | ||||||||||
| Col 10 Line Total. Self-explanatory. | ||||||||||
| NOTE: In addition to other totals entered on various pages, the grand total of column 10, plus overhead and profit will be shown on | ||||||||||
| the last page as follows. | ||||||||||
| TOTAL MATERIAL COSTS | $ | |||||||||
| TOTAL LABOR COSTS | $ | |||||||||
| TOTAL OTHER DIRECT COSTS | $ | |||||||||
| TOAL DIRECT COSTS | $ | |||||||||
| OVERHEAD | $ | |||||||||
| SUBTOTAL | $ | |||||||||
| PROFIT | $ | |||||||||
| TOTAL PRICE | $ | |||||||||
| DATE | FIRM NAME | |||||||||
| TITLE | BY | |||||||||
| (Signature) | ||||||||||
| INSTRUCTIONS TO OFFERORS | ||||||||||
| 1. The purpose of this form is to provide a standard format by which the offeror submits to the Government a summary of | ||||||||||
| incurred and estimated costs (and attached supporting information) suitable for detailed review and analysis. Prior to the award | ||||||||||
| of a contract resulting from this proposal the offeror shall, under the conditions stated in ASPR 3-807.3, be required to submit a | ||||||||||
| certificate of current cost or pricing data (see ASPR 3-807.3(e) and 3.807.4). | ||||||||||
| 2. In addition to the specific information required by this form, the offeror is expected, in good faith, to incorporate in and submit | ||||||||||
| with this form any additional data, supporting schedules, or substantiation which are reasonably required for the conduct of an | ||||||||||
| appropriate review and analysis in the light of the specific facts of this procurement. For effective negotiations, it is essential that | ||||||||||
| there be a clear understanding of | ||||||||||
| a. The existing, verifiable data | ||||||||||
| b. The judgmental factors applied in projecting from known data to the estimate, and | ||||||||||
| c. The contingencies used by the offeror in his proposed price. | ||||||||||
| In short, the offeror's estimating process itself needs to be disclosed. | ||||||||||
| 3. When attachment of supporting cost or pricing data to this form is impracticalbe, the data will be described (with schdules as | ||||||||||
| appropriate), and made available to the contracting officer or his authorized representative on request. | ||||||||||
| 4. By submission of this proposal the offeror grants to the contracting officer, or his authorized representative, the right to examine, | ||||||||||
| for the purpose of verifying the cost or pricing data submitted, those books, records, documents, and other supporting data which | ||||||||||
| will permit adequate evaluation of such cost or pricing data, along with the computations and projections used therein. This right | ||||||||||
| may be exercised in connection with any negotiations prior to contract award. | ||||||||||
| (Reverse of AF Form 3052, Jan 88) | ||||||||||
| *U.S. GOVERNMENT PRINTING OFFICE: 1988-24D-979:51319 |