This transmittal form outlines specifications for the construction of a mobile border police unit for the Ecuadorian National Police. Key items include the construction of modular steel containers that will house living quarters, administrative offices, kennels, and utilities like plumbing and electrical systems. The transmittal lists over 50 line items specifying the materials and components required for floors, walls, windows, doors, water, sewage, solar power, lighting, air conditioning, communications, kitchen appliances, furniture, and other fixtures and equipment for the mobile unit. The contractor must submit this transmittal form and supporting documents to the Contracting Officer's Representative for approval before procurement of long-lead materials and commencement of construction activities.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 19AQMM22R0187 B-M A001.pdf | ||
| 19AQMM22R0187 0001.pdf | ||
| Attachment 5 - Past Performance Questionnaire (PPQ).docx | DOCX document | |
| Attachment 3 - Drawings.zip | ZIP file | |
| 19AQMM22R0187 B-M.pdf | ||
| Attachment 4 - Firm and Project Information.pdf | ||
| Attachment 1 - SOW.pdf | ||
| 19AQMM22R0187.pdf | ||
| Attachment 2 - Bid Chart.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Page 1-3
| TRANSMITAL OF SHOP DRAWING, EQUIPMENT DATA, MATERIAL SAMPLES, OR MANUFACTUR'S CERTIFICATE, COMPLIANCE | TRANSMITTAL #: | 1 | ||
| PAGE: | 1 of3 | |||
| # OF ATTACHEMENTS | ||||
| DATE: 00/MONTH/0000 | ||||
| PROJECT: | CONSTRUCTION OF THE BORDER POLICE MOBILE UNIT # 1 ECUADORIAN NATIONAL POLICE | CONTRACT #: | ######## | |
| QUITO - ECUADOR | ||||
| FROM: | ||||
| TO: | ||||
| TRANSMITTAL SUMMARY: | CHECK ONE | |||
| In this cell provide a short description of the purpose of the transmittal. Include informtion about the use of the items, for what type of work is going to be used, etc. | THIS IS A NEW TRANSMITTAL | |||
| THIS IS A RESUBMITTAL | ||||
| OF TRANSMITTAL #: | ## |
| ITEM # | DESCRIPTION ITEM SUBMITTED | CONTRACT REFERENCE DOCUMENT | CHECK ON THIS ITEM FOR | OBSERVATIONS | APPROVAL | |||
| SPEC # | DRAWING # | INFORM. ONLY | GOV. APPROV | Y | N | |||
| Contractor Inspection System | E.5 / F.9 /H.27 | |||||||
| List of Proposed Subcontractors | H.10 / F.9 / H.29 | |||||||
| Contractor Licenses | H.10 / I.10 /F.9 | |||||||
| Project Schedule | F.5 / F.9 | |||||||
| Weekly inspection reports | E.5 / F.9 | |||||||
| Monthly progress report | E.5 / F.10 | |||||||
| Payment Tables | H.32/ F.9 / G.4 | |||||||
| Schedule for progress payment | G.3 | |||||||
| Certification of Payment to Subcontractors | G.5 | |||||||
| Project Schedule | F.5 / F.9 | |||||||
| Health and Safety Plan | H.27 / F.9 | |||||||
| Quality Control (QC) Plan | SOW C.2.3. | |||||||
| DBA Insurance | H.1 / H.31 | |||||||
| Bodily Injury | H.3/ F.9 | |||||||
| Property Damage | H.3/ F.9 | |||||||
| Motor Vehicle Liability | H.3/ F.9 | |||||||
| Personnel List | H.32 / H.27 | |||||||
| Local Social Security payment | H.32 | |||||||
| Manufacturing Site | SOW C.2.11. | |||||||
| Warning Signals | SOW C.2.5 | |||||||
| Prevention Measures for Covid-19 | SOW C.2..6 | |||||||
| Containers | SOW C.1.1 / C.3.1. | |||||||
| Containers' floors | SOW C.3.1.2 | |||||||
| Containers' roof | SOW C.3.1.3 | S-01 to S-17 | ||||||
| Containers' walls | SOW C.3.1.4 | S-01 to S-17 | ||||||
| Containers' windows | SOW C.3.1.5 | |||||||
| Containers' Exit doors | SOW C.3.1.6 | |||||||
| Containers' interior doors | SOW C.3.1.7 | |||||||
| Kennels doors | SOW C.3.1.8 | S-16 | ||||||
| Louver doors | SOW C.3.1.9 | S-16 | ||||||
| Exterior water network | SOW C.3.2.1 | P-01 | ||||||
| Interior Water network | SOW C.3.2.2 | P-01, P-02 | ||||||
| Hydro-pneumtic pressure system | SOW C.3.2.3 | P-02 | ||||||
| Pipes and accessories for hot water | SOW C.3.2.4 | P-01, P-02 | ||||||
| Galvanized pipes and fittings | SOW C.3.2.5 | P-01, P-02 | ||||||
| High pressure hose for water supply | SOW C.3.2.6 | P-01, P-02 | ||||||
| Quick couplings & valves for Potable Water | SOW C.3.2.7 | P-01, P-02 | ||||||
| 12000 w electric tankless water heater | SOW C.3.2.8 | P-01, P-02 | ||||||
| Sewer System | SOW C.3.3 | P-03, P-04, P-05, P-06 | ||||||
| Tank for the waste water (sewer tank) | SOW C.3.3.1 | P-05, P-06 | ||||||
| Pipes and accessories (Sewer System) | SOW C.3.3.2 | P-03, P-04 | ||||||
| High pressure hose for sewer system | SOW C.3.3.5 | S01, S11 | ||||||
| Quick connection coupling, valves for sewer system | SOW C.3.3.6 | S01, S12 | ||||||
| PRESENTATION DATE: 00/MONTH/0000 | PROCESS DATE: | APPROVING DATE: | ||||||
| I certify that the submitted items have been reviewed in detail and are correct in strict conformance with the contract drawings and specifications, except as otherwise stated. | I recommend the approval of the items listed and appointed with "Y", while items appointed with "N" the contractor shall submit new transmittals. Items for "information only" do not require approval. | I approve the items listed and appointed with "Y", while items appointed with "N" are not approved and the contractor shall submit new transmittals. The approval of these items does not means the acceptance of the works. Items for "information only" do not require approval. |
| CONTRACTOR | TECHNICAL ADVISOR INL - CES | CONTRACTING OFFICER'S REPRESENTATIVE |
| NAME | ENG.MARIO NARVAEZ | NAME |
| CREATIVE CORRECTIONS |
Page 2-3
| TRANSMITAL OF SHOP DRAWING, EQUIPMENT DATA, MATERIAL SAMPLES, OR MANUFACTUR'S CERTIFICATE, COMPLIANCE | TRANSMITTAL #: | 1 | ||
| PAGE: | 2 of 3 | |||
| # OF ATTACHEMENTS | ||||
| DATE: 00/MONTH/0000 | ||||
| PROJECT: | CONSTRUCTION OF THE BORDER POLICE MOBILE UNIT # 1 ECUADORIAN NATIONAL POLICE | CONTRACT #: | ######## | |
| QUITO - ECUADOR | ||||
| FROM: | ||||
| TO: | ||||
| TRANSMITTAL SUMMARY: | CHECK ONE | |||
| In this cell provide a short description of the purpose of the transmittal. Include informtion about the use of the items, for what type of work is going to be used, etc. | THIS IS A NEW TRANSMITTAL | |||
| THIS IS A RESUBMITTAL | ||||
| OF TRANSMITTAL #: | ## |
| ITEM # | DESCRIPTION ITEM SUBMITTED | CONTRACT REFERENCE DOCUMENT | CHECK ON THIS ITEM FOR | OBSERVATIONS | APPROVAL | |||
| SPEC # | DRAWING # | INFORM. ONLY | GOV. APPROV | Y | N | |||
| stainless steel washbasin | C.3.4.2 | |||||||
| Toilets | C.3.4.3 | |||||||
| Stainless steel sink | C.3.4.4 | |||||||
| Sshower enclosure cabins | C.3.4.5 | |||||||
| Generations by solar radiation | C.3.5.1.1. | |||||||
| Electrical generation by internal combustion | C.3.5.1.2. | |||||||
| General MDB-S electrical distribution board (solar) | C.3.5.2.1. | |||||||
| General electrical distribution board MDB-G | C.3.5.2.2. | |||||||
| Solar energy distribution board (SDB/S) | C.3.5.2.3. | |||||||
| Thermal energy distribution SDB/G | C.3.5.2.4. | |||||||
| Low voltage main connection | C.3.5.3.1. | |||||||
| Low voltage main connection to solar power | C.3.5.3.2. | |||||||
| Connection to solar power dist. under-boards | C.3.5.3.3. | |||||||
| Connection to the thermal energy dist. subpanel | C.3.5.3.4. | |||||||
| Indoor Containers Lighting | C.3.5.4.1. | |||||||
| Outdoor lighting | C.3.5.4.2. | |||||||
| Ground system | C.3.5.5.1. | |||||||
| Polarized 120V outlet circuits | C.3.5.5.2. | |||||||
| Polarized 120V outlet circuits for TVs and screens | C.3.5.5.3. | |||||||
| Polarized 120V outlet circuits for emergency lamps | C.3.5.5.4. | |||||||
| Polarized 120V outlet circuits for data racks | C.3.5.5.5. | |||||||
| Unregulated polarized 220V outlet circuits | C.3.5.5.6. | |||||||
| Unregulated polarized 220V outlet circuits-pumps | C.3.5.5.7. | |||||||
| Unregulated polarized 120/220V outlet circuits - A/C | C.3.5.5.8 | |||||||
| Electrical Protections | C.3.5.6. | |||||||
| Electrical Conductors | C.3.5.7. | |||||||
| Electrical distribution board for pump control | C.3.5.8. | |||||||
| Air conditioner systems | C.3.6 | |||||||
| Copper Pipes for Air Conditioning System | C.3.6.1. | |||||||
| Pipes and cablings for communication system | C.3.7.1 | |||||||
| Pipes and cablings for CCTV system | C.3.7.2 | |||||||
| Structured cabling for the data network | C.3.7.3. | |||||||
| Fire protection system | C.3.8 | |||||||
| Refrigerator 20 cubic feet | C.3.9.1. | |||||||
| Induction Stove 220V | C.3.9.2. | |||||||
| Kitchen Extraction hood | C.3.9.3. | |||||||
| Microwave | C.3.9.4. | |||||||
| Kitchen Furniture | C.3.9.5. | |||||||
| Dining Room Tables | C.3.9.6. | |||||||
| Metallic Buck Beds | C.3.9.7. | |||||||
| Metallic Lockers | C.3.9.8. | |||||||
| Desk for Bedrooms | C.3.9.9. | |||||||
| Metallic Closets | C.3.9.10. | |||||||
| PRESENTATION DATE: 00/MONTH/0000 | PROCESS DATE: | APPROVING DATE: | ||||||
| I certify that the submitted items have been reviewed in detail and are correct in strict conformance with the contract drawings and specifications, except as otherwise stated. | I recommend the approval of the items listed and appointed with "Y", while items appointed with "N" the contractor shall submit new transmittals. Items for "information only" do not require approval. | I approve the items listed and appointed with "Y", while items appointed with "N" are not approved and the contractor shall submit new transmittals. The approval of these items does not means the acceptance of the works. Items for "information only" do not require approval. |
| CONTRACTOR | TECHNICAL ADVISOR INL - CES | CONTRACTING OFFICER'S REPRESENTATIVE |
| NAME | ENG.MARIO NARVAEZ | NAME |
| CREATIVE CORRECTIONS |
Page 3-3
| TRANSMITAL OF SHOP DRAWING, EQUIPMENT DATA, MATERIAL SAMPLES, OR MANUFACTUR'S CERTIFICATE, COMPLIANCE | TRANSMITTAL #: | 1 | ||
| PAGE: | 3 of 3 | |||
| # OF ATTACHEMENTS | ||||
| DATE: 00/MONTH/0000 | ||||
| PROJECT: | CONSTRUCTION OF THE BORDER POLICE MOBILE UNIT # 1 ECUADORIAN NATIONAL POLICE | CONTRACT #: | ######## | |
| QUITO - ECUADOR | ||||
| FROM: | ||||
| TO: | ||||
| TRANSMITTAL SUMMARY: | CHECK ONE | |||
| In this cell provide a short description of the purpose of the transmittal. Include informtion about the use of the items, for what type of work is going to be used, etc. | THIS IS A NEW TRANSMITTAL | |||
| THIS IS A RESUBMITTAL | ||||
| OF TRANSMITTAL #: | ## |
| ITEM # | DESCRIPTION ITEM SUBMITTED | CONTRACT REFERENCE DOCUMENT | CHECK ON THIS ITEM FOR | OBSERVATIONS | APPROVAL | |||
| SPEC # | DRAWING # | INFORM. ONLY | GOV. APPROV | Y | N | |||
| Desk for Administrative Unit Module | C.3.9.11. | |||||||
| Metallic Files Cabinet | C.3.9.12. | |||||||
| Chairs for Desks | C.3.9.13. | |||||||
| Access Ladder | C.3.9.14. |
| PRESENTATION DATE: 00/MONTH/0000 | PROCESS DATE: | APPROVING DATE: |
| I certify that the submitted items have been reviewed in detail and are correct in strict conformance with the contract drawings and specifications, except as otherwise stated. | I recommend the approval of the items listed and appointed with "Y", while items appointed with "N" the contractor shall submit new transmittals. Items for "information only" do not require approval. | I approve the items listed and appointed with "Y", while items appointed with "N" are not approved and the contractor shall submit new transmittals. The approval of these items does not means the acceptance of the works. Items for "information only" do not require approval. |
| CONTRACTOR | TECHNICAL ADVISOR INL - CES | CONTRACTING OFFICER'S REPRESENTATIVE |
| NAME | ENG.MARIO NARVAEZ | NAME |
| CREATIVE CORRECTIONS |