Measurement and Payment- W. Murphy – 4244 S. Beaver Creek Rd., Waldport, OR

MEASUREMENT AND PAYMENT

1. MOBILIZATION & DEMOBILIZATION

Payment for transportation of equipment, material, and personnel to and from the job site location (regardless of trips required), required permits for water and electrical, and all other necessary items to complete the work.

2. ½ HP 10 GPM SUBMERSIBLE WELL PUMP

Payment for submersible well pumps shall be made at the contract lump sum price for the size of pump listed based. Compensation shall include payment for the pump, motor, pump control box, and all other necessary items for a complete and operational installation.

3. 1-INCH DROP PIPE AND SUBMERSIBLE CABLE

Payment for drop pipe and submersible cable shall be paid for at the contract unit price for the size and type of pipe listed based on the number of linear feel installed. Compensation shall include payment for the drop pipe, check valve, adapters, torque arrestor, submersible cable, and all other necessary items for a complete and operational installation.

4. 1-INCH PE WATER SERVICE LINE AND ELECTRICAL SERVICE TO WELL

Payment for water service line and electrical service to well shall be made at the contract unit price for the size of line listed based on the number of linear feet installed. Compensation shall include payment for excavation, backfilling and compaction; all fittings, including locating and connecting to existing service lines, disinfection and testing; electrical conduit and wiring; and all other necessary items for a complete and operational installation.

5. 1-INCH PE WATER SERVICE LINE SERVICE TO HOME

Payment for water service line and electrical service to well shall be made at the contract unit price for the size of line listed based on the number of linear feet installed. Compensation shall include payment for excavation, backfilling and compaction; all fittings, including locating and connecting to existing service lines, disinfection and testing; and all other necessary items for a complete and operational installation.

6. 80-GALLON WATER PRESSURE TANK AND CONTROLS

Payment for water pressure tank and controls shall be made at the contract lump sum price for the type of pressure system listed. Compensation shall include payment for the pressure tank, pressure gauge, pressure switch and controls, tank cross, piping, valves and fittings, and all other necessary items for a complete and operational installation.

7. SELF-CLEANING IRON OXIDATION/FILTRATION TREATMENT SYSTEM

Payment for self-cleaning iron oxidation/filtration treatment system shall be made at the contract lump sum price for the type of treatment system listed. Compensation shall include payment for all equipment, labor, and materials to install a pH neutralizing filter with auto control valve, iron/sulfur filter with auto control valve, chemical injection tee, cartridge filter, chemical feed tubing, potassium permanganate solution tank, positive displacement metering pump, 5/8” filter

Measurement and Payment- W. Murphy – 4244 S. Beaver Creek Rd., Waldport, OR backwash tubing, course gravel backwash discharge pad, and all other necessary items for a complete and operational installation.

8. DISINFECTION AND BACTERIOLOGICAL WATER TESTING

Payment for disinfection and water testing shall be made at the contract unit price based on the number of tests performed. Compensation shall include payment for disinfection, water sampling, and water quality testing.

9. POST INSTALLATION WATER TESTING - IOC

Payment for water testing shall be made at the contract unit price based on the number of number of tests performed to confirm satisfactory treatment system performance.

Compensation shall include payment for water sampling and water quality results to include the following: Nitrate, chloride, sulfate, sodium, silica, hardness, arsenic, manganese, iron, pH, alkalinity, and total dissolved solids (TDS).